DVALIN FIELD DEVELOPMENT
Transcript of DVALIN FIELD DEVELOPMENT
GENERAL INFORMATION
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 7
• Located NW of Heidrun
• Tieback to Heidrun
• Production through Polarled to Nyhamna
• Discovered 2010 / 2012
• Partners:
• Petoro (35%)
• Edison Norge (10%)
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020
DVALIN D&W ORGANIZATION
PAGE 11
WELLSITE
Logistics CoordinatorThomas Søreide
HSEQ AdvisorAnne Mork
TransoceanTom Sande
Operations Geologist
Kristian Tellefsen
Drilling Superintendent
Mark Gast
Cost ControllerAngus Bruce
Procurement CoordinatorThomas Evjen
Aker SLSNils Nagevik
Drilling EngineerTrenton Hirsch
Rig Intake Bjørn Engeseth
Well Team LeadJens Storhaug
Drilling ManagerTore Øian
Completions EngineerRobert Ritschel
Well Test / Completion Engineer
Duncan Bertram
Sr. Subsea EngineerScott Wood
Sr. Completions Engineer
Garbhan Gibbons
Sr. Drilling SupervisorBjørn Engeseth, Per Martin Kleven,
Guy Coleman
Drilling SupervisorRobert Ritschel, Henrik Grønne, Håkon Vatnebryn, Per Atle Flytle
Drilling EngineerIda Mo, Stefan Sonntag,
Karim Soliman, Denise Karlsen
Sr Drilling EngineerPiotr Byrski
GeologistDavide Duranti
Production Engineer
Reidar Birkeland
Subsurface Manager
Neal Hughes
PetrophysicistGeorge Lawrence
GeophysicistManuel Gelhaus
Reservoir Engineer
Eirik Jensen
Wellsite GeologistCompletion Engineer
Subsea EngineerPerformance Coach
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 12
Challenges• SR capacity
• Boost pressure facility removed by OEM• VDL capacity
• Heavy mud and 9 7/8 casing• Fluids capacities
• 2x mud systems, slops and brine• SPP limited to 5000 psi• Crane capacity vs heavy lifts
Highlights• Established CMS and SMS• Reliable personnel and equipment• Low operational cost• Low WOW cost
DVALIN DRILLING RIG – TO ARCTIC
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 13
TO ARCTIC – RIG INTAKE AND MODIFICATIONSRIG INTAKEConducted jointly with Cairn Utilised integrated DEA/Cairn rig intake document Included OWS and XT equipment integration testing
RIG MODIFICATIONSUpgrade XT skid and elevator to 110t
- Existing system rated to 70t – EDP/LRP assy weighs 100tModify cellar deck XT storage area
- To accommodate Dvalin XT and EDP/LRP assyVDL enhancement (added 600t!)
- Detailed lightship survey, inclining test, - Reduce sand trap volume, remove redundant eqt/structure
Increase Brine Storage (add second brine tank)– Convert pontoon drill water tank to brine tank
XT Umbilical LARS- Install XT A frame and winches on STB side
IWOCS and OWS- Platforms, 10k annulus line, sheaves, etc
Dvalin rig intake process and modifications executed during TOA SPS and completed within time and budget
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 14
CRITICAL ELEMENTS
› HPHT Environment
› Large bore for high production rates
› Ceramic sand screens
› Reservoir drill-in fluid
› Clean up to rig
› Flexible schedule allowing for changes
WELL DESIGN
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 15
Damage to Formation• Impairment of formation permeability due to mud/filtrate invasion
Damage to Lower Completion• Blockage of screens/lower completion due to mud solids
Failure in 9 7/8 in cement job• failure to qualify as barrier
Lower Completion Screen Failure• Sand production
CRITICAL RISKS
Incorrect Placement of Lower Completion• reduced productivity
Gas Leakage During Well Clean Up• explosion/fire
Insufficient Rig Variable Deck Load• Increased operational risk/cost
Loss of Wellbay Slot• delayed delivery of 4th well/increased cost
DVALIN D&C PERFORMANCE
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020PAGE 16
Z1 over AFE with 51% NPT/WOW
• 135 dys actual vs 85 dys AFE
• 48 dys WOW
Z4 under AFE with 32% NPT/WOW• 79 dys actual vs 85 dys AFE
Z3 under AFE with 22% NPT/WOW• 66 dys actual vs 85 dys AFE
Z2 under AFE with 4% NPT/WOW• 76 dys actual vs 85 dys AFE• Drilled 700+m extra horizontal section
P50 Budget Actual
Days % Days %
Productive 233 68 243 68
NPT 75 22 50 14
WOW 34 10 64 18
subtotal 342 100 357 100.0
Mob/demob 8 11
D&C campaign within 5% of AFE time
D&C campaign under AFE cost
50 dys NPT vs 75 dys NPT in AFE
64 dys WOW vs. 34 days WOW in AFE
DRILLING & COMPLETION - MAJOR NPT EVENTS
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020 PAGE 17
Event Days Description
WOW 64.0 43.5 days in Jan/Feb 2020LMRP disconnect events = 4
Pull BOP to repair acoustic controls
9.3 Includes 4.1 days WOW
Repair failed BOP crane winch
4.6
Failed SSR plug –unable to test casing
4.4 2 events – Z4 and Z3
Unable to set VMB plug
2.4
Failed Welltec tractor 5.5 7 runs total
Failed TCO plug 1.8 TCO plug failed to open on Z1 after 65 dys
Multiple failures in Franks eqt
1.7
Wait on parts for prod test
1.0 31 dys of 50 dys total NPT
DRILLING CAMPAIGN - OVERVIEW
DVALIN FIELD DEVELOPMENT – SPE STAVANGER – 14 OCT 2020SLIDE 19
• No major HSE incidents• 3 out of 4 wells delivered ahead of AFE• Drilling campaign delivered within 5% of AFE time
(360 days)• Average cost per well below MNOK 500• Drilled 715m (4%) more than initially planned• 64 days WOW accounted vs. 34 days in the AFE• Drilled 18.23 km of Open Hole• 917m geo-steered• Z2-H horizontal well from decision to drill < 4weeksZ4
Z1Z2
Z3
DVALIN D&C LL ITEMS – TOP SIXApplicability of horizontal drainage strategy
• Discounted in PDO due to well control, RSS and ROP
Use of separate contracts for subsea equipment procurement and installation
• Use of Conventional LLS instead of OWS
Employ fit for purpose third party equipment and service providers
• DD/LWD delivered top quartile performance
Use of BaraECD RDIF together with OH ceramic screen completion
Optimised production test installation to achieve 3m+ flow rates
Use of third generation rig
• Plus : low unit cost, WH fatigue, WOW
• Minus : SR’s, MP’s, setback, efficiency