Drainage Report Block 29002 Lot 45 · This report outlines the results of a hydrologic and...
Transcript of Drainage Report Block 29002 Lot 45 · This report outlines the results of a hydrologic and...
F:\Jobfile\0303M\_ENG\Hydrology\Drainage Report 6-25-20.doc
Drainage Report
Prepared For
Block 29002 Lot 45
Montgomery Township
Somerset County, New Jersey VCEA Project Number 0303M
July 17, 2018
Revised August 26, 2019
Revised March 13, 2020
Revised April 21, 2020
Revised May 27, 2020
Revised June 10, 2020
Revised June 26, 2020
Prepared For
CC1377, LLC
36 Brower Lane
Hillsborough, New Jersey 08844
Prepared By:
Van Cleef Engineering Associates, LLC
32 Brower Lane
PO Box 5877
Hillsborough, New Jersey 08844
Michael K. Ford, NJ PE No. 34722
1
Table of Contents
Title
1.0 Introduction
2.0 Site Description
2.1 Existing Conditions
2.2 Proposed Conditions
3.0 Methodology
4.0 Stormwater Management Objectives
5.0 Stormwater Runoff Control
6.0 Basin Surface Elevation Summary
7.0 Water Quality
8.0 Groundwater Recharge
9.0 Low Impact Development Techniques
10.0 Storm Sewer Design
11.0 Conclusions
12.0 References
Appendix A-Soil Map, CN Values and Time of Concentration
Appendix B-Reservoirs Report
Appendix C-Pre-Development Hydrographs
Appendix D-Post-Development Hydrographs
Appendix E-Water Quality Calculations
Appendix F-Low Impact Development Checklists
Appendix G-Pipe Calculations
Appendix H-Emergency Spillway Design
Appendix I-Recharge Analysis
Appendix J-Drainage Area Maps
2
1.0 Introduction
This report outlines the results of a hydrologic and hydraulic storm water runoff analysis
conducted by Van Cleef Engineering Associates (VCEA) with regard to the proposed
construction on Block 29002 Lot 45 as designated by the Montgomery Township Tax
Maps. The subject property is approximately 5.00 acres and is located along US-206.
The entire subject property lies in the Highway Commercial (HC) District.
This report has been prepared to summarize stormwater analysis design objectives,
methodologies and calculations for the conveyance of stormwater runoff from the
project area under pre and post-development conditions.
2.0 Site Description
2.1 Existing Conditions
The site presently contains a utility building and a parking lot. The rest of the
property is either wooded or covered with grass. A large patch of dirt lies in the
place of a recently demolished building. The entire site is drained by the storm
sewer network running along US-206. The Existing Drainage Area Map indicates
two drainage areas: Drainage Area DA 1 consists of the disturbed area which is
subject to the runoff reduction rates cited in the N.J.A.C. regulations whereas
Drainage Area DA 1A consists of the undisturbed area that will be drained by the
proposed basin under developed conditions and which is not subject to the
aforementioned reduction rates. The difference in elevation between the eastern
and western portions of the lot is greater than 30 feet. See Appendix I for the
Existing Drainage Areas plan. All the soils within the project area belong to
Hydrologic Group C.
2.2 Proposed Conditions
The proposed development of the site includes the construction of two
residential buildings, an appurtenant parking area, a storm sewer system and a
detention basin. The basin will discharge toward the same storm sewer system
running along US-206 as under existing conditions. Furthermore, there will be a
bypass area not drained by the basin which will also be directed toward the
aforementioned storm sewer system. The new buildings will be serviced by
public water and sewer.
3
3.0 Methodology
The assessment of stormwater runoff has been based upon the Soil Conservation
Service Methodology as described in Technical Release No. 55 (TR-55), “Urban
Hydrology for Small Watershed.” Theoretical storms are modeled with the 24-hour SCS
Unit Dimensionless Hydrograph, utilizing a Type III rainfall distribution and recurrence
intervals of 2, 10 and 100 years using Bentley Pond Pack version 8i . The program is
tailored to model the SCS Method for hydrograph generations and to perform interactive
solutions of continuity equation (outflow = inflow +/- storage) with the intermediate
values of the routing curve obtained through linear interpretation.
For Somerset County, New Jersey these 24-hour rainfall amounts are as follows: 2-Year = 3.34 inches 10-Year = 5.01 inches 100-Year = 8.21 inches
Rainfall intensities have been based upon the Somerset County rainfall
intensity/duration curve for all design storms.
The Soil Conservation Service Soil Survey (SCS) for Somerset County was utilized in
order to classify the soils within the watershed. All the soils within the project area
belong to Hydrologic Soil Group C.
Soil Symbol
Soil Name Hydrologic Soil Group
LbtB Lansdowne silt loam, 2 to 6 percent slopes C RoyB Royce silt loam, 2 to 6 percent slopes C
For detailed soils locations please refer to the soils information in the Appendix.
4.0 Stormwater Management Objectives
The primary objective of the Stormwater Management Plan is to provide water quantity
and quality control. The stormwater management is designed to meet all applicable
regulations. This report was prepared following currently accepted engineering
standards, and the measures proposed are designed to meet the requirements of the
Township of Montgomery, Residential Site Improvements Standards (RSIS), the New
Jersey Department of Environmental Protection (NJAC 7:8-5.2), and the Standards for
Soil Erosion and Sediment Control in New Jersey.
4
5.0 Stormwater Runoff Control
Almost all the runoff generated by the project area will be either conveyed to the
detention basin via the pipe network in the southern portion of the site or conveyed to
the existing storm sewer network running along US-206 via the pipe network located in
the Bypass Area within the northern portion of the site. The post construction allowable
peak flow rates for the point of analysis (See Appendix I) were determined by applying
the reductions required by N.J.A.C. 7:8. This project will add a total of 43,752 square
feet (1.01 acres) of impervious coverage to the existing 90,320 square feet (2.07 acres)
of impervious coverage which will result in a total of 134,072 square feet (3.08 acres)
of impervious coverage. The calculations for and results of our analysis can be found in
the tables below.
Project Area Peak Flow Reductions (POA)
Storm
Frequency
Pre-Development
Condition
Peak Flow CFS (EX.
POA – Disturbed
Area To Be
Reduced)
Pre-Development
Condition
Peak Flow CFS
(EX. POA –
Undisturbed
Area)
Allowable Peak
Flow CFS
Post-
Development
Condition Peak
Flow CFS (PR.
POA)
Water Quality 5.24 0.03 N/A 1.88
2 7.40 0.36 7.04*0.50+0.36=
4.06 4.02
10 13.26 0.85
13.26*0.75+0.85=
10.795 10.46
100 25.18 1.90
25.18*0.80+1.90=
22.044 22.03
6.0 Basin Water Surface Elevation Summary A summary of the basin water surface elevations and outflows for the underground basin facility for the 2-, 10-, and 100-year storm events are shown below in the following table.
5
Basin Outflow Water Surface Elevation Summary:
Detention Basin
Storm Event (Year)
Water Surface Elevation (ft) Outflow (cfs)
Water Quality 100.89 0.00 2 102.17 2.03
10 102.99 5.68 100 103.91 11.91
7.0 Water Quality
The total amount of impervious coverage for the proposed site is 3.08 acres. A sand
bottom infiltration basin will be used to treat paved impervious areas. The infiltration
basin has been designed in accordance with the NJDEP BMP Manual which is approved
for 80% TSS removal. See Appendix for soil data and calculations pertaining to water
quality. Below is a summary of the required and provided TSS removal rate by acreage-
removal rate per total acre of land.
