E3: Evolution of Empowering Employees Nicholas Calaceto - James Lau Mechanical Engineer - Associate Product Manager RAB Lighting

Transcript of E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New...

Page 1: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

E3: Evolution of Empowering Employees

Nicholas Calaceto - James LauMechanical Engineer - Associate Product Manager

RAB Lighting

Page 2: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Lighting Solutions

Page 3: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

New Product Development Process

• Spec creation to launch

• 10 Departments affected

Page 4: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.
Page 5: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

What was the problem?No visibility of processes

Products not launching on time

“Fire fighting” problems

No metrics

Previous lean events

Lack of priority

Reactive instead of proactive

Page 6: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

How did we start to tackle the

problem?Spoke to each department

Broke down the VSM

Got help for numbers

Mapped it out

Page 7: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Value stream map visualization

Page 8: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

How did we plan to fix the

problem?

• Daily stand ups

• Phase meetings

• Creating phases

• Defining nomenclature

• Formatting view of process

Page 9: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Developing a New Tool

Page 10: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Implementation

Sprints

Scrum

Standard work

Training

Page 11: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Challenges

SW not followed

Physical stand ups

Old processes

Lack of visibility

No buy in

Didn’t want extra work

Department silos

Page 12: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

How did we overcome the

challenges?

Old processes: Tested new method and got buy in

Lack of visibility: Insight into processes, showed it was to help not hinder

No buy in: Support from the top

Didn’t want extra work: Keep things simple and automated

Department silos: Gave visibility to everyone

Page 13: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

How are we doing?

• Phase meetings

• Garbage in, garbage out

• Responsibility confusion

• Project ownership

• Project L/T went from 317

days to 260

Page 14: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Current State

0%

20%

40%

60%

80%

100%

120%

Phase OTD Team Engagement C&A of Dashboard Project L/T

Actual Goal

Page 15: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

• Phase OTD 18%

• Quick experiments failing

• Work load

Page 16: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

• Project Management

• Feedback session

• Consolidated information

Page 17: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

As clear as a bus schedule

Change from real product to fake product

Page 18: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Project

Management

Communication

Accountability

Accomplishments

Standard

Process

Teams

Page 19: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

0%

20%

40%

60%

80%

100%

Jan-17 Feb-17 Mar-17 Apr-17 May-17

Phase OTD Year-to-Date

Page 20: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

LDM Boards

Meeting cadence

Standard Work

Sustainment

Page 21: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Remove department silos

Reduce oversight

Clarity

Reduced lead time

Future State

Page 22: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Patience

Training, training, training, training

Realigning priorities

No data? Get some!

Quick failures are great!

Lessons Learned

Page 23: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Team Effort

Page 24: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Questions

Page 25: E3: Evolution of Empowering Employees · 2017. 10. 4. · RAB Lighting. Lighting Solutions. New Product Development Process • Spec creation to launch • 10 Departments affected.

Thank You! Your opinion is important to us!

Please take a moment to complete the survey using the conference mobile app.

Session No: ThS/51

E3: Evolution of Empowering Employees

Nicholas Calaceto & James Lau

RAB Lighting

[email protected]

[email protected]