DSS 12 S4 03 Risk CheckList

download DSS 12 S4 03 Risk CheckList

of 8

Transcript of DSS 12 S4 03 Risk CheckList

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    1/8

    School of Computer Science & Software Engineering

    Bachelor of Computer Science (Digital Systems Security)

    CSCI321- Project

    Risk Check List - 27 February 2013

    Group: SS12/4B

    Khoo Jun Xiang 4000766 [email protected]

    Ang Wencan Stephen 4194032 [email protected]

    Goh Kheng Siang Joel 4187490 [email protected]

    Lim Sing Hui 4185948 [email protected]

    Low Jia Hui 4186448 [email protected]

    Supervisor: Mr Sionggo Jappit

    Assessor: Mr Tan Kheng Teck

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    2/8

    Design Specification [SS12/4B]

    Page 2 of8

    Document Control

    Title: Risk Check List

    Document Name: Risk Check List

    Owner Current VersionLast Change on

    Approved byDate Time

    Khoo Jun Xiang V0.3 27-Feb-

    2013

    8PM Project Manager

    Distribution List

    Name Title/Role Where

    Mr Sionggo Jappit Supervisor SIM-UOW

    Mr Tan Kheng Teck Accessor SIM-UOW

    Khoo Jun Xiang Project Manager SIM-UOW

    Low Jia Hui Software

    Architect

    SIM-UOW

    Goh Kheng Siang Joel Test Designer SIM-UOW

    Lim Sing Hui UI Designer SIM-UOW

    Stephen Ang DatabaseDesigner

    SIM-UOW

    Record of Revision

    Revision Date DescriptionSection

    Affected

    Changes

    Made by

    Version after

    Revision

    10/01/2012 Document Creation- Briefing

    and assign tasks

    All Khoo

    Jun

    Xiang

    0.1

    23/02/2012 Finalized on document ALL ALL 0.2

    27/02/2013 Update on final document ALL ALL 0.3

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    3/8

    Design Specification [SS12/4B]

    Page 3 of8

    Contents............................................................................................................................................................ 1Document Control................................................................................................................................ 21. Release Information ...................................................................................................................... 42. Records and Measures .................................................................................................................. 43. General Contigency ...................................................................................................................... 44. Major Risk .................................................................................................................................... 55. Minor Risk List ............................................................................................................................. 66. Risk Values................................................................................................................................... 87. Risk Checklist ............................................................................................................................... 8

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    4/8

    Design Specification [SS12/4B]

    Page 4 of8

    1.Release InformationProject: DB-Wrapper

    Internal Release Number: V1.1Related Documents: Design Specification

    Requirement Specification

    Project Document

    2.Records and MeasuresThe severity of a risk is its likelihood multiplied by its impact. Risks are classified as minor if they

    have low likelihood, negligible impact, or medium likelihood and marginal impact.

    Mitigation Plan Measures carried out now to reduce the likelihood and/or impact of the

    risk. Alternatively, risk could be accepted.

    Indicator A sign monitored to determine if the risk is beginning to have an impact

    on the project.

    Contingency Plan What to do if the risk does arise. General contingency plans are being

    specific

    3.General ContigencyCatastrophic Risk If a catastrophic risk occurs we will make an

    honest reassessment of the viability of the projectand notify the relevant project stakeholders

    Risk that consume development resources The project has a fixed deadline and presentationdate. The requirements are prioritized. If we delay

    our project completion time, we will reduceproject scope.

    The features specified are mostly essential If welose time, we will delay delivery.

    If we lose time, we will make time estimates for

    the remaining features, and meet with the

    customers to reconsider scope and delivery date.

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    5/8

    Design Specification [SS12/4B]

    Page 5 of8

    4.Major RiskName Description Likelihood Impact Plan Status Owner

    Requirements Requirements areonly partly known

    at project start.

    Stakeholders may

    not approve our

    proposal.

    Medium Critical toCatastrophic

    Requirementsare prioritizeaccordingly.

    Indicator:Track the raterequirements

    are discovered.

    Contingency:

    Communicate

    with client

    regularly

    Amber RequirementLead

    Communication Communicationproblems indevelopment

    team.