Minimum Required TSS Removal for Proposed Impervious
Area Acres Required TSS
Removal
Total Acreage –Removal
Rates
Proposed Impervious 1.01 80% 0.81
Existing Impervious 2.07 80% 1.66
Totals 3.08 2.47
Required TSS Removal Rate (Acreage-Removal Rate/Total Acres): 80%
Proposed TSS Removal for Proposed Impervious
Area Acres Required TSS
Removal
Total Acreage –Removal
Rates
Proposed Impervious 3.08 80% 2.47
Existing Impervious 0.00 80% 0.00
Totals 3.08 2.47
Proposed TSS Removal Rate (Acreage-Removal Rate/Total Acres): 80%
8.0 Groundwater Recharge
The groundwater recharge amount was calculated using the NJDEP GSR-32
Spreadsheet (See Appendix for Spreadsheet Calculations). The infiltration basin will
6
provide groundwater recharge by infiltrating more than 100 percent of the Annual
Recharge Deficit. The total annual recharge of the site under pre-developed conditions
is 135,266 cf. The annual recharge under post-developed conditions is 88,888 cf
resulting in a deficit of 46,378 cf. The annual recharge volume provided by the
infiltration basin is 233,252 cf and thus the groundwater recharge requirement is
fulfilled. The sand filter will drain within 72 hours (see Appendix F). An infiltration rate
of 0.50 in/hr has been used in the calculations as that is fifty percent of the slowest rate
observed.
9.0 Low Impact Development Techniques
According to the NJDEP Stormwater Management Rules at N.J.A.C. 7:8, the
groundwater recharge, stormwater quality, and stormwater quantity standards
established by the rules for major land development projects must be met by
incorporating nine specific nonstructural stormwater management strategies into the
project’s design to the maximum extent practicable.
The Low Impact Development Checklist was completed to demonstrate incorporation of nonstructural stormwater management strategies in the project’s design. The checklist is included in Appendix F.
The following is a summary of the nonstructural stormwater management strategies
incorporated into the site design:
a. Protect areas that provide water quality benefits or areas particularly susceptible
to erosion and sediment loss.
This project was designed in accordance with the Standards for Soil
Erosion and Sediment Control in New Jersey. As part of the proposed
project, a riprap apron has been designed to control erosion at the
outflow point of the storm sewer network.
b. Minimize impervious surfaces and break up or disconnect the flow of runoff over
impervious surfaces:
Impervious coverage for the site has been minimized so that it is
compliant with local regulations.
c. Maximize the protection of natural drainage features and vegetation.
7
This project is a redevelopment of a property that has been previously
disturbed. There are no natural drainage features to protect. There will
be a loss of vegetation which is necessary in order to construct the two
buildings. However, the proposed plantings depicted on the Landscape
Plan will compensate for this loss of vegetation.
d. Minimize the decrease in the “time of concentration” from pre-construction to
post construction. “Time of concentration” is defined as the time it takes for
runoff to travel from the hydraulically most distant point of the drainage area to
the point of interest within a watershed.
The decrease in the time of concentration has been minimized to the
maximum extent possible.
e. Minimize land disturbance including clearing and grading.
Clearing and grading have been minimized to the maximum extent
practicable.
f. Minimize soil compaction.
Soil compaction will be minimized where feasible.
g. Provide low-maintenance landscaping that encourages retention and planting of
native vegetation and minimizes the use of lawns, fertilizers and pesticides.
The landscape design for this project employs the use of native
ornamental, shade, and shrubs on the site. Because native and
adapted trees and shrubs have been chosen for this project, the
landscape will also require less use of fertilizers and pesticides.
h. Provide vegetated open-channel conveyance systems discharging into and
through stable vegetated areas.
Vegetated open-channel conveyance is proposed to collect and direct
the runoff from the basin.
i. Provide other source controls to prevent or minimize the use or exposure of
pollutants at the site in order to prevent or minimize the release of those
8
pollutants into stormwater runoff. Such source controls include, but are not
limited to:
1. Site design features that help to prevent accumulation of trash and debris
in drainage systems.
Proposed inlets on site will comply with the NJPDES storm drain
inlet criteria. Eco-curbs or approved equal, which are catch basin
curb tops, will be provided. They will have debris retention
openings to prevent debris from entering the storm drainage
system.
2. Site design features that help to prevent discharge of trash and debris
from drainage systems.
The outlet structure trash rack will trap the larger debris and
floatables discharged from the site. It is anticipated that no
large floatables will be discharged from the basin as the majority
of impervious pavement surfaces are routed through storm
grates.
3. Site design features that help to prevent and/or contain spills or other
harmful accumulations of pollutants at industrial or commercial
developments; and
This development is neither an industrial development nor a
commercial development.
4. When establishing vegetation after land disturbance, applying fertilizer in
accordance with the requirements established under the Soil Erosion and
Sediment Control Act, NJSA. 4:24-39 et seq., and implementing rules.
The applicant intends to apply fertilizer in accordance with the
requirements established under the Soil Erosion and Sediment
Control Act.
10.0 Storm Sewer Design
The stormwater management collection system was designed based upon 25-year
storm return frequency. Manning’s Formula with a Manning’s Coefficient of 0.013 for
9
reinforced concrete pipe was utilized for sizing the stormwater pipes. Weighted “C”
values were computed based upon land use. The time of concentration to the various
inlet drainage areas have been designed with a minimum of 10 minutes, and rainfall
intensities were based on the various times of concentration considering travel time
within the stormwater collection system. Flow rates were computed using the Rational
Method (Q = CIA). Calculations are provided in the Appendix.
11.0 Conclusion
The proposed development will reduce the peak flow rate from the developed area for
the 2, 10, and 100 year storms as required, will meet the required 80% TSS removal
rate for all new impervious surfaces, and meets the recharge requirements. The site
closely mirrors existing condition drainage patterns. Accordingly, the new development
will not negatively impact runoff on-site or downstream. The project has been designed
in accordance with the standards set forth by various regulatory agencies including the
Montgomery Township, the Residential Site Improvement Standards, the New Jersey
Department of Environmental Protection, and the New Jersey Department of Agriculture
for Soil Erosion Control Standards in the State of New Jersey. All engineering
calculations and their associated drainage area maps are incorporated in the appendix
for further review.
12.0 References
1. Urban Hydrology for Small Watersheds, TR-55, USDA Soil Conservation Service, June 1986.
2. NJDEP Stormwater Management Rules, NJAC 7:8, June 20, 2016.
3. NJDEP Stormwater Best Management Practices Manual, February 2016.
4. Standards for Soil Erosion and Sediment Control in New Jersey, New Jersey State
Soil Conservation Committee, January 2014.
5. Web Soil Survey, United States Department of Agriculture, Natural Resource Conservation Service, Version 8, 2008.
6. Montgomery Township Land Use Ordinance.
7. Bentley, StormCAD®, Version 8.11.02.75, 2011.
8. Bently, Pond Pack version 8i, 2012.
Appendix A
Soil Map, CN Values and Time of Concentration
Hyd
rolo
gic
Soi
l Gro
up—
Som
erse
t Cou
nty,
New
Jer
sey
Nat
ural
Res
ourc
esC
onse
rvat
ion
Serv
ice
Web
Soi
l Sur
vey
Nat
iona
l Coo
pera
tive
Soi
l Sur
vey
4/25
/201
8P
age
1 of
3
4472880447291044729404472970447300044730304473060
4472880447291044729404472970447300044730304473060
5297
3052
9760
5297
9052
9820
5298
5052
9880
5299
1052
9940
5299
7053
0000
5297
3052
9760
5297
9052
9820
5298
5052
9880
5299
1052
9940
5299
7053
0000
40° 2
4' 2
7'' N
74° 38' 58'' W40
° 2
4' 2
7'' N
74° 38' 46'' W
40° 2
4' 2
1'' N
74° 38' 58'' W
40° 2
4' 2
1'' N
74° 38' 46'' W
N
Map
pro
ject
ion:
Web
Mer
cato
r C
orne
r coo
rdin
ates
: WGS
84
Edge
tics
: UTM
Zon
e 18
N W
GS84
050
100
200
300Fe
et0
1530
6090M
eter
sM
ap S
cale:
1:1
,330
if p
rinte
d on
A la
ndsc
ape
(11"
x 8
.5")
shee
t.
