Earthling System Electrical and Instruments Test Procedure

download Earthling System Electrical and Instruments Test Procedure

of 23

description

Erathing Test Procedure

Transcript of Earthling System Electrical and Instruments Test Procedure

  • -----

    0 NATIONAL IRANIAN OIL COMPANY ~ South Pars Gas Field Development OIEC NJ.G.CPhases 20 & 21

    Pars Oil &, Gas Company OillncAlSfn~sJ ngwl/mng II.n"ConsbucfiOf1

    DOCUMENT TITLE DOCUMENT No. Rev. : 0 I Class : 1 Earthling System Electrical and Instruments Test Procedure Test TOT -SP20210NCO999P3320015 Page 1 of 23

    Procedure

    Earthing System Electrical and Instruments Test

    Procedure

    (ONSHORE FACILITIES - PRECOMMISSIONING)

    CONTRACT NO. : POGC572-88-35 PROJECT: SOUTH PARS GAS FIELD DEVELOPMENT

    PHASES 20&21 COMPANY: PARS OIL & GAS COMPANY SITE: ASSALUYEH, IRAN

    o 30/Sep/2013 Issued For Approval oleo

    Rev. Date Description Originator Prepared Checked

    A.Razzaghi

    Approved

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 2 of 23

    TABULATION OF REVISED PAGES

    Page Rev 0 Rev 1 Rev 2

    Page Rev 0 Rev 1 Rev 2 1 X 2 X 3 X 4 X 5 X 6 X 7 X 8 X 9 X 10 X 11 X 12 X 13 X 14 X 15 X 16 X 17 X 18 X 19 X 20 X 21 X 22 X 23 X

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 3 of 23

    TABLE OF CONTENT

    1. Object...............................................................................................................................................52. Definitions........................................................................................................................................53. General.............................................................................................................................................54. Test Methods...................................................................................................................................6

    4. 1 Insulation Resistance (IR) tests...............................................................................................64. 2 High voltage tests.......................................................................................................................6

    5. Test procedures..............................................................................................................................66. Earthing systems - Test Sheet T-PX-26......................................................................................7

    a. Continuity of protective conductors.............................................................................................7b. For main protective conductor,.....................................................................................................7

    7. Equipment earth return path impedance test.............................................................................7a. Definitions........................................................................................................................................7b. Method.............................................................................................................................................8c. Motor fed from LV motor control centre......................................................................................8d. Lighting circuit fed from distribution board (See Example 2).................................................10e. HV Motor fed from HV switchboard (See Example 3)............................................................12

    8. Grounding System Testing..........................................................................................................14a. Fall-of-Potential Method or 3-Point Test...................................................................................14b. Graphing & Evaluation.................................................................................................................16c. Invalid Tests..................................................................................................................................17d. Induced Frequency Testing or Clamp-On Testing..................................................................18e. Test Application............................................................................................................................19f. Ground Resistance Monitoring...................................................................................................20

    9. Appendix........................................................................................................................................20

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 4 of 23

    9.1. Appendix01: Electrical LV Power Cables (T-PX-09)...................................................................219.2. Appendix02: Electrical Earthing / Lightning System (T-PX-26).................................................229.3. Appendix03: Electrical Earthing (C-PX-26)..................................................................................23

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 5 of 23

    1. Object

    Pre-commissioning is a phase associated with the construction stage such that the completion

    of pre-commissioning marks the end of the construction for any specific equipment. Its object is

    to prepare and statically test the equipment, which has been constructed and installed, so that

    the equipment is ready to undergo dynamic testing during the commissioning phase.

    This document outlines the pre-commissioning activities and tests of the EARTHING SYSTEM.

    2. Definitions

    PRE-COMMISSIONING: Includes all activities required to make the facilities ready for

    COMMISSIONING (Conformity Checks, Static Tests, Flushing and Cleaning).

    3. General

    Record check results as required on the relevant check-list forms (CPX-26) (Refer to Appendix).

    Test voltages and frequency: The project procedures and Test Sheets shall take into account the project voltages and

    frequency.