    They might have

    problem

    expressing their

    ideas/views

    Medium Critical Development

    team could

    repeat what

    the other

    member has

    mentioned to

    prevent

    miscommunic

    ation.

    Green Team Leader

    Acceptance Stakeholders mayaccept sub-

    standard product,

    or product that

    exceed our level

    of capabilities .

    Medium Critical Customers areasked to

    declare

    acceptance

    criteria as each

    release is

    planned.

    Green Client

    Scope The total features

    requested may be

    beyond what the

    development team

    can deliver in the

    time available.

    High Marginal Assign levels

    of important to

    the use cases.

    Review of

    project scope

    after 6 months.

    Green Client

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    6/8

    Design Specification [SS12/4B]

    Page 6 of8

    5.Minor Risk ListName Descripti

    on

    Likelihood Impaction MitigationStrategy

    Status Owner

    Estimate Thedevelopmentteam might

    not be ableto estimatethe worktime.

    Medium Marginal The development teamwill gain experience inestimating the work,

    and deliver the firstestimates after 3months. We willcompare estimatedwork to actual work.

    Green Project

    Manager

    Correctness The systemas delivered

    may havelow take-up

    because of alack of

    confidencein its

    correctness.

    Low Catastrophic Contingency: stopdevelopment of new

    features until thequality of the existing

    code is assured.

    Green Team

    Leader

    Usability The systemas deliveredmay havelow take-up

    because ofpoorusability.

    Low Critical Produce a UserManual to guide End-Users on using the

    product.

    Green UI

    Designer

    Desire The statedrequirementsmight notmatch thestakeholders'desires andambitions forthe system.

    Low Critical Incremental deliveryof versions will

    provide experience ofusing the system,which will help thecustomers to identifythe real requirements.

    Indicator:Developer misleadingthinks that they knowwhat the stakeholder issaying

    Stakeholder sayingDevelopers know whatthey mean

    Contingency: RequestStakeholder to reviewrequirements regularly.

    Green Client

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    7/8

    Design Specification [SS12/4B]

    Page 7 of8

    Changes Afterrequirementshave beendocumented

    and agreed,development

    activitiesbegin to

    based onthem, first

    design thenimplementati

    on.

    If therequirements

    changes thenprevious

    effort iswasted.

    Low Critical A change controlprocedure is required,so changes are onlymade when the cost is

    worthwhile.

    Indicator: Comparecost of change to new

    development.

    Contingency: Requeststakeholders review of

    requirements regularly.

    Green Project

    Manger

    Process Somedevelopersmay notagree onsomestandards

    Low Critical Discussions indevelopment teammeetings to change thestandard or the actual

    practice asappropriate.

    Green LeadDeveloper

    Maintainability The systemas deliveredmight behard tomaintain.

    Low Marginal Review of code formaintainability.

    Green LeadDeveloper

  • 7/29/2019 DSS 12 S4 03 Risk CheckList

    8/8

    Design Specification [SS12/4B]

    Page 8 of8

    6.Risk ValuesRed Serious Impact

    Amber Marginal Impact

    Green No / Little Impact

    7.Risk ChecklistDo the plans provide an indicator to detect

    each of the risks becoming active?

    Yes, if all activities are carried out as planned, we

    will know if any of the risks is maturing.

    No, some risks could creep up on us.

    Correct "risk owners" assigned to monitor the

    risks?

    Yes, for each risk the assigned owner can detect

    the indicator, can launch the contingency plan,

    and is the person who will suffer by the risk.

    Does each risk have a mitigation strategy, or is

    the risk acceptable?

    Yes, we have plans to control some risks, and

    have accepted others.

    Does each risk have a contingency plan? Yes, for each risk there is a contingency plan

    above.

    Has this Risk Control Plan been communicated

    to the development team and other

    stakeholders?

    Yes, this document is being posted to the project

    website. It will also be discussed at an early team

    meeting, and discussed with the customers before

    the commit to the project.

    In the light of these risks, is the project worth

    carrying out?

    Yes, it is a low risk project.