Soi
l Map
may
not
be
valid
at
this
sca
le.
Hydrologic Soil Group
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
LbtB Lansdowne silt loam, 2 to 6 percent slopes
C 0.4 7.8%
RoyB Royce silt loam, 2 to 6 percent slopes
C 4.6 92.2%
Totals for Area of Interest 5.0 100.0%
Rating Options
Aggregation Method: Dominant Condition
Component Percent Cutoff: None Specified
Tie-break Rule: Higher
Hydrologic Soil Group—Somerset County, New Jersey
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
4/25/2018Page 3 of 3
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: UndevelopedArea Name EX. DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Woods: Good Condition 70 1.62 113.4C Open Space: Good Condition 74 1.38 102.12
Totals 3 215.52CN (weighted) = total product/ total area= 215.52
3 Use CN = 71.8
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: UndevelopedArea Name EX. DA 1A
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Woods: Good Condition 70 0.29 20.3C Open Space: Good Condition 74 0.18 13.32
Totals 0.47 33.62CN (weighted) = total product/ total area= 33.62
0.47 Use CN = 71.5
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: UndevelopedArea Name EX. DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Paved Parking Lots, Roofs, Driveways, Etc. 98 2.07 202.86
Totals 2.07 202.86CN (weighted) = total product/ total area= 202.86
2.07 Use CN = 98.0
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: DevelopedPre DevelopedSelect One: Tc Area Name EX. DA 1
Notes: Space for as many as two segments per flow type can be used for each worksheetInclude a Map, schematic, or description of flow segments
Sheet Flow (Applicable to Tc only) Segment ID A-B
1 Surface Description (table 3-1) Grass2 Mannings Roughness Coeff.,n (table 3-1) 0.243 Flow Length, L (total L < 300 ft) ft 1004 Two-yr 24-hr rainfall, P2 in 3.35 land slope, s ft/ft 0.06756 Tt=(0.007*(nL)^0.8/((P2^0.5)*(s^0.4)) Compute Tt hr 0.14 0.14
Shallow Concentrated Flow Segment ID B-C C-D
7 Surface Description (paved or unpaved) Unpaved Paved8 Flow Length, L ft 96 2129 Watercourse Slope, s ft/ft 0.065 0.04
10 Average velocity, V (figure 3-1) ft/s 4.1 411 Tt = L/(3600*V) Compute Tt hr 0.01 0.01 0.02
Channel Flow Segment ID D-POA
12 Cross sectional flow area, a ft^213 Wetted Perimeter, Pw ft14 Hydraulic Radius, r=a/Pw Compute r ft15 Channel Slope, s ft/ft16 Mannings roughness Coeff., n17 V = 1.49(r^(2/3))*(s^(1/2))/n Compute V ft/s 2 Assumed18 Flow Length, L ft 62819 Tt = L/(3600*V) Compute Tt hr 0.09 0.0920 Water shed or Subarea Tc or Tt (add Tt in steps 6, 11,19) hr 0.25
min 15.15
Worksheet 3: Time of Concentration (Tc) or Travel Time (Tt)
Project By KH Date 8/21/2019Location Montgomery, NJ Checked DateSelect One: DevelopedArea Name Basin DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Open Space: Good Condition 74 0.78 57.72C Woods: Good Condition 70 0.01 0.7
Totals 0.79 58.42CN (weighted) = total product/ total area= 58.42
0.79 Use CN = 73.9
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery, NJ Checked DateSelect One: DevelopedArea Name Basin DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Paved Parking Lots, Roofs, Driveways, Etc. 98 2.34 229.32
Totals 2.34 229.32CN (weighted) = total product/ total area= 229.32
2.34 Use CN = 98.000
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: Developed DevelopedSelect One: Tc Area Name Basin DA 1
Notes: Space for as many as two segements per flow type can be used for each worksheetInclude a Map, schematic, or description of flow segments
Sheet Flow (Applicable to Tc only) Segment ID A-B
1 Surface Description (table 3-1) Asphalt2 Mannings Roughness Coeff.,n (table 3-1) 0.0113 Flow Length, L (total L < 300 ft) ft 1004 Two-yr 24-hr rainfall, P2 in 3.35 land slope, s ft/ft 0.046 Tt=(0.007*(nL)^0.8/((P2^0.5)*(s^0.4)) Compute Tt hr 0.02 0.02
Shallow Concentrated Flow Segment ID B-C
7 Surface Description (paved or unpaved) Paved8 Flow Length, L ft 1839 Watercourse Slope, s ft/ft 0.046
10 Average velocity, V (figure 3-1) ft/s 4.411 Tt = L/(3600*V) Compute Tt hr 0.01 0.01
Channel Flow Segment ID D-POA
12 Cross sectional flow area, a ft^213 Wetted Perimeter, Pw ft14 Hydraulic Radius, r=a/Pw Compute r ft15 Channel Slope, s ft/ft16 Mannings roughness Coeff., n17 V = 1.49(r^(2/3))*(s^(1/2))/n Compute V ft/s 2 Assumed18 Flow Length, L ft 71219 Tt = L/(3600*V) Compute Tt hr 0.10 0.1020 Water shed or Subarea Tc or Tt (add Tt in steps 6, 11,19) hr 0.13
min 7.53
Worksheet 3: Time of Concentration (Tc) or Travel Time (Tt)
Project By KH Date 8/21/2019Location Montgomery, NJ Checked DateSelect One: DevelopedArea Name Bypass DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Open Space: Good Condition 74 1.34 99.16C Woods: Good Condition 70 0.33 23.1
Totals 1.67 122.26CN (weighted) = total product/ total area= 122.26
1.67 Use CN = 73.2
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery, NJ Checked DateSelect One: DevelopedArea Name Bypass DA 1
1. Runoff Curve NumberNames Cover Description Area Product
Soil Name and Hydrologic Group (appendix A)
(cover type, treatment, and hydrologic condition; percent impervious; unconnected/
connected area ratio) Tab 2-2 Fig 2-3 Fig 2-4
acres miles
% CN x areaC Paved Parking Lots, Roofs, Driveways, Etc. 98 0.74 72.52
Totals 0.74 72.52CN (weighted) = total product/ total area= 72.52
0.74 Use CN = 98.000
Worksheet 2: Runoff curve number and runoff
CN
Project By KH Date 8/21/2019Location Montgomery Township, NJ Checked DateSelect One: Developed DevelopedSelect One: Tc Area Name Bypass DA 1
Notes: Space for as many as two segements per flow type can be used for each worksheetInclude a Map, schematic, or description of flow segments
Sheet Flow (Applicable to Tc only) Segment ID A-B
1 Surface Description (table 3-1) Grass2 Mannings Roughness Coeff.,n (table 3-1) 0.243 Flow Length, L (total L < 300 ft) ft 1004 Two-yr 24-hr rainfall, P2 in 3.35 land slope, s ft/ft 0.0386 Tt=(0.007*(nL)^0.8/((P2^0.5)*(s^0.4)) Compute Tt hr 0.18 0.18
Shallow Concentrated Flow Segment ID B-C
7 Surface Description (paved or unpaved) Not Paved8 Flow Length, L ft 509 Watercourse Slope, s ft/ft 0.201
10 Average velocity, V (figure 3-1) ft/s 7.2511 Tt = L/(3600*V) Compute Tt hr 0.01 0.01
Channel Flow Segment ID C-POA
12 Cross sectional flow area, a ft^213 Wetted Perimeter, Pw ft14 Hydraulic Radius, r=a/Pw Compute r ft15 Channel Slope, s ft/ft16 Mannings roughness Coeff., n17 V = 1.49(r^(2/3))*(s^(1/2))/n Compute V ft/s 2 Assumed18 Flow Length, L ft 88119 Tt = L/(3600*V) Compute Tt hr 0.12 0.1220 Water shed or Subarea Tc or Tt (add Tt in steps 6, 11,19) hr 0.31
min 18.81
Worksheet 3: Time of Concentration (Tc) or Travel Time (Tt)
Appendix B
Reservoirs Report
Table of Contents
6Elevation-Volume-Flow Table (Pond), 100 yearsProposed Pond
4Outlet Input Data, 2 yearsO.C.S.
