Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Thursday, August 26, 2010 2:00 to 3:00 p.m. EDT

description

Duke Energy Carolinas Quarterly Stakeholder Meeting. Independent Entity Services Thursday, August 26, 2010 2:00 to 3:00 p.m. EDT. Agenda. Follow-up Action Items from May 13, 2010 Daylight Saving Time Change – Fall Back OASIS Transmission Outage Postings Load Data 676-E & 729 Impacts - PowerPoint PPT Presentation

Transcript of Duke Energy Carolinas Quarterly Stakeholder Meeting

Page 1: Duke Energy Carolinas Quarterly Stakeholder Meeting

Duke Energy CarolinasQuarterly Stakeholder

Meeting

Independent Entity ServicesThursday, August 26, 2010

2:00 to 3:00 p.m. EDT

Page 2: Duke Energy Carolinas Quarterly Stakeholder Meeting

222

Agenda Follow-up Action Items from May 13,

2010 Daylight Saving Time Change – Fall Back OASIS Transmission Outage Postings Load Data 676-E & 729 Impacts NAESB Update - Wholesale Electric

Quadrant Open Access Transmission Tariff Filing Duke – Progress Energy Non-Firm ATC

Agreement Wrap-up

Page 3: Duke Energy Carolinas Quarterly Stakeholder Meeting

3

Action Items Follow-up from May 13, 2010

Transmission Outages posted on OASISWill be discussed later in this presentation

There were no other items that required a follow up.

Page 4: Duke Energy Carolinas Quarterly Stakeholder Meeting

4

Daylight Saving Time Change2010 Fall Back

Prepare to Fall Back – November 7, 2010– Back to Eastern Standard Time– At 1:59 ED time will fall back to 01:00 ES – Change Time Zones in Systems– Be aware of other TP’s practices for DST changes

OASIS/TSRs (Appendix I)

– OATI User Guide (MARCH 2010 | VERSION 2.0)– Time Change Creates an Additional HE0200– Profile across time change / 25 Hour Reservation Profile

ETS/Tagging (Appendix II)

– OATI User Guide (For Spring 2010)– Only recognizes One Time Zone

Page 5: Duke Energy Carolinas Quarterly Stakeholder Meeting

OASIS Transmission Outage Postings

As requested, Duke is posting the same transmission outages on OASIS as they are posting on the NERC System Data Exchange (SDX)• Use the Security Data Screen and select Security

Type Outage• Set other fields as desired

5

Page 6: Duke Energy Carolinas Quarterly Stakeholder Meeting

Load DataLoad is now on the OASIS

• To access, go to the Sys Data Menu and select Load Zone in the Type field

• Set the other filters as desiredOn Sept 1st, this will be the only

place to find Load Data

6

Page 7: Duke Energy Carolinas Quarterly Stakeholder Meeting

777

FERC Order 676-E & 729 Impacts

FERC 676-E & 729 Ordered on November 24, 2009, coordinated implementation for both orders require a completion date of April 1, 2011.

Re-bid of Partial Service WEQ 001-4.7 through 4.12• Rebid MW - Coming in the Fall OASIS Release• Rebid Price - Complete

Priorities for Competing Requests WEQ 001-4.14 through 4.16• NAESB Table 4-3 revised - Duke Business Practices Revised to incorporate• Firm Network is Tier 1

OASIS Home Page General Posting Standards WEQ-001-13 / MOD-001, 004 & 008

• Links, Order and Naming Convention- Complete• ATC Information Link - When ATCID, CBMID, TRMID are completed (no later

than 4-1-11) ATC Narratives and Questions WEQ 001-14, 15 & 16

• Zero ATC Narratives - webOASIS release on 8-25-10 expected to complete Template Change

• Change Narrative (TTC/ATC changes are 10% or more ) – same as above• ATC or AFC Methodology Questions – ATC Contact Person posted on OASIS

Page 8: Duke Energy Carolinas Quarterly Stakeholder Meeting

888

FERC Order 676-E & 729 Impacts

Actual & Forecasted Load WEQ 001-17• Actual Daily Sys-wide (includes Native Load) and Daily Native Peak Load –

Complete• Forecasted Daily Sys-wide (includes Native Load) and Daily Native Peak Load

– Complete Postbacks WEQ 001-18

• Requires a Postback Methodology document be posted on OASIS under the ATC Information Link – Posted when complete (on or before 4-1-11)

Grandfathered Agreements WEQ 001-19 • GFA MW value is required to be queried on OASIS systemdata template –

template complete• Must be identified in the TP’s ATCID – Posted when complete (on or before 4-

1-11)• Duke does not have grandfathered agreements

Use of CBM WEQ 001-22 / MOD-004• Requires Posting and Tracking of CBM use• Ability to query, view and audit on OASIS the use of CBM• TRM/CBM page on OASIS http://www.oatioasis.com/DUK/DUKdocs/cbm.html• Must be Identified in the TP’s CBMID – Posted when complete (on or before 4-

