Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments...

45
Dungarvan Waste Water Treatment Plant WWDL Register Number: D0017-01 Annual Environmental Report for 2012

Transcript of Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments...

Page 1: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

Dungarvan Waste Water

Treatment Plant

WWDL Register Number: D0017-01

Annual Environmental Report for 2012

Page 2: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

2

Document Control Sheet:

Dungarvan Waste Water Treatment Plant

Annual Environmental Report 2012

Waterford County Council

Water Services

Civic Offices

Dungarvan

Co. Waterford.

Issued: Water Services Section

Waterford County Council

Date:

16th September 2013

Originator:

D. Whelan E.E

Final Approver:

P. Daly A/DoS

Revision 0 Description: Final Draft

Date: 29/09/2013

Page 3: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

3

Table of Contents

Executive Summary: ................................................................................................................................ 5

1. Introduction .................................................................................................................................... 6

1.1 Licence Register Number: ....................................................................................................... 6

1.2 Name: ...................................................................................................................................... 6

1.3 Site Location: ........................................................................................................................... 6

1.4 Description of activities at the site: ........................................................................................ 6

1.5 Company Environmental Policy (where available): ................................................................ 7

1.6 Company Organisational Chart for Environmental Management: ......................................... 7

2. Summary Information ..................................................................................................................... 9

2.1 Monthly Influent Monitoring: ................................................................................................. 9

2.2 Discharges from the Agglomeration: ...................................................................................... 9

2.3 Treatment Efficiency Report: ................................................................................................ 11

2.4 Treatment Capacity Report: .................................................................................................. 12

2.5 Ambient Monitoring Report: ................................................................................................ 13

2.6 Data Collection and Reporting Requirements under the Urban Waste Water Treatment

Directive: ........................................................................................................................................... 13

2.7 Pollutant Release and Transfer Register (PTRR) – Report for 2012: ..................................... 13

2.8 Pollutant Release and Transfer Register (PTRR) – Report for 2013: ..................................... 14

3. Operational Reports Summary ..................................................................................................... 14

3.1 Complaints Summary: ........................................................................................................... 14

3.2 Reported Incidents Summary: .............................................................................................. 15

3.3 Agency Monitoring and Enforcement: .................................................................................. 16

4. Infrastructural Assessments and Programme of Improvements .................................................. 17

4.1 Storm water overflow identification and inspection report: ................................................ 17

4.2 Report on progress made and proposals being developed to meet the improvement

programme requirements: ............................................................................................................... 18

4.2.1 Summary of Improvement Programme: .............................................................................. 18

4.2.2 Update of Improvement Programme Report: ..................................................................... 19

4.2.2.1 Schedule C of the licence - C.1 Improvement Programme for Primary Discharge ........... 19

4.2.2.2 Schedule C of the licence - C.2 Improvement Programme for Secondary Discharge ....... 20

4.2.2.3 Schedule C of the licence - C.3 Improvement Programme for Storm Water Overflows .. 22

4.2.2.4 Schedule A of the licence - A.3 Discharges to be discontinued. ....................................... 23

Page 4: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4

4.2.3 Summary Report Tables: ...................................................................................................... 24

5. Environmental Liability and Financial Provisions .......................................................................... 28

5.1 Statement of Measures: ....................................................................................................... 28

5.2 Environmental Liabilities Risk Assessment: .......................................................................... 28

6. Licence Specific Reports ................................................................................................................ 29

6.1 Priority Substances Assessment: .......................................................................................... 29

6.2 Drinking Water Abstraction Point Risk Assessment: ............................................................ 29

6.3 Shellfish Impact Assessment Report: .................................................................................... 29

6.4 Toxicity / Leachate Management: ........................................................................................ 32

6.5 Toxicity of the Final Effluent Report: .................................................................................... 32

6.6 Pearl Mussel Measures Report: ............................................................................................ 32

6.7 Habitats Impact Assessment Report: .................................................................................... 32

7. Certification and Sign Off .............................................................................................................. 33

8. Appendices .................................................................................................................................... 35

Appendix A: EPA Audit Effluent Analysis: ......................................................................................... 35

A.1 EPA Sample 23rd

October 2012: .................................................................................................. 35

A.2 EPA Sample 24th November 2012: .............................................................................................. 36

Appendix B: PRTR Data ..................................................................................................................... 37

Appendix C: Responses to the Agency’s Assessment of the 2011 AER. ........................................ 44

C.1 Treatment Capacity Report: ....................................................................................................... 44

C.2 Improvement Programme Progress: .......................................................................................... 44

C.3 Assessment of Licence: ............................................................................................................... 44

C.4 Report Statistics: ......................................................................................................................... 45

Page 5: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

5

Executive Summary:

Dungarvan Town is located on the estuary of the Colligan River and has a population of circa 9,000

persons as well as various commercial activities. There are no wet industries, with the main

industries being pharmaceutical processing. The current total population equivalent of the

agglomeration is estimated at 16,500.

Dungarvan and environs has a modern sewerage scheme, with a treatment plant located at

Ballinacourty (25,000 p.e.) capacity, which is operational since 2007. Wastewater is collected in a

number of catchments in Dungarvan and is pumped from these catchments to the main pump

station in Shandon from where it is pumped to the new waste water treatment plant in

Ballinacourty. Waste water is delivered to Ballinacourty from Dungarvan town via two rising mains

of over 6km length each. There is also a series of small catchments in the Ballinacourty / Clonea that

are pumped to the WWTP. Each pump station in the network has stormwater overflow facilities

which operate in storm conditions, when the forward pumping capacity of the stations is exceeded.

The WWTP is operated by Veolia who are contracted to operate and maintain the WWTP for a 20

year period.

The Licence required that SW2 and SW3 be upgraded by 1st November 2011 so as to be Emergency

Overflows only. As outlined in the 2010 AER, these overflows are designed as Storm Water

Overflows and cannot be converted to Emergency Overflows without a major redesign of the

network and a large capital investment. This is not achievable in the short term.

The Licence also required that SW16, SW17, SW18 and SW19 be upgraded by 1st November 2011 to

ensure that they complied with the DoEHLG’s ‘Procedures and Criteria in relation to Storm Water

Overflows, 1995’. Again, this is not achievable in the short term. The same issue regarding the

necessary redesign and upgrade of the overall Dungarvan network applies for these and the solution

is longer term and expensive. It is intended to carry out some investigative work in 2013.

The Ballinroad WWTP was replaced by a new pumping station in September 2011 and the discharge

from SW20 has now been discontinued. The full decommissioning of the plant will take place in

2013.

Page 6: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

6

1. Introduction

1.1 Licence Register Number:

D0017-01

1.2 Name:

Dungarvan Agglomeration and Waste Water Treatment Plant

1.3 Site Location:

The Wastewater Treatment Plant is located at Ballinacourty, Dungarvan, Co. Waterford.

The co-ordinates for the plant are 230500E, 092150N

1.4 Description of activities at the site:

The Dungarvan Waste Water Treatment Plant located at Ballinacourty, commenced operation in July

2007 and is designed to serve a population equivalent of 25,000. The plant was procured under a

DBO contract and the management of the facility is contracted to Veolia Water by Waterford County

Council.

The Ballinacourty Waste Water Treatment Plant treats domestic, commercial and industrial effluent

from Dungarvan Town and the Ballinacourty and Clonea catchment areas. Wastewater is transferred

to the plant via twin rising mains from Shandon Pumping Station in Dungarvan Town and via a single

rising main from the Ballinacourty and Clonea areas. Waste water in the Ballinroad area was

originally treated at its own WWTP but the effluent is now conveyed to Ballinacourty WWTP, as

stipulated in the waste water discharge licence of 2009. This change in operation commenced in

September 2011. The existing secondary treatment plant at Ballinroad is due to be fully

decommissioned in 2013.

Primary and Secondary treatment of waste water at Ballinacourty is achieved by screening and grit

removal at the inlet works, settlement, secondary biological treatment (activated sludge),

clarification and sludge removal. The sludge treatment process involves dewatering and thermal

drying on site to produce a final product which meets the requirements for use in agriculture. The

treatment plant is designed to treat sludge for a population equivalent of approximately 75,000. This

figure accommodates sludges imported for treatment, which includes dewatered, belt pressed,

aerobic and septic tank sludges. Due to difficulties experienced with the thermal sludge treatment of

Page 7: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

7

sludge arisings, lime stabilisation and land spreading was carried out for ten months in 2012.

