Drilling and Production Technology
description
Transcript of Drilling and Production Technology
Drilling and Production Technology
1st Semester In-Class Test
Question (1): Describe the components of drill string and the bottom-hole assembly and their
functions.
Solution (1): The term drill string is used to describe the tubular and accessories on, which the drill bit is run to the
bottom of the borehole. The drill string consists of drill pipe, drill collars, the Kelly and various
other pieces of equipment such as stabilisers and reamers, which are included in the drill string just
above the drill bit (see figure below). All of these components will be described in detail below. The
drill collars and the other equipment which is made up just above the bit are collectively called the
Bottom-Hole Assembly (BHA).
The functions of the drill string are:
• To suspend the bit
• To transmit rotary torque from the Kelly to the bit
• To provide a conduit for circulating drilling fluid to the bit.
Question (2): Describe the difference between over-balance pressure and under-balance
pressure.
Solution (2): The differential between the mud pressure and the pore pressure at any given depth is known as the
Over-balance pressure at that depth. If the mud pressure is less than the pore pressure then the
differential is known as the under-balance pressure. It will be seen below that the fracture pressure
gradient of the formations is also expressed in units of psi/ft.
Note: It is highly recommended to include graphs in your solution as shown below (Most
students lost marks last year because of this).
Question (3): (A bit tricky):
I remember we were given values for pore pressure and fracture pressure in psi at a certain
depth. Following these values, we were also given three values (or options) for mud weight
in ppg:
a) State which mud is NOT safe to be used for drilling at the given depth?
Solution (a): Firstly, you need to convert the values for pore and fracture pressures from
(Psi) to (ppg), then the mud weight which exceeds the pore pressure and fracture pressure
should be eliminated and it must not be used for drilling.
Note: To make the answer for this question easier, you need only to plot a graph showing
pore and fracture pressure trends versus depth (See Graph below)
b) By using the SAFE mud weight (value above) at a certain depth (15000 ft TVD for
example), Determine the leak-off pressure at the surface?
Solution (b): USE the following equation (ALWAYS REMEMBER IT):
1- Max. Bottom hole pressure during leak-off = Pressure when the formation already
fractured (fracture pressure value given above in Psi) / TVD (15000 ft).
2- Hydrostatic pressure of mud colom = (0.052 * TVD (15000 ft) * SAFE mud weight).
3- From equation above, Leak-off pressure at surface = (1) – (2).
Question (4): (Drill pipe, Drill Collars, Collapse Loading and Total Tension Load):
NOTE: FOCUS on Tutorial (1), Problems (1) and (2):
a) Calculate the number of 8 1/4” x 2 13/16” (83.9 Ib/ft) drill-collars (25ft/joint), drill
pipes (19.5 Ib/ ft) and Total Length of Drill string that would be required to provide
20,000lbs WOB and keep the drill pipe in tension in 12 ppg mud.
Solution (a):
1- Length of Drill Collars = WOB / (Ib/ft * fraction (if it is NOT given, always assume
it 1))
= 20,000 / (83.9 * 1) = 238.4 ft
2- Number drill collars= 238.4/25 = 10.
3- Length of Drill Pipe = [WOB (20,000)/ (19.5 Ib/ft)] – Length of Drill Collars (NOT
SURE)
4- Number of Drill pipes = Length of Drill pipe / 25 ft/joint
5- Total Length of Drill string = Length of (Drill Pipe + Drill Collars)
b) From Data above, calculate the collapse loading and total weight of drill string at a
TVD of 12,000 ft (This part is easier than the one in Tutorial 1, because the area was
given)?
Solution (b):
Step (1): Collapse loading at 12,000 ft = 0.052 * MW * TVD.
Step (2): Follow STEP 2 in TUTORIAL 1.
Step (3): Total Weight of Drill String (EASY) = Wc + Wp
(NO NEED TO CALCULATE THE WEIGHT FOR EACH SECTION, AT THE TOP AND
BOTTOM OF DRILL COLLAR AND DRILL PIPE).