ANNUAL REPORT 2016-17 DRILLING DEPARMENT OIL INDIA LIMITED

Transcript of DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell...

Page 1: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT

2016-17

DRILLING

DEPARMENT OIL INDIA LIMITED

Page 2: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

2

2016-17

Contents

1.0 PREAMBLE 2.0 INTRODUCTION 3.0 RECORDABLE & SIGNIFICANT EVENTS 4.0 MAJOR REASONS FOR SHORTFALL OF METERAGE 5.0 WORK OVER ACTIVITIES 6.0 DEVIATION 7.0 CEMENTING 8.0 RIG BUILDING 9.0 TECHNICAL SERVICES 10. EQUIPMENT & FISHING 11. HEALTH SAFETY & ENVIRONMENT 12. PLANNING & DATA SECTION 13. ADMINISTRATION 14. INSTITUTE OF WELL CONTROL TECHNOLOGY

Page 3: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

3

2016-17

1.0 PREAMBLE

Oil India Limited being an E&P Public Sector company of India, with its rich legacy, it

bears moral and corporate responsibility to contribute it’s best for strengthening

country’s energy security and hence the organization has its primary objective to

continuously endeavor for accretion of reserves and maintenance of production level. This

calls for drilling in logistically difficult and geologically complex boundary conditions.

Drilling Department is fully committed to achieve the organizational goals and the whole

work-force is relentlessly engaged as a team with dedication in carrying out the following

operations/ tasks to fulfill the targeted objective.

i. Drilling and completion of Exploratory & Development wells

ii. Drilling of infill and Water Disposal wells.

iii. Carrying out work-over/well servicing operations.

iv. Technical Services to support all the above operations.

v. To commensurate the successful completion of all the Drilling and Workover

(partly), Cementing services were carried out mostly through in-house resources

having only one hired support services.

vi. All administrative function in support of above operations & services which are to

be managed on 24X7 basis in spite of manpower constraints.

vii. First hand public relation function, Health, Safety & Environment function is

performed by field executives.

The challenges range from drilling shallow wells to deep Eocene wells, sub normal

to abnormally (high) pressure & temperature wells, development of ranked wildcat wells,

wells having straight, directional & horizontal trajectories are drilled having high

displacement profile. Servicing and enlivening of production wells of varied nature &

complicacies are also another challenge which is worth mentioning.

To carry out its drilling activities in the development and exploratory fields of

Assam & Arunachal Pradesh, Drilling Department utilized twelve (12) in-house drilling

Page 4: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

4

2016-17

rigs of varying capacities – six (06) 1400 HP, three (03) 2000 HP and one (01) each of 750

HP, 600 HP (for WDW) and 3000 HP. In addition to in-house fleet, Five (05) No of Charter-

Hire Drilling Rigs (03 No 1400 HP & 02 No. 2000HP) were also utilized for drilling

activities in Assam.

Drilling activity in the year 2016-17 was increased to achieve 1,59,987 M (51 nos

completed well) of drilling meterage compared to 1,38,339 M in the year 2015-16, which

is approximately 15.6 % higher than previous year. This achievement is the all time

highest in the history of OIL.

214 Work over jobs were completed against target of 200 jobs resulting achievement

of 107 % which is also all time highest achievement in the history of OIL.

It is also worth mentioning that adherence and compliance of more and more

stringent Safety & Environmental regulations and policies by statutory bodies like DGMS,

OISD, and APCB & CPCB were also remained a major challenge with limited supervisory

staff. All out efforts were being made for full compliance of the statutory regulations and

to ensure safety of men & machines.

ADOPTION OF NEW TECHNOLOGY- QUALITY ASSURANCE:

To remain competitive with quality enhancement in today’s global market as an E&P

company, Drilling Department continuously adapted itself to the environment by

inducting various new technologies & appropriate measures. Some of the major projects

in continuation are

Advanced Instrumentation System

IRD (Independent Rotary Drive)

MWD (Measurement While Drilling)

2000 HP VFD Rigs

Iron Roughneck

MAJOR ACHIEVEMENT:

2 (two) numbers 2000 HP VFD Drilling Rigs (V-1 & V-2) were purchased from

M/s CPTDC and same were installed and commissioned at Drilling locations MFJ

and MFK on 23.08.2016 and 28.08.2016 respectively

Page 5: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

5

2016-17

1 (one) number 100T capacity Workover Rig , 3 (there) numbers 125T capacity

Workover Rigs and 1 (one) number 125 T capacity Workover Rig with Mud tank

system were purchased from M/s Drillmec S.p.A and all the rigs were installed

and commissioned within 31.03.2017 .

1 (One) number Spare Statics (Mast & Sub Structure) was procured from M/s

BHEL and same was installed and commissioned in S-1 Drilling Rig

87% of total asset of Drilling department has been physically verified against the

target of 80%

All the newly procured capital items have been capitalized on time

All the unserviceable equipment has been written off during this period.

MAJOR PROJECTS IN HAND:

• Commissioning of 02 Nos of Iron Roughnecks in 2000 HP VFD drilling rigs by

August /September 2017.

• P.R has been raised and tender has been floated to procure 04 Nos new generation

mobile Workover Rigs and expected to be commissioned by December ’2018

• IRD (06 No.) – Materials arrived. 04 nos successfully commissioned and remaining

02 nos commissioning is in progress depending on Rigs operation

• Modification of mast & substructure of retired NAT-110MA rig to make compatible

with Branham type mast & sub structure by BHEL. Expected to complete the

modification by 2nd quarter of this year.

• 3 numbers of Disc Brake for 1400 HP Drawworks were received . Commissioning

of same by September ‘2017

• High Performance/Hybrid Bits are being procured.

• RSS compatible bits are being procured.

- Hiring Service for:-

• Charter Hired Service for 5 drilling and 12 Work over rigs.

• Horizontal Drilling services with tools, equipments and consumables.

• J- Bend Drilling services for high tech wells with tools & equipments and

consumables.

Page 6: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

6

2016-17

• Hiring of MWD-SDMM-Jar along with services of expert

• Cementing services along with tools & equipment and experts.

• NDT of mast and substructure

• NDT for tubular along with handling tools and equipment.

• Effluent Treatment Plant along with unit and consumables

• New Item procurement in progress for increasing work efficiency & reducing fatigue

of work force at rigs, thereby enhancing HSE standards

• High Performance Bit has been made stock item for regular use after vigorous field

trial.

Note:

Major problems being faced in enhancing the target achievement of Drilling & Work over

operations are mainly attributable to acquisition of land, preparation of plinth during

rainy season and environmental issues which has direct impact on timely availability of

locations for the rigs. During the year under review, a total of around 0.82 Rig Year losses

have been recorded for the said reasons. It is expected that the proposed J-bend &

Extended reach directional drilling will partially curb the above issues.

Page 7: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

7

2016-17

2.0 INTRODUCTION (Performance & Achievements)

For smooth and effective functioning of all the above activities the department comprises

of the following sections.

a. Drilling Operation

b. Work-over Operation

c. Deviation Cell

d. Cementing

e. Rig-building

f. Drilling Technical Service

g. Equipment & Fishing

h. Health Safety and Environment

i. Planning and Data Section

j. Administration

k. Well Control Training School

Page 8: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

8

2016-17

Drilling: Target Vs Achievement

TARGET (BE) ACHIEVEMENT

% BE TARGET

MTRG. WELLS MTRG WELLS

EXPLORATORY 82501 21 62606 18 75.9

DEVELOPMENT 65014 22 63595 18 97.8

NAG (Devl) 20709 6 18836 6 90.9

WDW (Devl) 10,500 7 14950 9 142.4

TOTAL 178724 56 159987 51 89.5

EXPLORATORY DEVELOPMENT TOTAL

TARGET 82501 96223 178724

ACHIVEMENT 62606 97381 159987

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

200000

MET

ERA

GE

TARGET VS ACHIVEMENT

Page 9: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

9

2016-17

QUATERLY METERAGE ACHIEVEMENT:

CATEGORY QUARTER-1 QUARTER-2 QUARTER-3 QUARTER-4

EXPLORATORY 18963 12953 17416 13274

DEVELOPMENT 11319 19601 14305 18370

NAG (DEVL) 0 2350 9913 6573

WDW (DEVL) 4378 3027 3225 4320

TOTAL 34660 37931 44859 42537

Quarter-1 Quarter-2 Quarter-3 Quarter-4

EXPLORATORY 18963 12953 17416 13274

DEVELOPMENT 15697 24978 27443 29263

TOTAL 34660 37931 44859 42537

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

MET

ERA

GE

QUARTERLY ACHIEVEMENT

Page 10: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

10

2016-17

3.0 RECORDABLE & SIGNIFICANT ACHIEVEMENTS

The total meterage 1,59,987 m. is the highest meterage achieved in the history of

OIL.

Total 214 no of Work over jobs completed for the year which is all time record for

OIL

Total numbers of 286 cementation jobs were carried out during the FY which is all

time highest. This comprises of 154 Primary jobs which is also highest and 132

secondary jobs.

Cement consumed is all time highest due to more numbers of 4 stage wells.

Installation and commissioning of 02 nos VFD rigs were successfully carried out.

A total of 09 numbers of 3512B DITA Caterpillar Power Packs have been procured

and commissioned in Rigs S#6 & S#8.These power packs have Acoustic Enclosure conforming to the latest sound level standards & extended exhaust stack height

which meets the guidelines prescribed by CPCB.

In order to comply with the latest emission norms and noise levels as prescribed by

CPCB, 06 (SIX) nos. of acoustic enclosures were procured for the CAT 3512A DITA

engines and same were commissioned in Rig S#1,S#2 & S#3 rigs.

Commissioning of 4 nos. of work over Rigs & one no drilling rig with solid control &

tank system for water disposal well procured against P.O. no.7950934 was

completed

At Loc: BGR, Maximum Horizontal Displacement of 2094m was achieved with TVD

of 3900 m. For this well, the deviation section designed the optimum well profile for

all the sections considering probable torque and drag issues.

Loc:MKB-1 was completed with 5 stage Casing policy ( two liners 7” and 5” with 7”

tie-back). It is the deepest well (5624m MD/ 5607m TVD) producing @ 70KLPD in

the history of OIL and the first planned 6” hole section with 5” liner completion.

Page 11: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

11

2016-17

4.0 MAJOR REASONS FOR REDUCTION IN DRILLING METERAGE

It may be noted that there has been considerable constraints in following areas which

resulted in reduced drilling meterage

A. Non-readiness of forward Locations & waiting for the same:

Total Loss of Days: 164 Days

Loss of Planned Rig Year: 0.45

Total Loss of Meterage: 4927 m

B. Critical Down Hole Problems (SUB SURFACE PROBLEM):

Total Loss of Days: 38 Days

Loss of Planned Rig Year: 0.10

Total Loss of Meterage: 1142 m

C. Rig-Repair (SURFACE PROBLEM):

Total Loss of Days: 98 Days

Loss of Planned Rig Year: 0.27

Total Loss of Meter age: 2944 m

D. Production Testing exceeding planned days (Extended PRODUCTION TESTING):

Total Loss of Days: 404 Days

Loss of Planned Rig Year: 1.11

Total Loss of Meterage: 12136 m

E. Environmental Problems: (Local problem. Bandh, Strike, blockade etc):

Total Loss of Days: 136 Days

Loss of Planned Rig Year: 0.37

Total Loss of Meterage: 4085 m

Page 12: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

12

2016-17

F. Miscellaneous Problems (Contract/Contractor related problems/other problems not

covered by above reasons)

Total Loss of Days: 174 Days

Loss of Planned Rig Year: 0.48

Total Loss of Meterage: 5227 m

H. Exploring in deeper horizon and due to logistic & environmental problem hampered

achievement of target meterage.

Note:

1. 178724 m drilling planned with 16.30 Rig Year for 2016-17. Hence, prorated per

days loss has been considered to be 30.04 M per day.

2. Thus a loss Of 30461 M has thus been recorded due to the above reasons for the

year 2016-17

SURFACE 10%

SUB-SURFACE 4%

ENVIRONMENTAL 13%

MISC 17%

EXTENDED PRODUCTION TESTING DAYS

40%

WAITING FOR LOC 16%

MAJOR REASONS FOR SHORTFALL

Page 13: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

13

2016-17

A GRAPHICAL COMPARISON ANALYSIS OF LOSS OF RIG YEARS DUE TO VARIOUS

REASONS DURING THE YEAR 2015-16 AND 2016-17

* PT- PRODUCTION TESTING

A GRAPHICAL COMPARISON OF AVAILABLE RIG YEAR VIS A VIS LOSS OF RIG YEAR

FOR LAST FIVE YEARS

0.23 0.13

0.67

0.47

0.72

1.21

0.27

0.1

0.37

0.48 0.45

1.11

SURFACE SUB-SURFACE ENVIRONMENTAL MISC WAITING FOR LOC EXTENDED PT DAYS

COMPARISON OF LOSS OF RIG YEAR

2015-16 2016-17

15 15

13.71

15.25 16.3

4.39 5.2

2.41 3.43

2.83

2012-13 2013-14 2014-15 2015-16 2016-17

RIG YEAR AVAILABLE VIS A VIS LOSS

RIG YEAR AVAILABLE LOSS OF RIG YEAR

Page 14: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

14

2016-17

COMPARISON OF DRILLING PERFORMANCE OF LAST TEN YEARS:

FINANCIAL

YEAR

TARGET

(Metres)

ACHIEVEMENT

(Metres) % OF ACHIEVEMENT

2006-2007 165000 105865 64.16

2007-2008 173500 125678 72.44

2008-2009 183000 107685 58.84

2009-2010 172000 130040 75.60

2010-2011 182150 109243 59.97

2011-2012 175104 124828 71.29

2012-2013 159715 126408 79.15

2013-2014 168310 105111 62.45

2014-2015

180330

130552

72.40

2015-2016 171590 138339 80.60

2016-17 178724 159987 89.52

159,715 168,310

180,330 171,590

178,724

126,408

105,111

130,552 138,339

159,987

2012-2013 2013-2014 2014-2015 2015-2016 2016-2017

TARGET VS ACHIEVEMENT COMPARISON

TARGET ACHIVEMENT

Page 15: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

15

2016-17

97026

130035

108623

153563

124142

105865

125678

107685

130040

109243

124830 126408

105111

130552

138339

159987

DRILLING METARGE FOR LAST 15 YEARS

METERAGE

76 98

105 100

87 87

119

88 87

66

107 120

130

154 170

214

WO JOBS DONE OF LAST 15 YEARS

NO OF JOBS

Page 16: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

16

2016-17

Information/ Data in details on the following aspect of Drilling operation are

enclosed at the end as Annexure:

a) Annexure – 1: Performance of Drilling rig(s) during 2016-17

b) Annexure - 2: Cycle & Comm. speed of Completed Drilling wells in 2016-17

c) Annexure – 3: Shut down analysis of Drilling operation for 2016-17

d) Annexure – 4: Performance of Drilling outfit since inception till 31.03.2017

e) Annexure – 5: Performance of WO outfit since inception till 31.3.2017

f) Annexure – 6: Work over job done during the financial year 2016-2017

g) Annexure - 7: Rig wise target vs actual comparison with rig year available & loss

5.0 WORK OVER ACTIVITIES

Work over Section of Drilling Department plays a significant role in facilitating the

servicing of multi natured wells for augmentation of crude oil and natural gas production.