However due to Planning difficulties with the lime stabilisation site, all sludge is now composted and

land spread.

(SW1) from Ballinacourty WWTP is via an outfall pipe and diffuser into the outskirts of Dungarvan

Harbour, off Ballinacourty Point. The secondary discharge point (SW20) is from the Ballinroad WWTP

into the Colligan Estuary. This discharge was discontinued by the 1st November 2011, in accordance

with the licence requirements.

1.5 Company Environmental Policy (where available):

Waterford County Council is committed to environmental protection and improvement as part of its

role in Local Government and its statutory obligations. It does not have a specific environmental

policy as all such policies are included in the Councils Strategic plan, but not in a format suitable for

extract to this document.

1.6 Company Organisational Chart for Environmental Management:

The organisational structure was developed in 2013. Waterford County Council has divided the

Water Services Operations & Maintenance Team into three relevant individual teams namely;

• the Waste Water Team,

• the Pollution Control and River Basin District Team and

• the Drinking Water Quality & Supply Team.

All of the above listed team members have duties in other areas of work under the umbrella of

Water Services Operations & Maintenance.

Page 8: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

8

Conor Foley

Senior Executive Engineer

Paul Carroll

Executive Scientist

EWWSS

Water / Wastewater

Water Pollution

Environment / Landfills

WATER

SERVICES

AREA

ENGINEERS

Tom Butler

Technician 1

Michael Maher

EWWSS Plant

Superintendent

Pat Lennon

Water

Conservation

Team

David Whelan EE

West County

David Hanratty EE

East County

6 FULL TIME WATER

SUPPLY CARETAKERS /

3 Full Time Sewerage

Caretakers

7 FULL TIME WATER

SUPPLY CARETAKERS /

3 Full Time Sewerage

Caretakers

Declan Halpin (Tech II)

Sue Cooke (Tech II)

WATER SERVICES STRUCTURE 2013

Eamon Morrissey

WATER FITTER

Reactive / Emergency

Maintenance

Bobby Ross

Tommy Wade

WASTEWATER FITTERS

3 Wastewater

Inspectors

Water East GSS

Tony O’Leary

Water West GSS

Stephen Browne

Michael Quinn DOS

Pat McCarthy SE Operations

Richard Barry Foreman

+ 7 Plant Operators

Colum Flynn EE

Wastewater

Timmy Bourke

S E Tech

WCC Machinery Yard – Fitter Resource

Foreman Plumber

plus two plumbers

3 Water Services

Gangs (x 2 MEN)

Foreman Plumber

plus two plumbers

3 Water Services

Gangs (x 2 MEN)

VisioDocument

Mary Hayes

ASO

PJ Kindregan

A/SE

Capital Projects

Ann-Marie Casey

EE

J Mansfield SEE

Suzanne Gough

ASO

John Leonard EE

Capital Projects Team

Noreen O’Neill

SSO Part-time

Page 9: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

9

2. Summary Information

2.1 Monthly Influent Monitoring:

Influent Monitoring was carried out monthly in accordance with the requirements of Condition 4.15 of

the licence.

Table 2.1.1 Influent Monitoring Monthly Results

Date

cBOD mg/l

COD mg/l

SS mg/l

Total Nitrogen mg/l Total Phosphorous

mg/l

No. of Samples 12 12 12 12 12

Annual Mean 134.42 304.92 208.83 11.93 2.80

Annual Max 363.00 668.00 435.00 30.70 4.70

Source: Operator PMS Reports

2.2 Discharges from the Agglomeration:

All licensed parameters are included in the monitoring programme (under Schedule B of the Licence) and

monitoring results are complete for 2012. Metal and Organic Compounds were not analysed in 2012, as

there were not any issues in 2011 sample results.

Faecal Coliforms, Escherichia coli and Intestinal enterococci were monitored monthly in accordance with

the licence.

The receiving water body for the discharge from the Dungarvan WWTP is designated as a Bathing Water

approximately 2km north of SW1 at Clonea Beach. This beach retained its Blue Flag Status in 2012 and

2013. Thus, the bathing waters at Clonea were not adversely impacted by the discharge from the

Dungarvan WWTP. This is the only designation on the receiving waters.

It was noted in the 2011 AER that the ELV of 10mg/l for TON was exceeded on two occasions, {January &

July}. There was no exceedance in 2012, thus indicating that the 2011 exceedances were of an isolated

nature. There are no requirements to upgrade the plant. The matter will continue to be monitored.

There are 5 No. WPA Licensed Activities in Dungarvan. Of these, two relate to a pharmaceutical company,

one relates to a mart, one relates to a petrol station and one relates to a hotel. The petrol station and

hotel discharge domestic-type wastewater only and there is no evidence of impact on the WWTP from

these facilities in 2012 or heretofore. The mart has a licence to discharge 25m³/day of wash waters from

their operation (one day per week) as well as domestic effluent from the facility. There has been no

impact noted on the WWTP in 2012 or heretofore. The discharges from the Glaxo Smithkline sites are

largely domestic-type because the plants are producing finished products only and are not wet processes.

Their licence sets typical discharge parameters to sewers with additional limits for Copper, Zinc,

Page 10: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

10

Sulphates, Chlorides, OFGs, Surfactants and Phenols. Their monthly analyses and annual environmental

reports show satisfactory compliance with the discharge licences. There has been no evidence of impacts

from their discharges on the WWTP in 2012 or heretofore.

Table 2.2.1

Effluent Monitoring Summary

BOD

(mg/l)

COD

(mg/l)

TSS

(mg/l)

Total

DIN

(mg/l)

Total

ON

(mg/l)

Ammonia

NH3-N

(mg/l)

Comment

WWDL ELV (Schedule A)

25 125 35 - 10 10

N

ON

E

ELV with Condition 2 Interpretation

included

50 250 52.5 - 12 12

Number of sample results

12 12 12 - 12 12

Number of sample results above

WWDL ELV

0 0 0 - 0 0

Number of sample results above

ELV with Condition 2 Interpretation

included

0 0 0 - 0 0

Annual Mean (for parameters

where a mean ELV applies)

2.31 27.75 13.75 - 4.98 1.64

Overall Compliance (Pass/Fail)

Pass Pass Pass - Pass Pass

Page 11: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

11

2.3 Treatment Efficiency Report:

Table 2.3.1

Treatment Efficiency Report

Summary Table

BOD

(kg/day)

COD

(kg/day)

SS

(kg/day)

Total P

(kg/day)

Total N

(kg/day)

Comment

Influent Mass Loading (kg/day) 1,051.7 2,561.6 1,546.6 24.2 98.2

No

ad

dit

ion

al

com

me

nts

Effluent Mass Loading (kg/day) 31.3 313.9 94.6 13.7 47.5

% Efficiency

(% reduction of influent load) 97.03% 87.75% 93.88% 43.39% 51.63%

As can be seen from Table 2.3.1, the average removal efficiency for COD is 87.75%, for BOD is 97.03% and

for Suspended Solids is 93.88%. These rates of removal show that the Dungarvan WWTP is performing

well and treating the effluent load effectively.

The removal efficiency for Total Nitrogen is 51.63% and for Total Phosphorous is 43.39%. These results

indicate that while the plant is operating at its current capacity that Nitrogen and Phosphorous removal is

adequate to meet the requirements of this licence. Given that the plant is operating at circa 66% of the

design capacity, these N and P removal efficiencies indicate that the plant is performing well on these

processes.

Page 12: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

12

2.4 Treatment Capacity Report:

The Dungarvan WWTP has a design capacity of 25,000 population equivalent. This translates to a

hydraulic capacity of 15,000m³ (3 DWF) and 1,500kgs of BOD. The current population equivalent as

calculated by the PRTR tool is 17,565. This equates to 70.26% of the design capacity. The average daily

flow into the WWTP was 8,853m³. This equates to 59.0% of the design capacity. The average daily BOD

load in the influent to the WWTP was 1,052kg/day. This equates to 70.1% of the design capacity.

