DRIVE TEST-3G MAXIS/ERICSSONSWAP PROJECT
1www.elabram.com
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
2/17
Fundamentally, there are 7 different test cases for Maxis/Ericssonswap project cluster drive. Below are the 7 test cases and brief guidelinesthat DT Engineers should give attention to.
Test Cases Summary
2
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
3/17
MS 1-MOC
External GPS
USB Hub
LAPTOP A
MS1-PS
DONGLE
LAPTOP B
Drive test tools configuration for Round 1
MS 1-MOC
3
MS 2-MTC DONGLE
ScannerMS 2-MTC
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
4/17
MS 1-MOC
External GPS
USB Hub
LAPTOP A
MS1-PS
DONGLE
LAPTOP B
Drive test tools configuration for Round 2
MS 1-MOC
4
MS 2-MTC DONGLE
ScannerMS 2-MTC
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
5/17
External GPS
USB Hub
LAPTOP A
MS1-PS
DONGLE
LAPTOP B
Drive test tools configuration for Round 3
5
MS 2-MTC DONGLE
ScannerMS 1-MOS BOX
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
6/17
MS1-PS
DONGLE
LAPTOP B
Drive test tools configuration for Round 4
6
MS 2-MTC
Scanner
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
7/17
Test case 1-Mobile to Mobile Voice Call Setup Laptop A (refer diagram);
-UE 1/MS1:MOC (Voice Mobile originating call)-UE 2/MS2:MTC (Voice Mobile terminating call)-PS1:External GPS Receiver
Test Cases Summary
Test Case - 1
7
-Dongle/License Use the correct Command Sequence/Script Mode: Normal (Dual Mode) Monitoring aspect:
i)Call Drop
ii)Call Block
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
8/17
Test Case 2-Mobile to Mobile(MTM) Video Call
Setup Laptop A
-UE 1/MS1:MOC (Video Mobile originating call)
-UE 2/MS2:MTC (Video Mobile terminating call)
Test Cases Summary
Test Case - 2
8
-PS1:External GPS Receiver-Dongle/License
Use the correct command sequence /script
Mode: Lock Band to 3G(WCDMA Mode)
Monitoring aspect :i)Call Drop
ii)Call Block
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
9/17
Test Cases Summary
Test Case - 3
Test Case 3-PESQ Call
In essence, Test 3 requires a different test methodology. As for this
Case UE3 will be attached to a MOS Box and eventually the MOS Box will
be connected to LAPTOP A. The purpose of this test is to generate a long PSTN Call to a callgenerator setup at HQ ECM.
Using UE3 through MOS Box.
9
Setup Laptop A-MOS Box/MS1:MOC (PSTN Mobile originating call)
-PS1:External GPS Receiver
-Dongle/License
Use the correct command sequence /script
Mode: Lock Band to 3G(WCDMA Mode) Monitoring Aspect
i)PESQ SCORE(Speech Quality)
ii)Call Drop
iii)Call Block
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
10/17
Test Cases Summary
Test Case - 4
Test Case 4- Packet Switch Down Link(PSDL)
Setup Laptop B-UE 3/MS1:R99 PACKET CALL/PDP Connection
-MS2:Scanner
-PS1:External GPS Receiver
10
-Dongle/License Mode: Normal(Dual Mode),Lock to R99
Use external application to perform DL :FTP-File Zila/TEMS will onlyrecord RLC Throughput
Monitoring Aspecti)Average Download Throughput Rate
ii) PDP Status- Failure Event (PDP Drop)
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
11/17
Test Cases Summary
Test Case - 5
Test Case 5- Packet Switch UP Link(PSUL)
Setup Laptop B-UE 3/MS1:R99 PACKET CALL/PDP Connection-MS2:Scanner-PS1:External GPS Receiver
11
-Dongle/License Mode: 3G(WCDMA Mode),Lock to R99 Use external application for ftp transfer: FTP-File Zila Monitoring Aspect
i) Average Upload Throughput Rate
ii) PDP status/Event Failure (PDP Drop)
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
12/17
Test Cases Summary
Test Case - 6
Test Case 6- PS-CSSR(HTTP Load)
Setup Laptop B-UE 3/MS1:R99 PACKET CALL/PDP Connection-MS2:Scanner-PS1:External GPS Receiver
12
- ong e cense Use the correct command sequence /script Mode: Normal(Dual Mode),Lock to R99 Monitoring Aspect
i)PDP Failure Events (PDP Drop)
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
13/17
Test Cases Summary
Test Case - 7
Test Case 7- HSDPA&HSUPA-Static Test
Setup Laptop B
-UE 3/MS1:HS PACKET CALL/PDP Connection
-MS2:Scanner
13
- : x erna ece ver
-Dongle/License
External FTP Software-File Zila
Manual file upload and download utilizing file Zila
Mode: 3G(WCDMA Mode),Lock to HSPA Monitoring Aspect
i)PDP Status
ii)Average throughput rate.
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
14/17
Combination of Test Cases
In-order to save time and cost, a practical approach have been initiated
by transforming the combination of test cases into 4 rounds. Below are
specification of each round.
Round 1---------TEST CASE 1 + TEST CASE 4 (Drive Test)
14
Round 2---------TEST CASE 2 + TEST CASE 5 (Drive Test)
Round 3---------TEST CASE 3 + TEST CASE 6 (Drive Test)
Round 4---------TEST CASE 7 (Static Test)
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
15/17
Caution
Tools Setup :
Always setup one laptop at one time to avoid hassles
Follow all the instructions accordingly. Log files must be created at every beginning of test.
Log files must be named properly according to the ECM protocol
YYMMDD C R P T N where YY= ear, MM=month, DD=da ,
15
_ _ _ _ _
C=cluster name, R=round number, T=Test Type (e.g. VCMOC forvoice call MOC), N=Drive Tester initials.
Compress together all of the drive test logs at the end of drive testwith following naming YYMMDD_C_R_P.zip
Run the script in-order to test the functionality before recording
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
16/17
Caution
Tools Setup :
Always aware that the scanners RF readings must be better/higherthen UE.
Tune/adjust the RF cable gently in-order to get a better RSCP andEC/No Reading.
16
ug n a t e equ pments accor ng to t e sequence eg. - -PS1).
Check all the equipment properties before start recording.
-
8/3/2019 Drive Test 3g Maxis Eric Swap Project
17/17
Caution
During Drive Test:
Follow the orientation of route accordingly
Speeding Rules
-50/60kmph
Monitor all the test accordingly, and always alert on notification by
17
. .
Strictly follow all the protocols that have been set by ECM for eachtest.