In addition to few normal work over jobs, the year under review witnessed multifarious

jobs like Gravel Pack, Temporary abandonment Jobs, casing recovery job, Cement Plug

Jobs, Cement Squeeze Jobs, Cement Cleaning Jobs, Aphron ICS Treatment Jobs,

Conversion to water injection jobs, gas wells, Live Condition Perforation Jobs, Well Killing

Jobs, Acid Jobs, fishing jobs, completed milling jobs, control of annular pressure,

backing off, control of loss circulation, microbial paraffin, radial drilling job, EGMBE

treatment jobs etc.

Resources:

During the year, work-over operations were carried out with 12(twelve) in-house Rigs and

12 (twelve) chartered hired Rigs, partially. 4(four) Nos. new Drillmec Rigs were

commissioned during the end of the year 2016 replacing 4nos. of in-house rigs (Cardwell

B & C, Kremco K-600 and Skytop C ). 2(two) Chartered hired Rigs were mobilized in the

month of November and December, 2016 totaling to 12 (twelve).

Page 17: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

17

2016-17

Out of 12 (twelve) Nos. in-house Rigs, 9(Nine) Rigs were run by MMC (16 Hours a day)

and remaining 03 Rigs were operated by in-house crew. Charter Hire Rigs are in

operation round the clock.

TARGET VIS-À-VIS ACHIEVEMENT

TARGET ACHIVEMENT % ACHIVEMENT

TOTAL NO OF

JOBS (INCLUDING

WLD & PROD

SETUP)

200 214 107 %

COMPLETION OF CRITICAL WELLS AND MAJOR ACHIEVEMENTS:

Sl

No

Well No

Well problem

Job done

1 HJN#14

Several fish

including sinker

bar, piano wire

and TCI tool

Successfully recovered all fish and

completed the well

2 SMD#3

High pressure

gas well with

depth 4500m+

Well killed successfully with

parted tubing string and recovered

the fish.

3 HJN #36

Multiple fish

below packer and

inside tubing

Successfully recovered gauge

cutter, sinker bar, piano wire and

completed well of depth around

2600m within 6 days from the day

of well killing till production

testing completion

4 KJN#9

Mud motor fish

during cement

cleaning at depth

around 3800m

Successfully recovered fish.

Page 18: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

18

2016-17

5 MKM#26

To push/mill

packer in a

horizontal well

Successfully milled/pushed

packer to the desired depth.

6 MRN#107

Tubing string

with GLV

mandrel as fish

top

Successfully recovered fish.

It was a unique feat and proud moment for Work over Section as it has achieved

100 % target with highest numbers of well completed & increase in production

potential in the history of Drilling Department. This historic achievement was made

possible due to dynamic Operational Action Plan as well as System Development

inculcated and implemented throughout the year.

Action Plan for enhancing achievement:

1) Rig selection as per well requirement/programme.

2) Continuous persuasion for the progress of the supporting departments.

3) Reduction of time by proper well operation programme.

4) Close mentoring & frequent field visits by senior officials.

System Development for improvement:

1) Field application of high-tech communication.

2) Workover operation planning (Well wise /Job wise) prior to execution.

3) SOPs & Check list development and upgradation.

4) Continuous knowledge sharing (“Knowledge Management” initiative)

5) Periodic onsite & offsite operation training to Officers & Work persons

Page 19: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

19

2016-17

6.0 DEVIATION SECTION

Land acquisition problem became more and more severe over the years. During the last

financial year, except water disposal wells, all the wells were directional wells i.e. in other

word 100% wells were deviated.

Moreover, few wells were of very high displacement (horizontal drift >1600-to-1930mts)

with TVD>3800mts. These wells were really very challenging.

The Deviation section of Drilling Department, with its very limited manpower strength, is

directly associated with vast jobs of planning and designing of Directional wells along

with supervising execution during actual drilling operation. Deviation section endeavored

to meet the geological targets and supervised the drilling operation with the help of hired

directional services.

This section plan & design the optimum well profile for minimum torque, drag, anti-

collision and hydraulics issues as per the surface and sub surface co-ordinates given in

the draft Geological DDDP ( Depth Data Drilling Policy) prior to finalization of the

DDDP for a particular location.

Whenever directional service provider declines to accept a well profile due to torque, drag

or anti-collision issues, this section takes up the responsibility and assists the service

provider for drilling by providing look ahead correction plan with a new BHA and

hydraulics.

Hence the responsibility lies on this section to approve the drillability of the well.

During 2016-17 this section had taken up:

1. OIL achieved a record drilling meterage of 1,59,987 m during the year. Out of this

1,25,201m drilling meterage i.e. around 78.21% of the total meterage was achieved

from directional drilling where the section contributed in designing drilling

parameters along with BHA and supervising the directional drilling operations with

the help of directional service providers.

Page 20: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

20

2016-17

2. Field operation:

A. No of wells done (2016-17)

LIST OF J- BEND WELLS DRILLED (2016-2017)

SL/No. LOC

Type of

Well

Completion

Status

Hole

Size

MD(in

M) STAGES

THD (in

m)

KOP (in

m)

Max.

Inc.(in

Deg) Remarks

1 HYA J-Bend Full 12.25" 3155 3 898.49 400 19.94

Drilled

Successfully

2 HYK J-Bend Full 12.25" 2688.51 3 1050 200 26.69

Drilled

Successfully

3 HYI J-Bend Full 12.25" 2860 3 638.67 700 19.21

Drilled

Successfully

4 HYR J-Bend Part 12.25" 3342 3 784.82 1000 20.88 Dril inp.

5 HYE J-Bend Full 12.25" 3181 3 1597 170 34.31

Drilled

Successfully

6 HYF J-Bend Full 12.25" 3268 3 839.6 1100 24.63

Drilled

Successfully

7 HYU J-Bend Full 12.25" 2965 3 823.85 200 26.87

Drilled

Successfully

8 HYB J-Bend Full 12.25" 3000 3 1254 200 27.89

Drilled

Successfully

9 HYD J-Bend Full 12.25" 2628 3 1006.54 200 26.87

Drilled

Successfully

10 NLK J-Bend Full 12.25" 3600 3 793 1100 19.61

Drilled

Successfully

11 CJ J-Bend Full 12.25" 4085 4 1208 1600 31.75

Drilled

Successfully

12 HYP J-Bend Full 12.25" 2767 3 1067 850 39.22

Drilled

Successfully

13 HYS J-Bend Full 12.25" 3082 3 1737.89 180 41.53

Drilled

Successfully

Full 42

Part

Total Number of directional wells drilled= 50 (42F+8P)

42

8

Total Number of directional wells drilled= 50 (42F+8P)

42

8

J-Bend : 33 Nos.

S-Bend : 17 Nos.

Page 21: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

21

2016-17

14 DHL J-Bend Full 12.25" 4057 4 684 2000 20.68

Drilled

Successfully

15 DHK J-Bend Full 12.25" 4085 4 710 1930 20.46

Drilled

Successfully

16 DHJ J-Bend Full 12.25" 4139 4 865.54 1730 22.54

Drilled

Successfully

17

DHP-

1 J-Bend Full 17.5" 2253 4 338 1000 20

Drilled

Successfully

18 TAT J-Bend Full 17.5" 4200 4 1702 200 27.09

Drilled

Successfully

19 TT J-Bend Full 17.5" 4365 4 1579 1000 30.19

Drilled

Successfully

20 TAL J-Bend Full 12.25" 4156 4 1050 1510 24.87

Drilled

Successfully

21 BGU J-Bend Part 12.25" 4334 4 1353 1510 30.82

Drilled

Successfully

22 DHM J-Bend Full 17.5" 4262 4 1416 800 25.26

Drilled

Successfully

23 HXA J-Bend Full 12.25" 2509 3 630 550 20.22

Drilled

Successfully

24 MFI J-Bend Full 12.25" 4485 4 960 2650 35.58

Drilled

Successfully

25 CZ J-Bend Full 17.5" 4229 4 1681 200 25.84

Drilled

Successfully

26 HYL J-Bend Full 17.5" 4052 4 1254 810 24

Drilled

Successfully

27 HXW J-Bend Full 12.25" 2880 3 1306 180 31.64

Drilled

Successfully

28 DHX J-Bend Part 12.25" 4402 4 1256.7 1600 28.77

Dril inp.

29 BGR J-Bend Full 17.5" 4539 4 2094 500 34.22

Drilled

Successfully

30 BGT J-Bend Part 12.25" 4220 4 1126 1650 28.09 Dril inp.

31 BGK J-Bend Full 17.5" 4189.8 4 1494 200 27.7

Drilled

Successfully

32 BGV J-Bend Part 17.5" 4278 4 1418.75 700 24.55 Dril inp.

33 DHN J-Bend Full 12.25" 4129 4 915.32 1710 23.75

Drilled

Successfully

Page 22: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

22

2016-17

LIST OF S- BEND WELLS DRILLED (2016-2017)

SL/No

. LOC

Type of

Well

Completion

Status

Hole

Size

MD(in

M) STAGES

THD (in

m)

KOP

(in

m)

Max.

Inc.(in

Deg) Remarks

1 HYG S-Bend Full 12.25" 3185 3 481.68 200 26.32

Drilled

Successfully

2 DIB S-Bend Full 12.25" 3341 3 246.19 550 18.57

Drilled

Successfully

3 CG S-Bend Full 12.25"

3821.8

1 4 302.09 1750 20.05

Drilled

Successfully

4 HYJ S-Bend Full 12.25" 2530 3 472.05 200 22.92

Drilled

Successfully

5 HYN S-Bend Full 12.25" 3345 3 555.36 200 24.8

Drilled

Successfully

6 HYX S-Bend Full 12.25" 2888 3 592.81 200 26.63

Drilled

Successfully

7 HYH S-Bend Full 12.25" 3155 3 409.99 300 20.5

Drilled

Successfully

8 HYT S-Bend Full 12.25" 2890 3 451.43 200 24.43

Drilled

Successfully

9 DHF S-Bend Full 12.25" 3027 3 259.28 800 22.25

Drilled

Successfully

10 HYW S-Bend Part 12.25" 2845 3 428.98 200 18.47

Drilled

Successfully

11 SPB S-Bend Full 12.25" 4313 4 390.26 1450 20.98

Drilled

Successfully

12 BGS S-Bend Full 12.25" 3997 4 433.82 1710 22.31

Drilled

Successfully

13 HYM S-Bend Full 12.25" 2381 3 374.86 200 19.31

Drilled

Successfully

14

MKB-

1 S-Bend Full 12.25" 5612 5 114.24 3218 15

Drilled

Successfully

15 MFJ S-Bend Full 17.5" 4411 4 320.8 350 18.37 Dril inp.

16 MFK S-Bend Full 12.25 4462 4 106 2570 17 Dril inp.

17

WDW-

173 S-Bend Full 8.5" 1510 2 9 256 5

Drilled

Successfully

Page 23: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

23

2016-17

B. Logistics – (i) Transfer of hired directional tool & equipments

(ii) Liaise with IT dept for internet connectivity at well site for directional

service provider for the purpose of transmitting online data of ongoing

wells to Drilling Dept.

C. Inspection of hired directional tool and equipment

D. Supervise directional drilling operation at site whenever required.

E. This section is involved directly in the field for drilling directional wells in the event of

non-availability of hired directional services.

3. Off-site (office) job:

A. Monitoring directional drilling operation on 24 X 7 basis.

B. Guide service providers with the necessary look ahead plans and decision based

upon real time simulation on landmark software on the following parameters /

issues like;

a. Hydraulics for hole cleaning/drag/tight spot

b. Torque & Drag

c. BHA behavior & design

d. Well trajectories

e. Guide the service providers to give a limit of geological target radius for

smooth hole profile.

C. Well design and construction with the help of in-house LANDMARK software.

D. Feasibility study for selection of surface position for proposed LAF-II locations

are done prior to selection of the final surface location for the future locations.

E. Maintained attendance of personnel of hired services and time sheet preparation

for each directional well.

F. Invoice processing and preparation of SES

G. Approval of directional drillers and MWD engineers.

H. Verification of claimed EC application of directional tools & equipment put up by

service providers.

I. Processing of LIH claims, if any.

Page 24: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

24

2016-17

3.1. New Contract framework during the year 2016-17:

A. To avoid waiting period for directional drilling service, 4(four) numbers of limited

directional drilling contracts were formulated in a very short span of time in this

financial year. Same were being floated and 3 numbers of contracts

(CDG0778/DRLG/2016,CDG2565/DRLG/2016,OIL/6208211/DRLG/2017)

have already been awarded to Service provider and for the fourth tender

CDG4029L17, price bid opening is expected in the first week of April’2017.

B. Whip-stock tender CDG1053/DRLG/2017 for services of whip-stock setting

and window milling of 13.3/8” cased hole was formulated in a very short span

of time in this financial year due to downhole problems at Loc:DHL (first time

independent tender in OIL). The contract was awarded to Service provider and

completed the job successfully.

C. Contract CDG3225P17 for drilling 4 numbers of horizontal wells, 3(three)

numbers (Loc: HXT-H, Loc: DIC-H, Loc: DHC-H) in FHQ & 1(one) number (

Banghewala Field) in RP are in final stage.