As can be seen from the foregoing, there is currently sufficient capacity left in the plant to ensure that

there is no environmental risk posed to the receiving waters with the current loading on the plant. It is

extremely unlikely that the loading will increase to the point of being a risk in the next three years.

Table 2.4.1 Treatment Capacity Report Summary Table

Criteria Value As % terms

Hydraulic Capacity (Design)

(m3/day) 15,000 100.00%

Hydraulic Capacity

(Current Loading)

(m3/day)

8,853 59.02%

Hydraulic Capacity (Remaining)

(m3/day) 6,147 40.98%

Organic Capacity (Design) PE 25,000

100.00%

Organic Capacity –

Current Loading PE 16,500 66.00%

Organic Capacity – Remaining PE 8,500 34.00%

Will the capacity be exceeded in

the next three years? No -

Page 13: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

2.5 Ambient Monitoring Report:

Schedule D of the licence requires: “Summary report on ambient water quality of Colligan Estuary and

Dungarvan Harbour pursuant to the requirements of the Shellfish Directive (2006/113/EC).”

This report is provided under Section 6.3 Shellfish Impact Assessment Report of this report.

2.6 Data Collection and Reporting Requirements under the Urban Waste Water

Treatment Directive:

Data collection for Urban Waste Water Treatment returns for Dungarvan has been prepared and

uploading via the EDEN on-line system. The on-line WWTP database for Waterford has been updated with

respect to WWTP details and complaints for all WWTPs including Dungarvan. This was completed in

advance of the closing date of 26th February 2013.

2.7 Pollutant Release and Transfer Register (PTRR) – Report for 2012:

A Pollutant Release and Transfer Register (PRTR) Report has been prepared for 2012. It was prepared in

conformance with the Agency’s guidelines for the PRTR. The influent monitoring data and waste arisings

data were utilised to complete the PRTR calculation tool. Priority and hazardous substances have been

estimated by the use of this PRTR calculation tool. The report was uploaded through the EPA’s on-line

system on 26th

February 2013. The relevant pages from the uploaded PRTR are included in Appendix B of

this report.

There was a total of 3,186,530m³ of treated effluent discharged from the WWTP in 2012 with fugitive

emissions of 58,209m³ as a result of stormwater overflows from the plant. There were no releases to

sewers or other wastewater networks nor any releases to lands from the WWTP. There was on-site

treatment of sludges which were then transported off-site for lime stabilisation / composting and land

spreading. There were off-site transfers of grit and screenings also.

There was a significant increase in discharged treated effluent from 2011, this increase can be quantified

as approximately 52%, which can be attributed to the exceptionally wet summer, and the additional

incoming volume from Ballinroad.

Page 14: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

14

2.8 Pollutant Release and Transfer Register (PTRR) – Report for 2013:

Since the PRTR report for 2012 was carried out using the EPA’s calculation tool and PRTR template, there

is no requirement for the Council to submit proposals for 2013.

3. Operational Reports Summary

3.1 Complaints Summary:

Section 6.6 of the licence states that:

“The licensee shall record all complaints of an environmental nature related to the discharge(s) to waters

from the waste water works in accordance with the national environmental complaints procedure. Each

such record shall give details of the date and time of the complaint, the name of the complainant (if

provided), and the nature of the complaint. A record shall also be kept of the response made in the case of

each complaint.”

No complaints occurred during reporting year.

Table 3.1.1 Complaints Summary Table

Number Date Nature of Complaint Cause of Complaint Actions taken to resolve issue Status

None

Page 15: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

15

3.2 Reported Incidents Summary:

Section 6.1 of the licence states that:

“The licensee, shall notify the Agency by both telephone and facsimile, to the Agency’s headquarters in

Wexford, or to such other Agency office as may be specified by the Agency, as soon as practicable after the

occurrence of any incident (as defined in this licence). The licensee shall include as part of the notification,

date and time of the incident, summary details of the occurrence, and where available, the steps taken to

minimise any discharges.”

No incidents occurred during reporting year.

Table 3.2.1 Summary of Incidents:

Date &

Time

Incident

Description

Cause Corrective

Action

Authorities

Contacted Note 1

Reported to EPA

(Yes/No)

Closed

(Y/N)

None

Number of Incidents in 2012 0

Number of Incidents reported to the EPA via EDEN in 2012 0

Explanation of any discrepancies between the two numbers above

N/A

Page 16: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

16

3.3 Agency Monitoring and Enforcement:

As per the 2011 AER; “A site visit and audit was carried out by the Agency on November 24th 2011. The

Council awaits the report on the audit and will address the audit and any issues/recommendations in the

2012 AER for Dungarvan.”

In addition an Audit was undertaken on 23rd October 2012.

Emission sampling and analysis carried out by the Agency is contained in Appendix A.

The 2011 Audit refers to:

Flow Meter

2.6 The flow recorder is not maintained. Please outline why no maintenance is necessary.

Maintenance of said meter is undertaken since the Audit.

Notifications, Records & Reports

6.1 Since the last audit, all discharges from the waste water works have not complied with the Emission

Limit Values as set out in Schedule A of the Licence (subject to condition 2 of the licence).

6.2 There have been notifiable incidents since the last audit – Total Oxidised Nitrogen exceedances from

Jan - July 2011.

6.3 The incident was not reported to the EPA. Please review EPA incident notification guidance

(attached).

These matters were addressed in the 2011 AER.

The 2012 Audit refers to:

The 2012 Audit did not highlight any matters that were in need of corrective action.

A sample was taken during the Audit, the results of which are provided in Appendix A.

Page 17: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

17

4. Infrastructural Assessments and Programme of Improvements

4.1 Storm water overflow identification and inspection report:

“4.12.1 The licensee shall, prior to the date for submission of the second AER (required under Condition

6.12), carry out an investigation for the identification and assessment of storm water overflows. A report

on the storm water overflows shall be submitted to the Agency as part of the second AER. The assessment

shall include a determination of compliance with the criteria for storm water overflows, as set out in the

DoEHLG ‘Procedures and Criteria in Relation to Storm Water Overflows’, 1995 and any other guidance as

may be specified by the Agency.”

Report:

An assessment of the overflows was carried out in 2010 and included in the AER for 2010, as required by

the Licence. There is likely to be a significant redesign of the entire Dungarvan sewerage network to

enable all of the secondary discharge points to meet the licence requirements. The cost for these works is

likely to be very high and the timeframe for completing them would be in the medium term rather than

the short term.

It is intended to carry out an initial detailed assessment of the existing network in 2013, vis-a-vis the

requirements set out in this licence. This will then enable a programme of works to be drafted and cost

estimates produced. Given the likely high cost of any improvement programme, it is probable that such

works will need to be funded under the Water Services Investment Programme. The AER for 2013 will

include an update on the status of the Storm Water Overflows in Dungarvan.

Table 4.1.1 SWO Identification and Inspection Summary Report Table A:

WWDL Name

/ Code for

Storm Water

Overflow

Irish Grid

Reference

Included in

Schedule

A4 of the

WWDL

Compliance

with

DoEHLG

Criteria

No. of

times

activated

in 2012

(No. of

events)

Estimated

/Measure

d data

Total

volume

discharged

in 2012 (m3)

Estimated

/Measured

data

SW4 225026,

092513 No Compliant Not Known Not Known Not Known N/A

SW16 225660

093321 Yes Not Known Not Known Not Known Not Known N/A

SW17 226239

093116 Yes Not Known Not Known Not Known Not Known N/A

SW18 226108

092714 Yes Not Known Not Known Not Known Not Known N/A

SW19 226615

092807 Yes Not Known Not Known Not Known Not Known N/A

Page 18: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

18

Table 4.1.2 SWO Identification and Inspection Summary Report Table B:

Is each SWO identified as non-compliant with DoEHLG Guidance included in the

Programme of Improvements? Yes

The SWO assessment includes the requirements of Schedule A3 & C3 Yes

Have the EPA been advised of any additional SWOs / changes to Schedule C3 and

A4 under Condition 1.7? No

4.2 Report on progress made and proposals being developed to meet the

improvement programme requirements:

4.2.1 Summary of Improvement Programme:

Licence Condition 5.1: The licensee shall, as a part of the second AER (required under Condition 6.12),

prepare and submit to the Agency a programme of infrastructural improvements to maximise the

effectiveness and efficiency of the waste water works in order to:

a) achieve improvements in the quality of all discharges from the works; The WWTP is new,

commissioned in 2007. There are no proposals for improvement as it is showing compliance with

the licence.

b) meet the emission limit values specified in Schedule A: Discharges, of this licence;

Schedule A1 relates to the treatment plant, and our compliance level is shown in Table 2.2.1 of

this report. There were no compliance issues in 2012.

