E. Hazen, Boston University BU Meeting, Apr. 6, 2001 Front-end Readout of the CMS Hadronic Forward...
-
date post
22-Dec-2015 -
Category
Documents
-
view
213 -
download
0
Transcript of E. Hazen, Boston University BU Meeting, Apr. 6, 2001 Front-end Readout of the CMS Hadronic Forward...
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Front-end Readout of the CMS Hadronic Forward Calorimeter (HF)
Conceptual Design (Summary)
by
Eric Hazen and Jim Rohlf
Boston University
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Summary• 9U modules (6 readout cards each) are cost-effective,
manageable way to package the HF readout• Total of 8 crates, each with 9 readout modules
(72 modules needed)• Controller module uses the standard TIMING, SERIAL
and TEMP cards (8 needed)• WBS contains only 54 modules but cost per unit is
“reasonable” need to add 26 modules + spares• Schedule is strongly influenced by arrival of first
readout and control cards
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Cost Comparison: RBX vs. VMERBX Scheme (WBS hcal_Apprvd_Dec00_rev1)
Boxes 20 $11,278 $225,556Backplanes 20 $1,131 $22,611Pwr supply 6 $3,444 $20,667
$268,833 TOTAL
VME SchemeModules 10 $1,382 $13,820Crate 1 $7,471 $7,471
$21,291 per cratefull crates 8 $21,291 $170,328 TOTAL
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Production Cost Comparison: WBS vs. Conceptual Design
2.5.5.6.2modules 54 $1,382 $74,6142.5.5.8 crates 4 $11,798 $47,192
$121,806 TOTAL
Conceptual Designmodules 80 $1,382 $110,560crates 8 $7,471 $59,768
$170,328 TOTAL
* Cost based on quotes for DCC modules
*
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
For comparison:Production cost of DCC Motherboard
PCB $590hardware $35components $750assembly $400
$1,775 TOTAL
plus about $4600 one-time charges per design iteration
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Development Schedule (WBS)ID Task Name
1 VME Modules
2 VME Module Development
3 VME Module Requirements Report
4 VME Module Design Report
5 VME Module Design
6 VME Module Design Engineering
7 VME Module Design Layout
8 VME Module Technical Support
9 VME Module Prototype
10 VME Module Prototype Acquisition
11 VME Prototype Assembly
12 VME Module Test Stand
13 Design Engineering
14 VME Module Test Stand Acquisition
15 VME Module Software Development
16 VME Module Production
17 VME Module Acquisition
18 VME Module Spares
5/9
engineer - boston - FY97
engineer - boston - FY00
engineer - boston - FY00
technician - Boston - FY00
VME Module Prototype (HF)/1 each[200%]
VME Module Prototype Assembly (HF)/1 each[2
engineer - boston - FY97[50%]
VME Module Test Stand (HF)/1 each
postdoc-fermilab-TBN
VME Module Production (HF)/10 each[540%]
VME Module Production (HF)/10 each[167%]
VME Module Components (HF)/1 each[5,400%]
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2002
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Development Schedule (New)ID Task Name Duration
1 VME Modules 445 days
2 VME HF Module Development 153 days
3 VME Module Requirements Report 0 days
4 VME Module Design Report 5 days
5 VME Module Design 50 days
6 VME Module Design Engineering10 days
7 VME Module Design Layout 20 days
8 VME Module Technical Support 20 days
9 VME Module Prototype 60 days
10 VME Module Prototype Acquisition20 days
11 VME Prototype Assembly 20 days
12 VME Module Test Stand 35 days
13 Design Engineering 5 days
14 VME Module Test Stand Acquisition20 days
15 VME Module Software Development30 days
16 VME Module Production 292 days
5/9
engineer - boston - FY97
engineer - boston - FY00
engineer - boston - FY00
technician - Boston - FY00
VME Module Prototype (HF)/1 each[
VME Module Prototype A
engineer - boston - FY97[50%]
VME Module Test Stand (HF)/1 ea
postdoc-fermilab-TBN
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2002
Note: Detailed design cannot start until FE card design is complete
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Readout Options1) HB readout boxes
• Internal water cooling• Severe cabling problems for HF• Expensive (compare later)
2) HB readout cards in custom crates with FNAL backplane • Must engineer entire crate!
3) HB readout cards in 3U crates• Non-standard card spacing requires a custom
backplane to make any sense• Multiple crates per quadrant
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Readout Options, cont.
4) 9U standard VME* crate with readout cards as daughterboards
This option is our preferred choice on the basis of both ease of implementation and cost
* VME Bus not used except possibly for diagnostics
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
2448 Channels (includes “ECAL” & “TC”) 1224 Channels per end 306 Channels per quadrant (4 crates on each end)
51 Readout cards per crate(6 QIE per card)
HF Channel Count
306
306
306
306
need 51 Readout cards per crate
306 = 9 x 34
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
One HF Module per PMT Box
(to scale!)
Backup OnlyBackup Only
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
HF Readout Module
External coax cabling from PMT input to readout card (36 total)
Multisignal microcoaxconnector
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
HF Crate Layout (8 total)
TTCin
CAN bus
RBX busFiber out
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Each Crate has:• One controller• 9 readout modules (324 channel capacity)• “RBX bus” inter-card connection via front
panel cables• 306 input signal cables• Connector panel on or near back of crate
where larger coax is converted to micro-coax
• 18 front panel 9-fiber optical connectors for output
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
HF Readout Module (summary):• 36 input cables
(possibly an Axon multi-microcoax connector)• External coax cabling to each of 6 readout cards• Internal “RBX bus” at center of card, so that digital
operations occupy adjacent real estate• “RBX bus” cable input on front panel• Two 9-fiber optical connectors on the front panel for
output to the HTR• Power and system reset via 3U VME backplane (J1)
E. Hazen, Boston UniversityBU Meeting, Apr. 6, 2001
Controller Motherboard:• Three controller daughter cards,
Timing, Serial and Temperature
• One TTC front-panel fiber connector (input)
• Nine cat-5 front-panel connectors to distribute “RBX bus” to readout modules
(4-pin + 5-pin or 10-pin)
• One 9-pin D-type front-panel CAN bus connector