Dynamics AX 2009 MRP training

54
OAD Dynamics AX 2009 Training: Master Plan

description

Master planning training for Dynamics AX 2009

Transcript of Dynamics AX 2009 MRP training

Page 1: Dynamics AX 2009 MRP training

OADDynamics AX 2009 Training:Master Plan

Page 2: Dynamics AX 2009 MRP training

Agenda

Master Plan Overview

Parameters Setting

Master Scheduling

Forecast Scheduling

Items Coverage

Planned Order

Page 3: Dynamics AX 2009 MRP training

Master Plan Overview

Page 4: Dynamics AX 2009 MRP training

Dynamics AX Master Plan Position

Materials Requirements Planning(MRP)

CapacityRequirements Planning(CRP)

Microsoft Dynamics AXMaster Plan

• Materials Planning• Finite Materials• Items Dimensions• Lead Time• BOM structure• ……

• Work Center• Work Capacity• Finite Capacity• Job Scheduling• …….

Page 5: Dynamics AX 2009 MRP training

Multi-sites Master Plan

Page 6: Dynamics AX 2009 MRP training

Generous Flow in Master Plan

Item MasterSetting

Item Coverage

RunMasterPlan

SetupMaster

Plan

ParametersSetting

PlannedPurchase

Order

PlannedProduction

Order

PlannedTransfer

Order

PurchaseOrder

ProductionOrder

TransferPlan

Optional

Page 7: Dynamics AX 2009 MRP training

ParametersSetting

Page 8: Dynamics AX 2009 MRP training

Master Plan Setup ParametersGeneral Tag

1

2

3

Page 9: Dynamics AX 2009 MRP training

1. 1 Static Master Plan

Calculate requirements based on current data.

The plan remain unchanged until next static master plan running.

It is an operation plan most likely run by purchaser or production planner.

Page 10: Dynamics AX 2009 MRP training

1.2 Dynamics Master Plan

Calculate requirements based on net requirements.

It is an sales plan most likely run under the changing of sales order.

Page 11: Dynamics AX 2009 MRP training

1.3 Dual Plan

Single plan (both static and dynamics are the same plan) and Dual plan (use different plan for static and dynamics).

Dual plan is used while sales simulation without affecting current results.

Single plan is used when the sales simulations is usually firmed to planned order.

Page 12: Dynamics AX 2009 MRP training

2.1 General Coverage Group

It is default item coverage group in running master plan when item has not defined Item coverage group.

Priority:

Item Coverage >> General Coverage Group

Page 13: Dynamics AX 2009 MRP training

2.2 Future Time

If receipt time > future time, one day will be added in future day (planned day).

E.g.

Page 14: Dynamics AX 2009 MRP training

3. Today date

Running master plan based on this calendar.

User can select different calendar and run master plan.

Page 15: Dynamics AX 2009 MRP training

4

Master Plan Setup ParametersPlanned Order Tag

Page 16: Dynamics AX 2009 MRP training

4.1 Find Trade Agreement

Search vendor either in lowest price or shortest lead time when running master scheduling.

Page 17: Dynamics AX 2009 MRP training

4.2 Receipt Time

Automatically assigned to planned production order.

If receipt time > future time, future message will be generated.

User can choose amend delivery date (receipt date of planned order) as future date.

Page 18: Dynamics AX 2009 MRP training

Master Plan Setup ParametersStandard Update tag

5

Page 19: Dynamics AX 2009 MRP training

5.1 Group by Vendor/ buyer / Period

Group planned purchase order by vendor / buyer / period.

Page 20: Dynamics AX 2009 MRP training

MasterPlan

Page 21: Dynamics AX 2009 MRP training

Master Plan Setup Plans Master PlanStandard Update tag

6

7

8

Page 22: Dynamics AX 2009 MRP training

6 Include criteria

User can include following criteria in master plan:

- On hand

- Inventory Transaction

- Sales Quotation (include %)

- RFQ

- Forecast Plan

Page 23: Dynamics AX 2009 MRP training

7.1 Scheduling Method

Operation Scheduling

- Production will be scheduled in work center group and date

Job Scheduling

- Production will be scheduled in work center and time

Page 24: Dynamics AX 2009 MRP training

7.2 Time fence (I)

Background capacity time fence

- Search for capacity which available

- usually 0 (search to today) Finite capacity

- Time fence for finite production scheduling Bottleneck capacity

- Time fence for bottleneck resources

Normally, finite capacity for short-term scheduling and bottleneck capacity for middle term scheduling

