EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

21
EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM

Transcript of EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Page 1: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME

GOVERNMENT OF SIKKIM

Page 2: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Earthquake of 2011

Parameter Value

Magnitude 6.8

Date-Time 18:10 IST, 18th Sept, 2011, Sunday

Location 27.72°N, 88.06°E

Depth 19.7 km (shallow depth)

Duration 30-40 seconds

Extent In India, Nepal, Bhutan, Bangladesh and ChinaIn India, in Sikkim and northeast, West Bengal, Bihar, Jharkhand, UP, Rajasthan, Chandigarh and Delhi

Source: USGS / IMD

Page 3: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Assessment of Loss and Damage

Page 4: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Assessment of Loss and Damage

Page 5: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Prime Minister’s Special Package (Rs in Crores): Progress upto 26TH March 13

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

1. Re-construction of State Civil Secretariat (Tashiling)

1 193.00 132.54 112.10 58% All Works are in progress

2. Reconstruction of Rural Houses

7972 389.83 227.03 227.03 75% All Works are in progress

3. Renovation and Re-building of State Roads & Bridges and Rural Roads

381 216.00 190.59 184.87 85% All Works are in progress

4. Retrofitting of State Government Buildings

593 68.37 59.23 56.22 83% All Works are in progress

5 Retrofitting of State Buildings - Schools

771 50.00 40.57 31.69 65% All Works are in progress

6 Retrofitting of State Buildings - State Power Projects

10 52.80 31.32 24.33 52% All Works are in progress

7 Retrofitting of State Buildings - PHC’s

27 20.00 11.22 8.16 58% All Works are in progress

8 Retrofitting of State Buildings - ICDS

134 5.00 2.50 2.50 62% All Works are in progress

9 Sewerage Schemes 25 5.00 5.00 5.00 100% All Works are completed

Total 1000 700 651.90

Page 6: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/14

Physical Progress

Remarks

1. Re-construction of State Civil Secretariat (Tashiling)

1 193.00 132.54 112.10 58% All Works are in progress

RECONSTRUCTION OF STATE CIVIL SECRETARIAT

Before

Page 7: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

2. Reconstruction of Rural Houses

7972 389.83 227.03 227.03 75% All Works are in progress

Before

Page 8: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

3. Renovation and Re-building of State Roads & Bridges and Rural Roads

381 216.00 190.59 184.87 85% All Works are in progress

ROADS BRIDGES

Sl. No.

Details of Road Total length (km)

Length proposed to be restored (km)

Physical progress (km)

Total no. of bridge

No. of bridges completed

No. of bridges under progress

1 State Highway 156 90.75 90.75 55 40 15

2 Major District Roads

509.5 331.95 275.56

3 Other District Roads

278.18 183.12 125.57

Total 943.68 605.82 491.878

Page 9: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

RONGLI RORATHANG ROAD

Before After

DUGA PACHEYKHANI ROAD

During After

Page 10: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

BRIDGE OVER ROTHAK KHOLA ALONG NAYA BAZAR RESHI ROAD

Before After

JALI KHOLA BRIDGE

Page 11: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

4. Retrofitting of State Government Buildings

593 68.37 59.23 56.22 83% All Works are in progress

RECONSTRUCTION OF GREEN HOUSE

RM&DD CIRCLE OFFICE & GUEST HOUSE AT JORETHANG, SOUTH SIKKIM

Before After

Page 12: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

BAHAI SCHOOL ROAD

Before After

RATEYCHU WATER SUPPLY

Construction of Sausage Wall Protection Work at Charcharey / Seti Bhir

Page 13: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

RECONSTRUCTION OF BOUNDARY WALL FOR GOVT FRUIT PRESERVATION FACTORY

RETROFITTING OF STATE LEGISLATIVE ASSEMBLY

Before After

Page 14: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

5 Retrofitting of State Buildings - Schools

771 50.00 40.57 31.69 65% All Works are in progress

TASHIDING SENIOR SECONDARY SCHOOL

Before After

Before

PACHEYKHANI SECONDARY SCHOOL

After

Page 15: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

6 Retrofitting of State Buildings – State Power Projects

10 52.80 31.32 24.33 52% All Works are in progress

RABBHOM CHU WATER HEP

Before

After

Before

After

Page 16: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

7 Retrofitting of State Buildings - PHCs

27 20.00 11.22 8.16 58% All Works are in progress

Before

Before

SINGTAM

After

After

TUMIN

Page 17: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

8 Retrofitting of State Buildings - ICDS

134 5.00 2.50 2.50 62% All Works are in progress

CHUNBHATTI NIMACHEN

PHADAMCHEN PASTING

Page 18: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Sl. No.

Name of the Project

No of Projects

Total Project Cost

TotalReceipt up to 31/03/2014

Expenditure up to 31/03/2014

Physical Progress

Remarks

9 Sewerage Schemes

25 5.00 5 .00 5.00 100% All Works are completed

Before

OFFICE-CUM-LABORATORY, ADAMPOOL

After

Before

RESTORATION OF DAMAGED PROTECTIVE WALL ALONG APPROACH ROAD TO STP

After

Page 19: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Prime Minister’s Special Package

Till 31st March 2014, the State Government has received Rs 700.00 Crores

Total expenditure made till 31st March 2014 is Rs 651.90 Crores , all works are in progress and RA bills, bills for the works completed are in process

Page 20: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

Prime Minister’s Special PackageMonitoring and Evaluation

Every Department has its own multidisciplinary Internal Monitoring Committee to supervise work and submit reports before release of payments.

The Land Revenue & Disaster Management Department officials also inspects the works.

Chief Secretary along with the Senior Officials and Technical Team has been regularly monitoring and inspecting important areas for recovery and rebuilding.

Page 21: EARTHQUAKE OF 2011- PROGRESS OF RECOVERY PROGRAMME GOVERNMENT OF SIKKIM.

THANK YOU!

Towards a Safe and Disaster Resilient Sikkim