D. ROTARY STEERABLE DRILLING SYSTEM (RSS) including advanced LWD tools

tender CDG2661P17 is in the final stage. Approval of revised BEC and FPWD

tool from CBC has been received.

E. For drilling 6” slim hole for Loc:MKB-1 and MFK , a new tender

CDG2565/2016 was formulated and floated in a very short span of time. The

contract was awarded to Service Provider.Till now one job at Loc:MKB-1 has

been done successfully.

Page 25: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

25

2016-17

4.0. Special Job Done during 2016-17:

4.1. Loc. TU:

Completed OIL’s benchmarking well for achieving highest ever THD of 1942m at TVD

3982m in record time. (1st time in NE India)

4.2. Loc.BGR:

Maximum Horizontal Displacement of 2094m was achieved with TVD of 3900m at Loc:

BGR. For this well, the deviation section designed the optimum well profile for all the

sections, with due consideration of probable torque and drag issues and also designed

the drill string considering abnormal surface torque.

It is to be noted here that, directional service provider M/s Schlumberger had declined to

drill the 8. ½” section due to expected surface torque of 28 Klb-fts (M/up torque of S

grade D/P).However, this section took the challenge to complete the well by designing the

BHA and hydraulics to keep the T&D within the permissible limit and was successful to

drill up to the target depth achieving highest ever displacement in OIL’s history of drilling

directional well of such high range of horizontal displacement.

Page 26: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

26

2016-17

4.3. Loc:MKB-1( Mechaki-5):

Well Mechaki-4 (Loc. MKB) was drilled as a vertical hole during the year 2014 and due to

various down hole problems, B, C & D-holes were drilled but could not be completed

successfully. Finally the said well had to be abandoned in the year 2015 due to severe

down hole problems.

Subsequently, Loc: MKB-1 was proposed to be drilled as a substitute for Loc.MKB well

from the existing plinth of Loc. MKB in 2016-17 to probe the up-dip extent of the

hydrocarbon bearing reservoirs within Paleocene/Eocene formations of the West Mechaki

structure.

Extensive planning and analysis was done by this section based on the last well’s history

and came up with 5 stage Casing policy ( two liners 7” and 5” with 7” tie-back) as a

solution. This helped to isolate the pressure variance zones (Fig-1). It is the deepest

(5624m MD/ 5607m TVD) producing from this directional well @ 70KLPD in the history

of OIL and the first planned 6” hole section with 5” liner completion. The well was

completed with scientifically designed in-house drilling fluid. This prestigious well of OIL

was drilled and completed successfully overcoming all down hole problems before

planned days. To address the bit walking issue, which was experienced in last location

due to formation dip and to ensure verticality of the hole, it was planned and engaged

directional drilling service from 17 ½” to 6” section hole section.

Figure-1

Page 27: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

27

2016-17

4.4. Loc: MFK:

Loc.MFK was also planned with 5 stage casing to avoid casing overlap in primary target

above kopili shale as explained below:

4.5. Loc. HYS:

This is the first J-profile well designed by in-house deviation expert with hole inclination

above 40 degree to overcome the presence of fault as intimated by G&R department based

on seismic data interpretation. In-house directional team took extreme precaution while

drilling and completed the well successfully.

4.6. Loc: TAT:

This well was present in cluster plinth of Loc: TT, TAL, TAD. So while designing the

directional well profile of Loc: TAT as per geological note, found severe collision issue with

Loc: TT & TAL. So, well was designed to turn its trajectory in the opposite direction of

Loc: TT & TAL and realigned it in the desired direction with minimum dog leg severity.

Well trajectory becomes 3D J-profile for the first time in the history of OIL. Well was

drilled and completed without any down hole complexity with 4CP.

Page 28: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

28

2016-17

4.7. Loc. DHL:

Loc: DHL was designed as J-bend well with KOP@1950m in 12.1/4” section with

maximum inclination of 19.34˚with a vertical section of 684m.Range of 12.1/4” section

was initially planned as (1970m-3400m). After completion of drilling the 17.1/2” hole

section and at the time of cementation of the 13.3/8″x68PPFxN80xBTC casing, the casing

string got disengaged at around 1870m during bumping of cement plug at 2500 PSI. The

string was matched on and annulus was cemented keeping shoe at 1951.18m (drilled

depth@1954m). While running in bit, got cement top @1166m; which was cleaned upto

1870m. However, no further progress observed beyond 1870m. Thereafter milling was

carried out with the help of number of tapered mills to the depth of 1872.35m, beyond

which no further milling was possible. Finally a cement plug was placed in the range of

1800m-1870m. The rig was released on 31-03-2016 and next cluster loc: DHK was

drilled. Meanwhile during drilling of Loc:DHK, a new contract was lined up for hiring of

expert service immediately for setting of whip-stock and window milling of 13.3/8” cased

hole at Loc:DHL so that rig idling time could be minimised. Consequently 13.3/8″ casing

scrapper trip was made up to cement top @1759m.Ran the whip stock assembly in

combination with the milling assembly consisting of lead mill, secondary mill and steering

mill. Scribed the entire string after orienting the face of the whip stock towards 126˚ TB

(S 54˚ E). Set the whip stock at the depth of 1751m and milling was done from 1738.5m

to 1747m and exited from the casing and drill a rat hole up to 1747.5m (0.5m

only).Subsequently, ran in bit to bottom and drilled a rat hole into the formation up to

the depth of 1750.50m.Thereafter pulling out of hole and ran in directional hook up

containing mud motor with 1.5˚ bend for further directional drilling upto TD and

completed the well successfully without any downhole anomalies. The well later started

producing @80KLPD.

Page 29: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

29

2016-17

5.0. Cost saving measures during 2016-17:

Enhanced ROP was achieved by

o Limiting sliding mode to the maximum extent during drilling of tangent

section in directional wells.

o PDC bit was successfully used to the maximum extent to reduce the drilling

time.

o All S-bend wells in dropping stage from 8 degree angle are done by in-house

rotary BHA; saving considerable amount of company’s outgo to directional

drilling service.

Effective utilization of hired directional services saved substantial amount of well

cost.

Page 30: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

30

2016-17

After expiry of drilling software consultant tenure from March’15, this section

managed and handled directional software on its own and delivered the quality

service to its stake holder and saved around 2,67,57,000.00 INR up to 31/03/2017

in terms of company’s financial outgo for engaging outside expert/consultant.

Without using North seeking Gyro tool for setting whip-stock at Loc: DHL and

scribed the entire string after orienting the face of the whip-stock towards desired

direction successfully, considerable amount to the tune of around INR

57,64,379.00 was saved.

Exclusive contribution of the section to the company:

i) This refers mainly to the land acquisition problem. Many directional wells were

drilled from existing plinth saving a huge amount against land procurement.

ii) Due to the success of the high displacement and high angle J-Bend wells,

targets once in-accessible, are now explored to hit those geological targets which

helped OIL to enhance the existing production.

6.0. Manpower position:

This section is headed by DGM-Drilling (Deviation), with 02 (Two) numbers of Executives

in Level-1, who are responsible for carrying out in house directional ( S-Profile) wells,

side tracking operations and also assist in monitoring the directional contracts under the

service providers.

7.0. HR update:

Absorption Superannuation Training on Directional Drilling

01 01 Nil

8.0. Others:

This section imparted total 25 nos. of summer trainees/apprentices from various

universities of the country during 2016-17.

Page 31: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

31

2016-17

7.0 CEMENTING SECTION

In search of liquid gold, Cementing Section plays a definitive vital role in successful completion and thereby the ultimate potential of a drilling well. Internationally it is

considered as a High Tech Operation.

During the FY 2016-2017 Cementing section successfully completed 286 no of cementing jobs which is all time highest, as against 267 no during previous FY. Screening & blending of oil well cement required for these entire Primary and Secondary jobs as well

as responsibility of transportation of screened virgin/ blended cement to various wells are done in-house by Cementing section.

Cementing section also played a major role in providing prompt & efficient back up services to drilling & work-over wells like Torque Turn services, Rig up & Rig down of

present instrumentation system, well killing pumps hook up and maintenance services, maintenance of compressors, power subs, various packers, Liner Hangers, Cement Retainers etc.

Hook up & maintenance of weight indicators, SPM meters, RPM meters, Torque gauges

ROP gauges, pressure gauges along with Record-O-graph are also carried out by Cementing section as a part of Instrumentation System. Furthermore, splicing of wire line sling of various sizes used for different wells and requirement of different sizes of slings to

various departments were also catered by cementing section.

Manpower:

A tabulated form of actual manpower position is shown below.

Year Sanctioned

man power Actual strength Shortfall

2008-09 103 81 22

2009-10 103 79 24

2010-11 103 72 31

2011-12 103 69 34

2012-13 103 67 36

2013-14 103 66 37

2014-15 103 78 25

2015-16 103 72 31

2016-17 103 67 36

Page 32: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

32

2016-17

Primary & Secondary Cementation Jobs:

Tabulated forms of cementing jobs performed during last five financial years are given below.

TYPE OF JOBS 2010-11 2011-

12

2012-13 2013-14 2014-

15

2015-16 2016-17

CONDUCTOR 32 40 37 33 37 41 46 ISOLATION 40 43 47 30 45 68 61 OIL STRING 32 32 32 27 29 26 43 LINER JOBS 4 4 3 5 6 1 4 SQUEEZE 32 21 47 30 25 64 60 PLUG 44 56 74 60 70 67 72

TOTAL 184 196 240 185 214 267 286

A comparative study of nature and number of jobs carried out during the last three financial years is depicted below graphically:

0

50

100

150

200

250

300

46 61

43

4

60 72

286

41 68

26

1

64 67

267

37 45

29

6 25

70

214

F.Y.2016-17 F.Y.2015-16 F.Y.2014-15

Page 33: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

33

2016-17

CEMENT USED:

Cement used in last eight years for carrying out Primary & Secondary cementing jobs is shown below.

Year

2007-0

8

2008-0

9

2009-1

0

2010-1

1

2011-1

2

2012-1

3

2013-1

4

2014-1

5

2015-1

6

2016-1

7

Cem

en

t

used,

MT

5266.0

0

4790.0

0

6258.0

0

6457.0

0

6328.7

0

6365.3

0

5080.7

0

7160.4

0

8106.5

0

10160.0

0

Major Achievement:

1) Total numbers of 286 (previous year 267) cementation jobs were carried out during

the FY which is all time highest. This comprises of 154 Primary jobs and 132 secondary jobs. This is all time record highest cementing jobs carried out by company in any financial year till now.

2) Cement consumed is all time highest due to more numbers of 4 stage wells.

3) Cementing is the only service provider from OIL who provide services to all Charter Hire rigs and thus saved a huge amount of company’s money.

4747 5266

4790

6258 6457 6328.7 6365.3

5080.7

7160.4

8106.5

10160

0

2000

4000

6000

8000

10000

12000

Cement used(MT)

Cement used(MT)

Page 34: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

34

2016-17

Modification job/Fabrication job:

Considering increase in secondary cementing job requirement, additional five nos. of Cement premix Tank with a Capacity of 700 gals are fabricated with Complete In-

house resources and facility out of which seven (07 ) numbers of such Tanks has already been put in service successfully. Two (02) numbers of in house fabricated

hopper sets are being used for fly mixing cement in drilling rig site and has been put in service.

Human Resource Development for Cementing Section:

Description Nos. of Employees Nos. of Executives

In house Training 20 0

In country Training 28 1

Overseas training 0 0

Total 48 1

Instrumentation Activities carried out in 2016 – 17 Introduction:

Instrumentation activities in Drilling Department have been carried out by Instrumentation

Department since its inception. Initially three numbers of engineers were recruited in June 2015 on

contractual basis to look after all Instrumentation activities in Drilling Department. Consequent upon

procurement of two numbers of 2000HP VFD Rigs, it was decided to setup a cell permanently for

instrumentation activites in Drilling Department. Subsequently, three numbers of engineers were

transferred from Instrumentation department to Drilling Department located in New Industrial

Area(NIA) to serve the purpose.

Objective:

Ensure safe and reliable operation of rig instruments installed in various Drilling and Workover locations.

Provide workshop and calibration services for all measuring instruments used in

Drilling, Workover and Cementing. Provide technical expertise in procurement of electronic & instrumentation systems

related to to Drilling. Ensuring that the required safety guidelines are followed as per statutory norms.

Page 35: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

35

2016-17

[A] Major Activities:

1. Commissioning of 2(two) numbers of 2000 HP VFD Rigs

a) Rig V1, Loc: MFJ

The commissioning of instrumentation systems of this Rig was commenced on

16th June and the commissioning of all instrumentation related systems was

completed by 22-Dec-2016. However, the Rig was spudded on 28-Aug-2016 and

drilling operation was in progress in the meantime. Following are the systems

commissioned for that Rig-

i) Drillwatch System with Rigsense Server

ii) Video Monitoring System

iii) Rig Intercom System

iv) Gas Monitoring System

v) Monitoring System of Top Drive System

b) Rig V2, Loc: MFK

The commissioning of instrumentation systems of this Rig was commenced on

3rd June and the commissioning of all instrumentation related systems was

completed by 22-Dec-2016. However, the Rig was spudded on 23-Aug-2016 and

drilling operation was in progress in the meantime. Following are the systems

commissioned for that Rig-

i) Drillwatch System with Rigsense Server

ii) Video Monitoring System

iii) Rig Intercom System

iv) Gas Monitoring System

v) Monitoring System of Top Drive System

2. Commissioning of 2(two) numbers of Drillmec make Workover Rigs

a) DM # 4, Location: NIA Yard, Commissioning Date: 25-Mar-2017

The following systems were successfully commissioned –

i) Data Acquisition System(DAS)

ii) Allision Transmission System

iii) Emergency Shutdown System

b) DM # 5, Loc: WDW # 180, Commissioning Date: 31-Mar-2017

The following systems were successfully commissioned –

i) Data Acquisition System(DAS)

ii) Allision Transmission System

iii) Emergency Shutdown System

3. Commissioning of OGMS

Commissioning of 9(nine) sets of Online Gas Monitoring systems has been completed in

May 2017. The last set was commissioned on 28-May-2016 in Rig S7, Location: DHK.