1-11)• Duke Energy Carolinas does not currently allocate Capacity Benefit Margins

(CBM) on its ATC Paths

Page 9: Duke Energy Carolinas Quarterly Stakeholder Meeting

999

FERC Order 676-E & 729 Impacts

Rollover Rights WEQ 001-20• Duke Business Practice 3.J has been modified to reference the 5yr/1yr

requirement• Service agreements with rollover rights queued prior to 4-01-09 will be

subject to the 5yr/1yr requirement on the first rollover date after 04/01/09

• webTrans Rollover functionality is in place • webOASIS Rollover functionality is expected in a Fall 2010 release

Rollover on Redirects – WEQ 001-9.7• FERC did not incorporate 001-9.7 with reference to Renewal

Rights on Redirects• Once adopted by FERC webOASIS and webTrans will be upgraded

to meet the requirement Conditional Curtailment Option WEQ 001-21

• CCO applies to requests for Long-term Firm Point-to-Point Transmission Service

• Upon request of the Transmission Customer Duke will accommodate CCO

• CCO service is treated as firm in calculation of ATC in the full amount reserved

• Tag NERC Priority 6 or Transmission Product code 6-CF during defined periods

• Required template changes and Management Tool are expected with a Fall 2010 release of webOASIS & webTrans

• Management, posting and notification processes done manually now

Page 10: Duke Energy Carolinas Quarterly Stakeholder Meeting

101010

FERC Order 676-E & 729 Impacts

NERC Standards for Duke Energy Carolinas• Available Transmission System Capability - MOD-001-1 • Capacity Benefit Margin Methodology - MOD-004-1• Transmission Reliability Margin Methodology - MOD-008-

1 • Area Interchange Methodology - MOD-028-1

Page 11: Duke Energy Carolinas Quarterly Stakeholder Meeting

111111

NAESB Update Wholesale Electric Quadrant

Network Service on OASIS – The timeline for completion of the recommendation was

extended – expect completion by OASIS subcommittee 4th quarter 2010

Coordination of Transmission Requests Across Transmission Providers

– Recommendation adopted by Executive Committee & sent to OASIS subcommittee

Proposed 3 Step Process • Customer flags the set of requests for service across multiple

systems (“linked group”). • Each Transmission Provider processes the request on its system

the same as it would process any request on its system (“pre-true-up final state”).

• Upon confirmation, the Customer determines the final capacity amount of each request (“true-up”), which must be equal to or less than the capacity offered. The amount of capacity the Customer confirms may vary per transmission system.

Page 12: Duke Energy Carolinas Quarterly Stakeholder Meeting

121212

NAESB Update Wholesale Electric Quadrant Parallel Flow Visualization for Eastern

Interconnect (Business Practices Subcommittee)– NAESB role is to provide a mechanism for determining

transmission service priority used by on-line generation and also to determine curtailment methodology that is fair

– NERC role is to develop IDC and associated tools to support Reliability Coordinator function

– The Business Practices Subcommittee (BPS) is working on NAESB role

• Interim Solution - posted and formal comments due August 30• Final Solution to be completed by November 1, 2011

Page 13: Duke Energy Carolinas Quarterly Stakeholder Meeting

131313

NAESB Update Wholesale Electric Quadrant

Electric Industry Registry– Transfers TSIN Registry from NERC to NAESB– Contractor selection nearing completion– Should be finalized by end of 2010

Page 14: Duke Energy Carolinas Quarterly Stakeholder Meeting

141414

Open Access Transmission Tariff Filing

In 2010 Duke Energy Carolinas will request FERC approval of a new rate for the Transmission Service under our Open Access Transmission Tariff (OATT). • Current rate was approved in 1996 and was based on 1994

data• Propose to move from a stated (fixed) rate to a formula rate

to be updated annually• Propose to have new rates in effect prior to the end of 2010• Holding discussions with our Network Customers prior to

filing the new rate with FERC• Some of rate impacts have been evaluated but because

discussions are ongoing, nothing has been finalized

Page 15: Duke Energy Carolinas Quarterly Stakeholder Meeting

151515

Duke - Progress EnergyNon-Firm ATC Agreement

• Duke Energy Carolinas and Progress Energy Carolinas have negotiated an agreement addressing Non-Firm parallel flows across the PJM interface

• Implementation details and timeline are to be determined

• Combined Non-Firm ATC with PJM will be calculated and posted on Duke and PEC OASIS sites

• Customers will still reserve transmission service with either PEC or Duke

Page 16: Duke Energy Carolinas Quarterly Stakeholder Meeting

161616

Wrap-up

Proposed Next Quarterly Stakeholder Meeting– Thursday, December 2, 2010 – 2 p.m. to 3

p.m. ETCustomer Suggested Topics?