1Master Network Summary
Subsection: Master Network Summary
Catchments Summary
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
0.201.35535.0001WQEX. DA 1 PERVIOUS
2.3212.2010,688.00022-YearEX. DA 1 PERVIOUS
5.4712.2023,756.0001010-YearEX. DA 1 PERVIOUS
7.9312.2034,078.0002525-YearEX. DA 1 PERVIOUS
12.2312.2052,784.000100100-YearEX. DA 1 PERVIOUS
0.111.20208.0001WQBASIN DA 1 PERVIOUS
0.8212.153,150.00022-YearBASIN DA 1 PERVIOUS
1.8212.106,756.0001010-YearBASIN DA 1 PERVIOUS
2.6012.109,577.0002525-YearBASIN DA 1 PERVIOUS
3.9412.1014,606.000100100-YearBASIN DA 1 PERVIOUS
5.231.107,771.0001WQEX. DA 1 IMPERVIOUS
5.2412.1523,047.00022-YearEX. DA 1 IMPERVIOUS
7.9912.1035,791.0001010-YearEX. DA 1 IMPERVIOUS
9.9312.1044,743.0002525-YearEX. DA 1 IMPERVIOUS
13.1612.1059,813.000100100-YearEX. DA 1 IMPERVIOUS
5.911.108,785.0001WQBASIN DA 1IMPERVIOUS
5.9212.1526,053.00022-YearBASIN DA 1IMPERVIOUS
9.0312.1040,459.0001010-YearBASIN DA 1IMPERVIOUS
11.2212.1050,579.0002525-YearBASIN DA 1IMPERVIOUS
14.8712.1067,614.000100100-YearBASIN DA 1IMPERVIOUS
0.141.40389.0001WQBYPASS DA 1PERVIOUS
1.3212.256,417.00022-YearBYPASS DA 1PERVIOUS
2.9912.2513,926.0001010-YearBYPASS DA 1PERVIOUS
4.2812.2519,785.0002525-YearBYPASS DA 1PERVIOUS
6.5412.2030,377.000100100-YearBYPASS DA 1PERVIOUS
1.871.102,778.0001WQBYPASS DA 1IMPERVIOUS
1.8712.158,239.00022-YearBYPASS DA 1IMPERVIOUS
2.8612.1012,795.0001010-YearBYPASS DA 1IMPERVIOUS
3.5512.1015,995.0002525-YearBYPASS DA 1IMPERVIOUS
4.7012.1021,382.000100100-YearBYPASS DA 1IMPERVIOUS
0.031.3579.0001WQEX. DA 1A PERVIOUS
0.3612.201,647.00022-YearEX. DA 1A PERVIOUS
Page 1 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Subsection: Master Network Summary
Catchments Summary
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
0.8512.203,680.0001010-YearEX. DA 1A PERVIOUS
1.2312.205,289.0002525-YearEX. DA 1A PERVIOUS
1.9012.208,210.000100100-YearEX. DA 1A PERVIOUS
Node Summary
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
5.241.108,306.0001WQEX. POA (TO BEREDUCED)
7.4012.1533,735.00022-YearEX. POA (TO BEREDUCED)
13.2612.1559,547.0001010-YearEX. POA (TO BEREDUCED)
17.6512.1578,821.0002525-YearEX. POA (TO BEREDUCED)
25.1812.15112,596.000100100-YearEX. POA (TO BEREDUCED)
1.881.153,167.0001WQPR. POA
4.0212.2034,813.00022-YearPR. POA
10.4612.2564,890.0001010-YearPR. POA
13.1112.2595,200.0002525-YearPR. POA
22.0312.20124,935.000100100-YearPR. POA
0.031.3579.0001WQEX. POA
0.3612.201,647.00022-YearEX. POA
0.8512.203,680.0001010-YearEX. POA
1.2312.205,289.0002525-YearEX. POA
1.9012.208,210.000100100-YearEX. POA
Pond Summary
MaximumPond Storage
(ft³)
MaximumWater
SurfaceElevation
(ft)
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
(N/A)(N/A)5.951.158,993.0001WQProposedPond (IN)
8,992.000100.890.000.000.0001WQProposedPond (OUT)
(N/A)(N/A)6.7412.1529,202.00022-YearProposedPond (IN)
16,040.000102.172.0312.5020,157.00022-YearProposedPond (OUT)
(N/A)(N/A)10.8612.1047,215.0001010-YearProposedPond (IN)
Page 2 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Subsection: Master Network Summary
Pond Summary
MaximumPond Storage
(ft³)
MaximumWater
SurfaceElevation
(ft)
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
21,061.000102.995.6812.3538,170.0001010-YearProposedPond (OUT)
(N/A)(N/A)13.8312.1060,156.0002525-YearProposedPond (IN)
19,201.000103.106.9712.3559,420.0002525-YearProposedPond (OUT)
(N/A)(N/A)18.8212.1082,221.000100100-YearProposedPond (IN)
27,616.000103.9411.9112.3073,175.000100100-YearProposedPond (OUT)
Page 3 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: O.C.S.
Return Event: 2 yearsSubsection: Outlet Input Data
Requested Pond Water Surface Elevations
ft99.00Minimum (Headwater)
ft0.50Increment (Headwater)
ft104.00Maximum (Headwater)
Outlet Connectivity
E2(ft)
E1(ft)
OutfallDirectionOutlet IDStructure Type
104.00100.90TWForwardOrifice - 1Orifice-Circular
104.00101.90TWForwardWeir - 1Rectangular Weir
(N/A)(N/A)TailwaterTailwater Settings
Page 4 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: O.C.S.
Return Event: 2 yearsSubsection: Outlet Input Data
Structure ID: Orifice - 1Structure Type: Orifice-Circular
1Number of Openings
ft100.90Elevation
in7.5Orifice Diameter
0.60Orifice Coefficient
Structure ID: Weir - 1Structure Type: Rectangular Weir
1Number of Openings
ft101.90Elevation
in13.00Weir Length
(ft^0.5)/s3.00Weir Coefficient
Structure ID: TWStructure Type: TW Setup, DS Channel
Free OutfallTailwater Type
Convergence Tolerances
30Maximum Iterations
ft0.01Tailwater Tolerance(Minimum)
ft0.50Tailwater Tolerance(Maximum)
ft0.01Headwater Tolerance(Minimum)
ft0.50Headwater Tolerance(Maximum)
ft³/s0.001Flow Tolerance (Minimum)
ft³/s10.000Flow Tolerance (Maximum)
Page 5 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: Proposed Pond
Return Event: 100 yearsSubsection: Elevation-Volume-Flow Table (Pond)
Infiltration
No InfiltrationInfiltration Method(Computed)
Initial Conditions
ft99.00Elevation (Water Surface,Initial)
ft³0.000Volume (Initial)
ft³/s0.00Flow (Initial Outlet)
ft³/s0.00Flow (Initial Infiltration)
ft³/s0.00Flow (Initial, Total)
hours0.05Time Increment
2S/t + O(ft³/s)
Flow (Total)(ft³/s)
Infiltration(ft³/s)
Area(ft²)
Storage(ft³)
Outflow(ft³/s)
Elevation(ft)
0.000.000.004,334.000.0000.0099.00
24.690.000.004,555.732,222.2030.0099.50
50.630.000.004,783.004,556.6560.00100.00
77.830.000.005,009.877,004.6550.00100.50
100.510.000.005,195.159,045.5480.00100.90
106.330.030.005,242.009,567.4040.03101.00
136.820.750.005,473.5012,246.0700.75101.50
162.041.220.005,662.3014,473.1231.22101.90
168.541.410.005,710.0015,041.7371.41102.00
203.033.190.006,068.0617,985.7973.19102.50
240.305.720.006,437.0021,111.6075.72103.00
280.638.810.006,974.7224,463.6388.81103.50
324.4712.360.007,534.0028,089.91812.36104.00
Page 6 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Index
Proposed Pond (Elevation-Volume-Flow Table (Pond), 100 years)...6
P
O.C.S. (Outlet Input Data, 2 years)...4, 5
O
Master Network Summary...1, 2, 3
M
Page 7 of 727 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: Proposed Pond (OUT)
Return Event: 100 yearsSubsection: Time vs. Elevation
Time vs. Elevation (ft)
Output Time increment = 0.05 hoursTime on left represents time for first value in each row.