Page 36: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

36

2016-17

4. Revamping of 5 numbers of DG sets of Drilling TS

During the year, service was provided to revamp 5 numbers of Greaves 3G11 - 30 KVA

Gensets under the supervision of Drilling TS department.

[B] Hired Services

1. Hiring of Rig Up/Rig Down Services for of 3 Nos. Advanced Instrumentation System

by M/s NOV

Rig up & Rig Down services along with maintenance is being rendered by M/s NOV for 3

numbers of Advanced Instrumentation System of NOV for Rigs S4, S5 and M1(750HP

Mobile Rig) as per Contract No. 6206997. Total Rig up & Rig Down services carried out

during this year was 11(Eleven) and On call services carried out was 3(Three).

2. Hiring of Rig Up/Rig Down Services for of 6 Nos. Advanced Instrumentation System

by M/s Innovative Electronics

Rig up & Rig Down services along with maintenance is being rendered by M/s Innovative

Electronics for 6 numbers of Advanced Instrumentation System of Innovative Electronics

for Rigs S1, S2, S3, S6, S7 and S8 as per Contract No. 6206743. Total Rig up & Rig Down

services carried out during this year was 21(twenty one) and On call services carried out

was 3(three).

3. Annual Maintenance Contract for 10 Number Allison Transmission Systems of

5(Five) Workover Rigs

Preventive Maintenance job are periodically carried out by M/s G D Motors, Guwahati as

per the contract number 6107674. During this year preventive maintenance job of the

5(five) numbers RG Rigs were carried out twice, 1st from 26-Apr-2016 to 29-Apr-2016

and 2nd from 1-Dec-2016 to 5-Dec-2016. There was one breakdown maintenance job

which was carried out at Rig RG – E, Location: MKM # 42 which was a problem of gear

engagement.

[C] In-house Services

1. Online Gas Monitoring Systems

As per statutory requirement, 9(nine) numbers of Online Gas Monitoring Systems are in

operation for 9(nine) numbers of in-house Drilling Rigs. The rig up and rig down services

of these systems are carried out in-house in association with crew from drillometer of

cementing section. During this year the rig up and rig down jobs were carried out as per

the following –

Page 37: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

37

2016-17

Rig E 1400

S1

HYA HYG DIB

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

- - 21-Oct-16 15-Nov-16 18-Feb-17 28-Mar-17

Rig

E 1400 S2

CG HYK HYI HYR

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

25-Feb-16 27-May-16 - - 24-Nov-16 17-Jan-17

7-Mar-17

Rig E 1400

S3

HYE HYJ HYN HYX

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

19-Apr-16 18-Jun-16 22-Aug-16 4-Oct-16 29-Nov-16 16-Jan-17

2-Mar-17 17-Apr-17

Rig E 1400

S4

HYH HYT HYU

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

17-May-16 23-Jun-16 13-Dec-16 19-Jan-17 22-Feb-17 7-Apr-17

Rig

E 1400 S5

HYB HYD NLK

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

23-Mar-16 20-Jul-16 16-Sep-16 17-Nov-16 18-Jan-17 13-Apr-17

Rig E 1400

S6

CJ HYP DHF HYS

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

12-Mar-16 6-Jun-16 16-Aug-16 6-Sep-16 9-Dec-16 27-Dec-16

1-Feb-17 20-Mar-16

Rig E 1400

S7

DHK DHJ HYW

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

28-May-16 5-Jul-16 4-Jan-17 23-Feb-17 12-Apr-17

Rig E 1400

S8

DHP # 1 SPB SPB

Rig Up Rig Down Rig Up Rig Down

17-Mar-16 29-Apr-16 1-Dec-16 22-Mar-17

Rig 750 HP

M1

HWY HXA HYM

Rig Up Rig Down Rig Up Rig Down Rig Up Rig Down

19-Feb-16 26-Apr-16 21-Jun-16 16-Aug-16 1-Nov-16 10-Jan-17

** Green indicates the system is running in the respective rigs at present.

2. Day to Day Reports attended in Drilling Rigs

During the year, service was provided to drilling operation section for malfunction of

various rig instruments associated with various subsystems. 40 numbers of such jobs

were attended and rectified.

3. Day to Day Reports attended in Workover Rig

Service was also provided to workover operation section and during the year 33 such

jobs were carried out.

4. Day to Day Reports attended in Drilling TS

23 numbers of jobs were attended in Drilling TS section mostly for malfunction of

gensets and Air Dryer systems.

5. Day to Day Reports attended in Cementing Yard & Workshop Services

Page 38: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

38

2016-17

Apart from the above, service was also provided to Bulk Handling Plant of Cementing

section for malfunction of various instruments. 20 Numbers of calibration job was also

carried out during the year for various Pressure Gauges and Weight Indicators of various

rigs in workshop of Drillometer section.

[D] Overseas Training

Sl Training Duration Venue Participant's

Name

1

Training on Rig operation, maintenance, troubleshooting and working principle of various equipments of 100MT & 125 MT mobile (workover) rigs

29-Aug-16 2-Sep-

16 Piacenza, Italy

Abhijit Konwar

**********

8.0 RIG-BUILDING SECTION

Rig building section played a major role in achieving the Drilling meter age of 1,59,987

mtrs for the year 2016-17 by completing rig up, rig down and maintenance jobs within

stipulated time frame .The section also provided day to day on site maintenance support

for round the clock drilling and work over operations.

Major Achievements:

1. A total 32 Nos. of Rig- up & 34 Nos. of Rig-down operations were successfully carried

out with minimum downtime.

2. Under the “Refurbishment & Up gradation programme”, refurbishment job of Mast &

sub-substructure of S-6 rig is in progress at Rig building yard (NIA).

Modification of 110M (A) M&SS into a Branham M&SS is in progress at Rig building

yard (NIA).

Major Maintenance/ Overhauling/Repairing:

1. During the year overhauling jobs of Draw-works/Crown block /Rotary counter

shaft/Compound transmission/PTO/ Bevel Gear box/ Power divider etc. of the

Page 39: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

39

2016-17

Rigs S1,S2, S3,S4,S5, S6, S7,S8 and work over rigs were carried out at Rig building

yard /NIA.

2. Over hauling of draw works of Rig S-2, S-4, S-7 and S-8 were carried out at Central

workshop (CWS).

3. Over hauling of LMSS & LMMC of Rig S-4 and S-8 were carried out at Central

workshop (CWS)/ Rig Building yard.

Commissioning of new Rig & equipment:

1. Commissioning of one no of New Mast & Sub structure procured against P.O

no. 7907223 is completed at Loc.HYA in S1 rig.

2. Commissioning of LMSS & LMMC procured against P.O No. 7950890 was

commissioned in 01 no. of Rig (S-6) & it is in progress in S-1 rig.

3. Installation & Commissioning of IRD against P.O. no. 7906463 was completed in 2

nos. of Rigs.( S-1 & S-2)

4. Commissioning of 4 nos. of work over Rigs & one no drilling rig with solid control &

tank system for water disposal well procured against P.O. no.7950934 was

completed.

5. Completed modification of 05 nos RG workover rig substructure as per contract no

6108914.

Manpower Position & Separation:

As on 01.04.2017, total work persons in the section are 161. A total 16 (sixteen) no of

work persons were superannuated & 01 (one) no of work person expired during the year.

Training:

Total 08 work persons attended in-House training on MVT, FA, and GT& FF and 17 work

persons attended in-country training at various training institute and 2 nos work persons

attended foreign training.

Page 40: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

40

2016-17

9.0 TECHNICAL SERVICES

RIG SECTION

1. Targets and achievements with reasons for shortfall, if any, along with remedial

measures adopted during the year :

A. Targets:

Reduction of downtime by performing preventive and predictive maintenance

of equipments and technology up gradation.

Enhance customer satisfaction.

Adopt and promote safe & eco friendly technology to meet the latest

government emission norms.

Design & adopt best in class safety practice.

Build up people skill sets & capabilities to support organizational growth.

To supply potable water in Drilling Rigs.

Identification of Asset no. of the Equipment

Write-off and Disposal of un-serviceable equipment

Carry out major overhauling of Caterpillar engines and rig pumps

B. Achievements:

Drilling –Technical Service section, being a major servicing wing of drilling department played a vital role in achieving the highest meterage ever in the year 2016-17 by doing preventive and predictive maintenance job timely and completing rig up, rig down

pertaining to drilling rigs within stipulated time frame and negligible NPT.

Besides the day to day on site maintenance jobs to support the round the clock uninterrupted drilling operations, the major jobs done by the rig section to enhance performance have been highlighted below:

A total of 09 numbers of 3512B DITA Caterpillar Power Packs have been

procured and commissioned in Rigs S#6 & S#8.These power packs have Acoustic Enclosure conforming to the latest sound level standards & exhaust

stack height which meets the guidelines prescribed by CPCB.

Installation and commissioning of 02 nos VFD rigs were successfully carried

out.

Top overhauling of power pack-3 of Rig S#4 was carried out at the well

site(LOC:HYU) without any shutdown even after drilling was on.

Page 41: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

41

2016-17

All the D399 old Engines will be replaced phase wise by CAT 3512B DITA Engines. Inspection of 09 nos of 3512B DITA Caterpillar Power Packs are in

progress and will be soon shipped and ready for use in our rigs.

In order to comply with the latest emission norms and noise levels as

prescribed by CPCB, 06(SIX) nos of acoustic enclosures were procured for the CAT 3512A DITA engines and same were commissioned in Rig S#1,S#2 &

S#3 rigs.

Conversion of Two (02) nos of old 12-P-160 pumps from engine driven to belt

driven system has been completed by Gates Unitta Co. Pvt Ltd.

63 KVA gensets – 04 Nos. with acoustic enclosure were procured, inspected

and will be delivered by June 2017.

Action has been initiated for procurement of capital items sanctioned in the

budget.

Present & Future Projects, Commissioning of new infrastructure, Equipment & Facilities:

a. Present & Future Projects:

Diesel Engines – of 09 nos of 3512B DITA Caterpillar Power Packs with acoustic enclosure were procured, will be inspected and delivered by July

2017. A tender has been floated to procure a Standby Mud Pump of One (01) set. We are in the process of replacing the existing booster pump. As a part of

this process, purchase of 16 nos. pumps has already been initiated. A tender has been floated to procure 12 numbers of 63 KVA genset.

b. Commissioning of New Equipment/ Facility:

Installation and commissioning of 02 nos VFD rigs were successfully carried out.

06 (six) nos. of LDO tanks were commissioned in the in-house Drilling rigs (S#1 to S#6 rig). These LDO tanks replaced the old LDO tanks used in the rigs.

2. Adoption of State-of-the-art technologies, innovations & performance of

excellence with resultant benefits attained there from:

We are in the process of replacing the existing CAT D399 engines in power

packs with new engines which would be more fuel efficient, environment friendly with lesser emissions and conforming to CPCB norms. As a part of this initiative, 8 (six) CAT 3512 B engines with acoustic

enclosure have been in operation for more than a year. 09 (nine) new CAT 3512 B with acoustic enclosure have already been commissioned last year. Procurement process has already been completed for the purchase of 9 (nine)

more engines. These are energy efficient electronic engines which have reduced fuel consumption in the rigs. Also there is visible reduction in

the emissions and noise levels as these engines conform to the latest emission standards.

Page 42: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

42

2016-17

3. Outstanding achievements & records made, breakthroughs achieved & milestone crossed:

03 nos. of Safety Relief Valves have been hydraulically tested by means of our in

house Hydraulic Testing Unit which is statutory requirement as per OISD safety

norms.

4. Energy Consumption Pattern in Drilling Rigs (Excluding the Chartered Rigs):

Legend 2012-13 2013-14 2014-15 2015-16 2016-17

HSD Consumption in Liter.

69,45,241.5 63,20,508.5 84,31,133 69,98,080 89,31,869

Engine Running Hrs. 1,10,359 1,00,214 1,21,803 110900 1,24,882.6

Lube Oil Consumption in Liter

93,590 82,875 95,688 82742.5 1,00,514

Meterage Drilled in Meter

77,123 71,351 83,252 82477 1,05,319

HSD Cons/Meter Drilled

90.05 88.58 101.27 84.84 84.80

Lube Oil Cons/Meter Drilled

1.21 1.16 1.15 1.00 0.954

HSD consumption/engine R/hrs

62.93 63.07 69.22 63.10 71.5221

Fig 1: HSD Consumption Trend on Yearly Basis

6945241.5

6320508.5

8431133

6998080

8931869

0

1000000

2000000

3000000

4000000

5000000

6000000

7000000

8000000

9000000

10000000

HSD consumption in LTR

2012-13

2013-14

2014-15

2015-16

2016-17

Page 43: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

43

2016-17

Fig 2: HSD Consumption/Meter Drilled

Fig 3: Lube Oil Consumed/Meter Drilled

90.05 88.58

101.27

84.84 84.8

75.00

80.00

85.00

90.00

95.00

100.00

105.00

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

1.21 1.16 1.15

1 0.954

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

Page 44: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

44

2016-17

Fig 4: HSD Consumption/Engine Running Hours

5. Environmental Protection & Pollution control measures adopted with resultant benefits attained there from:

The exhaust stack height of power pack engines (CAT 3512 A ) of rigs S#1(one number) ,S#2(four numbers) & S#3(one number) was increased to 9.31

mtrs., above ground level (from the earlier 3.6 mtrs). This increase, in 06 (six) nos. engines meets the guidelines prescribed by CPCB regarding exhaust stack height for generating sets.

We are in the process of making this the standard stack height in all the engines which will be procured in the future.

WORKOVER SECTION

During the financial year 2016 – 2017, the Workover section of Drilling Technical

Service extended vital contribution & support services for achieving company’s target

through various measures set for Workover operation. The various activities of Drilling-TS

(W/O) during the period are detailed as below:-

62.93 63.07

69.22

63.11

71.522

58.00

60.00

62.00

64.00

66.00

68.00

70.00

72.00

74.00

20

12

-13

20

13

-14

20

14

-15

20

15

-16

20

16

-17

Page 45: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

45

2016-17

Job Desc ription

Target

Achievement as on

31.03.2017

Achievement %

WDW well (Mtr) 10,500 14,950 142.4 %

Work-over jobs (No) 200 214 107.0 %

Potential retrieval-oil (build up) ( KLPD )-

on stream

2315 1459 63.0 %

A. Planned Maintenance of Equipment:

Apart from the regular jobs of operation and maintenance of all engines, pumps,

compressors etc. pertaining to day to day Workover operation, planned major jobs for few

equipments were also carried out during the year, which are as follows :-

1. 04 (four) nos. new Workover Rig & 01(one) no new mobile Drilling Rig [Drillmec,

Italy] were commissioned & operated successfully.