    The power frequency dielectric test voltages shall be based on the following IEC

    recommendations and shall be adjusted to take into account the fact that some equipment has

    already been subjected to factory tests.

    In no case the test voltage shall exceed the value indicated in the equipment VENDOR

    maintenance manual.

    IEC 60034 for Rotating Electrical machines

    IEC 60060 High Voltage test techniques

    IEC 60071 - Insulation co-ordination

    IEC 60076 for Electrical Transformers

    IEC 60502-2 for HV cables

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 6 of 23

    IEC 62271 and IEC 60694 for HV and LV switchgears

    4. Test Methods

    4. 1 Insulation Resistance (IR) tests

    IR testing shall be carried out by applying a D.C. voltage from an insulation tester at voltage

    levels given in this specification.

    4. 2 High voltage tests

    Before high voltage tests are executed, insulation resistance tests shall be carried out.

    High voltage testing shall be carried out by D.C. voltage at a level above the operating voltage.

    High-voltage testing of electrical equipment, except LV cables, shall have been carried out at

    the Manufacturer's works with A.C. at voltage levels in accordance with the IEC.

    Repeated high voltage tests may introduce weak points in the insulation of windings, and

    therefore such tests shall not be applied at site to generators, motors or transformers.

    The HV tests at full voltage shall not be repeated two times. If however for special reasons

    these tests are considered to be remade a second time, they shall be carried out only after

    consultation with the Manufacturer and with a test voltage of 80 % of the initial full test voltage.

    5. Test procedures

    Prior of any test, relevant Project Specifications and MANUFACTURER's Test Procedures shall

    be adhered to.

    The CONTRACTOR shall carry out tests as laid down on the Test Sheet.

    If the obtained IR or PI values fall below the minimum values, then the equipment should not be

    energized or subjected to high voltage testing.

    Appropriate action should be taken, e.g. drying, to normalize the figures.

    In case of 'flash-over' during high voltage testing appropriate measures shall be taken (e.g.

    cleaning, drying, repair) to eliminate the cause. Re-testing shall be performed after repair.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 7 of 23

    In the event that any of the tests fails to meet the specification requirements, it will be necessary

    for the CONTRACTOR to list any discrepancies and to present them to the COMPANY

    Engineer.

    The Test Sheet will be completed, signed and dated, and presented to the COMPANY Engineer

    for approval.

    Copies of the Test Sheet will be issued to the Certifying Authority if required. The original shall

    be inserted in the Ready for Commissioning dossier.

    6. Earthing systems - Test Sheet T-PX-26

    a. Continuity of protective conductors

    A continuity test shall be made in order to check the continuity of the protective conductors,

    including the equipotential bonding.

    b. For main protective conductor,

    Test results shall be obtained from cable test sheet T-PX-09 LV POWER CABLES AND

    CONTROL CABLE.

    7. Equipment earth return path impedance test

    a. Definitions

    To comply with IEC 60364-4-41, touch voltages shall not exceed 50 volts AC rms.

    The earth impedance loop shall be lower than the RA calculated:

    RA x Id < UL

    RA = the earthing resistance of all exposed conductive parts connected by a protective

    conductor to an earth electrode

    Id = Fault current for the first dead fault between a phase conductor

    UL = Conventional touch voltage.

    Example:

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 8 of 23

    Distribution system Id (mA) UL (V) RA (ohms)

    LV 30 50 167

    HV 30000 50 1.67

    b. Method

    All power supplies to the systems under test shall be isolated before commencing the tests.

    All testing shall be carried out in accordance with the attached detail drawings using an AC

    current injection test set.

    The injected current shall be equal to 1.5 times the design current of the circuit under test

    except that the current shall not exceed 25 A.

    The loop impedance value measured is equal to:

    E = (test set generator current) / (test set generator voltage)

    This measurement is applicable for:

    Verification of trip condition upon 2nd fault phase to earth in IT system. Verification of trip condition upon earth fault in TN system (circuits without ELCB).