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Time(hours)
99.0099.0099.0099.0099.000.00
99.0099.0099.0099.0099.000.25
99.0099.0099.0099.0099.000.50
99.0199.0099.0099.0099.000.75
99.0299.0199.0199.0199.011.00
99.0399.0399.0399.0299.021.25
99.0599.0599.0499.0499.041.50
99.0799.0799.0699.0699.051.75
99.1099.0999.0999.0899.082.00
99.1299.1299.1199.1199.102.25
99.1599.1499.1499.1399.132.50
99.1899.1799.1799.1699.162.75
99.2199.2199.2099.1999.193.00
99.2599.2499.2499.2399.223.25
99.2999.2899.2799.2799.263.50
99.3399.3299.3199.3199.303.75
99.3799.3699.3599.3599.344.00
99.4299.4199.4099.3999.384.25
99.4699.4599.4499.4399.434.50
99.5199.5099.4999.4899.474.75
99.5699.5599.5499.5399.525.00
99.6199.6099.5999.5899.575.25
99.6699.6599.6499.6399.625.50
99.7199.7099.6999.6899.675.75
99.7799.7699.7599.7499.726.00
99.8399.8299.8099.7999.786.25
99.8999.8899.8799.8599.846.50
99.9699.9599.9399.9299.906.75
100.03100.02100.0099.9999.977.00
100.11100.09100.08100.06100.057.25
100.19100.17100.16100.14100.127.50
100.27100.26100.24100.22100.217.75
100.37100.35100.33100.31100.298.00
100.47100.45100.43100.41100.398.25
100.58100.56100.53100.51100.498.50
100.70100.68100.65100.63100.608.75
100.83100.81100.78100.75100.739.00
100.97100.95100.92100.89100.869.25
101.11101.08101.06101.03101.009.50
101.22101.20101.18101.16101.139.75
101.33101.31101.29101.27101.2510.00
101.43101.41101.39101.37101.3510.25
101.52101.51101.49101.47101.4510.50
Page 1 of 827 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/5/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: Proposed Pond (OUT)
Return Event: 100 yearsSubsection: Time vs. Elevation
Time vs. Elevation (ft)
Output Time increment = 0.05 hoursTime on left represents time for first value in each row.
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Time(hours)
101.62101.60101.58101.56101.5410.75
101.73101.71101.69101.66101.6411.00
101.89101.85101.82101.79101.7611.25
102.13102.06102.01101.96101.9211.50
102.74102.58102.45102.32102.2211.75
103.87103.70103.47103.20102.9512.00
103.74103.83103.90103.94103.9412.25
103.20103.31103.43103.54103.6512.50
102.77102.84102.92103.01103.1012.75
102.50102.55102.59102.65102.7113.00
102.33102.36102.39102.42102.4613.25
102.20102.23102.25102.27102.3013.50
102.12102.13102.15102.17102.1813.75
102.05102.06102.07102.09102.1014.00
102.00102.01102.02102.03102.0414.25
101.96101.96101.97101.98101.9914.50
101.91101.92101.93101.94101.9514.75
101.87101.88101.89101.90101.9115.00
101.83101.83101.84101.85101.8615.25
101.78101.79101.80101.81101.8215.50
101.73101.74101.75101.76101.7715.75
101.68101.69101.70101.71101.7216.00
101.63101.64101.65101.66101.6716.25
101.58101.59101.60101.61101.6216.50
101.54101.55101.56101.57101.5716.75
101.50101.51101.52101.53101.5317.00
101.46101.47101.48101.49101.4917.25
101.43101.44101.44101.45101.4617.50
101.40101.41101.41101.42101.4217.75
101.37101.38101.38101.39101.3918.00
101.35101.35101.36101.36101.3718.25
101.32101.33101.33101.34101.3418.50
101.31101.31101.31101.32101.3218.75
101.29101.29101.30101.30101.3019.00
101.28101.28101.28101.29101.2919.25
101.27101.27101.27101.27101.2819.50
101.26101.26101.26101.26101.2619.75
101.25101.25101.25101.25101.2520.00
101.24101.24101.24101.24101.2420.25
101.23101.23101.23101.23101.2320.50
101.22101.22101.22101.23101.2320.75
101.21101.22101.22101.22101.2221.00
101.21101.21101.21101.21101.2121.25
Page 2 of 827 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/5/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: Proposed Pond (OUT)
Return Event: 100 yearsSubsection: Time vs. Elevation
Time vs. Elevation (ft)
Output Time increment = 0.05 hoursTime on left represents time for first value in each row.
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Time(hours)
101.20101.20101.20101.21101.2121.50
101.20101.20101.20101.20101.2021.75
101.19101.19101.19101.19101.1922.00
101.18101.19101.19101.19101.1922.25
101.18101.18101.18101.18101.1822.50
101.17101.18101.18101.18101.1822.75
101.17101.17101.17101.17101.1723.00
101.16101.17101.17101.17101.1723.25
101.16101.16101.16101.16101.1623.50
101.15101.16101.16101.16101.1623.75
101.14101.14101.15101.15101.1524.00
101.11101.11101.12101.12101.1324.25
101.08101.08101.09101.09101.1024.50
101.06101.06101.07101.07101.0724.75
101.04101.04101.05101.05101.0525.00
101.03101.03101.03101.04101.0425.25
101.02101.02101.02101.02101.0325.50
101.01101.01101.01101.01101.0225.75
101.00101.01101.01101.01101.0126.00
101.00101.00101.00101.00101.0026.25
100.99101.00101.00101.00101.0026.50
100.99100.99100.99100.99100.9926.75
100.99100.99100.99100.99100.9927.00
100.98100.98100.98100.98100.9927.25
100.98100.98100.98100.98100.9827.50
100.98100.98100.98100.98100.9827.75
100.97100.97100.97100.97100.9728.00
100.97100.97100.97100.97100.9728.25
100.97100.97100.97100.97100.9728.50
100.96100.96100.96100.96100.9728.75
100.96100.96100.96100.96100.9629.00
100.96100.96100.96100.96100.9629.25
100.95100.96100.96100.96100.9629.50
100.95100.95100.95100.95100.9529.75
100.95100.95100.95100.95100.9530.00
100.95100.95100.95100.95100.9530.25
100.95100.95100.95100.95100.9530.50
100.94100.94100.94100.94100.9530.75
100.94100.94100.94100.94100.9431.00
100.94100.94100.94100.94100.9431.25
100.94100.94100.94100.94100.9431.50
100.94100.94100.94100.94100.9431.75
100.93100.93100.94100.94100.9432.00
Page 3 of 827 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/5/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: Proposed Pond (OUT)
Return Event: 100 yearsSubsection: Time vs. Elevation
Time vs. Elevation (ft)
Output Time increment = 0.05 hoursTime on left represents time for first value in each row.