2. Upgraded discharge capacity of 01(one) no old Well Servicing Pump to higher

capacity [from 1.75LPS to 3.09LPS] through proper planning, procurement &

replacement of fluid end module.

3. Total 45 nos. of work-over equipment viz. Well Servicing pump & engine, Cementing

pump & engine, Water pump & engine, Generator engine, Air compressor etc were

overhauled. Through proper maintenance planning & adherence to the schedule, the

quantum of equipment failure has drastically decreased [almost Nil].

4. Keeping in mind Prime Minister’s “Swatch Bharat Abhiyan” mission, we have

initiated & constructed 1no toilet and improved housekeeping for the employees

inside Workover maintenance yard; thus created a better working atmosphere to

carryout overhauling & maintenance jobs of various rig equipment.

B. New Equipment Installed & Commissioned

1. 03(three) nos. new Well Servicing pump of NOV, USA were procured,

commissioned & inducted in the fleet of new Drillmec Workover rigs.

2. 04(four) nos. new Fire Tank were procured & commissioned successfully in the in-

house Workover rigs. Thus completed requirement of Fire Tanks in all the in-house

Workover Rigs.

3. 06(six) nos. new Water/Chemical storage Tank were procured, commissioned &

inducted in the fleet of new Drillmec Workover rigs.

4.

Page 46: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

46

2016-17

C. Special type of Workover operation

1. Drilling-TS Workover section has extended its support with manpower and

equipment for cementing jobs [approx 52nos] in several in-house as well as chartered

Drilling & Workover wells in addition to regular Workover wells.

2. Special effort was put with equipment and manpower and completed 11 nos. of

acid job operation in different Workover as well as Drilling locations as per the

requirement.

3. Special effort was put with equipment and manpower and completed 2 nos. of

EGMBE treatment job.

D. Cost Saving Measures adopted

1. 05(five) Nos. of “Solar Gen Set” unit were commissioned in May, 2013 for

illumination purpose at the work-over locations. A considerable quantity of non

renewable energy is saved by using these 5nos Solar Gen Set.

2. 07(seven) Nos. of new & technologically upgraded with higher capacity “Solar Gen

Set” unit were procured & commissioned in Feb – March, 2017 for illumination purpose

at the work-over locations. A considerable quantity of HSD has been saved by using

these 7nos Solar Gen Sets. The quantity of HSD saved is 2355 Litres amounting

Rs. 1,29,525.00 (considering average price of HSD @ Rs. 55.00 per litre).

E. Energy Conservation & Pollution Control Measures Adopted:-

1. The installed generating capacity of each new Solar Genset commissioned is 1.5

KW having 06 Nos. of 250 Wp Poly Crystalline PV panel mounted on the solar Gen

sets with an unique structure. The area illumination is done with 8 Nos. pole mounted

LED lights of 24Wp each. The total Renewable Energy generated till the end of the

FY 16-17 is 542.77 units.

2. All efforts were given for work-over operations and Production without Pollution. To

achieve this, system has been adopted in all Workover wells to collect the fluids

associated with crude oil production during testing of the wells in a closed covered tank

instead of disposing the same in the effluent pit.

We have also collected the burnt oil from engines & pumps during servicing job and put

into this tank. Used lube oil and fuel filters are buried under earth within the plinth to

avoid any further spillage.

We use Lube oil evacuating & dispensing pump unit to BHEL#A rig for evacuating burnt

lube oil from engine/pump & take utmost care to minimize pollution hazards.

Page 47: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

47

2016-17

10. EQUIPMENT SECTION

During the financial year 2016-17, Drilling Department has achieved a total Drilling

Meterage of 1,59,987 Mtrs. (51 Wells) and also have completed a total of 214 Work-over

jobs. In this remarkable achievement, the Equipment & Fishing Operation Section has,

as in the past, played a vital role by providing constant support on 24x7 basis for both

Drilling and Work-over activities of the department.

In addition to supply of various consumables to respective Drilling and Work-over

locations on daily basis, Servicing, Maintenance/Repairing & Testing of various Drilling

and Work-over tools/equipment, Well Control Equipments, etc. the section also met the

day-to-day requirement of various locations by transferring heavy equipments and

tubular in liaison with Logistics Department by issuing VTRs. Moreover, a good number

of repair, service & fabrication jobs were also undertaken by Equipment & Fishing

Operation Section through CWS by issuing notifications.

The section also carried our regular maintenance (i.e. preventive, scheduled &

breakdown) of all rotating, hoisting, well control, surface & sub-surface equipment/tools

and handling gears, etc. in order to keep them in working condition, quick respond to

field calls for attending any break-down maintenance of tools/equipment have

contributed immensely for smooth & trouble free Drilling & Work-over operations thus

minimizing the down-time. The Equipment & Fishing Operation Section has been

successful in its efforts in providing commendable logistic support to both drilling &

work-over operations due to the perseverance of its committed and competent work force.

Some of the note-worthy contributions of Equipment & Fishing Operation Section during

the financial year 2016-17 are as follows:

Servicing, Repairing & Hydro Testing of BOPs, BOPCUs, Remote Choke

manifold Panel, HCR Valves, Torque Wrenches, High Pressure testing Units,

etc. at Drilling Equipment & Fishing Operation Section’s Yard and Fields.

Page 48: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

48

2016-17

1. Major repairing, servicing & hydro testing jobs carried out at Equipment &

Fishing Operation Section Yard during the year:-

a) BOPs (7-1/16” x 5M Double Ram) - 10 Nos.

b) BOPs (13-5/8” x 5M Annular) - 6 Nos.

c) BOPs (13-5/8” x 5M Double Ram) - 3 Nos.

d) BOPCUs - 9 Nos.

e) Remote Choke Manifold Panels - 6 Nos.

f) HCR Valves - 13 Nos.

g) Gate Valves - 34 Nos.

h) Portable High Pressure Testing Unit - 6 Nos.

i) Torque Wrenches - 7 Nos.

2. Total Field Call attended successfully at various Drilling and Work-over

locations for repairing &/or rectification of problems related to BOPCUs, BOPs,

Remote chokes, Hoisting equipments, etc. during the year – 56 Jobs.

Repairing & Servicing Details of Major Hoisting and Rotating Equipments:

During the year, following equipments had been major overhauled &

repaired/Serviced with the help of CWS.

a) 27-1/2” Rotary Table - 7 Nos.

b) Drilling Rotary swivels - 3 Nos.

c) Travelling Block - 3 Nos.

d) Drilling Hook - 2 Nos.

e) Crossover rethreading - 16 Nos.

f) Tubing Swivel - 14 Nos.

g) Flat bottom Mill & Tapper Mill reconditioning - 64 Nos.

h) Rig Tongs parts repairing & reconditioning - 2 pairs of tong

Servicing cum repairing & replacing of the slip dies jobs:

a) Heavy Duty Spiders Elevators & Slips prior to sending well sites – 96 Pairs

b) Drill Pipe Elevators - 26 Nos.

c) Drill Pipe Slips - 95 Nos.

d) Tubing Hand Slips - 55 Nos.

Page 49: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

49

2016-17

e) Tubing Foot Slips - 22 Nos.

f) Drill Collar Elevators - 6 Nos.

g) Drill Collar Slips - 32 Nos.

Servicing cum repairing and/or fabrication of customized Fishing Tools:

a) Overshot Serviced – 79 Nos.

b) Fabrication of Internal & External Grabs – 26 Nos.

NDT Inspection of Drill Pipes/Tubular and Handling Tools: During the year

following NDT inspections was carried out through Contracts No. 6108573/CDI.

a) 5” OD Grade ‘G’ Drill Pipes - 2244 Nos.

b) 5” OD Grade ‘S’ Drill Pipes - 97 Nos.

c) 4-1/2” OD Grade ‘G’ Drill Pipes - 170 Nos.

d) 3-1/2”OD Grade ‘G’ Drill Pipes - 543 Nos.

e) 2-7/8” OD Grade ‘E’ Drill Pipes - 457 Nos.

f) 5” OD HWDP - 41 Nos.

g) 3-1/2” OD Drill Collar - 35 Nos.

h) 6-1/2” OD Drill Collar - 8 Nos.

i) 8” OD Drill Collar - 1 Nos.

j) Rig Tongs - 5 Pairs

k) Hand Slips - 18 Nos.

l) Drilling Spools - 20 Nos.

m) Elevator Links - 2 Pairs

n) Rotary Substitutes - 22 Nos.

Core Barrels & Mud Motor Servicing cum testing (prior to sending them to

sites):

a) 7-3/4” OD Core Barrel - 2 Times

b) 3-1/2” & 4-3/4” Mud Motors - 24 Times

c) 6-3/4” OD Core barrels - 6 Times

Page 50: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

50

2016-17

Improvement of Infrastructure to meet urgent requirement: Designed and

Fabricated following items at CWS in order to meet the urgent requirement of

Drilling & Work-over operations during the year:

a) One No. of Drilling Tool Bin

b) One No. of Work-over Tool Bin

c) Eleven Nos. of BOP Skids

d) Two Nos. of Bit Breakers for 37-1/2” Rotary table.

e) Carried Regular Painting Jobs of Equipments wherever required to prevent

rusting.

Write off Materials: Proposed for Write off of various capital items including

tubular whose economical life was over and are not in usable conditions.

Budget (Capital & Revenue) and Stock items: Monitored and put up proposal for

Capital & Revenue Budgeted items for the year 2018-19 to centralized planning

section of drilling department. Advised immediate replenishment of stock nil items

on regular basis and opening of new matcodes for new capital items received by the

section during the year.

ERP System: Created requisitions, STOs, Gate Passes SESs, etc. on regular basis.

Also cleared the storage location on monthly basis.

Cost & Energy Saving: The Equipment & Fishing Operation Section reviews and

monitors the issuance of consumables like High Speed Diesel, Hydraulic Oil, Lube

oil, etc to Drilling & Work-over locations on a day-to-day basis and being

committed towards saving all forms of energy , initiates proactive action as

required.

Equipment on Rental: During the year, the section has issued various equipment

on rental basis for smooth operations at various Charter hired rigs engaged for

drilling and work-over jobs, viz. Fishing tools, Heavy Duty Spiders, Rotary

substitutes, Wellhead equipment, etc. and thereby contributed to the company’s

exchequer in the process.

Page 51: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

51

2016-17

Details of various capital items received & inspected during the year

1) Blow Out Preventers

a) 21-1/4” x 2M (Annular) – 2 Nos.

b) 13-5/8” x 10M (Single Ram) – 2 Nos.

c) 7-1/16 x 5M (Double Ram) – 10 Nos.

d) 13-5/8” x 5M (Annular) – 4 Nos.

2) BOP Control units

a) 160 Gallons – 5 Nos.

b) 20 Gallons – 4 Nos.

3) Kellys

a) 5-1/4” Hexagonal – 4 Nos.

b) 2-1/2” Square – 2 Nos.

4) Shock subs, shock absorber and friction reduction tools

a) 8” OD 2 + 1 = 3 Nos.

b) 6-3/4” OD = 2 Nos.

5) 3-3/4” OD Super Fishing Jar – 2 Nos.

6) 3-1/2 OD HWDP – 45 Nos.

7) 2-7/8 Tubing Stripper – 6 Nos.

8) 2-7/8” EU DP (250Ton) Elevator – 4 Nos.

9) 2-7/8” OD Tubing Hand Slip – 4 Nos.

10) 3-1/2” OD Mud Motors – 4 Nos.

11) 7-5/8” Reg. RH Twin Pin Sub – 2 Nos.

12) 5” Drill Pipe Elevator CL-350 – 3 Nos.

13) Drill Collar Safety Clamps

a) For use on 8-1/2” OD to 9-5/8” OD tubular – 3 Nos.

b) For use on 4” OD to 5” OD tubular – 2 Nos.

c) For use on 5-1/2 OD to 7” OD Tubular – 4 Nos.

14) 5-1/2” OD Casing Hand Slip – 3 Nos.

15) Drilling Hook, 350 Ton – 3 Nos.

16) Ditch Magnet (Heavy Duty) – 3 Nos.

17) Side Door Elevators

a) For 4-1/2” OD Casing (250 Ton) – 4 Nos.

b) For 5-1/2” OD Casing (250 Ton) – 2 Nos.

Page 52: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

52

2016-17

18) 13-3/8” OD Casing Single Joint Collar type Elevator - 4 Nos.

19) Rotary Hand Slips

a) For 5” OD Drill Pipe (Type SDXL) – 4 Nos.

b) For 3-1/2” OD Drill Pipe (Type SDML) – 4 Nos.

c) For 4-1/2” OD Drill Pipe – 3 Nos.

d) For 7” OD Casing – 4 Nos.

e) For 6-1/2” OD Drill Collar – 3 Nos.

f) For 8” OD Drill Collar – 3 Nos.

g) For 9-1/2” OD Drill Collar – 2 Nos.

20) Master Bushing for 17-1/2” Rotary Table – 2 Nos.

21) 5” OD Grade ‘G’ Drill Pipes – 10000 Mtrs.

SAP Notifications issued by Equipment & Fishing Operation Section during

the year for smooth running of Drilling and Work-over operations are as

follows:

a) Transport – VTR (for transfer of heavy materials): 457 Notifications

b) Workshop Services (for major repairs/servicing/overhauling): 358

Notifications

c) Civil / Electricals maintenance: 26 Notifications

Procurement of urgent material through ‘Non-Stock Spot’ by the section

during the year are as follows:

a) Total No. of Purchase Requisitions Created in SAP System and receipt of

material thereby: 32 Nos.

Bio-Metric Time Capturing Device (BTCD): One no. of BTCD was installed and

commissioned at Equipment & Fishing Operation Section during the month of

February 2017.

Swachh Bharat Abhiyaan: As per PM’s Swachh Bharat Abhiyaan campaign,

Equipment & Fishing Operation Section regularly works for maintaining the

cleanness of the Drilling Equipment yard both at Industrial Area and New

Industrial Area.

