    Remedial Works of Kantale Dam - DSWRPP

    Project Progress

    Item

    NoDescription

    2010Remarks

    Oct Nov

    2011

    OVERALL PHYSICAL PROGRESS TO END OF MARCH :2012

    80%

    2.0

    Monitoring & Safety

    Facilities9Piezometers installed. 200

    Nos Boundary stones casting

    finished, but not plaeced.

    V-notecs to be instaled. Levelling

    monuments -250 Concrete blocks -

    60%

    82%

    1.0 Preliminaries

    Dec

    3.1 Clearing Completed100%

    3.2

    Earth filling in eroded

    sections450-800m : 60% Finished (5000Cum)

    1225-1275m : Only Stripping

    1590-1615 : Only earth piling

    1615-2500: Not yet Started

    25%

    3.0Slope Stability and

    Seepage ControlOver all progress 34%

    35%

    * Super Bund Work is in progress62%

    Impts. to access road3.5 Not yet Started

    3.3 Const. of toe drain andaccess road Work is in progress(Access rd notcomenced)80%

    3.4Const. of drainage

    trenches20 trenches are completed out of 26

    85%

  • 8/2/2019 DSWRPP Progress Mar.31

    2/4

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprItem

    NoDescription

    2010Remarks

    Oct Nov

    2011 2012

    Dec

    3.6Impts. To existing rip-

    rapWork is in progress

    80%

    3.10 Clearing Completed100%

    3.11Earth filling in eroded

    sectionsCompleted

    100%

    * 87th mile post Bund Not yet Started

    * Bund After Spill Work is in progress70%

    3.14Earth filling in eroded

    sectionsEarth dumping at site -10,200m

    330%

    100%

    3.12

    Impts. To existing rip-

    rap at spillway

    abutments

    Not yet Started(Mobilized)

    *Connecting Bund-

    kantale & vendrasan

    Clearing work done, 500m3earth

    dumping at site10%

    Work is in progress as mentioned

    below57%

    4.1Construction of bathing

    stepsWork in Progress

    4.0 Structures

    50%

    3.15 Impts. to U/S slope Not yet started

    3.13 Clearing Completed

  • 8/2/2019 DSWRPP Progress Mar.31

    3/4

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprItem

    NoDescription

    2010Remarks

    Oct Nov

    2011 2012

    Dec

    4.3 Impts to LB Sluice house

    Roofing & Ceiling works are

    finished, front door has to be fixed80%

    4.4

    Repairs to Retaining

    wall (access to RB

    Sluice)

    Completed100%

    4.2Repairs to concrete in

    Spill way Ogee section to be done70%

    4.7Impts. to existing

    Surface drains

    partly catch pits work done, D/S

    rubble packing has to be done75%

    Not yet startedSeepage Control in RB

    Sluice barrels4.8

    4.5

    Impts to RB Sluice

    house

    Supper Structure & Roofing finised,

    But Door , Windows & flooring has

    to be done95%

    4.6Construction of guard

    houseNot yet started

    30%

    Radial Gates to main

    spill way5.1 Fixing parts for 6 gates are fabricated

    5.0Electro-Machanical

    WorksWork is in progress

    10%

    4.9

    Civil works for Electro-

    mechanical works in

    spill way and Sluices

    Not yet started

    4.10Const.of new Surface

    Drains and Side drainsWork is in progress

    100%

  • 8/2/2019 DSWRPP Progress Mar.31

    4/4

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprItem

    NoDescription

    2010Remarks

    Oct Nov

    2011 2012

    Dec

    5.3 LB Sluice Not yet started

    5.4 RB Sluice Not yet started

    5.2 Lighting of Spill area Not yet started