Schedule A2 is for a discharge that was discontinued in September 2011 in accordance with the

requirements of Schedule A3.

Schedule A4 does not have ELVS associated with the discharge points.

c) give effect to Regulation 2 of the Waste Water Discharge (Authorisation) Regulations 2007 (S.I.

No. 684 of 2007); Section 2 of S.I.684 is a statement of the purpose of the said regulations and is

quite general. It is the Council’s opinion that there are no works currently required to give effect

to this regulation.

d) reduce Total Nitrogen loadings in the discharge to the maximum practicable extent: The nitrogen

removal from the existing plant is more effective than expected from a plant of its type. The

ability of the plant to maintain the licence ELV of TON is not expected to continue when the load

on the plant begins to approach the design capacity of the WWTP (25,000 p.e.). Compliance has

Page 19: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

been achieved in 2012 as a result of the plant’s current operating parameters and loading. It is

recommended that further monitoring of loading and TON concentration in the discharge be

carried out and, if and when necessary, a programme of works can be prepared to upgrade the

WWTP. It is anticipated that the loading from the agglomeration will not alter significantly in the

short-term as residential development in the town has virtually stopped.

e) meet the obligations of Condition 1.7. This refers to treatment capacity at the WWTP and this is

currently within capacity on the principal determinant of biological loading. The Plant has a design

capacity of 25,000 p.e., which is equivalent to 1,500Kg of BOD per day for the year 2022. The

plant was constructed with a design capacity equal to the ultimate requirement for the year 2022.

The current average daily loading to the plant, as per tables on the mass loadings Table 2.3.1 of

this report is 1,052 kgs/day of BOD. The plant is operating at approximately 70.10% of its ultimate

capacity.

4.2.2 Update of Improvement Programme Report:

Report on progress made and proposals being developed to meet the improvement programme

requirements namely those set out in Schedule C of the licence. This summary report shall provide detail

on all measures proposed and undertaken under Water Services Investment Programme for

agglomeration, including progress reports on infrastructural works and a statement of compliance with

timeframes set out in this licence.

4.2.2.1 Schedule C of the licence - C.1 Improvement Programme for Primary Discharge

Page 20: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.2.2.2 Schedule C of the licence - C.2 Improvement Programme for Secondary Discharge

Specified Improvement: Implement a programme of works to ensure SW2 and SW3 only discharge in the

event of an emergency, that is, during pump failure and/or power failure at the associated pumping

station.

Report: SW2 is the storm overflow from Shandon Pump Station. Dungarvan sewerage scheme comprises

a number of sub catchments each delivering to individual pump stations, from where a multiple of Dry

Weather flow is pumped forward in the network until the waste water arrives at Shandon Pump Station.

Each pump station has an overflow facility that is reached when rainfall invades the network and forward

flows are at their limit. These pump stations act as storm water overflow facilities. Shandon pump station

has its own contributing catchment as well as the pumped inputs from the other peripheral stations.

SW2 is the main pump station pumping to the Waste Water Treatment Plant. Its pumping capacity, via

two rising mains is 650m3 per hour to the plant. Any flows into the station in excess of this are overflowed

via a screen to a storm well and subsequently discharged by pumping to the Colligan Estuary.

This discharge would comply with Formula A discharges to non sensitive areas according to the DoECLG‘s

‘Procedures and Criteria in relation to Storm Water Overflows, 1995’. Using a population of 9,000 with a

domestic contribution of 200litres/day and an industrial loading of 400m3 per day, Formula A flows are

calculated as 9,000x0.200 + 1.36x9,000 + 2x400 = 14,840m3/day = 618m

3/hr. This is less than the 650m

3

pumping capacity of the pump station.

Discharge at SW3: This discharge is also a storm water overflow. The pump station is designed to pump

forward multiple times the dry weather flow. The capacity of the pumps is up to 230m3 hour forward via

the network to Shandon station. The contributing catchment population is not calculated so the

compliance of the Storm overflow threshold against Formula A flows is not available. Given the design

philosophy adopted for this new station, it is quite likely compliant, as the design was carried out using a

computer simulation model.

Discontinuation of SW2 and SW3: Both these discharge points are storm overflows as well as pump

stations. Elimination of these discharges will require a complete re-design of the collection system, the

pump stations and the Waste Water Treatment Plant. The nature and extent of the work involved could

Page 21: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

21

not be implemented by the local authority under its own finances and would have to be put forward

under the WSIP (Water Services Investment Programme). The current WSIP programme is 2010 to 2013

and the required works for planning are not in this programme. The next WSIP will be under the control

of Irish Water, and the format for this new investment programme is not yet available to Local

Authorities. Therefore Waterford County Council can not establish the funding time lines for these works.

An extensive design and modelling of the network must then be carried out to evaluate the performance

of the storm overflows and to then agree with the Agency as to the appropriate direction to take.

Currently this design/ planning has to be carried out as a scheme “under planning” under the Water

Services Investment Programme (WSIP), due to the size of the design task and the implications for works.

If the scheme is deemed to require from the planning stage to stop discharges at SW2 and SW3, the

whole of Dungarvan Sewerage scheme has to go forward for Planning and design and this will include the

New Waste water treatment plant. A similar and smaller agglomeration of Tramore is currently at

planning stage for network improvements, including reducing Storm water overflows. This scheme is

currently estimated to cost €11m. Given the larger network of Dungarvan and its layout, the likely costs of

such measures would exceed €20m.

Condition 5.6 requires that SW2 and SW3 only discharge in the event of an emergency in after 1st

November 2011. As clearly outlined above, this is a very complex task that involves more than simply

increasing storage at the two pump stations. The necessary storage volumes would not be economical or

practical. The only possible solution is the network upgrade outlined above. This is not feasible within any

short to medium timeframe and, therefore, this licence condition cannot be met by Waterford County

Council.

However, it should be noted that these Discharges were not intended to work as emergency overflows

only and the Dungarvan network that was upgraded in 2004/2005 was designed with these overflows to

act as Stormwater Overflows which complied with the DoECLG’s ‘Procedures and Criteria in relation to

Storm Water Overflows, 1995’. It is possible that the Council may seek a Technical Amendment to this

licence condition in the future.

Page 22: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.2.2.3 Schedule C of the licence - C.3 Improvement Programme for Storm Water Overflows

Specified Improvement:

Upgrading of sewer network, as required, to ensure Storm Water Overflows comply with the criteria

outlined in the DoEHLG’s ‘Procedures and Criteria in relation to Storm Water Overflows, 1995’ for SW16,

SW17, SW18 and SW19. These improvements are to be made by 1st

November 2011.

Report: The specified date for these works has not been met. A full assessment of the Dungarvan network

needs to be made to see whether or not these Storm Water Overflows comply with the guidance or not.

This has not yet been prepared. If they are not in compliance with the guidance, then a programme of

works is likely to be required to upgrade the full Dungarvan network to ensure the overflows do meet the

requirements of the guidelines. As outlined in the Section 4.2.2.2 on SW2 and SW3, this is a very

significant body of work that will be expensive and will not be in place in the short-to-medium term

future.

Page 23: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.2.2.4 Schedule A of the licence - A.3 Discharges to be discontinued.

This discharge was discontinued as per the licence requirements.

Page 24: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

24

4.2.3 Summary Report Tables:

These summary tables are requested in EPA “Guidance on the Preparation & Submission of the Annual

Environmental Report (AER) for Waste Water Discharge Licences for 2012 Issue No.3, Revision No. 1

14/12/2012.

Table 4.2.3.1 Improvement Programme Summary Report:

Specified

Improvement

Programmes

(under Schedule

A and C of

WWDL)

Licence

Schedule

(A or C)

Licence

Completion

Date

Date

Expired?