    It shall be performed for each switchboard/MCC on the longest cable run on onshore plants.

    c. Motor fed from LV motor control centre

    Connect injection test set between MCC Phase Busbar R and switchboard earth, manually close contactor (outgoing feeder) and determine loop impedance E4 by

    shorting motor terminal R phase to motor earth conductor.

    Short across high impedance earthing resistor F and close circuit breaker E to determine loop impedance E4.

    Total earth return path impedance = E3 + E4. (This is a conservative value since the phase conductor resistances are also included).

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 9 of 23

    Example 1: Typical return path impedance loop 440 V 3 phase motor circuit

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 10 of 23

    d. Lighting circuit fed from distribution board (See Example 2)

    Connect injection set between Phase T Busbar and Distribution Board Earth. Manually close Breaker A and determine loop impedance E3 by shorting the end light fitting

    Terminal T to the Earth Conductor.

    Short across high impedance earthing Resistor F and manually close circuit breaker E to determine Loop Impedance E4.

    Total Earth Return Path Impedance = E3 + E4. (This is a conservative value since the phase conductor resistances are also included).

    Note: Earth return path impedance tests on small power circuits shall be at the direction and the discretion of the COMPANY Engineer.

    With the level of protection provided, it is only considered necessary to test one circuit per

    distribution board providing results are satisfactory.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 11 of 23

    Example 2: Typical return impedance loop small power circuit

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 12 of 23

    e. HV Motor fed from HV switchboard (See Example 3)

    Connect injection test set between switchboard Phase Busbar R and switchboard earth, close breaker/contactor A and determine loop impedance E6 by shorting motor

    terminal R phase to motor earth conductor.

    Connect injection test set between switchboard Phase Busbar R and switchboard earth, close earthing transformer contactor B and determine loop impedance E5 by

    shorting earthing transformer terminal R phase to transformer earth conductor.

    Total earth return path impedance = E5 + E6.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 13 of 23

    Example 3: Earth return impedance path loop 6.6 kV motor circuits

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 14 of 23

    8. Grounding System Testing

    The measurement of ground resistance for an earth electrode system is very important. It

    should be done when the electrode is first installed, and then at periodic intervals thereafter.

    This ensures that the resistance-to-ground does not increase over time. There are two (2)

    methods for testing an existing earth-electrode system. The first is the 3-point or fall-of-

    Potential method and the second is the Induced Frequency test or clamp-on method. The 3-

    point test requires complete isolation from the power utility. Not just power isolation, but also

    removal of any neutral or other such ground connections extending outside the grounding

    system. This test is the most suitable test for large grounding systems and is also suitable for

    small electrodes. The induced frequency test can be performed while power is on and actually

    requires the utility to be connected to the grounding system under test. This test is accurate only

    for small electrodes, as it uses frequencies in the kilo Hertz range, which see long conductors

    as inductive chokes and therefore do not reflect the 60 Hz resistance of the entire grounding

    system.

    a. Fall-of-Potential Method or 3-Point Test

    The 3-point or fall-of-potential method is used to measure the resistance-to-ground of existing

    grounding systems. The two primary requirements to successfully complete this test are the

    ability to isolate the grounding system from the utility neutral and knowledge of the diagonal

    length of the grounding system (i.e. a 10 x 10 grounding ring would have a 14 diagonal

    length).

    In this test, a short probe, referred to as probe Z, is driven into the earth at a distance of ten

    times (10X) the diagonal length of the grounding system (rod X). A second probe (Y) is placed

    in-line at a distance from rod X equal to the diagonal length of the grounding system.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 15 of 23

    At this point, a known current is applied across X & Z, while the resulting voltage is measured

    across X & Y.

    Ohms Law can then be applied (R=V/I) to calculate the measured resistance. Probe Y is then

    moved out to a distance of 2X the diagonal length of the grounding system, in-line with X & Z, to

    repeat the resistance measurement at the new interval.

    This will continue, moving probe Y out to 3X, 4X ... 9X the diagonal length to complete the 3

    point test with a total of nine (9) resistance measurements.