Page 25: Dynamics AX 2009 MRP training

8. Forecast Plan

Forecast Plan: link to forecast plan Reduction Key: used to reduce forecast

amount in future Alternative: set reduction principle in

master plan

Page 26: Dynamics AX 2009 MRP training

Master Plan Setup Plans Master PlanTime Fence tag

9

Page 27: Dynamics AX 2009 MRP training

9. Time fence (II)

Coverage: time fence for master plan cover

Freeze: will not create planned orders in this period

Firming: will automatically generate purchase / production order

Explosion: will explore BOM item in this period

Page 28: Dynamics AX 2009 MRP training

Con’t

Forecast Plan: Consider forecast in this time period.

Capacity: Consider working capacity for this period

Action Message: Time fence to consider action date

Future Message: Time fence to consider possible future date.

Page 29: Dynamics AX 2009 MRP training

Master Plan Setup Plans Master PlanFuture Message tag / Action Message tag

10

11

Page 30: Dynamics AX 2009 MRP training

10. Future Message

Update planned production / purchase / transfer order

- Update delivery date to possible future date

- e.g.

Page 31: Dynamics AX 2009 MRP training

11. Action Message

Update delivery date to date which nearest requirement datee.g.

Page 32: Dynamics AX 2009 MRP training

Master Plan Setup Plans Master PlanSafety Margin tag

12

Page 33: Dynamics AX 2009 MRP training

12. Safety Margin

Receipt Margin

- Additional time for purchase receipt Issue Margin

- Deduce issue requirements (Sales Order) from master scheduling

Reorder Margin- Additional lead time for purchase in master

scheduling

Page 34: Dynamics AX 2009 MRP training

Forecast Scheduling

Page 35: Dynamics AX 2009 MRP training

Forecast plan overview

Forecast Plan

Forecast Scheduling

Forecast Model 1

ForecastModel 2

Forecast Model n

………

ITEMs

Page 36: Dynamics AX 2009 MRP training

Inventory Management Setup Forecast Forecast ModelForecast Model

Page 37: Dynamics AX 2009 MRP training

13

Page 38: Dynamics AX 2009 MRP training

13. Forecast Model

Arrange sub-model for the forecast model Run forecast plan using upper forecast

model

Page 39: Dynamics AX 2009 MRP training

Master Plan Setup Forecast PlansForecast Plan

14

Page 40: Dynamics AX 2009 MRP training

14. Define the forecast plan

User can select whether forecast plan include sales/purchase forecast

Select forecast model the forecast plan apply to.

Page 41: Dynamics AX 2009 MRP training

Inventory Management Periodic Forecast Item EntryItem

15

Page 42: Dynamics AX 2009 MRP training

15. Define forecast

Model: Define which forecast model to be run

Customer Account / Group: Create customer-based forecast

Item Allocation Key: allocate item ratio to item group

Sales Quantity: forecast Qty for 1 unit per forecast

Allocation: Set length of forecast period

Page 43: Dynamics AX 2009 MRP training

Item Coverage

Page 44: Dynamics AX 2009 MRP training

Inventory Management Periodic Forecast Item EntryItem

1415

16

Page 45: Dynamics AX 2009 MRP training

14. Coverage

Coverage plan: Days coverage in this group

Coverage code:

- Period

- Requirements

- Min.Max

Page 46: Dynamics AX 2009 MRP training

Con’t

Period: consolidate requirements by period

Requirements: Driven by sales order / forecast

Min/ Max: Safety stock

Page 47: Dynamics AX 2009 MRP training

15. Positive & Negative Days

Positive days: Days of period not issue PO under positive requirements

Negative days: Days of period not issue PO under negative requirements

Page 48: Dynamics AX 2009 MRP training

16. Others

BOM version requirements: Requirements by BOM version.

Route Version requirements: Different route will be taken consideration in coverage planning

Page 49: Dynamics AX 2009 MRP training

Planned Order

Page 50: Dynamics AX 2009 MRP training

Master Plan Periodic Forecast Plan / Master Plan

17

Page 51: Dynamics AX 2009 MRP training

17. Planned Order

Select master plan / forecast plan to run Planned order will be generated Release planned purchase order /

production order / transfer order in

“ Master Plan Place Planned”

Page 52: Dynamics AX 2009 MRP training

Lab

Please follow the instruction sheet.

Page 53: Dynamics AX 2009 MRP training

Q & A