(N/

NA/

Y)

Status of Works

((i) Not Started;

(ii) At planning

stage; (iii) Work

ongoing on-site;

(iv)

Commissioning

Phase; (v)

Completed; (vi)

Delayed;)

%

Completed

Licensee

Timeframe

for

Completing

the Work

Comments

Discharges to

be

discontinued:

SW20

A3 1/11/2011 N Completed 100% N/A

Storm water

overflows to be

upgraded

SW16

SW17

SW18

SW19

A4

C3

1/11/2011 Y Not Started 0% Not

established

Implement a

programme of

works to

ensure that

SW2 and SW3

only discharge

in the event of

an emergency,

that is, during

pump failure

and/or power

failure at the

associated

pumping

station. Refer

to Condition

5.6

C3 1/11/2011 Y Not Started 0% Not

established

Page 25: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

25

It should be noted that a complete change in prioritising of, and funding for Water Services projects

Nationally is scheduled from 1st

January 2014.

The Sewer Integrity Risk Assessment Tool is currently being undertaken by a Consulting Engineering

Company working on behalf of the Council, this risk assessment will be included with the AER for 2013.

Table 4.2.2 Sewer Integrity Risk Assessment Tool Improvement Programme Summary Report A:

Element

Risk Assessment

Rating

{ie. Risk Category as

given in “Summary”

worksheet of Sewer

Integrity Tool

Risk

Assessment

Score

Reference to relevant

section of AER

Hydraulic Risk

Assessment Score N/A N/A

NOTE:

The Sewer Integrity

Tool Assessment is

currently being

undertaken by an

external consulting

engineer.

Environmental Risk

Assessment Score N/A N/A

Structural Risk

Assessment Score N/A N/A

Operation &

Maintenance risk

Assessment Score

N/A N/A

Overall Risk Score for

the agglomeration N/A N/A

Table 4.2.3 Sewer Integrity Risk Assessment Tool Improvement Programme Summary Report B:

Are the findings of the Sewer Integrity

Risk Assessment included in the

Improvement Programme?

N.b. each licensee should prioritise the findings of the risk assessment in

the Improvement Programme starting with High Risk aspect.

N/A Yes/No 0% Complete NOTE:

The Sewer

Integrity Tool

Assessment is

currently being

undertaken by

an external

consulting

engineer.

What % of leakage is reported /

estimated? Unknown

What % of misconnections is reported /

estimated? Unknown

Comment

Page 26: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

26

Table 4.2.4 Improvement Programme (Works) Summary Table

The Improvement Programme should include an

assessment of the integrity of the existing wastewater

works for the following:

Licensee self- assessment

check to determine whether

all relevant information is

included in the Programme

of Improvements

Reference to relevant

section of the

Improvement

Programme.

Capacity of the works Yes / No

Currently, these have

not been assessed.

The Consulting

Engineers report will

highlight problematic

areas.

Leaks from the works Yes / No

What % of leakage is reported? %

Misconnections between foul sewer to surface

water drainage Yes / No

What % of misconnections is reported? %

Surface water infiltration Yes / No

Groundwater infiltration Yes / No

Comment

Table 4.2.5 Improvement Programme (Secondary Discharges) Summary Table:

The Improvement Programme should

include an assessment of Secondary

Discharges (e.g. cease discharge /upgrade

to meet requirements) for the following :

Licensee self-

assessment check to

determine whether all

relevant information is

included in the

Programme of

Improvements

Reference to relevant

section of the

Improvement

Programme. Date for

completion

Receiving water body designation

Refer to Section

4.2.2.2 of this report.

Downstream abstractions and uses of

water

Water quality objectives for the water

body

Comment

Page 27: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

27

Table 4.2.6 Improvement Programme (Storm Water Overflows) Summary Table:

The findings of the SWO Identification and

Inspection Report should be included in the

Improvement Programme (upgrades to meet licence

requirements)

Licensee self- assessment check

to determine whether all relevant

information is included in the

Programme of Improvements

Reference to relevant

section of the Improvement

Programme.

SW16 Yes Refer to Section 4.2.1

for Summary of

Improvement Works,

and Section 4.2.2.3

Schedule C of the

licence - C.3

Improvement

Programme for Storm

Water Overflows

SW17 Yes

SW18 Yes

SW19 Yes

Table 4.2.7 Improvement Programme (Licence Specific Reports) Summary Table:

The findings of the Licence Specific Reports should

be included in the Improvement Programme (i.e. any

identified upgrades to meet licence requirements)

Licensee self- assessment check

to determine whether all relevant

information is included in the

Programme of Improvements

Reference to relevant

section of the Improvement

Programme.

Include a row for each licence specific report finding

No works identified

Comment

Table 4.2.8 Improvement Programme (Implementation Plan) Summary Table:

For each improvement identified the Improvement

Programme should include an implementation

plan that :

Licensee self- assessment check to

determine whether all relevant

information is included in the

Programme of Improvements

Reference to relevant

section of the

Improvement Programme.

Identifies and describe each improvement

including a timeframe for implementation? (Cond.

5.3) Yes Refer to Sections:

4.2.1

4.2.2.2

4.2.2.3

of this report

Specifies the parameters that will be affected by

the improvement? Yes

Estimates the costs and source of funding? Yes

Estimates the water quality improvement

associated with the Improvement? Yes

Comment -

Page 28: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

28

5. Environmental Liability and Financial Provisions

5.1 Statement of Measures:

7.2.1 The licensee shall as part of the AER provide an annual statement as to the measures taken or

adopted in relation to the prevention of environmental damage, and the financial provisions in place in

relation to the underwriting of costs for remedial actions following anticipated events (including closure)

or accidents/incidents, as may be associated with discharges or overflows from the waste water works.

The statement of measures and assessment of risks associated with Dungarvan WWTP is contained in the

ELRA issued with the 2010 AER for this licence, as far as it is possible to ascertain these risks. On the issue

of underwriting costs: Waterford Co. Council has a long term contract in place for the operation of the

waste water treatment plant and is committed to financing same. Local authorities are state bodies and

dependant on Government for funding. Financial provisions for remedial works, if required, would come

from current annual revenue funds, as far as these would be available.

As from 1st January 2013, Irish Water will be the responsible financing authority for this DBO Contract.

5.2 Environmental Liabilities Risk Assessment:

7.2.2 The licensee shall arrange for the completion, by an independent and appropriately qualified

consultant, of a comprehensive and fully costed Environmental Liabilities Risk Assessment (ELRA) to

address the liabilities from present or planned discharges. A report on this assessment shall be submitted

to the Agency for agreement as part of the second AER (required under Condition 6.12). The ELRA shall be

reviewed as necessary to reflect any significant change to the volume or character of effluent discharged,

and in any case every three years following initial agreement (the results of the review shall be notified as

part of the AER).

The 2010 AER contained a copy of the ELRA for the Dungarvan Agglomeration. There have been no

significant changes to the volume or character of effluent discharged since that assessment was prepared,

nor are there any expected changes to the effluent discharged. Thus, there has been no requirement to

provide a new ELRA for the 2012 AER. The next revision of the ELRA will be due in 2013 and reported on

in the 2013 AER, unless otherwise recommended by the Agency.

Page 29: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

6. Licence Specific Reports

Table 6.0.1 Licence Specific Reports Summary Table:

Licence Specific Report Required in 2012 AER or outstanding from previous AER

Included in 2012 AER

Reference to relevant section of AER (e.g. Appendix 2 Section4.

Priority Substances Assessment

No No

Drinking Water Abstraction Point Risk Assessment

No No

Habitats Impact Assessment

No No

Shellfish Impact Assessment

Yes Yes

Pearl Mussel Report No No

Toxicity/Leachate Management

No No

Toxicity of Final Effluent Report

No No

6.1 Priority Substances Assessment:

Not required by Licence.

6.2 Drinking Water Abstraction Point Risk Assessment:

Not Required by Licence.

6.3 Shellfish Impact Assessment Report:

Schedule D of the Discharge Licence:

Page 30: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

30

This assessment was prepared and included in the 2010 AER, as required under the Condition 5.8. It did

not appear to show any significant issues with E coli and in 2010, all sampling showed that the shellfish in

Dungarvan were compliant with the guidelines.