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Elevation(ft)
Time(hours)
100.93100.93100.93100.93100.9332.25
100.93100.93100.93100.93100.9332.50
100.93100.93100.93100.93100.9332.75
100.93100.93100.93100.93100.9333.00
100.93100.93100.93100.93100.9333.25
100.93100.93100.93100.93100.9333.50
100.93100.93100.93100.93100.9333.75
100.92100.92100.92100.92100.9234.00
100.92100.92100.92100.92100.9234.25
100.92100.92100.92100.92100.9234.50
100.92100.92100.92100.92100.9234.75
100.92100.92100.92100.92100.9235.00
100.92100.92100.92100.92100.9235.25
100.92100.92100.92100.92100.9235.50
100.92100.92100.92100.92100.9235.75
100.92100.92100.92100.92100.9236.00
100.92100.92100.92100.92100.9236.25
100.92100.92100.92100.92100.9236.50
100.91100.91100.91100.91100.9236.75
100.91100.91100.91100.91100.9137.00
100.91100.91100.91100.91100.9137.25
100.91100.91100.91100.91100.9137.50
100.91100.91100.91100.91100.9137.75
100.91100.91100.91100.91100.9138.00
100.91100.91100.91100.91100.9138.25
100.91100.91100.91100.91100.9138.50
100.91100.91100.91100.91100.9138.75
100.91100.91100.91100.91100.9139.00
100.91100.91100.91100.91100.9139.25
100.91100.91100.91100.91100.9139.50
100.91100.91100.91100.91100.9139.75
100.91100.91100.91100.91100.9140.00
100.91100.91100.91100.91100.9140.25
100.91100.91100.91100.91100.9140.50
100.91100.91100.91100.91100.9140.75
100.91100.91100.91100.91100.9141.00
100.91100.91100.91100.91100.9141.25
100.91100.91100.91100.91100.9141.50
100.91100.91100.91100.91100.9141.75
100.91100.91100.91100.91100.9142.00
100.91100.91100.91100.91100.9142.25
100.91100.91100.91100.91100.9142.50
100.90100.90100.90100.90100.9042.75
Page 4 of 827 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/5/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Appendix C
Pre-Development Hydrographs
Tabl
e of
Con
tent
s
17Un
it Hy
drog
raph
Sum
mar
y, 1
00 y
ears
15Un
it Hy
drog
raph
Sum
mar
y, 1
0 ye
ars
13Un
it Hy
drog
raph
Sum
mar
y, 2
yea
rs
EX. D
A 1A
PER
VIOU
S
11Un
it Hy
drog
raph
Sum
mar
y, 1
00 y
ears
9Un
it Hy
drog
raph
Sum
mar
y, 1
0 ye
ars
7Un
it Hy
drog
raph
Sum
mar
y, 2
yea
rs
EX. D
A 1
PERV
IOUS
5Un
it Hy
drog
raph
Sum
mar
y, 1
00 y
ears
3Un
it Hy
drog
raph
Sum
mar
y, 1
0 ye
ars
1Un
it Hy
drog
raph
Sum
mar
y, 2
yea
rs
EX. D
A 1
IMPE
RVIO
USSt
orm
Eve
nt:
Synt
hetic
curv
e 2Y
RLa
bel:
EX.
DA
1 IM
PERV
IOUS
Retu
rn E
vent
: 2
year
sSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
Synt
hetic
cur
ve2Y
RSt
orm
Eve
nt
year
s2
Retu
rn E
vent
hour
s72
.00
Dura
tion
in3.
3De
pth
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
3Ti
me
to P
eak
(Com
pute
d)ft³
/s5.
33Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.15
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
5.24
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
98.0
0SC
S CN
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
in0.
2M
axim
um R
eten
tion
(Per
vious
)
in0.
0M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in3.
1Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³23
,046
.704
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³23
,047
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s14
.07
Unit
peak
, qp
Page
1 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
2YR
Labe
l: E
X. D
A 1
IMPE
RVIO
USRe
turn
Eve
nt:
2 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
11Un
it pe
ak ti
me,
Tp
hour
s0.
44Un
it re
cedi
ng li
mb,
Tr
hour
s0.
56To
tal u
nit t
ime,
Tb
Page
2 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1
IMPE
RVIO
USRe
turn
Eve
nt:
10 y
ears
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
Synt
hetic
cur
ve10
YRSt
orm
Eve
nt
year
s10
Retu
rn E
vent
hour
s72
.00
Dura
tion
in5.
0De
pth
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
3Ti
me
to P
eak
(Com
pute
d)ft³
/s8.
13Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.10
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
7.99
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
98.0
0SC
S CN
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
in0.
2M
axim
um R
eten
tion
(Per
vious
)
in0.
0M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in4.
8Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³35
,790
.921
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³35
,791
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s14
.07
Unit
peak
, qp
Page
3 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1
IMPE
RVIO
USRe
turn
Eve
nt:
10 y
ears
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
11Un
it pe
ak ti
me,
Tp
hour
s0.
44Un
it re
cedi
ng li
mb,
Tr
hour
s0.
56To
tal u
nit t
ime,
Tb
Page
4 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1 IM
PERV
IOUS
Retu
rn E
vent
: 10
0 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
Synt
hetic
cur
ve10
0YR
Stor
m E
vent
year
s10
0Re
turn
Eve
ntho
urs
72.0
0Du
ratio
nin
8.2
Dept
h
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
3Ti
me
to P
eak
(Com
pute
d)ft³
/s13
.38
Flow
(Pea
k, C
ompu
ted)
hour
s0.
05Ou
tput
Incr
emen
t
hour
s12
.10
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
13.1
6Fl
ow (P
eak
Inte
rpol
ated
Outp
ut)
Dra
inag
e Ar
ea
98.0
0SC
S CN
(Com
posit
e)ft²
90,1
69.2
0Ar
ea (U
ser D
efin
ed)
in0.
2M
axim
um R
eten
tion
(Per
vious
)
in0.
0M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in8.
0Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³59
,812
.853
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³59
,813
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
02Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s14
.07
Unit
peak
, qp
Page
5 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1 IM
PERV
IOUS
Retu
rn E
vent
: 10
0 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
11Un
it pe
ak ti
me,
Tp
hour
s0.
44Un
it re
cedi
ng li
mb,
Tr
hour
s0.
56To
tal u
nit t
ime,
Tb
Page
6 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
2YR
Labe
l: E
X. D
A 1
PERV
IOUS
Retu
rn E
vent
: 2
year
sSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
Synt
hetic
cur
ve2Y
RSt
orm
Eve
nt
year
s2
Retu
rn E
vent
hour
s72
.00
Dura
tion
in3.
3De
pth
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.2
2Ti
me
to P
eak
(Com
pute
d)ft³
/s2.
32Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
2.32
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
71.8
0SC
S CN
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
in3.
9M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in1.
0Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³10
,688
.112
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³10
,688
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s13
.46
Unit
peak
, qp
Page
7 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
2YR
Labe
l: E
X. D
A 1
PERV
IOUS
Retu
rn E
vent
: 2
year
sSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
8 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1
PERV
IOUS
Retu
rn E
vent
: 10
yea
rsSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
Synt
hetic
cur
ve10
YRSt
orm
Eve
nt
year
s10
Retu
rn E
vent
hour
s72
.00
Dura
tion
in5.
0De
pth
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
9Ti
me
to P
eak
(Com
pute
d)ft³
/s5.
50Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
5.47
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
71.8
0SC
S CN
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
in3.
9M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in2.
2Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³23
,756
.500
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³23
,756
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s13
.46
Unit
peak
, qp
Page
9 o
f 19
27 S
iem
on C
ompa
ny D
rive
Suite
200
WW
ater
tow
n, C
T 06
795
USA
+1-
203-
755-
1666
6/2/
2020
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1
PERV
IOUS
Retu
rn E
vent
: 10
yea
rsSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
10
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1 PE
RVIO
USRe
turn
Eve
nt:
100
year
sSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
Synt
hetic
cur
ve10
0YR
Stor
m E
vent
year
s10
0Re
turn
Eve
ntho
urs
72.0
0Du
ratio
nin
8.2
Dept
h
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
9Ti
me
to P
eak
(Com
pute
d)ft³
/s12
.35
Flow
(Pea
k, C
ompu
ted)
hour
s0.
05Ou
tput
Incr
emen
t
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
12.2
3Fl
ow (P
eak
Inte
rpol
ated
Outp
ut)
Dra
inag
e Ar
ea
71.8
0SC
S CN
(Com
posit
e)ft²
130,
680.
