Duration Control Sheet
-
Upload
vicky-aademi -
Category
Documents
-
view
212 -
download
0
description
Transcript of Duration Control Sheet
Read Me1)Dear User, thank you for using my template. Please remove sample entries from the "Estimation Sheet".
2)
3)You downloaded this sheet free of charge from
You may use this sheet for your personal use and projects. However, selling the sheet is strictly prohibited.
Please make your data entries on the sheet "Estimation Sheet" only. Cells containing formulas or functions are protected, the password is blank should you wish to modify anything.
http: project-management.magt.biz
Read MeDear User, thank you for using my template. Please remove sample entries from the "Estimation Sheet".
You downloaded this sheet free of charge from
You may use this sheet for your personal use and projects. However, selling the sheet is strictly prohibited.
Please make your data entries on the sheet "Estimation Sheet" only. Cells containing formulas or functions are protected, the password is
This template is downloaded from http://project-management.magt.biz
Prepared by: Marc Arnecke,PMP
Project: [Project Name]Activity Duration Control Sheet
Sub-Project or Phase: [Sub-Project or Phase]
Client: [Client] Project Mngr.: [Proj. Mngr.] Printed on: 4/20/2023
Client's Representative: [Client's Representative] Recorded by: [Author]
Contractor: [Contractor]Work Package: [Work Package Description]
Sub-Contractor:
ActivityPlanned Actual
Difference RemarksStart Finish Duration Start Finish Duration
A B C D E F G H I J
0001 Excavate footings no. 1 - 15 1/1/2015 1/5/2015 5 1/2/2015 1/6/2015 5 0
0002 Pour blinding concrete footings no. 1 - 15 1/6/2015 1/9/2015 4 1/6/2015 1/7/2015 2 -2
0003 Install reinforcement footings no. 1- 15 1/13/2015 1/17/2015 5 1/12/2015 3,021 3016
0004
Total: 3014 days lost
This template is downloaded from http://project-management.magt.biz
Prepared by: Marc Arnecke,PMP