    Record all the results in the related test sheet (TPX26) (Refer to Appendix).

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 16 of 23

    b. Graphing & Evaluation

    The 3-point test is evaluated by plotting the results as data points with the distance from rod X

    along the X-axis and the resistance measurements along the Y-axis to develop a curve.

    Roughly midway between the center of the electrode under test and the probe Z, a plateau or

    flat spot should be found, as shown in the graph. The resistance of this plateau (actually, the

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 17 of 23

    resistance measured at the location 62% from the center of the electrode under test, if the soil is perfectly homogeneous) is the resistance-to-ground of the tested grounding system.

    c. Invalid Tests

    If no semblance of a plateau is found and the graph is observed to raise steadily the test is

    considered invalid. This can be due to the fact that probe Z was not placed far enough away

    from rod X, and can usually indicate that the diagonal length of the grounding system was not

    determined correctly. If the graph is observed to have a low plateau that extends the entire

    length and only rises at the last test point, then this also may be also considered invalid. This is

    because the utility or telecom neutral connection remains on the grounding system.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 18 of 23

    d. Induced Frequency Testing or Clamp-On Testing

    The Induced Frequency testing or commonly called the Clamp-On test is one of the newest

    test methods for measuring the resistance-to-ground of a grounding system or electrode. This

    test uses a special transformer to induce an oscillating voltage (often 1.7 kHz) into the

    grounding system. Unlike the 3-point Test which requires the grounding system to be

    completely disconnected and isolated before testing, this method requires that the grounding

    system under test be connected to the electric utilities (or other large grounding system such as

    from the telephone company) grounding system (typically via the neutral return wire) to provide

    the return path for the signal. This test is the only test that can be used on live or hot systems.

    However, there are some limitations, primarily being:

    1. The amount of amperage running through the tested system must be below the

    equipment manufacturers limits.

    2. The test signal must be injected at the proper location, so that the signal is forced

    through the grounding system and into the earth.

    3. This instrument actually measures the sum of the resistance of the grounding system

    under test and the impedance of the utility neutral grounding, including the neutral

    wiring. Due to the high frequency used, the impedance of the neutral wiring is non-

    negligible and can be greater than the ground resistance of a very low resistance

    grounding system, which can therefore not be measured accurately.

    4. The ground resistance of a large grounding system at 60 Hz can be significantly lower

    than at 1.7 kHz.

    Many erroneous tests have been conducted where the technician only measured metallic loops

    and not the true resistance-to-ground of the grounding system. The veracity of the Induced

    Frequency Test has been questioned due to testing errors, however when properly applied to a

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 19 of 23

    small to medium sized, self-standing grounding system, this test is rapid and reasonably

    accurate.

    e. Test Application

    The proper use of this test method requires the utility neutral to be connected to away-type

    transformer. The oscillating voltage is induced into the grounding system at a point where it will

    be forced into the soil and return through the utility neutral. Extreme caution must be taken at

    this point as erroneous readings and mistakes are often made. The most common of these

    occur when clamping on or inducing the oscillating voltage into the grounding system at a point

    where a continuous metallic path exists back to the point of the test. This can result in a

    continuity test being performed rather than a ground resistance test.

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 20 of 23

    Understanding the proper field application of this test is vital to obtaining accurate results. The

    induced frequency test can test grounding systems that are in use and does not require the

    interruption of service to take measurements.

    f. Ground Resistance Monitoring

    Ground resistance monitoring is the process of automated timed and/or continuous resistance-

    to ground measurement. These dedicated systems use the induced frequency test method to

    continuously monitor the performance of critical grounding systems. Some models may also

    provide automated data reporting. These new meters can measure resistance-to-ground and

    the current that flows on the grounding systems that are in use. Another benefit is that it does

    not require interruption of the electrical service to take these measurements.