00Ar
ea (U
ser D
efin
ed)
in3.
9M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in4.
8Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³52
,783
.457
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³52
,784
.000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s13
.46
Unit
peak
, qp
Page
11
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1 PE
RVIO
USRe
turn
Eve
nt:
100
year
sSu
bsec
tion:
Uni
t Hyd
rogr
aph
Sum
mar
y
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
12
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
2YR
Labe
l: E
X. D
A 1A
PER
VIOU
SRe
turn
Eve
nt:
2 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
Synt
hetic
cur
ve2Y
RSt
orm
Eve
nt
year
s2
Retu
rn E
vent
hour
s72
.00
Dura
tion
in3.
3De
pth
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.2
2Ti
me
to P
eak
(Com
pute
d)ft³
/s0.
36Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
0.36
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
71.5
0SC
S CN
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
in4.
0M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in1.
0Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³1,
646.
989
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³1,
647.
000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s2.
11Un
it pe
ak, q
p
Page
13
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
2YR
Labe
l: E
X. D
A 1A
PER
VIOU
SRe
turn
Eve
nt:
2 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
14
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1A
PER
VIOU
SRe
turn
Eve
nt:
10 y
ears
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
Synt
hetic
cur
ve10
YRSt
orm
Eve
nt
year
s10
Retu
rn E
vent
hour
s72
.00
Dura
tion
in5.
0De
pth
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
9Ti
me
to P
eak
(Com
pute
d)ft³
/s0.
85Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
0.85
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
71.5
0SC
S CN
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
in4.
0M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in2.
2Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³3,
680.
107
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³3,
680.
000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s2.
11Un
it pe
ak, q
p
Page
15
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
10YR
Labe
l: E
X. D
A 1A
PER
VIOU
SRe
turn
Eve
nt:
10 y
ears
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
16
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1A P
ERVI
OUS
Retu
rn E
vent
: 10
0 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
Synt
hetic
cur
ve10
0YR
Stor
m E
vent
year
s10
0Re
turn
Eve
ntho
urs
72.0
0Du
ratio
nin
8.2
Dept
h
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
tho
urs
12.1
9Ti
me
to P
eak
(Com
pute
d)ft³
/s1.
92Fl
ow (P
eak,
Com
pute
d)ho
urs
0.05
Outp
ut In
crem
ent
hour
s12
.20
Tim
e to
Flo
w (P
eak
Inte
rpol
ated
Out
put)
ft³/s
1.90
Flow
(Pea
k In
terp
olat
edOu
tput
)
Dra
inag
e Ar
ea
71.5
0SC
S CN
(Com
posit
e)ft²
20,4
73.2
0Ar
ea (U
ser D
efin
ed)
in4.
0M
axim
um R
eten
tion
(Per
vious
)
in0.
8M
axim
um R
eten
tion
(Per
viou
s, 2
0 pe
rcen
t)
Cum
ulat
ive R
unof
f
in4.
8Cu
mul
ativ
e Ru
noff
Dept
h(P
ervio
us)
ft³8,
209.
521
Runo
ff Vo
lum
e (P
ervi
ous)
Hyd
rogr
aph
Volu
me
(Are
a un
der H
ydro
grap
h cu
rve)
ft³8,
210.
000
Volu
me
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
25Ti
me
of C
once
ntra
tion
(Com
posit
e)
hour
s0.
03Co
mpu
tatio
nal T
ime
Incr
emen
t
483.
43Un
it Hy
drog
raph
Sha
peFa
ctor
0.75
K Fa
ctor
1.67
0Re
cedi
ng/R
ising
, Tr/
Tpft³
/s2.
11Un
it pe
ak, q
p
Page
17
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Stor
m E
vent
: Sy
nthe
tic cu
rve
100Y
RLa
bel:
EX.
DA
1A P
ERVI
OUS
Retu
rn E
vent
: 10
0 ye
ars
Subs
ectio
n: U
nit H
ydro
grap
h Su
mm
ary
SCS
Uni
t Hyd
rogr
aph
Para
met
ers
hour
s0.
17Un
it pe
ak ti
me,
Tp
hour
s0.
67Un
it re
cedi
ng li
mb,
Tr
hour
s0.
84To
tal u
nit t
ime,
Tb
Page
18
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Inde
x
EX. D
A 1A
PER
VIOU
S (U
nit H
ydro
grap
h Su
mm
ary,
2 y
ears
)...1
3, 1
4
EX. D
A 1A
PER
VIOU
S (U
nit H
ydro
grap
h Su
mm
ary,
100
yea
rs)..
.17,
18
EX. D
A 1A
PER
VIOU
S (U
nit H
ydro
grap
h Su
mm
ary,
10
year
s)...
15, 1
6
EX. D
A 1
PERV
IOUS
(Uni
t Hyd
rogr
aph
Sum
mar
y, 2
yea
rs)..
.7, 8
EX. D
A 1
PERV
IOUS
(Uni
t Hyd
rogr
aph
Sum
mar
y, 1
00 y
ears
)...1
1, 1
2
EX. D
A 1
PERV
IOUS
(Uni
t Hyd
rogr
aph
Sum
mar
y, 1
0 ye
ars)
...9,
10
EX. D
A 1
IMPE
RVIO
US (U
nit H
ydro
grap
h Su
mm
ary,
2 y
ears
)...1
, 2
EX. D
A 1
IMPE
RVIO
US (U
nit H
ydro
grap
h Su
mm
ary,
100
yea
rs)..
.5, 6
EX. D
A 1
IMPE
RVIO
US (U
nit H
ydro
grap
h Su
mm
ary,
10
year
s)...
3, 4
E
Page
19
of 1
927
Sie
mon
Com
pany
Driv
e Su
ite 2
00 W
Wat
erto
wn,
CT
0679
5 U
SA +
1-20
3-75
5-16
666/
2/20
20
Bent
ley
Pond
Pack
V8i
[08.
11.0
1.56
]Be
ntle
y Sy
stem
s, In
c. H
aest
ad M
etho
ds S
olut
ion
Cen
ter
2005
27 B
asin
Des
ign.
