Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs...

26
Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50 PM Content Area: Project Systems
  • date post

    19-Dec-2015
  • Category

    Documents

  • view

    215
  • download

    0

Transcript of Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs...

Page 1: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Earned Value Managementmade Simple

Keith Lee, SAP Systems Integration AmericaJay Wilson, SAP Labs

Session 3802Monday May 19, 200311:20 AM to 12:50 PM

Content Area: Project Systems

Page 2: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Objectives

Understand Basics of Earned Value Management Systems (EVMS)

Understand SAP/R3 approach to EVMS

Learn Simple steps to configure EVMS in SAP/R3

Become Aware of Options to approaching EVMS in SAP/R3

Page 3: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Earned Value Management is the analysis of work completed compared compared to the amount of work planned and the cost of the work.

Simple example: The task is creating a 10 foot Wall and takes $1000 (material and labor)

1. Prepare Ground – 10%2. Pour Concrete Base – 20%3. Every foot of wall – 7%

In this example, when completed with the first 2 steps and 3 feet of wall the amount of work complete is 30% + 21% = $510.

What is Earned Value?

Page 4: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

What is Earned Value?

• There are lots of ways to measure Earned Value.

• The wall example uses a combination of milestones (first 2 steps) and counts (feet of wall)

• The simplest approach is to use “estimate”. I am 70% complete because I say so.

Page 5: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Why use EVMS?

• Given: – total budget of $1000– 5 months effort– produce 10’ brick wall

• Status:– spent to date: $700– time elapsed: 4 months– Wall in process

• How are you doing, and how do you know how you are doing?

• How far along are you? (75%, 50%, >40%)

Life without EVMS

Page 6: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Why use EVMS?

• Early and accurate identification of trends and problems

• Accurate picture of contract status– cost, schedule, and technical

• Basis for course correction• Supports mutual goals of contractor and

customer– bring project in on schedule and cost

Page 7: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Five Basic Elements

BCWS Budgeted Cost of Work Scheduled

BCWP Budgeted Cost of Work Performed

ACWP Actual Cost of Work Performed

BAC Budget at Completion

EAC Estimate at Completion

Page 8: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

A Spectrum of Implementation

Where

When

Core EV PrinciplesANSI/EIA-748-1998

(32 criteria)Tailored Applications

Small Companies Larger Companies

Major Defense

Contractors

as desired

Government Organic

Reports

Foreign Countries

streamlined, no paper?

corporate policy,

“enterprise wide”

DoD Non-Major Contracts

(>12 months)

<$6M* >$6M

DoD Major Contracts

>$70M RDT&E

>$300M Prod

tailored to needs C/SSR CPR

FFP contracts?

Commercial or Defense

Page 9: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

SAP Approach to EVMS

• Integrated with all financials and schedule.

Page 10: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

SAP Approach to EVMS

• Calculate both BCWS and BCWP based on a “Baseline” cost Plan using an Earned Value Method.

Period Plan $ BCWS % BCWP % BCWS $ BCWP $1 300$ 30% 10% 300$ 100$ 2 150$ 15% 20% 150$ 200$ 3 200$ 20% 14% 200$ 140$ 4 200$ 20% 7% 200$ 70$ 5 150$ 15% 150$

Page 11: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

SAP Approach to EVMS

• Calculate ALL elements of cost for an object using the same percentage

Period Plan Mat $ Plan Lab $ BCWP % BCWP Mat $ BCWP Lab $1 200$ 100$ 10% 35$ 65$ 2 50$ 100$ 20% 70$ 130$ 3 50$ 150$ 14% 49$ 91$ 4 50$ 150$ 7% 25$ 46$ 5 -$ 150$

Page 12: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

CONFIGURATION

• Statistical Key Figures (SKF’s)– Use SKF’s to store the planned and actual percent

complete• Versions – Baseline, Progress, EAC, …• EV Methods

– Methods can be tailored and named to suite the client• EV Cost Elements

– Create cost elements that summarize the planned cost elements into groups (ex: Engineering labor, Manufacturing Labor, Materials, G&A, …)

• Value Categories– Make Value categories consistent with the EV cost

elements for ease of reporting

Page 13: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

3 different SKF’s are required

Aggrigated – Summary of all percents up the structure based on weighting

Non-Aggrigated – the individual object’s percent complete

Results Analysis – Percent complete used in results analysis (revenue recognition based on EV)

SKF Configuration

Page 14: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Version Configuration

Page 15: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Version Configuration

Page 16: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

EV Methods Configuration

Page 17: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

EV Cost Elements

Page 18: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

EV Cost Elements

Page 19: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Value Categories

Cost Element group should containAll normal cost elementsANDThe earned value cost element

This is the same cost element group as associated with the EV cost element

Page 20: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

A Simple Example

• With these few basic configuration settings it is now possible to do Earned Value.

• Now let’s see a simple example– A project with 1 network activity that is 40%

complete– Run EV using CNE1 (Calculate Progress)– See the results

Page 21: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Project Example

Page 22: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Calculate Earned Value

Page 23: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Report

Page 24: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

40% of BCWS

Report

What is the good news?What is the bad news?

Page 25: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Questions

Page 26: Earned Value Management made Simple Keith Lee, SAP Systems Integration America Jay Wilson, SAP Labs Session 3802 Monday May 19, 2003 11:20 AM to 12:50.

Thank you for attending!

Please remember to complete and return your evaluation form following this session.

Session Code: 3802Keith Lee – [email protected] Wilson – [email protected]