EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.
-
Upload
jarrod-tuft -
Category
Documents
-
view
219 -
download
0
Transcript of EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.
EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME
GOVERNMENT OF SIKKIM
Earthquake of 2011
Parameter Value
Magnitude 6.8
Date-Time 18:10 IST, 18th Sept, 2011, Sunday
Location 27.72°N, 88.06°E
Depth 19.7 km (shallow depth)
Duration 30-40 seconds
Extent In India, Nepal, Bhutan, Bangladesh and ChinaIn India, in Sikkim and northeast, West Bengal, Bihar, Jharkhand, UP, Rajasthan, Chandigarh and Delhi
Source: USGS / IMD
Assessment of Loss and Damage
Assessment of Loss and Damage
Prime Minister’s Special Package (Rs in Crores): Progress upto 26TH March 13
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
1. Re-construction of State Civil Secretariat (Tashiling)
1 193.00 132.54 112.10 58% All Works are in progress
2. Reconstruction of Rural Houses
7972 389.83 227.03 227.03 75% All Works are in progress
3. Renovation and Re-building of State Roads & Bridges and Rural Roads
381 216.00 190.59 184.87 85% All Works are in progress
4. Retrofitting of State Government Buildings
593 68.37 59.23 56.22 83% All Works are in progress
5 Retrofitting of State Buildings - Schools
771 50.00 40.57 31.69 65% All Works are in progress
6 Retrofitting of State Buildings - State Power Projects
10 52.80 31.32 24.33 52% All Works are in progress
7 Retrofitting of State Buildings - PHC’s
27 20.00 11.22 8.16 58% All Works are in progress
8 Retrofitting of State Buildings - ICDS
134 5.00 2.50 2.50 62% All Works are in progress
9 Sewerage Schemes 25 5.00 5.00 5.00 100% All Works are completed
Total 1000 700 651.90
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/14
Physical Progress
Remarks
1. Re-construction of State Civil Secretariat (Tashiling)
1 193.00 132.54 112.10 58% All Works are in progress
RECONSTRUCTION OF STATE CIVIL SECRETARIAT
Before
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
2. Reconstruction of Rural Houses
7972 389.83 227.03 227.03 75% All Works are in progress
Before
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
3. Renovation and Re-building of State Roads & Bridges and Rural Roads
381 216.00 190.59 184.87 85% All Works are in progress
ROADS BRIDGES
Sl. No.
Details of Road Total length (km)
Length proposed to be restored (km)
Physical progress (km)
Total no. of bridge
No. of bridges completed
No. of bridges under progress
1 State Highway 156 90.75 90.75 55 40 15
2 Major District Roads
509.5 331.95 275.56
3 Other District Roads
278.18 183.12 125.57
Total 943.68 605.82 491.878
RONGLI RORATHANG ROAD
Before After
DUGA PACHEYKHANI ROAD
During After
BRIDGE OVER ROTHAK KHOLA ALONG NAYA BAZAR RESHI ROAD
Before After
JALI KHOLA BRIDGE
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
4. Retrofitting of State Government Buildings
593 68.37 59.23 56.22 83% All Works are in progress
RECONSTRUCTION OF GREEN HOUSE
RM&DD CIRCLE OFFICE & GUEST HOUSE AT JORETHANG, SOUTH SIKKIM
Before After
BAHAI SCHOOL ROAD
Before After
RATEYCHU WATER SUPPLY
Construction of Sausage Wall Protection Work at Charcharey / Seti Bhir
RECONSTRUCTION OF BOUNDARY WALL FOR GOVT FRUIT PRESERVATION FACTORY
RETROFITTING OF STATE LEGISLATIVE ASSEMBLY
Before After
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
5 Retrofitting of State Buildings - Schools
771 50.00 40.57 31.69 65% All Works are in progress
TASHIDING SENIOR SECONDARY SCHOOL
Before After
Before
PACHEYKHANI SECONDARY SCHOOL
After
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
6 Retrofitting of State Buildings – State Power Projects
10 52.80 31.32 24.33 52% All Works are in progress
RABBHOM CHU WATER HEP
Before
After
Before
After
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
7 Retrofitting of State Buildings - PHCs
27 20.00 11.22 8.16 58% All Works are in progress
Before
Before
SINGTAM
After
After
TUMIN
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
8 Retrofitting of State Buildings - ICDS
134 5.00 2.50 2.50 62% All Works are in progress
CHUNBHATTI NIMACHEN
PHADAMCHEN PASTING
Sl. No.
Name of the Project
No of Projects
Total Project Cost
TotalReceipt up to 31/03/2014
Expenditure up to 31/03/2014
Physical Progress
Remarks
9 Sewerage Schemes
25 5.00 5 .00 5.00 100% All Works are completed
Before
OFFICE-CUM-LABORATORY, ADAMPOOL
After
Before
RESTORATION OF DAMAGED PROTECTIVE WALL ALONG APPROACH ROAD TO STP
After
Prime Minister’s Special Package
Till 31st March 2014, the State Government has received Rs 700.00 Crores
Total expenditure made till 31st March 2014 is Rs 651.90 Crores , all works are in progress and RA bills, bills for the works completed are in process
Prime Minister’s Special PackageMonitoring and Evaluation
Every Department has its own multidisciplinary Internal Monitoring Committee to supervise work and submit reports before release of payments.
The Land Revenue & Disaster Management Department officials also inspects the works.
Chief Secretary along with the Senior Officials and Technical Team has been regularly monitoring and inspecting important areas for recovery and rebuilding.
THANK YOU!
Towards a Safe and Disaster Resilient Sikkim