Page 53: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

53

2016-17

Conclusion:

With the increase in Drilling and Work-over activities over the last few years consequent

to the deployment of total 17 nos. of Drilling rigs (includes 1 rig for water well drilling

operations) and 24 Nos. of Work-over rigs there has been a manifold increase in our in-

house activities to cater for these additional rigs with the existing manpower.

It may be appreciated that besides the conventional day-to-day jobs, the need for carrying

out various on-line transactions for issuance or transfer of materials, maintenance &

testing of equipment, record-keeping, planning & monitoring, etc is increasing day-by-

day. Owing to increased deployment of our equipment to Charter Rigs the frequency of

maintenance jobs has also substantially increased. Stringent safety and testing norms

being the order of the day, has necessitated better and detailed record-keeping & status

monitoring for all the equipment.

This substantial increase in work volume has however not been offset by the requisite

increase in manpower allocation to the section. To add to its woes, the section has on the

contrary been handicapped due to superannuation of experienced personnel in the recent

past with an ageing and ever-depleting workforce. With the present manpower strength it

is proving to be a herculean task to deliver the quality of service that has come to be

expected of the section. A review of the manpower strength allocated to the section is the

need of the hour to enable us to continue providing quality service in the days ahead.

11. HEALTH, SAFETY AND ENVIRONMENT

Operational Excellence is a continuous and long-term strategy to improve Company’s

performance systematically. HSE criteria functions such as employee safety, process and

asset safety, product safety and environmental impacts are important considerations

when analyzing operational risks. Therefore HSE domain plays major role in the

improvement of operational excellence of a Company.

Keeping in view of the above, Drilling department is constantly working hard in complying

and improving its HSE aspects. Drilling department is committed for implementation of

Page 54: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

54

2016-17

HSE regulations in its operations as well as improving its day to day HSE related

activities.

Drilling Department of OIL believes that achieving and sustaining a positive HSE culture

is a journey and not a discreet event. Focus is always on Top driven (leadership) HSE

management system with bottom support.

HSE Section of Drilling Department always strive for quality improvement with above

objectives

The performance report of HSE section of Drilling Department for the financial 2016-17

is furnished below:

Objectives:

Healthy Life of Men & Machines

Safe Working Condition [Zero incident]

Environment Friendly Atmosphere

Roles & Activities:

In order to fulfill the above objectives, the following roles/ activities are being

undertaken:-

Periodical inspections as well as audits of installations and suggestion for remedial

measures.

Monitoring of HSE measures.

EIA & EMP [Environment Impact Assessment & Environment Management Plan] of

the operational areas.

Obtaining EC [Environment Clearance] for drilling activities.

Quarterly OISD ESA compliance reporting, quarterly report of implementation of

actions pertaining to the recommendations of enquiry reports of accidents/

incident took place in installations, half-yearly EC-compliance reporting to MoEF,

Quarterly Incident report to OISD through S & E, Quarterly legal compliance report

etc.

Correspondences with all the Statutory & Regulatory authorities [DGMS, MoEF,

CPCB, SPCB, OISD etc]

Annual Return preparation and submission.

To facilitate all the installations with Stationeries/ Registers/ Formats etc.

Annual projection & Provision of PPE to all concerned.

Page 55: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

55

2016-17

Annual Report preparation.

Accident/ Incident Analysis and investigation.

Preparation and submission of accident report (IV-A, IV-B, IV-C) to Mines

authority.

Conduction of bimonthly departmental Safety Meetings, monitoring of the safety

points discussed in the meeting for necessary compliance.

Projection of Safety items for Annual Budget.

Statutory training to employees.

IME & PME of the employees.

Centralized record keeping of employee’s Bio data, Training, IME/PME.

Assistance/ guidance to all Installations in respect to HSE matter.

Involvement in internal and external audits during Safety week.

Monitoring & Implementation of EC conditions.

Appointment/Termination of competent officials/persons on behalf of Mines

Managers as per statutory guidelines.

Necessary helps and guidance to installations during Safety Week-Audit, other

internal and any external HSE-audits.

ACHIEVEMENTS AT A GLANCE:

General:

1. Down trend in departmental accident [8 to 4].

2. Preparation and Submission of all required Statutory, Regulatory, inter

departmental & intra departmental documents on time.

3. Accelerated safety inspection frequency in Drilling & Work-over Installations.

4. Process is on for integrated EC, FC and NBWL.

Training:

Statutory and non statutory training program like Mines Vocational Training (MVT),

Refresher MVT, Gas Testing and Work Permit (GT & WP) Training, First Aid Certificate &

Refresher course (FA) were carried out both in-house (MTDC) and in-country with close

liaison with L & D Department. Similarly, First Aid Fire Fighting (FAFF) training was also

conducted at various well-sites by the Fire Service Department. Given below is the

number of work-persons undergone training during the year:

Page 56: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

56

2016-17

1. TRAINING: (DEPARTMENT EMPLOYEES)

MVT: 03

MVT(R): 35

First Aid: 19

Gas Testing: 13

Though full effort was made, no more OIL- employees could be trained due to

operational reasons

2. TRAINING( CONTRACTOR EMPLOYEES)

MVT: 965

3. EXECUTIVE TRAINING:

Shri AMALENDU

BISWAS

RAAP NOIDA MANAGING RISK OF MAJOR

ACCIDENT IN O&GI

Shri BEDANTA NATH HYDR DIGBOI HYDROCARBON INDUSTRY

GROWTH PROSPECTS &

Shri BEDANTA NATH OSCS MUMBAI OIL SPILL INDIA 2016 - 4TH

NATIONAL CONF

Shri BEDANTA NATH NEBOSH MANAGEMENT

TRAINING &

DEVELOPMENT

CENTER

National Examination Board

of SH

Shri BEDANTA NATH CCO&G GUWAHATI INTERNATIONAL OIL & GAS

OPERATIONAL SAFE

Shri MANOJ KUMAR

BORBORA

GHSEC NEW DELHI 3RD GLOBAL HSE

CONFERENCE

Shri MANOJ KUMAR

BORBORA

HSE&OISL JAIPUR HSE OPERATIONAL

INTEGRITY-CLOSING THE

SA

Shri AMIT KUMAR

DEY

HSE TRNG MANAGEMENT

TRAINING &

DEVELOPMENT

CENTER

HSE TRAINING

Page 57: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

57

2016-17

ACCIDENT ANALYSIS FOR LAST 05 YEARS:

Year

M&D MR Serious Fatal Total (No) Averag

e Age

(Years) Dept Others Dep

t Others Dept Others Dept Others Dept Others

2012-

13 2 - 4 1 2 3 - - 8 4 54

2013-

14 3 2 1 1 5 1 - - 9 4 49

2014-

15 2 1 2 - 2 1 - 1 6 3 51

2015-

16 2 - 1 - 4 1 - - 7 1 41

2016-

17 6 - - - 3 - - 1 4 0 50

ACCIDENT ANALYSIS FOR THE YEAR 2016-17:

Mine M&D MR Serious Fatal Total (No)

Average

Age

(Years)

Dept Others Dept Others Dept Others Dept Others Dept Others

Drilling

3

3

47.33

Workover

1

1

53

Page 58: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

58

2016-17

Safety Audits:

(a) Internal Audit/ Inspection:

During the year under review the HSE Section carried out Internal Safety Audits/

Inspection by HSE-Engineers and Workmen Inspectors as per Mines Act 1952.

(b) External Audit:

External audit had been carried out during the year by DGMS-Elect, DMS, DDMS.

The audits both internal & external helped us in improving safety standard at our

installations as well as safety awareness amongst the mine working personnel.

Environment related issues:

Environment Clearance:

Provided inputs for Processes of obtaining prior EC (Environmental Clearance), FC

and NBWL from MoEF (Ministry of Environment & Forests) which shall be done

centrally for Field Headquarter. GM (HSE)

In addition to this, submission of six monthly compliance report on the stipulated

condition of EC and uploading the compliance report as well as test results of

monitoring report is being done by Drilling department.

Others

Observed all programs related to environment as done at company level

Awareness program in drilling location about Environment Protection.

Organize Mass Tree Plantation

Page 59: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

59

2016-17

12. PLANNING & DATA SECTION

Activities:

a. Preparation of Departmental Budgets- Capital and Revenue.

b. Drilling Engineering & Scheduling of consumables for Drilling & Work-over Rigs /

wells.

c. Procurement – Planning and processing of all the items required for the whole

department.

d. Departmental Planning jobs pertaining to preparation and award of contracts,

extension / renewal of contracts and hiring any other services.

e. Carrying out of Technical Scrutiny of all the Capital, Revenue/ Direct purchase and

Stock items.

f. Finalization of Casing and Bit policies for all wells.

g. Well Budget: Planning & Preparation of requirement for capital equipment, casing,

spares and all other consumables for 3(three) consecutive years as per TDP.

h. Work related to Management Information System (MIS) involving preparation of

Annual Plan/Action Plan, Performance Review, Annual, Quarterly & Monthly

Performance Reports, Reports/ document for External/ Statutory authorities, Data

Management for Drilling & W-over Operation, Well completion Reports etc.

i. Written and Disposed off scrap equipment and spares of Drilling Department.

Performance worth mentioning:

My Annual Plan (MAP): Annual Revenue budgeting for the Department (including

well cost, maintenance cost) for 2016-17 was done as per the developed Excel Format

and submitted. The voluminous job involves cost planning for 38 cost centers and 60

(including 9 No WDW) Wells, each divided into Rig up – Drilling – Production Testing –

Rig Down phases for multiple direct cost elements for the year.

Management Information System (MIS): All the related work was done within the

stipulated / scheduled time and hence department has earned reputation of providing

all the MIS related information in time. In addition planning section submits weekly

reports on Drilling and Workover activities to CMD and DED apart from the

comprehensive report on Drilling performance to DGH on monthly basis.

Page 60: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

60

2016-17

Contracts/ Contracting process handled / maintained:

1. Charter hire of 1400 HP/2000HP Drilling Rigs : 5 No

2. Charter hire of 500HP-750 HP Work-over Rigs : 12 No

3. Man Management Contracts :

For WDW rig : 1 No

For Drilling Rig : 4 No

For Work-over Rigs : 8 No

4. Contracts for Expert/Consultancy services:

Horizontal Drilling services with tools, equipments and consumables

J- Bend Drill services for high tech wells with tools & equipments and

consumables.

Hiring of MWD-SDMM-Jar along with services of expert

Cementing services along with tools & equipments and experts.

Drilling consultancy services

NDT of mast and substructure

NDT for tubular along with handling tools and equipments.

Work-over Rig health check-up.

Effluent Treatment Plant along with unit and consumables

5. Services for Rig painting with supply of consumables.

6. AMC of Emergency Escape device.

7. AMC of Advance Instrumentation Services.

8. Services for EIA study.

9. Different labour oriented contracts

10. Services of Automatic Bulk handling plants

11. Services for transportation of oil well cement.

12. Hiring of services for digitization of old well reports.

13. Hiring of services for dismantling of mast and substructure of DC-DC rig.

14. Hiring of water tanker.

Page 61: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

61

2016-17

Purchase and Contracts:

During the year Purchase Requisition were released for 108 Budget Heads of total 111

Budget Heads from the Department for procurement of Capital/ Sp Revenue and Revenue

items amounting to 81.93 cr, out of which 22 PRs have been converted to Order till

31.03.2017 which is 20% of the number of raised indents and a total of 08 Purchase

Requisition for Hired Services were released amounting to 300.49 Cr till 31.03.2017.

13. ADMINISTRATION

Administration Section of the Drilling Department plays a vital role in achieving the

Drilling and Workover Target. The main Function of Administration Section are listed

below.

1. Personnel and Administration related activities of all executives, Drilling and

Workover Section Employees of Drilling Department which includes

a. Managing and maintaining record of leave/sick etc.

b. Joining, Absorption, Confirmation, Transfer and separation at departmental

level.

c. Processing of career progression at departmental level.

d. Disciplinary actions as and when required.

2. Allocation of shift personnel (both executive and employees) to Drilling and

workover locations. All is managed through a control room is run on 24 hrs basis

to cater to any urgent need like relief crew, emergency vehicle etc.

3. Manpower Planning and Projection for continuation of uninterrupted drilling &

workover operation is carried out by Admin Section.

4. Deployment of Company representative to various projects like NEF, KGB etc is

facilitated by Admin Section.

5. Nomination for various training of executives and employees and maintaining

record of the same.

6. Allocation of hired vehicle for other sections, shift movement and processing their

SES.

7. Liaison with Administration Department, Security and PR to carry out smooth

wellsite operation and also during bandh, blockade, strikes etc.

Page 62: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

62

2016-17

8. Conducting various departmental activities like meeting, conference, get to-gathers

etc.

9. Infrastructure development and beautification in and around NIA.

10. Preparing GM (Drilling Services)’s report for Friday Meeting.

11. Supplying casual workers for casing handling, Telephone attendant and Pollution

control at wellsite. Contract Management of these contracts is also done by Admin

Section.

12. Personnel and Administration related activities of contractual officers of Drilling

department like

a. Maintaining their leave, sick record.

b. Processing of their monthly remuneration.

c. Contract Renewal formalities at departmental level.

Manpower Strength

Executives 126

Employees (Drilling & Workover Operation, Duliajan) 260

Employees (Drilling Operation, Moran) 39

Contractual Officers 15

Training Data

Description No. Of Executives No. Of Employees

MVT / First Aid / Gas

Testing

NIL 70

In house training 49 27

In Country Training 38 39

Abroad Training /

Inspection / Conference

10 00

* Training record of all sections of Drilling Department, excluding Drilling TS in FHQ.

Page 63: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

63

2016-17

Joining & Separation:

Description No. Of Executives No. Of Employees**

Joining 14 01

Separation 03 44

Transfer to Drilling

Department

08 00

Transfer From Drilling

Department

12 00

Promotion 37 183(127SG/PG+52GOP+04VB)

**Employees of Drilling and WO Section both field and non field, Duliajan

Apart from this, Job rotation of Executives was done in a phase wise manner as per

requirements as advised by HOD. Distributions as well as submission of APR’s of

Executive and Employees were carried out within specified period. Also,

industrial/apprenticeship training etc. was arranged for about 47 nos students from

various technical institutions / universities during the year.

