DS BOOSTERS ATHLETIC CAMPUS CAMPAIGN
INVESTING IN OUR COMMUNITY’S YOUTH • Total Project Cost $ 3M– All Phases– 3 to 4 years
• Current Goal $ 2M– Complete Fundraising by May 2012– Two Turf fields by September 2012
• Minimum Goal to Start Project $ 1M– One Turf Field by September 2012
Investing in our Community's Youth
What is the Athletic Campus Master Plan
Three Phases• Phase 1
– Add 1 New Synthetic Turf Stadium Field (replaces current grass)– Repair Track Drainage System – Regrade Booster Field #3
• Phase 2– Move 4 Current Tennis Courts– Add 2 New Tennis Courts– Improve Baseball/Softball Fields (Regrade, move, add dugouts/safety fencing)– Reconstruct Junction Street Field - (current football practice field)– Option - Add New Synthetic Turf Field on Junction Street
• Phase 3– Add 2 New Multi-purpose Grass Fields on Farm Street– Enhance Walkways, Netting & Appurtenances
Investing in our Community's Youth
Goal: Reconstruct existing fields/facilities and develop new fields to better meet the needs of the athletes in our community
Why is the Master Plan Needed?
• The Dover Sherborn Community needs turf fields to maintain and excel in our sports programs
• 82% of DSHS Students participate in athletics – 27 Sports - 43 Teams - 3 State Championship Teams in past 3 years
• 10 Outdoor Fields ~ 2,387 Team Events ~ 894 Team Athletes• 40% of the Fields exceed “maximum use” criteria by 20%
– Causing Deterioration!
• Demand for fields increasing with active Youth and Adult Sports• Current fields require significant cost to maintain
Investing in our Community's Youth
Sports are an integral part of the Dover Sherborn Community
A strong athletic program and facilities are pillars of our community
How will it benefit our Community?
• New and Improved Fields will:– Improve safety– Solve “maximum use” issues– Make DS teams more competitive, with training on turf– Provide options for “early” spring training– Reduce “rain outs”– Allow for additional sporting events/uses– Provide approved facilities for State Competition– Give Youth & Adult Sports additional space for
practices/games, especially on weekends– Provide options for building Community Spirit (Pep Rallies,
Camps, etc)
Investing in our Community's Youth
Project Cost
Investing in our Community's Youth
Location FY 2012 FY 2013 FY 2014 Total
PHASE I
Stadium Field $ 850,000
Booster Field $ 50,000
PHASE II
Tennis Courts $ 260,000
Baseball/Softball Improvements $ 140,000
Reconstruct Junction Street Field $ 360,000
Incremental $ for Turf on Junction Street Field (Optional) $ 390,000
Phase III
Two new Grass Fields Farm Street $ 315,000
Site Improvements $ 125,000
Sub-Total $ 900,000 $ 1,150,000 $ 440,000 $ 2,490,000
Soft Costs 5 - 7 % $ 63,000 $ 80,500 $ 30,800 $ 174,300
Project Contingencies 10- 15% $ 135,000 $ 172,500 $ 66,000 $ 373,500
Phase Total $ 1,098,000 $ 1,403,000 $ 536,800 $ 3,037,800
Subtotal without Optional Phase $ 2,562,000