The monitoring results for 2012 are shown in the Table below received from the SFPA and the DoECLG.

Table 6.3.1 SWD designated monitoring points compared with actual sampling undertaken under

the SFPA monitoring programme (November 2009-November 2011)

Designated Area Species Comment

Dungarvan Bay PO SFPA sample location closely matches designated sampling

location.

Species code: PO Pacific oysters;

For assessment purposes a value of ≤≤≤≤230 E. coli MPN 100g-1 was considered equivalent to the directive

guide value of ≤≤≤≤300 faecal coliforms MPN 100g-1.

Table 6.3.2 E. coli data used to make assessment of compliance with the Guide Value

SWD Site

E. coli MPN 100g-1

Nov-

09

Feb-

10

May-

10

Aug-

10

Nov-

10

Feb-

11

May-

11

Aug-

11

Nov-

11

Feb-

2012

May-

2012

Aug-

2012

Nov-

2012

Dungarvan

Harbour

490 170 20 230 230 790 20 50 80

170

110

1100

490

Table 6.3.3 Assessment of compliance with guide value of ≤≤≤≤230 E. coli MPN

100g-1

between November 2009 and November 2011

SWD Site

Percentage Compliance with E. coli 230

MPN 100g-1

(n)

2009

(n=4)*

2010

(n=4)*

2011

(n=4)*

2012

(n=4)*

2009 - 2012

(n=16)*

Dungarvan Harbour

50

100

75

50

69

Page 31: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

Overall assessment of parameter 8 (organohalogens) and parameter 9 (trace metals) for each shellfish

water body. This is based on a ‘worst case’ scenario for compliance with proposed guide values for biota

(2009) and current mandatory limits (SI 268 of 2006) and WFD EQS limits for seawater. PCB assessment is

based on compliance with proposed guide values sum of ICES 7 CBs and not compliance of individual

congener concentrations with EACs.

Table 6.3.5: Overall Status Summary

Designated

Shellfish

Area

Overall

Status

Biota Water Parameter 9 Parameter 8

Overall

Paramet

er 9:

Metals

Me

tals

Overall

Parameter 8:

Organo-

halogenated

Substances

Ch

loro

bip

he

ny

ls

Org

an

ocl

ori

ne

s

He

xa

chlo

rocy

clo

he

xan

es

DD

Ts

Cy

clo

die

ne

s

Dungarvan

Harbour

Table 6.3.4 Summary assessment of compliance with SWD Mandatory (I) and Guide (G) values of SI 268

of 2006 for each designated shellfish water

Designated Shellfish

Area

Temp

0C

pH Salinity DO% Saturation Colour TSS

mg 1-1

Vis.

HC

268/2006 standards.

I=Imperative,

G=Guide

>7 <9

(I)

<40

(I)

<38

(G)

>70%

(I)

>80%

(G)

Compliance required 75% 75% 95% 95% 95% 95% 75% 75% 75%

Dungarvan Harbour

Page 32: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

32

Results have been received from the Sea Fisheries Protection Authority (SFPA) for monitoring of

microbiological quality in the oysters in Dungarvan Harbour for the period January 2010 to January 2013.

All results for Dungarvan (all areas) from February 2009 to June 2011 are summarised as follows:

Table 6.3.6 Oyster Summary of Results Jun 10-Jan13:

Dungarvan –all areas

Oysters

Current Classification - B

Seasonality of B/C results

Category Number Max % of Total

Results

Spring

Mar-May

Summer

June-Aug

Autumn

Sept-Nov

Winter

Dec-Feb

A Results 37 66%

B Results 19 2,400 34% 3 6 6 4

C Results 0 0%

Total

Results 56 N/A N/A

Source: Sea Fisheries Protection Authority

6.4 Toxicity / Leachate Management:

Not Required by Licence.

6.5 Toxicity of the Final Effluent Report:

Not Required by Licence.

6.6 Pearl Mussel Measures Report:

Not Required by Licence.

6.7 Habitats Impact Assessment Report:

Not Required by Licence.

Page 33: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

33

7. Certification and Sign Off

Table 7.1 AER Submission Checklist:

Does the AER include an executive summary? Yes

Does the AER include an assessment of the performance of the Waste Water Works

(i.e. have the results of assessments been interpreted against WWDL requirements

and or Environmental Quality Standards)?

Yes

Is there a need to advise the EPA for consideration of a technical amendment / review

of the licence? Yes

List reason e.g. additional SWO identified

Extension of Improvement Works Completion Timelines Yes

Is there a need to request/advise the EPA of any modifications to the existing WWDL?

Refer to Condition 1.7 (changes to works/discharges) & Condition 4 (changes to

monitoring location, frequency etc.)

No

List reason e.g. failure to complete specified works within dates specified in the

licence, changes to monitoring requirements (insert lines as required)

Improvement Works are not complete as the assessment of the requirements have not been

assessed in detail, and there is a current level of uncertainty with regard to the replacement

of the current WSIP 2010 – 2013.

Yes

Have these processes commenced? (i.e. Request for Technical Amendment / Licence

Review / Change Request) No

Are all outstanding reports and assessments from previous AERs included as an

appendix to this AER? Yes

List outstanding reports (insert lines as required) None

Page 34: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

34

As per condition 6.11 of the Discharge Licence D0015-01, I certify that the above reports accurate and

representative:

Prepared By: David Whelan --------------------------------

(Executive Engineer) Signature

Reviewed By: Colum Flynn --------------------------------

(A/ Senior Executive Engineer) Signature

Approved By: Paul Daly --------------------------------

(A/ Director of Services) Signature

Page 35: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

8. Appendices

Appendix A: EPA Audit Effluent Analysis:

A.1 EPA Sample 23rd

October 2012:

Page 36: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

A.2 EPA Sample 24th

November 2012:

Page 37: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

Appendix B: PRTR Data

| PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant |

Filename : D0017_2012.xls | Return Year : 2012 |

Guidance to completing the PRTR workbook

Version 1.1.15

REFERENCE YEAR 2012

1. FACILITY IDENTIFICATION

Parent Company Name Waterford County Council

Facility Name Dungarvan UDC Waste Water Treatment Plant

PRTR Identification Number D0017

Licence Number D0017-01

Waste or IPPC Classes of Activity

No. class_name

30.4 General

Address 1 Civic Offices

Address 2 Davitts Quay

Address 3 Dungarvan

Address 4 Co. Waterford

Waterford

Country Ireland

Coordinates of Location -7.55505 52.0805

River Basin District IESE

NACE Code 3700

Main Economic Activity Sewerage

AER Returns Contact Name Colum Flynn

AER Returns Contact Email Address [email protected]

AER Returns Contact Position Executive Engineer, Water Services Section

AER Returns Contact Telephone Number 058-20807

AER Returns Contact Mobile Phone Number 087-2388044

AER Returns Contact Fax Number 058-20883

Production Volume 0.0

Production Volume Units

Number of Installations 0

Number of Operating Hours in Year 0

Number of Employees 4

User Feedback/Comments

Web Address

2. PRTR CLASS ACTIVITIES

Activity Number Activity Name

5(f) Urban waste-water treatment plants

3. SOLVENTS REGULATIONS (S.I. No. 543 of 2002)

Is it applicable? No

Have you been granted an exemption ?

If applicable which activity class applies (as per

Schedule 2 of the regulations) ?

Is the reduction scheme compliance route being

used ?

4. WASTE IMPORTED/ACCEPTED ONTO SITE Guidance on waste imported/accepted onto site

Do you import/accept waste onto your site for on-

site treatment (either recovery or disposal

activities) ?