Page 64: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

64

2016-17

14. INSTITUTE OF WELL CONTROL TECHNOLOGY

The institute was accredited by International Well Control Forum (IWCF) as a primary centre for conducting the Well Intervention Pressure Control and Drilling Well Control

Programme on 21.06.2012 after auditing the physical resources, management systems, instructors and course materials. A portable drilling simulator was installed and commissioned on 10.09.2012.

1. COURSE CONDUCTED

The institute conducted SEVEN numbers of Drilling Well Control Programme in the

financial year 2016 - 2017 as per the following details:

Name of the Course

Course Dates Batch Size

Participant’s Profile

Instructors Pass Percenta

ge

Drilling Well Control

Programme

06.06.16 -

10.06.16

10

Drilling - 0 External - 10

J. Chetia P. Buragohain

S. K. Gogoi

100%

Drilling Well

Control Programme

11.07.16 - 15.07.16

9 Drilling - 3 External - 6

P. Buragohain

KJ Deka 100%

Drilling Well

Control Programme

05.09.16 -

09.09.16 10

Drilling - 2

External - 8

J. Chetia

P. Buragohain KJ Deka

100%

Drilling Well Control

Programme

03.10.16 -

07.10.16 9

Drilling - 1

External - 8

J. Chetia P. Buragohain 100%

Drilling Well Control

Programme

05.12.16 - 09.12.16

8 Drilling - 3

External -

5

S. K. Gogoi J. Chetia

KJ Deka

100%

Drilling Well

Control Programme

16.01.17 - 20.01.17

5 Drilling - 0 External - 5

P. Buragohain

KJ Deka 100%

Drilling Well Control Programme

07.03.17 -

11.03.17 3

Drilling - 2

External - 1

S. K. Gogoi P. Buragohain KJ Deka

100%

2. PARTICIPANTS

The total numbers of participants for the courses in 2016 – 2017 were as given below:

Name of the Course

Number of

Batches

Total Number of

participant

Internal Candidates

External Candidates

Page 65: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

65

2016-17

Rotary Drilling Well Control

Course

7 54 11 43

The total numbers of participants for the courses from 2012 – 2016 are as given below:

Year Number

of Batches

Total

Number of participant

Internal

Candidates

External

Candidates

2012 – 2013 5 45 36 9

2013 – 2014 9 85 41 44

2014 – 2015 11 124 49 75

2015 - 2016 8 74 24 50

2016 - 2017 7 54 11 43

TOTAL 40 382 161 221

3. INSTRUCTOR RE-CERTIFICATION AND TRAINING

The instructor as mentioned below attended the following technical training.

Training Course Name of the participant Particapants

Course Duration

Location

IWCF Train the Trainer Course

Mr Sanjib Kumar Gogoi 12.09.16 – 14.09.16

Mumbai

IWCF Train the Trainer Course

Mr Krantijyoti Deka 12.09.16 – 14.09.16

Mumbai

IWCF Train the Trainer Course

Mr Ashok Borgohain 12.09.16 – 14.09.16

Mumbai

Page 66: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

66

2016-17

ACKNOWLEDGEMENT

I take this opportunity to acknowledge the excellent and outstanding contributions made

by each and every one of Drilling Department during the year to achieve highest ever

drilling meterage of 1,59,987 m, 51 nos. of completed wells and 214 nos. Workover job

completion.

The achievements were possible due to the sincere and dedicated efforts put in by Team –

Drilling.

I am immensely grateful to the Corporate Management, Local Management, for their

active support and guidance. I offer my sincere gratitude to RCE, ED (C&P), ED (F&A),

ED (ES), ED (HR&A) and ED (BM). I would also like to thankfully acknowledge the

support and co-operation received from various departments.

I would also like to acknowledge the contribution made by the executives, as well as work

persons of Drilling Department and specially the support & guidance/ advice extended by

the Management which have enabled the department to achieve the excellent result in

Drilling & Work-over operations including other support services. We would also like to

place on record our deep appreciation and acknowledge the intangible support from

various associated departments including the Admin/Security Departments for their

instant and continuous support as and when required to maintain continuous progress

of operations.

Dr Khargeswar Saikia General Manager (Drilling Services)

Page 67: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

67

2016-17

Page 68: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNEXURE - 1

Performance of Drilling Rig(s) during 2016-17

Sr. No.

RIGNAME Owned/ C-Hired/

MMC

EXP DEV TOTAL Rig Mode-wise Time Break-up Out Cycle Cycle Days

Comm Days

Cycle Speed

Comm Speed Wells MET Wells MET Wells MET RB DR PT Cap

Rep OTH O/C

Nos (m) Nos (m) Nos (m) days days days days days

A C D F G H I J K L M N O P W X Y Z

1 750 HP Owned 1 2519 1 2412 2 4931 101.00 137.12 24.00 0 102.88 262.12 137.12 572 1094

2 S-1 Owned 0 0 3 9626 3 9626 97.00 154.98 80.82 0 32.20 332.8 154.98 880 1889

3 S-2 Owned 1 694 2 8243 3 8937 131.03 191.89 24.75 0 17.33 347.67 192 782 1417

4 S-3 MMC 1 2286 2 8809 3 11095 87.74 193.62 61.33 0 22.31 342.69 194 985 1743

5 S-4 Owned 0 0 4 12289 4 12289 108.46 205.42 41.83 0 9.29 355.71 205 1051 1820

6 S-5 Owned 1 1764 2 6431 3 8195 70.00 180.00 80.64 0 34.36 330.64 180 754 1385

7 S-6 MMC 3 7661 1 2559 4 10220 66.21 202.17 47.00 0 49.63 315.375 202.165 986 1538

8 S-7 MMC 0 0 3 11646 3 11646 81.26 243.32 30.85 0 9.57 355.43 243 997 1456

9 S-8 MMC 1 4571 0 0 1 4571 99.67 157.00 28.66 0 79.67 285.33 157 487 886

10 VFD-1 Owned 1 4409 0 0 1 4409 0.00 167.40 36.55 0 12.05 203.95 167.40 658 801

11 VFD-2

Owned 1 4450 0 0 1 4450 0.00 153.81 42.67 0 24.52 196.48 153.81 689 880

12 BHEL-IRA MMC 0 0 9 14950 9 14950 125.66 199.95 29.00 0 10.39 354.61 200 1282 2274

13 CH-2 (SIL) C-HIRED 2 5596 1 3994 3 9590 31.25 223.31 89.75 0 20.69 344.31 223 847 1306

14 CH-3 (JB) C-HIRED 1 5695 1 4371 2 10066 29.38 307.39 26.00 0 2.23 362.77 307 844 996

15 CH-4 (SIL) C-HIRED 1 5988 2 6957 3 12945 50.00 195.74 84.12 0 35.14 329.86 196 1194 2012

16 CH-5

(Quippo) C-HIRED 2 8284 0 0 2 8284 30.00 235.10 91.05 0 8.85 356.15 235 708 1072

17 CH-6 (SV) C-HIRED 0 0 1 958 1 958 4.00 56.94 5.82 0 6.24 66.76 56.94 437 512

18 CH-6

(Quippo)) C-HIRED

2 8689 1 4136 3 12825 43.00 228.67 47.60 0 18.73 319.27 228.67 1222 1706

TOTAL 18 62606 33 97381 51 159987 1155.66 3433.83 872.44 0 496.08 5462 3434 891 1417

Page 69: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

69

2016-17

ANNEXURE - 2 Cycle & Comm. Speed of Completed Drilling wells in 2016-17

S. No.

Well Name

Nature Rig Name Target Depth (TD)

Drilled Depth (DD)

Spudding Date

Hermetical Test Date

Rig Release

Date

Rig Building (RB)

Drilling (DR) Production Testing (PT) Cycle

Speed Comm Speed

Planned Actual Planned Actual Planned Actual

1 2 3 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 WDW-162 WDW BHEL-IRI-A 1500 1357 3/30/2016 4/19/2016 4/23/2016 15 11 25 21 10 4 1147 1966

2 WDW-163 WDW BHEL-IRI-A 1500 1506 5/8/2016 5/26/2016 5/29/2016 15 15 25 18 10 3 1273 2545

3 HYE EXPL E-1400 (S.3) 3182 2286 3/15/2016 5/25/2016 6/20/2016 25 31 80 71 15 26 543 979

4 CG EXPL E-1400 (S.2) 3825 3864 2/15/2016 5/29/2016 25 44 90 104 15 0 794 1130

5 BGR EXPL CH-5 4540 4485 2/8/2016 5/8/2016 7/19/2016 25 0 120 90 15 72 842 1516

6 HYB EXPL E-1400 (S.5) 2930 2934 2/26/2016 6/8/2016 7/18/2016 25 39 70 103 15 40 490 867

7 DGY EXPL CH-2 4283 4321 2/6/2016 6/3/2016 7/18/2016 25 36 120 118 15 45 661 1114

8 DHM DEV CH-6 4250 4240 1/20/2016 6/2/2016 6/9/2016 15 16 120 134 10 7 822 963

9 TT EXPL CH-3 4365 4365 2/28/2016 6/14/2016 6/26/2016 15 8 120 107 15 12 1046 1241

10 CJ EXPL E-1400(S.6) 3939 4139 3/4/2016 6/12/2016 15 23 120 100 15 0 1024 1259

11 HYH DEV E-1400(S.4) 3150 3161 4/21/2016 6/15/2016 6/28/2016 25 38 70 55 10 13 907 1748

12 HYA DEV E-1400(S.1) 3155 3088 4/28/2016 6/18/2016 08/06/2016 15 13 70 51 10 49 831 1842

13 DHP-1 WDW E-1400(S.8) 4828 2970 2/4/2016 5/5/2016 25 21 120 91 15 0 807 993

14 WDW-171 WDW BHEL-IRI-A 1500 1515 6/15/2016 7/4/2016 7/8/2016 10 4 25 19 10 4 1707 2426

15 DHK DEV E-2000(S.7) 4086 4112 4/14/2016 7/15/2016 7/18/2016 10 5 120 92 10 3 1251 1360

16 CZ EXPL CH-4 4230 4248 5/20/2016 8/5/2016 8/27/2016 10 4 120 77 15 22 1255 1678

17 HXA EXPL 750-HP 2510 2519 5/30/2016 8/11/2016 15 12 60 73 15 0 902 1050

18 WDW-166 WDW BHEL-IRI-A 1500 1513 8/1/2016 8/19/2016 8/23/2016 10 6 26 18 10 4 1644 2557

19 BGK EXPL CH-6(Quippo) 4320 4271 4/28/2016 8/18/2016 9/13/2016 15 0 121 112 15 26 941 1160

20 HYP DEV E-1400(S.6) 2556 2559 7/19/2016 9/6/2016 9/30/2016 10 4 70 49 10 24 1011 1589

21 HYJ DEV E-1400 (S.3) 2536 2546 8/12/2016 9/28/2016 10/7/2016 10 3 80 47 10 9 1313 1648

22 HYF DEV E-1400(S.4) 3268 3269 7/27/2016 9/26/2016 10/7/2016 10 5 70 61 10 11 1291 1630

23 HYK DEV E-1400 (S.2) 2674 2694 7/25/2016 9/16/2016 9/29/2016 10 8 70 53 10 13 1107 1546

24 WDW-168 WDW BHEL-IRI-A 1500 1514 9/6/2016 9/25/2016 9/29/2016 10 3 25 19 10 4 1771 2424

25 HYD DEV E-1400 (S.5) 2768 2823 8/14/2016 10/28/2016 11/18/2016 10 3 70 75 10 21 867 1145

26 DHL DEV E-2000(S.7) 4053 4260 2/3/2016 10/6/2016 10/22/2016 20 15 120 246 10 16 468 527

27 HYG DEV E-1400(S.1) 3200 3193 9/15/2016 11/8/2016 11/29/2016 10 7 70 54 10 21 1185 1799

28 WDW-172 WDW BHEL-IRI-A 1600 1608 10/13/2016 11/6/2016 11/9/2016 10 4 25 24 10 3 1578 2038

29 TAT EXPL CH-2 4158 4160 8/6/2016 11/9/2016 12/4/2016 10 2 120 95 15 25 1037 1332

Page 70: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

70

2016-17

30 HYL NAG CH-4 4052 4053 9/4/2016 11/13/2016 11/25/2016 10 3 120 70 10 12 1450 1761

31 TAL DEV CH-3 4157 4251 7/7/2016 11/25/2016 12/9/2016 10 3 120 141 10 14 818 917

32 HYM NAG 750-HP 2392 2412 10/17/2016 12/23/2016 1/23/2017 10 4 60 67 10 31 719 1095

33 HYN DEV E-1400 (S.3) 3345 3348 11/4/2016 12/31/2016 2/3/2017 10 7 70 57 10 34 1039 1787

34 DHF EXPL E-1400(S.6) 3027 3027 11/20/2016 12/28/2016 1/3/2017 15 4 70 38 15 6 1918 2423

35 WDW-167 WDW BHEL-IRI-A 1600 1617 11/23/2016 12/11/2016 12/15/2016 10 5 25 18 10 4 1822 2733

36 BGU EXPL CH-6 4334 4314 10/3/2016 12/7/2016 12/15/2016 15 4 120 65 15 8 1704 2019

37 HYI Dev E-1400 (S.2) 2900 2902 11/15/2016 1/4/2017 1/16/2017 10 7 70 50 10 12 1279 1766

38 HYT NAG E-1400(S.4) 2890 2894 11/20/2016 1/6/2017 1/17/2017 10 5 70 47 10 11 1397 1873

39 HXW NAG CH-4 2880 2904 12/3/2016 1/2/2017 2/22/2017 10 2 60 30 10 14 1920 2945

40 MKB-1 EXPL CH-5 5600 5624 8/13/2016 1/16/2017 2/11/2017 15 5 151 156 15 27 910 1097

41 WDW-170 WDW BHEL-IRI-A 1500 1515 1/1/2017 1/27/2017 1/30/2017 10 4 25 26 10 3 1397 1773

42 MFK EXPL 2000 VFD-2 4000 4445 8/23/2016 2/16/2017 170 177 22 44 612 764

43 MFJ EXPL 2000 VFD-1 4500 4409 8/28/2016 2/20/2017 170 176 22 40 621 762

44 DHJ DEV E-2000(S.7) 4139 4135 12/3/2016 2/23/2017 3/8/2017 25 42 120 82 10 13 918 1534

45 BGS DEV CH-2 4100 3994 12/23/2016 2/27/2017 25 19 120 66 10 22 1135 1841

46 SPB EXPL E-3000(S.8) 4312 4406 10/20/2016 3/5/2017 25 168 120 136 15 27 405 986

47 HYS EXPL E-1400(S.6) 3082 3085 1/25/2017 3/15/2017 20 15 70 49 15 17 1159 1915

48 DIB DEV E-1400(S.1) 3341 3345 1/19/2017 3/18/2017 30 51 70 58 10 14 827 1754

49 HYU NAG E-1400(S.4) 2965 2965 2/7/2017 3/25/2017 30 21 70 46 10 7 1219 1961

50 DHN DEV CH-6(Quippo) 4150 4132 1/9/2017 3/15/2017 15 25 120 65 10 17 1175 1934

51 NLK NAG E-1400(S.5) 3534 3608 1/2/2017 3/7/2017 30 45 70 64 10 25 819 1715

Page 71: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

71

2016-17

ANNEXURE - 3

Shut Down analysis of Drilling Operation for 2016-17

RIGS TARGET ACHIVEMENT

SHUT DOWN HOURS

SURFACE SUBSURFACE ABSENTEESM ENVIRONMENTAL

MISC.

