Earned Value Management
description
Transcript of Earned Value Management
![Page 1: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/1.jpg)
Earned Value Management
How to apply Earned Value Management to
measure the Performance of your Project
alphaPM Inc. www.alphaPM.com
![Page 2: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/2.jpg)
2
PROJECT MILESTONESPlanned
DatePlanned
DateNotes
Develop Strategy and Vision
Establish Readiness and Blueprint
Identify Business and User Goals
Document Project Scope
Prepare Detailed Requirements
Build and Test
Launch
Project Issues/Risks Mitigating Actions To Be Taken
Project Performance Tracking (Project Dashboard)
![Page 3: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/3.jpg)
How To Earned Value Management Overview
Earned Value Management (EVM) is a management methodology for integrating scope, schedule and resources, and for objectively measuring project performance and progress.
Performance is measured by determining the budgeted cost of work performed (i.e. earned value) and comparing it to the actual cost of work performed (i.e. actual cost).
Progress is measured by comparing the earned value to the planned value.
Source: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 2004
Example:
Project Budget: $400K
Project Schedule: 4 months (= Baseline Duration)
At the 3 month checkpoint:
Spent: $200K
Work completed: $100K
Earned Value Management helps you to report how the project is doing in terms of cost and schedule?
![Page 4: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/4.jpg)
Earned Value ManagementTerms and Formulas
Terms and Formulas Alternative Definition
Earned Value (EV) Budgeted Cost of Work Performed (BCWP)i.e. the budgeted cost to date x % complete
Actual Cost (AC) Actual Cost of Work Performed (ACWP)
i.e. actual cost of work performed to date
Planned Value (PV) Budgeted Cost of Work Scheduled (BCWS) i.e. the estimated value of work to be performed
Cost Variance (CV)= EV - AC
Budgeted Cost of Work Performed (BCWP) - Actual Cost of Work Performed (ACWP)
Schedule Variance (SV)= EV - PV
Budgeted Cost of Work Performed (BCWP) - Budgeted Cost of Work Scheduled (BCWS)
Cost Performance Index (CPI) = EV/AC
Budgeted Cost of Work Performed (BCWP)/ Actual Cost of Work Performed (ACWP)
Schedule Performance Index (SPI) = EV/PV
Budgeted Cost of Work Performed (BCWP)/Budgeted Cost of Work Scheduled (BCWS)
Example
$100K
$200K
$300K
$100K – $200K = ($100K)
$100K - $300K= ($200K)
$100K/$200K= 0.5 i.e. 50%
$100K/$300K= 0.33 i.e 33%
Example:Project Budget: $400KProject Schedule: 4 months
At the 3 month checkpoint:Spent: $200KWork completed: $100K
Revised Total Duration Baseline Duration/Schedule Performance Index4/0.33
= 12 months
![Page 5: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/5.jpg)
0
100
200
300
400
500
600
700
800
J F M A M J J A S O N D
Budget
3 MonthCheckpoint
PV
Earned Value ManagementChart for project example
Actual Cost
Earned Value
CV = EV – AC = (100K)
SV = EV – PV = (200K)
CPI = EV/AC = (50%)
SPI = EV/PV = (33%)
Example:
Project Budget: $400K
Project Schedule: 4 months
At the 3 month checkpoint:
Spent: $200K
Work completed: $100K
Revised Total Duration = Baseline Duration/SPI = 4/0.33 = 12 months
![Page 6: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/6.jpg)
How To Exercise
Report the Performance for the Project at the 10 day point. (Assume a labour rate of $1,000/day)
Step 1: Determine the value of the three variables needed to measure the project performance at the 10 day point (all activities are sequential)
Planned Value: PV =
Earned Value: EV =
Actual Cost AC =
Click here when youhave your answer
Planned Value: PV = $10,000 {2,000 + 4,000+ 4,000 since Jim should have completed 4 days of coding at the 10 day point}
Earned Value: EV = $9,000 {2,000 + 4,000 + 3,000 since Jim is only 30% complete}
Actual Cost: AC = $12,000 (4,000 + 3,000 + 5,000 since that is the actual amount that all have spent}
Activities Owner Planned Effort
(Days)
Budget(Planned Value)
$
ActualEffort
(As of Day 10)
Actual Cost(As of Day 10)
$
Status
(As of Day 10)
Prepare Plan John 2 $2,000 4 $4,000 Completed
Design Solution Susan 4 $4,000 3 $3,000 Completed
Code Programs Jim 10 $10,000 5 $5,000 30% of all work completed
Test Programs Debbie
2 $2,000 Not started
Deploy into Production Brad 2 $2,000 Not started
Total 20 $20,000
![Page 7: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/7.jpg)
How To Exercise (continued)
Report the Performance for the Project at the 10 day point. (Assume a labour rate of $1,000/day)We now know that Planned Value (PV) = $10,000
Earned Value (EV) = $ 9,000 Actual Cost (AC) = $12,000
Step 2: Calculate the Earned Value Performance Indices
Cost Performance Index (CPI): CPI = EV/AC
Schedule Performance Index (SPI): SPI = EV/PV
Click here when youhave your answerCost Performance Index (CPI): CPI = EV/AC = $9.000/$12,000 = 0.75 or 75%
Schedule Performance Index (SPI): SPI = EV/PV = $9,000/10,000 = 0.90 or 90%
Activities Owner Planned Effort
(Days)
Budget(Planned Value)
$
ActualEffort
(As of Day 10)
Actual Cost(As of Day 10)
$
Status
(As of Day 10)
Prepare Plan John 2 $2,000 4 $4,000 Completed
Design Solution Susan 4 $4,000 3 $3,000 Completed
Code Programs Jim 10 $10,000 5 $5,000 30% of all work completed
Test Programs Debbie
2 $2,000 Not started
Deploy into Production Brad 2 $2,000 Not started
Total 20 $20,000
![Page 8: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/8.jpg)
8
PROJECT MILESTONESPlanned
DatePlanned
DateNotes
Develop Strategy and Vision
Establish Readiness and Blueprint
Identify Business and User Goals
Document Project Scope
Prepare Detailed Requirements
Build and Test
Launch
Project Issues/Risks Mitigating Actions To Be Taken
Project Performance Tracking (Project Dashboard)
![Page 9: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/9.jpg)
An Easy Way to Remember the Formulas
Fou
r F
orm
ulas
S
C
S
C
Three Variables: EV PV AC
![Page 10: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/10.jpg)
An Easy Way to Remember the Formulas
Three Variables: EV PV AC
Fou
r F
orm
ulas
SV
CV
SPI
CPI
EV
EV
EV
EV
-
-
=
=
=
=
/
/
P
A
P
A
![Page 11: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/11.jpg)
An Easy Way to Remember the Formulas
Three Variables: EV PV AC
Fou
r F
orm
ulas
SV
CV
SPI
CPI
EV
EV
EV
EV
-
-
=
=
=
=
/
/
PV
AC
PV
AC
![Page 12: Earned Value Management](https://reader035.fdocuments.in/reader035/viewer/2022070416/568150eb550346895dbf0416/html5/thumbnails/12.jpg)
Earned Value Management
How to apply Earned Value Management to
measure the Performance of your Project
alphaPM Inc. www.alphaPM.com