    9. Appendix

    TPX09 ElectricalLVPowerCablesTPX26 ElectricalEarthing/LightningSystemCPX26 ElectricalEarthingSystem

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 21 of 23

    9.1. Appendix01: Electrical LV Power Cables (T-PX-09)

    Tas k Num ber :Form :Dwg / PID :

    Tas k Location : Us er Group :Es tim ated Tim e (MH) : Expended Tim e (MH) :Punch Lis t Item s :Module :Subsystem :

    TPX09 - LV POWER CABLES

    PRECOMMISSIONING TEST SHEETELECTRICAL

    LV POW ER CABLES

    0

    T E S T IN G IN S T R U M E N T S U S E D

    T Y P E / S E R IA L N : T Y P E / S E R IA L N :

    T Y P E / S E R IA L N :E L E C T R IC A L T E S T S ( C A B L E D IS C O N N E C T E D )

    U PS T R EA M C O N N EC T IO N A C C O R D IN G C A B L E S C H ED U L E

    D O W N S T R EA M C O N N EC T IO N A C C O R D IN G C A B L E S C H ED U L E

    C R O S S S EC T IO N A C C O R D IN G C A B L E S C H ED U L E

    P H 1

    P H 2

    P H 3A R M O U R C O N T IN U IT Y

    PR O T EC T IV E C O N D U C T O R C O N T IN U IT Y

    P H 1 / P H 2 - P H 3 - E

    P H 2 / P H 1 - P H 3 - E

    P H 3 / P H 1 - P H 2 - E

    C O R E / A R M O U R M o h m

    C A B L E IS C O R R EC T L Y R E- C O N N EC T ED .

    N o te : T h e M in im u m A c c e p ta b le V a lu e W ill b e : * 4 4 0 V c a b le s - 5 0 M o h m - 1 0 0 0 v M e g g e r * 2 4 0 V c a b le s - 1 0 M o h m - 5 0 0 v M e g g e r

    ( M o h m )

    ( M o h m )

    ( M o h m )

    C O R ES / EA R T H M o h m

    IN S U L A T IO N

    C O R E C O N T IN U IT Y

    C O N T IN U IT Y

    S i g n

    T P A / C O M P A N YC O M M IS S IO N IN GC O N S T R U C T IO NS U B C O N T R A C T O R

    D a t eN a m e

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 22 of 23

    9.2. Appendix02: Electrical Earthing / Lightning System (T-PX-26)

    1.

    T a s k N u m b e r :F o r m :D w g / P ID :

    T a s k L o c a t i o n : U s e r G r o u p :E s t i m a te d T i m e ( M H ) : E x p e n d e d T i m e ( M H ) :P u n c h L i s t I te m s :M o d u le :S u b s y s t e m :

    T P X 2 6 - E A R T H I N G S Y S T E M

    P R E C O M M IS S IO N IN G T E S T S H E E TE L E C T R I C A L

    E A R T H IN G / L IG H T N IN G S Y S T E M

    0

    2.

    T E S T I N G I N S T R U M E N T S U S E D

    T Y P E / S E R I A L N : T Y P E / S E R I A L N :

    T Y P E / S E R I A L N :

    T E S T R E S U L T S

    G L O B A L E A R T H I N G R E S I S T A N C E O h m T E S T C U R R E N T A

    E A R T H I N G R O D R E S I S T A N C E O h mE A R T H I N G / L I G H T N I N G E L E C T R O D S A R E T O B E T E S T E D I N D I V I D U A L L Y A N D A S A G R O U P

    * I N D I V I D U A L L E L E C T R O D E R E S I S T A N C E :N o . 1 : . . O h m N o . 2 : . . O h m

    N o . 3 : . . O h m N o . 4 : . . O h m

    * I N D I V I D U A L L G R O U P R E S I S T A N C E A S A P P L I C A B L E : . . O h m

    D R A W I N G N A S S O C I A T E D

    C A B L E N L O O P

    R E S I S T A N C EE A R T H D I S P A T C H E R (T O )E Q U I P M E N T N (F R O M )

    3.