AER Returns Workbook

Page 38: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.1 RELEASES TO AIR Link to previous years emissions data | PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant | Filename : D0017_2012.xls | Return Year : 2012 | 01/10/2013 09:58

8 20 28 28 36 36 6 6 6

SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

01 Methane (CH4) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

02 Carbon monoxide (CO) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 2.0 0.0 2.0

03 Carbon dioxide (CO2) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 330116.0 0.0 330116.0

05 Nitrous oxide (N2O) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 2.0 0.0 2.0

07 Non-methane volatile organic compounds (NMVOC) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 1.0 0.0 1.0

08 Nitrogen oxides (NOx/NO2) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 5.0 0.0 5.0

11 Sulphur oxides (SOx/SO2) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 1.0 0.0 1.0

0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0

0.0 0.0 0.0 0.0

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

SECTION B : REMAINING PRTR POLLUTANTS

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence)

Please enter all quantities in this section in KGs

QUANTITY

Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

Additional Data Requested from Landfill operators

Landfill: Dungarvan UDC Waste Water Treatment Plant

Please enter summary data on the

quantities of methane flared and / or

utilised

additional_pollutant_no T (Total) kg/Year M/C/E Method Code

Designation or

Description

Facility Total Capacity

m3 per hour

Total estimated methane generation (as per

site model) 0.0 N/A

Methane flared 0.0 0.0 (Total Flaring Capacity)

Methane utilised in engine/s 0.0 0.0 (Total Utilising Capacity)

Net methane emission (as reported in

Section A above) 0.0 N/A

RELEASES TO AIR

METHOD

POLLUTANT METHOD

Method Used

For the purposes of the National Inventory on Greenhouse Gases, landfill operators are requested to provide summary data on

landfill gas (Methane) flared or utilised on their facilities to accompany the figures for total methane generated. Operators should

only report their Net methane (CH4) emission to the environment under T(total) KG/yr for Section A: Sector specific PRTR pollutants

above. Please complete the table below:

Method Used

Method Used

RELEASES TO AIR

POLLUTANT METHOD

Method Used

POLLUTANT

RELEASES TO AIRADD NEW ROW DELETE ROW *

ADD NEW ROW DELETE ROW *

ADD NEW ROW DELETE ROW *

ADD EMISSION POINT

ADD EMISSION POINT

ADD EMISSION POINT

Page 39: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.2 RELEASES TO WATERS Link to previous years emissions data | PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant | Filename : D0017_2012.xls | Return Year : 2012 | 01/10/2013 09:58

8 73 81 81 89 144 6 6 6

SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS Data on ambient monitoring of storm/surface w ater or groundw ater, conducted as part of your licence requirements, should NOT be submitted under AER / PRTR

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

34 1,2-dichloroethane (EDC) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

25 Alachlor E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

26 Aldrin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

61 Anthracene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.009 0.009 0.0 0.0

17 Arsenic and compounds (as As) E ESTIMATE

EPA UWWTP Tool

Version 5.0 7.063 7.142 0.0 0.079

27 Atrazine E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.033 0.034 0.0 0.001

62 Benzene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.054 0.064 0.0 0.01

91 Benzo(g,h,i)perylene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.006 0.006 0.0 0.0

63 Brominated diphenylethers (PBDE) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

18 Cadmium and compounds (as Cd) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.159 0.175 0.0 0.016

28 Chlordane E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

29 Chlordecone E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

30 Chlorfenvinphos E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

79 Chlorides (as Cl) E ESTIMATE

EPA UWWTP Tool

Version 5.0 2797773.34 2856836.072 0.0 59062.732

31 Chloro-alkanes, C10-C13 E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.669 0.681 0.0 0.012

32 Chlorpyrifos E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

19 Chromium and compounds (as Cr) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.929 0.935 0.0 0.006

20 Copper and compounds (as Cu) E ESTIMATE

EPA UWWTP Tool

Version 5.0 9.825 10.154 0.0 0.329

82 Cyanides (as total CN) E ESTIMATE

EPA UWWTP Tool

Version 5.0 9.342 9.505 0.0 0.163

33 DDT E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

70 Di-(2-ethyl hexyl) phthalate (DEHP) E ESTIMATE

EPA UWWTP Tool

Version 5.0 2.923 3.095 0.0 0.172

35 Dichloromethane (DCM) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.145 0.152 0.0 0.007

36 Dieldrin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

37 Diuron E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.084 0.084 0.0 0.0

38 Endosulphan E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

39 Endrin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

65 Ethyl benzene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.053 0.06 0.0 0.007

88 Fluoranthene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.007 0.008 0.0 0.001

RELEASES TO WATERS

POLLUTANT

Method Used

ADD EMISSION POINT

Page 40: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

83 Fluorides (as total F) E ESTIMATE

EPA UWWTP Tool

Version 5.0 770.742 789.951 0.0 19.209

40 Halogenated organic compounds (as AOX) E ESTIMATE

EPA UWWTP Tool

Version 5.0 7.606 7.745 0.0 0.139

41 Heptachlor E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

90 Hexabromobiphenyl E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

42 Hexachlorobenzene (HCB) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

43 Hexachlorobutadiene (HCBD) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

89 Isodrin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

67 Isoproturon E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.024 0.025 0.0 0.001

23 Lead and compounds (as Pb) E ESTIMATE

EPA UWWTP Tool

Version 5.0 9.685 10.314 0.0 0.629

45 Lindane E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.001 0.001 0.0 0.0

21 Mercury and compounds (as Hg) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.006 0.0 0.006

46 Mirex E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

68 Naphthalene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.013 0.021 0.0 0.008

22 Nickel and compounds (as Ni) E ESTIMATE

EPA UWWTP Tool

Version 5.0 13.567 13.777 0.0 0.21

64 Nonylphenol and Nonylphenol ethoxylates (NP/NPEs) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.264 0.327 0.0 0.063

87 Octylphenols and Octylphenol ethoxylates E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

69 Organotin compounds (as total Sn) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

48 Pentachlorobenzene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

49 Pentachlorophenol (PCP) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

71 Phenols (as total C) E ESTIMATE

EPA UWWTP Tool

Version 5.0 2.899 7.606 0.0 4.707

50 Polychlorinated biphenyls (PCBs) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

72 Polycyclic aromatic hydrocarbons (PAHs) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.028 0.041 0.0 0.013

51 Simazine E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.045 0.046 0.0 0.001

52 Tetrachloroethylene (PER) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.188 0.188 0.0 0.0

53 Tetrachloromethane (TCM) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

Page 41: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

73 Toluene E ESTIMATE

EPA UWWTP Tool

Version 5.0 1.572 2.382 0.0 0.81

12 Total nitrogen M

EN ISO 11905-

1:1998 17689.225 17997.733 0.0 308.508

76 Total organic carbon (TOC) (as total C or COD/3) E ESTIMATE

EPA UWWTP Tool

Version 5.0 29379.082 30141.736 0.0 762.654

13 Total phosphorus M ALT EN ISO 6838:2004 5217.943 5356.771 0.0 138.828

59 Toxaphene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

74 Tributyltin and compounds E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

54 Trichlorobenzenes (TCBs)(all isomers) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

57 Trichloroethylene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

77 Trifluralin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

75 Triphenyltin and compounds E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

60 Vinyl chloride E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

78 Xylenes E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.369 0.461 0.0 0.092

24 Zinc and compounds (as Zn) E ESTIMATE

EPA UWWTP Tool

Version 5.0 157.299 164.395 0.0 7.096

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

SECTION B : REMAINING PRTR POLLUTANTS

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0

RELEASES TO WATERS

POLLUTANT

Method Used

ADD NEW ROW DELETE ROW *

ADD EMISSION POINT

Page 42: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

SECTION C : REMAINING POLLUTANT EMISSIONS (as required in your Licence)

Please enter all quantities in this section in KGs

QUANTITY

Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

370 Selenium E ESTIMATE

EPA UWWTP Tool

Version 5.0 15.136 15.175 0.0 0.039

205 Antimony (as Sb) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.492 0.52 0.0 0.028

368 Molybdenum E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.081 0.0 0.081

358 Tin E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.345 0.345 0.0 0.0

373 Barium E ESTIMATE

EPA UWWTP Tool

Version 5.0 73.211 75.285 0.0 2.074

374 Boron E ESTIMATE

EPA UWWTP Tool

Version 5.0 935.247 954.184 0.0 18.937

356 Cobalt E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.56 0.579 0.0 0.019

386 Vanadium E ESTIMATE

EPA UWWTP Tool

Version 5.0 8.691 8.994 0.0 0.303

388 Dichlobenil E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.014 0.014 0.0 0.0

383 Linuron E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

385 Mecoprop Total E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.341 0.348 0.0 0.007

380 2,4 Dichlorophenol (2,4 D) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.163 0.165 0.0 0.002