– This is the forum for discussing emergent topics (Upcoming changes, stakeholder input)

Questions and Comments

Page 17: Duke Energy Carolinas Quarterly Stakeholder Meeting

17

AppendixAppendix 1 Title

PageOASIS / TSRs 2010 Fall Back - OATI User Guide

18OASIS / TSRs 2010 Fall Back - Create a TSR that Crosses the Fall Change 19OASIS TSRs / Starting in ED - Ending in ES Option 1 & Option 2

20OASIS TSRs / Starting in ED - Ending in ES Option 3

21

Appendix 11Title

PageETS/Tagging 2010 Fall Back – OATI User Guide (4-6 weeks prior to

11/7/10) 22ETS/Tagging 2010 Fall Back - Creating a Tag that Crosses the Fall

Change 23ETS/Tagging 2010 Fall Back - Using Daylight Time Submitting One Tag

24ETS/Tagging 2010 Fall Back – Tag View / Change Time Zone 25

Page 18: Duke Energy Carolinas Quarterly Stakeholder Meeting

18

OATI OASIS User Guide webOASIS - HELP – Table of Contents – DST Cutover Document

OASIS / TSRs 2010 Fall Back

Appendix I

Opens to the WEBOASIS TIME ZONE USER GUIDE

Page 19: Duke Energy Carolinas Quarterly Stakeholder Meeting

19

Create a TSR that Crosses the Fall Change• “Option 1”

– Start TSR in ED 11/07/10 00:00 & End on or after 02:00 in ES on 11/07/10

– OASIS defaults to the correct time zone (Based on Start and Stop Time)

• “Option 2”– Create a profiled TSR that crosses 02:00– OASIS will populate 2 - HE 0200s (one in both ED & ES)

• “Option 3”– Create a 25 hour reservation profile TSR – OASIS will populate 2 - HE 0200s (one in both ED & ES)

Appendix I OASIS / TSRs 2010 Fall Back

Page 20: Duke Energy Carolinas Quarterly Stakeholder Meeting

OASIS TSRs Starting in ED - Ending in ES

20

Appendix I

Option 1

System knows to adjust time zone based on date and time.

2 - HE 02:00’s

Option 2

System will add 2 HE 02:00’s when profiling over the time conversion

Profiled

Page 21: Duke Energy Carolinas Quarterly Stakeholder Meeting

OASIS TSRs Starting in ED - Ending in ES

21

Appendix I

To Create a 25 hour profile, Check the 25Hr box and select “Create”. 2 – Hour Ending 02:00 will be created, one ending in ED and the other ending in ES.

Option 3 – 25 Hour Profile

Page 22: Duke Energy Carolinas Quarterly Stakeholder Meeting

E-Tagging -2010 Fall Back

22

OATI User GuideTo Be Posted 4-6 weeks prior 11/07/10

webTag – Help – Forms/Documentation – User Guides/Requirements: – OATI instructions for tagging across the Daylight Saving Time conversion

Appendix II

Guide for the 2010 Fall Time conversion to come (4-6 weeks prior to 11/7/10) .

Page 23: Duke Energy Carolinas Quarterly Stakeholder Meeting

23

Creating a Tag that Crosses the Fall Change– Fall Time Change creates a 25hr day– One Tag or Two Tags

• Suggest Create Two Tags – One in Eastern Daylight Time

» Begin with the hours 0000 through 0200 ED– One in Eastern Standard Time

» Begin with the hours 0100 through 0000 ES– Change the default TZ to ES

» Misc / Misc User Options

– Verify your tags by re-checking them in both ED and ES• Verify Profile Total• Verify Hours with respect to Standard and Daylight

Saving Time

ETS/Tagging 2010 Fall Back

Appendix II

Page 24: Duke Energy Carolinas Quarterly Stakeholder Meeting

24

Using Daylight Time Submitting One Tag– To use this option, user must set time to ED

» Misc / Misc User Options – Begin @ 00:00 on 11/07/10 through 01:00 on11/08/10– Enter as a Delayed Tag– Change the default TZ to ES

» Misc / Misc User Options – Reopen Tag

» In Eastern Standard verify the end to be 00:00 on 11/08/10 (Note: Start time will show 23:00 11/06/10 ES)

– Revert your TZ back to ED – Re-open the Delayed Tag in Daylight Saving Time and

verify the hours and Profile are accurate.» In Eastern Daylight Saving verify the end to be 01:00 on 11/08/10 (Note: Start time will show 00:00 11/07/10 ED)

Verify your tags by re-checking them in both ED and ES time

• Verify Profile Total• Verify Hours with respect to Standard and Daylight Time

ETS/Tagging 2010 Fall Back

Appendix II

Page 25: Duke Energy Carolinas Quarterly Stakeholder Meeting

ETS/Tagging 2010 Fall Back

25

Appendix II

To change Time Zone Setting