    S i g n

    C O M P A N YC O M M I S S I O N I N GC O N S T R U C T I O NS U B C O N T R A C T O R

    D a t eN a m e

  • OilIndustriesEngineeringandConstruction

    NATIONAL IRANIAN OIL COMPANY

    South Pars Gas Field Development Phases 20 & 21

    DOCUMENT TITLE DOCUMENT No. Rev.: 0 Class: 1 Earthling System Electrical and Instruments Test Procedure Test

    Procedure TOT-SP2021-ON-CO-999-P332-0015 Page 23 of 23

    9.3. Appendix03: Electrical Earthing (C-PX-26)

    T a s k N u m b e r :

    I T E M

    P R E C O M M IS S IO N IN G C H E C K L IS TE L E C T R I C A L

    E A R T H IN G S Y S T E M

    T a s k L o c a t i o n :

    S u b s y s t e m :

    C P X 2 6 - E A R T H I N G S Y S T E M

    U s e r G r o u p :

    E s t i m a te d T i m e ( M H ) : E x p e n d e d T i m e ( M H ) :

    C H E C K L I S T

    F o r m :

    M o d u le :

    1

    2

    3

    4

    5

    6

    7

    8

    9

    1 0

    1 1

    1 2

    1 3

    1 4

    1 5

    1 6

    1 7

    1 8

    1 9

    2 0

    2 1

    N / A N o t A p p l i c a b l e P N o t a c c e p te d ( P u n c h ) C h e c k e d & A c c e p te dD r a w in g s & d o c . r e f . :

    R E M A R K S :

    P r o d u c e m a r k e d - u p d r a w i n g s i n a c c o r d a n c e w i th i n s ta l l a t i o n .

    C h e c k L i g h tn i n g a i r te r m i n a l i n s ta l l e d a s p e r th e D r a w i n g s /S p e c i f i c a t i o n .

    P r o d u c e a d e fe c ts l i s t fo r p u n c h l i s t i s s u e .

    C h e c k e a r th i n g / l i g h tn i n g W e l l ( P i t ) l o c a t i o n a s p e r d r a w i n g s .

    C h e c k c o n n e c t i o n e a r th c a b l e / e l e c t r o d e b e fo r e b a c k f i l l i n g .

    C h e c k c o n t i n u i ty e l e c tr o d e - e a r th b a r / p l a n t e a r th r i n g .

    C h e c k c o n t i n u i ty e l e c tr o d e - e a r th p i t to e a r th b a r .

    C h e c k c o n t i n u i ty o f e q u i p m e n t l o o p p r o te c t i o n c o n d u c to r s .

    C h e c k e a r th i n g n e tw o r k s s e g r e g a t i o n ( IS )

    C h e c k e a r th r o d s c o r r e c t i n s ta l l a t i o n

    C h e c k a l l e a r th b a r s i n s ta l l a t i o n a n d ta g g i n g a g a i n s t d r a w i n g s .

    C h e c k e a r th i n g c a b l e s i n s ta l l a t i o n a n d ta g g i n g a g a i n s t d r a w i n g s .

    C h e c k a l l c o n n e c t i o n s a r e t i g h t , c l e a n a n d c o a te d w i th a n a p p r o v e d a n t i - c o r r o s i v e g r e a s e .

    C h e c k e a r th i n g c a b l e s c r o s s s e c t i o n a g a i n s t d r a w i n g s .

    C h e c k d i s p a tc h e r c o n t i n u i ty a n d d r a w i n g .

    C h e c k v i s u a l i n s p e c t i o n b e fo r e b a c k f i l l i n g .

    C h e c k th e r m a l c o n n e c t i o n i n s u l a t i o n .

    C h e c k th e r m a l c o n n e c t i o n b e fo r e b a c k f i l l i n g .

    C h e c k r i s e r c o n d u i t i n s ta l l a t i o n w i th r e l a te d d r a w i n g .

    C h e c k c o m p r e s s i o n o f c o n n e c t i o n s .

    C h e c k i n s u l a t i o n o f c o m p r e s s i o n c o n n e c t i o n s .

    D a t eN a m e

    S i g n

    T P A / C O M P A N YC O M M I S S I O N I N GC O N S T R U C T I O NS U B C O N T R A C T O R