TOTAL TOTAL DAYS

Excess PT

Days GRAND TOTAL

Loc Non-readiness

Waiting for Allied Services

SHUT DOWN HOURS

750-HP 10200 4931 155.50 0.00 14.00 68.50 2328.00 56.75 2622.75 109.28 21 130.28

E-1400 (S-1) 9800 9626 19.50 0.00 3.00 113.25 288.00 378.50 802.25 33.43 54 87.43

E-1400 (S-2) 9900 8937 152.50 0.00 218.92 212.00 0.00 36.00 619.42 25.81 5 30.81

E-1400 (S-3) 10740 11095 44.00 0.00 12.50 321.00 148.00 75.00 600.50 25.02 35 60.02

E-1400 (S-4) 11850 12289 175.50 18.00 5.00 142.00 0.00 23.00 363.50 15.15 5 20.15

E-1400 (S-5) 9614 8195 43.50 8.00 218.00 144.50 0.00 517.00 931.00 38.79 51 89.79

E-1400 (S-6) 9500 10220 22.50 48.00 0.00 207.00 0.00 987.50 1265.00 52.71 16 68.71

E-2000 (S-7) 11950 11646 39.00 192.00 0.00 55.67 120.00 222.00 628.67 26.19 9 35.19

E-3000 (S-8) 12950 4571 26.50 198.00 24.00 712.00 216.00 672.00 1848.50 77.02 12 89.02

C/HIRED-01 12609 0.00 0.00

C/HIRED-02 8350 9590 156.75 0.00 0.00 156.00 264.00 219.00 795.75 33.16 52 85.16

C/HIRED-03 11850 10066 557.00 60.00 0.00 38.50 0.00 15.00 670.50 27.94 4 31.94

C/HIRED-04 9550 12945 5.50 0.00 0.00 41.00 576.00 94.50 717.00 29.88 13 42.88

C/HIRED-05 10961 8284 176.00 0.00 0.00 179.25 0.00 31.25 386.50 16.10 69 85.10

C/HIRED-06 958 46.75 0.00 0.00 188.75 0.00 16.00 251.50 10.48 10.48

C/HIRED-06 10200 12825 123.50 108.00 0.00 208.00 0.00 217.00 656.50 27.35 18 45.35

2000 VFD (V-1) 4400 4409 144.00 0.00 0.00 306.50 0.00 0.00 450.50 18.77 18 36.77

2000 VFD (V-2) 3800 4450 149.25 0.00 5.45 32.00 0.00 546.00 732.70 30.53 22 52.53

BHEL-IRI-A 10500 14950 310.85 274.00 0.00 127.75 0.00 62.50 775.10 32.30 32.30

TOTAL 178724 159987 2348.10 906.00 500.87 3253.67 3940.00 4169.00 15117.64 630

Rig Days 98 38 21 136 164 174 630 404 1033.90

Rig Year 0.27 0.10 0.06 0.37 0.45 0.48 1.73 1.11 2.83

Page 72: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

72

2016-17

ANNEXURE - 4

PERFORMANCE OF DRILLING OUTFIT SINCE INCEPTION

(TILL FINANCIAL YEAR ENDING ON 31st MARCH-2017

Sl. No. Outfit

Date of Commissioning

Achievement Apr'15 - Mar'16

Job done Last well drilled Cum. Meterage

Full Part Full Part 1 750-HP 8/4/2015 4931 5 0 HYM

12742

2 E-1400 (S-1) 16/07/1984 9626 94 0 DIB

333307 3 E-1400 (S-2) 17/02/1985 8937 80 1

HYR 289669

4 E-1400 (S-3) 02/08/1985 11095 76 1

HYX 290071 5 E-1400 (S-4) 15/05/1986 12289 77 0 HYU

263749

6 E-1400 (S-5) 17/06/1987 8195 76 0 NLK

272615 7 E-1400 (S-6) 26/02/1988 10220 71 0 HYS

259882

8 E-2000 (S-7) 31/03/1989 11646 41 0 DHL

178151 9 E-3000 (S-8) 17/03/1990 4571 25 1

HYW 112243

10 2000VFD (V-1) 28/08/2016 4409 1 0 MFJ

4409 11 2000VFD (V-2) 23/08/2016 4450 1 0 MFK

4450

12 BHEL-IRI-A 16/05/1987 14950 126 1

WDW-173 194086

Page 73: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

73

2016-17

ANNEXURE-5

Performance of WO outfit since inception till 31.3.2017

SL NO.

OUTFIT DATE OF COMMISSIONING

CUMULATIVE JOB CARRIED OUT SINCE INSPECTION

METERAGE.

SKYTOP-A 01/02/1978 282F + 7P Retired.

SKYTOP-B 04/04/1978 319F +11P Retired.

SKYTOP-C 29/03/1978 288F +11P Retired.

CARDWEL-A 04/06/1971 249F + 4P Retired.

CARDWEL-B 20/10/1983 181F + 9P Rig scrapped

CARDWEL-C 28/09/1983 184F + 8P Rig scrapped

BHEL-IRI-A 16/05/1987 37F + 1P + 1R Drlg Opn

BHEL-IRI-B 25/06/1988 117F +7 P + 0R Under Production

KREMCO-K-600 18/02/1986 248F + 16P Retired.

F.E.COOPER 18/08/1986 138F + 4P Retired.

CARDWEL-KB-150 01/02/1986 156F + 14P Retired.

1 BHEL-IRI-C 31/03/1989 110F + 17P + 1R

2 BHEL-IRI-D 31/03/1989 128F + 15P + 1R

3 CARDWELL-K-600 10/06/1985 223F + 12P +1R

4 RG-600-A 10/09/2008 51F + 2P + 1R

5 RG-600-B 10/09/2008 31F + 1P + 1R

6 RG-600-C 10/09/2008 35F + 1P + 1R

7 RG-600-D 10/09/2008 31F + 3P + 1R

8 RG-600-E 19/12/2008 17F + 3P + 1R

9 DM-01 19/01/2017 0F + 0P + 1R

10 DM-02 28/11/2016 1F + 0P + 1R

11 DM-03 10/02/2017 OF + 0P + 1R

BHEL-IRI-B (Static) 24F + 3P

BHEL-IRI-C (Static) 20F + 0P

Cardwell-C (Static) 4F + 0P

Page 74: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

74

2016-17

ANNEXURE –6

WORKOVER JOB DONE OF FISCAL YEAR 2016-17 (I.E. 01.04. 2016 TO 31.03.2017)

TARGET -170

DATE : 31.03.2017 TOTAL DAYS : 365 SL

NO. OUTFIT JOB DONE Full Part R/ing

1 BHEL-C F F F F F F F R .

NHK-262 NHK- 67 JRN-45 NHK-605 NHK-387 NHK-332 NHK-622 NHK-417 7 0 1

2 BHEL-D F F F F F R

NHK-329 NHK-427 NHK-107 MKM-43 NHK-203 NHK-395 5 0 1

3 Cardl-K-600 F F F F F F F

NHK-322 NHK-126 NHK-222 JRN-23 NHK-163 NHK-261 JRN-38 7 0 0

4 RG-A F F F F F R

TMK-01 TMK- 06 SLM-22 KLN-22 KLN-14 NHK-159 5 0 1

5 RG-B F F F F F F F R

CBA-08 CBA-14 NHK-298 NHK-591 NHK-470 NHK-169 NHK-161 NHK-197 7 0 1

6 RG-C F F F F F R

TNL - 02 NHK-399 NHK-474 NHK-319 NHK-270 JRN-24 5 0 1

7 RG-D P F F F F F R

NHK-594 NHK-480 SLM-06 SLM-21 NHK-380 NHK-566 NHK-397 5 1 1

8 RG-E P F F R

MKM-42 NHK-606 NHK-547 NTL-02 2 1 1

9 DM - 01 R

NHK-207 0 0 1

10 DM - 02 F R

NHK-525 BPR-15 1 0 1

11 R

DM - 03 NHK-189 0 0 1

12 C/Hired -01 F F F F F F F F F R

JRN-18 BPR-02 BPR-18 MKM-50 BMR - 02 SLM-16 SLM-07 MRN-49 MRN-43 MRN-21 9 0 1

13 C/Hired -02 F F F F F F F F R

BPR-03 NHK-152 MKM-42 NHK-595 NHK-248 EKJ-01 MKM-50 NHK-389 NHK-529 8 0 1

14 F F F F F F F F F F F R

C/Hired-3

HJN-55 HJN-28 HJN-05 MKM-48 MKM-05 MKM-26 MKM-35 MKM-28 HJN-62 HJN-36 SMD-03 BGP-02 11 0 1

15 C/Hired-04 F F F F F F F F F F F R

Page 75: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

75

2016-17

SCM-002 BRK-08 HJN-29 HJN-07 MKM-35 HJN-41 HJN- 06 HJN-58 HJN-23 HJN-14 MKM-13 HJN-58 11 0 1

16 C/Hired-05 F F F F

BPR-09 BPR - 20 BPR-18 KLN-12 4 0 0

17 C/Hired-06 F F F F F F

MRN-116 MRN-108 MKM-14 DHL-01 MRN-86 MRN- 50 6 0 0

18 C/Hired-05( R ) F F F F F F F F F R

MRN - 27 MRN-107 MRN-108 MRN-83 SLM-27 MRN-68 MRN-104 BGN-19 BGN-17 BGN-03 9 0 1

19 C/Hired-06 ( R ) F F F F F R

NHK-499 NHK-389 KJN-09 NHK-614 NHK-358 NHK-375 5 0 1

20 C/Hired-07 F F F F F F F F F F R

HJN-33 NHK-314 JNG-03 MKM-42 NHK-631 EKJ-01 NHK-529 JRN-18 SLM-16 MTN-04 HJN-62 10 0 1

21 C/Hired-08 F F F F F F F F R

NHK-248 SLM - 40 NHK-619 NHK-562 BGN-11 NHK-592 NHK-606 MKM-09 MKM-12 8 0 1

22 C/Hired - 9 F F R

JRN- 45 NHK-329 BGN-21 2 0 1

23 C/Hired -10 F F F F R

BPR-10 BPR-14 BPR-10 BPR-14 BPR-05 4 0 1

24 C/Hired - 11 F F F R

NHK-537 KLN-14 KLN-21 NHK-421

3 0 1

25 C/Hired-12 F F F F R

BPR-001 BPR-09 BPR-13 BPR-11 BPR-14 4 0 1

Total 138 2 22

Full Part R/ing 138 2 22

149.00 %AGE OF Achievement 81.18

SUMMURY: (DRILLING) - 138 (PRODUCTION) - 76 = 214

Page 76: DRILLING DEPARMENT - · PDF fileDrilling Operation b. Work -over Operation c. Deviation Cell d. Cementing e. Rig-building f. Drilling Technical Service g. Equipment & Fishing h. Health

ANNUAL REPORT DRILLING DEPARMENT

76

2016-17 ANNEXURE –7

RIG WISE TARGET Vs ACTUAL COMPRAISON WITH RIG YEAR AVAILABLE & LOSS 2016-17

Target Actual Percent

Achievement Rig

Yr.Tgt Rig Days Lost

Rig Yr lost

Actual Rig Yr utilized

750-HP 10200 4931 48.34 1.00 130.28 0.36 0.64 E-1400 (S-1) 9800 9626 98.22 1.00 87.43 0.24 0.76 E-1400 (S-2) 9900 8937 90.27 1.00 30.81 0.08 0.92 E-1400 (S-3) 10740 11095 103.31 1.00 60.02 0.16 0.84 E-1400 (S-4) 11850 12289 103.70 1.00 20.15 0.06 0.94 E-1400 (S-5) 9614 8195 85.24 1.00 89.79 0.25 0.75 E-1400 (S-6) 9500 10220 107.58 1.00 68.71 0.19 0.81 E-2000 (S-7) 11950 11646 97.46 1.00 35.19 0.10 0.90 E-3000 (S-8) 12950 4571 35.30 1.00 89.02 0.24 0.76 C/HIRED-01 12609 0.00 1.00 0.00 0.00 0.00 C/HIRED-02 8350 9590 114.85 1.00 85.16 0.23 0.77 C/HIRED-03 11850 10066 84.95 1.00 31.94 0.09 0.91 C/HIRED-04 9550 12945 135.55 1.00 42.88 0.12 0.88 C/HIRED-05 10961 8284 75.58 1.00 85.10 0.23 0.77 C/HIRED-06 958

0 10.48 0.03 0.00

C/HIRED-06 10200 12825 125.74 1.00 45.35 0.12 0.88 2000 VFD (V-1) 4400 4409 100.20 0.65 36.77 0.10 0.55 2000 VFD (V-2) 3800 4450 117.11 0.65 52.53 0.14 0.51

BHEL-IRI-A 10500 14950 142.38 1.00 32.30 0.09 0.91 TOTAL 178724 159987 89.52 16.30 1033.90 2.83 13.47