DULLES AREA HIGHLIGHTS
Gary GarczynskiCommonwealth Transportation BoardNorthern Virginia District
Committee for DullesAugust 4, 2016
Smart Scale (formerly HB2) Overview
• Round 1 completed with the adoption of the Six-Year Improvement Program in
June; overall, 19 projects awarded over $500M in Smart Scale funds in NOVA.
• Preparation for Round 2 of Smart Scale underway; applications to be accepted
starting August 1, 2016 and continuing through September 30, 2016.
• Scoring process will again consider factors of congestion mitigation, economic
development, accessibility, safety, environmental quality and land use.
• Congestion mitigation remains the highest weighted factor in NOVA (45%).
• To be eligible for funding, all projects must meet a need identified in VTrans 2040
for a corridor of statewide significance, regional network, urban development
area, and/or a safety need.
• In July, the CTB considered minor changes to measures, policy documents,
application and administrative processes based on lessons learned in Round 1.
• Online application tool has been expanded to include other funding programs,
including Revenue Sharing Program, Transportation Alternatives Program,
Highway Safety Improvement Program and Bicycle-Pedestrian Safety Program.
TRANSFORM 66
Outside the Beltway
• Three regular lanes in each direction.
• Two express lanes in each direction.
• High-frequency bus service with
predictable travel times.
• Direct access between the express
lanes and new or expanded commuter
lots.
• Improvements to Rte 28 interchange.
• June 2016 – FONSI issued by FHWA.
• 2017 – Start of construction if funded.
Inside the Beltway
• Move more people.
• Enhance connectivity.
• Improve transit service.
• Reduce roadway congestion.
• Increase travel options.
• 2017 - HOV and EZ Pass changes.
• 2018 – Start of construction of 3rd
eastbound lane.
Projects in Design
Route 7 Interchange at Battlefield Pkwy
• Preliminary engineering underway to
replace at-grade intersection with an
interchange.
• Total project cost - $58 million, $33
million funded to date.
• Winter 2018 – Design Public Hearing.
• Spring 2018 – Design-Build RFP if
funded.
Route 7 Widening
• Reconstruction and widening from four
to six lanes for 6.8 mi. from Reston
Avenue to Jarrett Valley Dr.
• Total project cost - $234 million, $178
million funded to date.
• November 2016 – Design Public
Hearing.
• 2018 – Start of construction if funded.
Projects in Design
Belmont Ridge Road at Dulles Greenway
• Interim widening from two to four lanes
using the existing bridge, 0.4 mi.
• Total project cost - $7.5 million.
• 2017 – Public Hearing.
• 2020 – Start construction.
Northstar Boulevard
• New road on new alignment.
• Administered by Loudoun County.
• Funding postponed to FY18 in order to
advance the Rte 7 widening in Fairfax
County.
• Two segments• Tall Cedars Pkwy to Rte 50, 0.6 mi., $36M.
• Rte 50 to Shreveport Drive, 1.6 mi., $64M.
Tall Cedars Parkway to Rte 50
Rte 50 to Shreveport Drive
Projects Recently Completed
Route 50 Widening
• Reconstruct and widen 3.7 mi. to six
lanes from Poland Road to Rte 28.
• Total project cost - $95 million.
• Completed December 2015.
Gloucester Parkway Extension
• Completion of 0.8 mi. missing
segment from Loudoun County
Parkway to Pacific Blvd.
• Total project cost - $30 million.
• Completed July 2016.
Projects Recently Completed
Route 7 Truck Climbing Lane
• Construct 2.6 mi. 3rd westbound lane
from Route 9 to West Market Street.
• Total project cost - $32 million.
• Completed December 2015.
Route 7 Widening
• Construct 1.2 mi. six lane facility from
Rolling Holly Drive to Reston Avenue.
• Total project cost - $34 million.
• Completed February 2016.
Projects Recently Completed
Route 29 Interchange at Linton Hall Road
• Grade separation of Route 29, Linton
Hall Road and Norfolk Southern
Railroad.
• Total project cost - $230 million.
• Completed November 2015.
Braddock Road / Pleasant Valley Road
Roundabout
• Replacement of four-way stop with a
roundabout.
• Total project cost - $5.8 million.
• Completed May 2016.
Projects Under Construction
Old Ox Road Expansion
• Reconstruction and widening from two
to four lanes from Evergreen Mills Road
to the Dulles Greenway, 5.3 miles.
• Total project cost - $108 million.
• May 2014 – Contract award.
• September 2015 – Begin construction.
• Summer 2018 – Construction complete.
I-66 / Route 15 Interchange
Reconstruction
• Construction of a diverging-diamond
interchange with intersection
improvements at Heathcote Blvd and
John Marshall Hwy.
• Total project cost - $59 million.
• May 2014 – Contract award.
• September 2015 – Begin construction.
• Fall 2017 – Construction complete.
Projects Under Construction
Route 28 Spot Improvements
• Construction of a fourth lane at congested spots along both directions of a 5.7
mi. segment of Route 28 between Route 50 and Sterling Boulevard.
• Total project cost - $17 million.
• October 2015 – Begin construction.
• Summer 2017 – Construction complete.
Projects Under Construction
Belmont Ridge Road Widening
• 1.9 mi. of four lane median divided
roadway from Hay Road to Gloucester
Pkwy with overpass at the W&OD Trail.
• Total Project Cost - $61 million.
• September 2015 Contract Award
• September 2016 – Begin construction.
• Fall 2018 – Construction complete.
Route 7 Interchange at Belmont Ridge
Road
• Single Point Urban Diamond
Interchange and 0.9 mi. of four lane
median divided Belmont Ridge Road to
Gloucester Pkwy.
• Total Project Cost - $80 million.
• October 2015 – Begin construction.
• Fall 2018 – Construction complete.
Projects Under Construction
I-66 Widening
• Widen from four to eight lanes for 4.7
mi. from Route 15 to Route 29.
• Total project cost - $65 million.
• April 2014 – Begin construction.
• Summer 2016 – Construction
complete.
Route 7 Bridge Over Dulles Toll Road
• Bridge deck replacement and widening
to six lanes.
• Total project cost - $45 million
• April 2016 – Begin construction.
• May 2018 – Construction complete.
Thank you!