384 MCPA E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.282 0.283 0.0 0.001

382 Glyphosate E ESTIMATE

EPA UWWTP Tool

Version 5.0 4.884 4.907 0.0 0.023

389 Benzo[a]pyrene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.006 0.006 0.0 0.0

390 Benzo[b]fluoranthene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.006 0.006 0.0 0.0

391 Benzo[k]fluoranthene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.006 0.006 0.0 0.0

392 Indeno[1,2,3-c,d]pyrene E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.007 0.007 0.0 0.0

393 Carbon tetrachloride E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

394 2,6-Dichlorobenzamide E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.256 0.259 0.0 0.003

395 Dicofol E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

396 Hexabromocyclodecane (HBCD) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

397 PFOS E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.002 0.002 0.0 0.0

238 Ammonia (as N) M OTH MEWAM 1981 1822.695 1822.695 0.0 0.0

303 BOD M OTH APHA 2005:5210:B 11898.503 18403.359 0.0 6504.856

306 COD M OTH APHA 2005:5220:C 115107.023 130183.154 0.0 15076.131

362 Kjeldahl Nitrogen E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

327 Nitrate (as N) M OTH 15865.733 15865.733 0.0 0.0

372 Nitrite (as N) E ESTIMATE

EPA UWWTP Tool

Version 5.0 0.0 0.0 0.0 0.0

332 Ortho-phosphate (as PO4) M

EN ISO

6878:2004 4524.873 4524.873 0.0 0.0

240 Suspended Solids M OTH APHA 2005:2450:B 34698.125 44026.117 0.0 9327.992

Method Used

POLLUTANT

RELEASES TO WATERS

ADD EMISSION POINT

Page 43: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

4.3 RELEASES TO WASTEWATER OR SEWER Link to previous years emissions data | PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant | Filename : D0017_2012.xls | Return Year : 2012 |01/10/2013 09:58

8 8 16 16 6 6 6 6

SECTION A : PRTR POLLUTANTS

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)

Please enter all quantities in this section in KGs

QUANTITY

Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year

0.0 0.0 0.0 0.0

OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER

OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER

Method Used

Method Used

POLLUTANT METHOD

POLLUTANT METHOD

ADD NEW ROW DELETE ROW *

ADD EMISSION POINT

ADD EMISSION POINT

4.4 RELEASES TO LAND Link to previous years emissions data | PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant | Filename : D0017_2012.xls | Return Year : 2012 | 01/10/2013 09:58

8 8 16 16 6 6 6 6

SECTION A : PRTR POLLUTANTS

Please enter all quantities in this section in KGs

QUANTITY

No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year

0.0 0.0 0.0

* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button

SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)

Please enter all quantities in this section in KGs

QUANTITY

Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year

0.0 0.0 0.0

POLLUTANT METHOD

Method Used

RELEASES TO LAND

RELEASES TO LAND

POLLUTANT METHOD

Method Used

ADD NEW ROW DELETE ROW *

ADD EMISSION POINT

ADD EMISSION POINT

5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE | PRTR# : D0017 | Facility Name : Dungarvan UDC Waste Water Treatment Plant | Filename : D0017_2012.xls | Return Year : 2012 | 01/10/2013 09:58

5 8 Please enter all quantities on this sheet in Tonnes 8

Quantity

(Tonnes per

Year)

Haz Waste : Name and

Licence/Permit No of Next

Destination Facility

Non Haz Waste: Name and

Licence/Permit No of

Recover/Disposer

Haz Waste : Address of Next

Destination Facility

Non Haz Waste: Address of

Recover/Disposer

Name and License / Permit No.

and Address of Final Recoverer /

Disposer (HAZARDOUS WASTE

ONLY)

Actual Address of Final

Destination i.e. Final Recovery /

Disposal Site (HAZARDOUS

WASTE ONLY)

Transfer Destination

European Waste

Code Hazardous Q u a n tity T /Y e a r Description of Waste

Waste

Treatment

Operation M/C/E Method Used

Location of

Treatment N a m e a n d L ic e n c e / P e rm it N o . o f R e c o v e re r / D isp o se r / B ro k e r A d d re ss o f R e c o v e re r / D isp o se r / B ro k e r N a me a n d A d d re ss o f F in a l D e stin a tio n i.e . F in a l R e c o v e ry / D isp o sa l S ite (H A Z A R D O U S W A S T E O N L Y ) L ic e n c e / P e rmit N o . o f F in a l D e stin a tio n i.e . F in a l R e c o v e ry / D isp o sa l S ite (H A Z A R D O U S W A S T E O N L Y )

Within the Country 19 08 01 No 59.9 screenings D5 C Volume Calculation Offsite in Ireland

Greenstar Ltd.,WCP-KK-

054(A)-08

Carriganard,Six Cross

Roads,Waterford,.,Ireland

Within the Country 19 08 05 No 263.47

sludges from treatment of urban waste

water R10 M Weighed Offsite in Ireland

SEDE Ireland Ltd.,WCP-KE-

10-0569-01

Carran,Dunbell,Co.

Kilkenny,.,Ireland

Within the Country 19 08 05 No 21.5

sludges from treatment of urban waste

water R10 M Weighed Offsite in Ireland

M&T Plant Hire Ltd.,WFP-

WX-12-0061-01

Ballyeden,The

Leap,Enniscorthy,Co.

Wexford,Ireland

Within the Country 19 08 05 No 18.33

sludges from treatment of urban waste

water R10 M Weighed Offsite in Ireland

McGill Environmental

Ltd.,W0245-01

Molaisin Compost

Ltd.,Kilmolash,Cappoquin,C

o. Waterford,Ireland

Method Used

Page 44: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

44

Appendix C: Responses to the Agency’s Assessment of the 2011 AER.

C.1 Treatment Capacity Report:

“Explain differences in the number of reported incidents between database and AER” – “Review

Incident classification”

With reference to Section 2.4 Environmental Incidents and Complaints of the 2011 AER;

“There were two exceedences of ELVs that are deemed non-compliant in accordance with Condition 2

of the Licence. These were not notified to the Agency owing to a misunderstanding with respect to

when they were to be reported. It was believed that the overall number of exceedences was still less

than outlined in Condition 2 and that the results would be notified in the AER for 2011. Such non-

compliances will be notified to the Agency as soon as possible should they occur in the future.”

This section outlines how the error occurred due to a misinterpretation of the licence and that this

was now clarified; “Such non-compliances will be notified to the Agency as soon as possible should

they occur in the future.”

C.2 Improvement Programme Progress:

“Is the Improvement Programme on time with the Schedule A3 and C dates? - If no, what is the

scheduled completion date?”

“upgrade of SW2 & SW3 to emergency overflow due 01/11/2011. No date is given and WCC may

seek a technical amendment in this respect”

Agreed, Waterford County Council will seek a Technical Amendment to this requirement once the

solution has been defined and funding provision / funding timelines identified.

C.3 Assessment of Licence:

“Is there a need to advise the EPA for consideration of a technical amendment/review to the licence?

- List reason - Eg. Additional SWO identified - IP dates not being met and will not be met in the short-

term”

“From the EPA assessment of the AER, is there a need to request/advise the EPA of any modifications

to the existing WWDL? - List reason - Eg. Additional SWO identified, failure to complete specified

works within date - IP dates not being met and will not be met in the short-term”

It has not yet been established the extent of these works, the associated costs and the funding

streams required to provide such works.

Page 45: Dungarvan Waste Water Treatment Plant of catchments in Dungarvan and is pumped from these catchments to the main pump station in Shandon from where it is pumped to the new waste water

45

C.4 Report Statistics:

“Has the Improvement Programme passed or will pass the Schedule A3 & C Dates?– What is the

Estimated completion date? - upgrade of SW2 & SW3 to emergency overflow due 01/11/2011. No

date is given and WCC may seek a technical amendment in this respect”

Agreed, Waterford County Council will seek a Technical Amendment to this requirement once the

solution has been defined and funding provision / funding timelines identified.