DS BOOSTERS ATHLETIC CAMPUS CAMPAIGN

INVESTING IN OUR COMMUNITY’S YOUTH

April 2012

DS BOOSTERS ATHLETIC CAMPUS CAMPAIGN

INVESTING IN OUR COMMUNITY’S YOUTH • Total Project Cost $ 3M– All Phases– 3 to 4 years

• Current Goal $ 2M– Complete Fundraising by May 2012– Two Turf fields by September 2012

• Minimum Goal to Start Project $ 1M– One Turf Field by September 2012

Investing in our Community's Youth

What is the Athletic Campus Master Plan

Three Phases• Phase 1

– Add 1 New Synthetic Turf Stadium Field (replaces current grass)– Repair Track Drainage System – Regrade Booster Field #3

• Phase 2– Move 4 Current Tennis Courts– Add 2 New Tennis Courts– Improve Baseball/Softball Fields (Regrade, move, add dugouts/safety fencing)– Reconstruct Junction Street Field - (current football practice field)– Option - Add New Synthetic Turf Field on Junction Street

• Phase 3– Add 2 New Multi-purpose Grass Fields on Farm Street– Enhance Walkways, Netting & Appurtenances

Investing in our Community's Youth

Goal: Reconstruct existing fields/facilities and develop new fields to better meet the needs of the athletes in our community

Why is the Master Plan Needed?

• The Dover Sherborn Community needs turf fields to maintain and excel in our sports programs

• 82% of DSHS Students participate in athletics – 27 Sports - 43 Teams - 3 State Championship Teams in past 3 years

• 10 Outdoor Fields ~ 2,387 Team Events ~ 894 Team Athletes• 40% of the Fields exceed “maximum use” criteria by 20%

– Causing Deterioration!

• Demand for fields increasing with active Youth and Adult Sports• Current fields require significant cost to maintain

Investing in our Community's Youth

Sports are an integral part of the Dover Sherborn Community

A strong athletic program and facilities are pillars of our community

How will it benefit our Community?

• New and Improved Fields will:– Improve safety– Solve “maximum use” issues– Make DS teams more competitive, with training on turf– Provide options for “early” spring training– Reduce “rain outs”– Allow for additional sporting events/uses– Provide approved facilities for State Competition– Give Youth & Adult Sports additional space for

practices/games, especially on weekends– Provide options for building Community Spirit (Pep Rallies,

Camps, etc)

Investing in our Community's Youth

Project Cost

Investing in our Community's Youth

Location FY 2012 FY 2013 FY 2014 Total

PHASE I

Stadium Field $ 850,000

Booster Field $ 50,000

PHASE II

Tennis Courts $ 260,000

Baseball/Softball Improvements $ 140,000

Reconstruct Junction Street Field $ 360,000

Incremental $ for Turf on Junction Street Field (Optional) $ 390,000

Phase III

Two new Grass Fields Farm Street $ 315,000

Site Improvements $ 125,000

Sub-Total $ 900,000 $ 1,150,000 $ 440,000 $ 2,490,000

Soft Costs 5 - 7 % $ 63,000 $ 80,500 $ 30,800 $ 174,300

Project Contingencies 10- 15% $ 135,000 $ 172,500 $ 66,000 $ 373,500

Phase Total $ 1,098,000 $ 1,403,000 $ 536,800 $ 3,037,800

Subtotal without Optional Phase $ 2,562,000

Investing in our Community's Youth

DS BOOSTERS ATHLETIC CAMPUS CAMPAIGN

INVESTING IN OUR COMMUNITY’S YOUTH