ppc
Appendix D
Post-Development Hydrographs
Table of Contents
39Unit Hydrograph Summary, 100 years
37Unit Hydrograph Summary, 25 years
35Unit Hydrograph Summary, 10 years
33Unit Hydrograph Summary, 2 years
31Unit Hydrograph Summary, 1 years
BYPASS DA 1 PERVIOUS
29Unit Hydrograph Summary, 100 years
27Unit Hydrograph Summary, 25 years
25Unit Hydrograph Summary, 10 years
23Unit Hydrograph Summary, 2 years
21Unit Hydrograph Summary, 1 years
BYPASS DA 1 IMPERVIOUS
19Unit Hydrograph Summary, 100 years
17Unit Hydrograph Summary, 25 years
15Unit Hydrograph Summary, 10 years
13Unit Hydrograph Summary, 2 years
11Unit Hydrograph Summary, 1 years
BASIN DA 1 PERVIOUS
9Unit Hydrograph Summary, 100 years
7Unit Hydrograph Summary, 25 years
5Unit Hydrograph Summary, 10 years
3Unit Hydrograph Summary, 2 years
1Unit Hydrograph Summary, 1 years
BASIN DA 1 IMPERVIOUS
Storm Event: Synthetic curve 1YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
Synthetic curve1YR
Storm Event
years1Return Event
hours72.00Duration
in1.3Depth
hours0.17Time of Concentration(Composite)
ft²101,930.40Area (User Defined)
hours0.02Computational TimeIncrement
hours1.13Time to Peak (Computed)
ft³/s6.07Flow (Peak, Computed)
hours0.05Output Increment
hours1.10Time to Flow (PeakInterpolated Output)
ft³/s5.91Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²101,930.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in1.0Cumulative Runoff Depth(Pervious)
ft³8,787.864Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³8,785.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s15.91Unit peak, qp
Page 1 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 2 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
Synthetic curve2YR
Storm Event
years2Return Event
hours72.00Duration
in3.3Depth
hours0.17Time of Concentration(Composite)
ft²101,930.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s6.02Flow (Peak, Computed)
hours0.05Output Increment
hours12.15Time to Flow (PeakInterpolated Output)
ft³/s5.92Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²101,930.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in3.1Cumulative Runoff Depth(Pervious)
ft³26,052.796Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³26,053.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s15.91Unit peak, qp
Page 3 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 4 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
Synthetic curve10YR
Storm Event
years10Return Event
hours72.00Duration
in5.0Depth
hours0.17Time of Concentration(Composite)
ft²101,930.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s9.19Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s9.03Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²101,930.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in4.8Cumulative Runoff Depth(Pervious)
ft³40,459.302Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³40,459.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s15.91Unit peak, qp
Page 5 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 6 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
Synthetic curve25YR
Storm Event
years25Return Event
hours24.00Duration
in6.2Depth
hours0.17Time of Concentration(Composite)
ft²101,930.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s11.41Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s11.22Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²101,930.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in6.0Cumulative Runoff Depth(Pervious)
ft³50,639.425Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³50,579.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s15.91Unit peak, qp
Page 7 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 8 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
Synthetic curve100YR
Storm Event
years100Return Event
hours72.00Duration
in8.2Depth
hours0.17Time of Concentration(Composite)
ft²101,930.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s15.12Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s14.87Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²101,930.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in8.0Cumulative Runoff Depth(Pervious)
ft³67,614.529Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³67,614.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s15.91Unit peak, qp
Page 9 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BASIN DA 1 IMPERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 10 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BASIN DA 1 PERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
Synthetic curve1YR
Storm Event
years1Return Event
hours72.00Duration
in1.3Depth
hours0.13Time of Concentration(Composite)
ft²34,412.40Area (User Defined)
hours0.02Computational TimeIncrement
hours1.20Time to Peak (Computed)
ft³/s0.11Flow (Peak, Computed)
hours0.05Output Increment
hours1.20Time to Flow (PeakInterpolated Output)
ft³/s0.11Flow (Peak InterpolatedOutput)
Drainage Area
73.90SCS CN (Composite)
ft²34,412.40Area (User Defined)
in3.5Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in0.1Cumulative Runoff Depth(Pervious)
ft³207.961Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³208.000Volume
SCS Unit Hydrograph Parameters
hours0.13Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s7.13Unit peak, qp
Page 11 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BASIN DA 1 PERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.08Unit peak time, Tp
hours0.33Unit receding limb, Tr
hours0.42Total unit time, Tb
Page 12 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BASIN DA 1 PERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
Synthetic curve2YR
Storm Event
years2Return Event
hours72.00Duration
in3.3Depth
hours0.13Time of Concentration(Composite)
ft²34,412.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s0.85Flow (Peak, Computed)
hours0.05Output Increment
hours12.15Time to Flow (PeakInterpolated Output)
ft³/s0.82Flow (Peak InterpolatedOutput)
Drainage Area
73.90SCS CN (Composite)
ft²34,412.40Area (User Defined)
in3.5Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in1.1Cumulative Runoff Depth(Pervious)
ft³3,149.313Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³3,150.000Volume
SCS Unit Hydrograph Parameters
hours0.13Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s7.13Unit peak, qp
Page 13 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BASIN DA 1 PERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.08Unit peak time, Tp
hours0.33Unit receding limb, Tr
hours0.42Total unit time, Tb
Page 14 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BASIN DA 1 PERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
Synthetic curve10YR
Storm Event
years10Return Event
hours72.00Duration
in5.0Depth
hours0.13Time of Concentration(Composite)
ft²34,412.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s1.86Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s1.82Flow (Peak InterpolatedOutput)
Drainage Area
73.90SCS CN (Composite)
ft²34,412.40Area (User Defined)
in3.5Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in2.4Cumulative Runoff Depth(Pervious)
ft³6,755.790Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³6,756.000Volume
SCS Unit Hydrograph Parameters
hours0.13Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s7.13Unit peak, qp
Page 15 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BASIN DA 1 PERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.08Unit peak time, Tp
hours0.33Unit receding limb, Tr
hours0.42Total unit time, Tb
Page 16 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BASIN DA 1 PERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
Synthetic curve25YR
Storm Event
years25Return Event
hours24.00Duration
in6.2Depth
hours0.13Time of Concentration(Composite)
ft²34,412.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.11Time to Peak (Computed)
ft³/s2.64Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s2.60Flow (Peak InterpolatedOutput)
Drainage Area
73.90SCS CN (Composite)
ft²34,412.40Area (User Defined)
in3.5Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in3.3Cumulative Runoff Depth(Pervious)
ft³9,589.274Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³9,577.000Volume
SCS Unit Hydrograph Parameters
hours0.13Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s7.13Unit peak, qp
Page 17 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BASIN DA 1 PERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.08Unit peak time, Tp
hours0.33Unit receding limb, Tr
hours0.42Total unit time, Tb
Page 18 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BASIN DA 1 PERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
Synthetic curve100YR
Storm Event
years100Return Event
hours72.00Duration
in8.2Depth
hours0.13Time of Concentration(Composite)
ft²34,412.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.11Time to Peak (Computed)
ft³/s3.99Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s3.94Flow (Peak InterpolatedOutput)
Drainage Area
73.90SCS CN (Composite)
ft²34,412.40Area (User Defined)
in3.5Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in5.1Cumulative Runoff Depth(Pervious)
ft³14,605.735Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³14,606.000Volume
SCS Unit Hydrograph Parameters
hours0.13Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s7.13Unit peak, qp
Page 19 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BASIN DA 1 PERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.08Unit peak time, Tp
hours0.33Unit receding limb, Tr
hours0.42Total unit time, Tb
Page 20 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
Synthetic curve1YR
Storm Event
years1Return Event
hours72.00Duration
in1.3Depth
hours0.17Time of Concentration(Composite)
ft²32,234.40Area (User Defined)
hours0.02Computational TimeIncrement
hours1.13Time to Peak (Computed)
ft³/s1.92Flow (Peak, Computed)
hours0.05Output Increment
hours1.10Time to Flow (PeakInterpolated Output)
ft³/s1.87Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²32,234.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in1.0Cumulative Runoff Depth(Pervious)
ft³2,779.068Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³2,778.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s5.03Unit peak, qp
Page 21 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 22 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
Synthetic curve2YR
Storm Event
years2Return Event
hours72.00Duration
in3.3Depth
hours0.17Time of Concentration(Composite)
ft²32,234.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s1.90Flow (Peak, Computed)
hours0.05Output Increment
hours12.15Time to Flow (PeakInterpolated Output)
ft³/s1.87Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²32,234.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in3.1Cumulative Runoff Depth(Pervious)
ft³8,238.918Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³8,239.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s5.03Unit peak, qp
Page 23 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 24 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
Synthetic curve10YR
Storm Event
years10Return Event
hours72.00Duration
in5.0Depth
hours0.17Time of Concentration(Composite)
ft²32,234.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s2.91Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s2.86Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²32,234.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in4.8Cumulative Runoff Depth(Pervious)
ft³12,794.822Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³12,795.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s5.03Unit peak, qp
Page 25 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 26 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
Synthetic curve25YR
Storm Event
years25Return Event
hours24.00Duration
in6.2Depth
hours0.17Time of Concentration(Composite)
ft²32,234.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s3.61Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s3.55Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²32,234.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in6.0Cumulative Runoff Depth(Pervious)
ft³16,014.177Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³15,995.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s5.03Unit peak, qp
Page 27 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 28 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
Synthetic curve100YR
Storm Event
years100Return Event
hours72.00Duration
in8.2Depth
hours0.17Time of Concentration(Composite)
ft²32,234.40Area (User Defined)
hours0.02Computational TimeIncrement
hours12.13Time to Peak (Computed)
ft³/s4.78Flow (Peak, Computed)
hours0.05Output Increment
hours12.10Time to Flow (PeakInterpolated Output)
ft³/s4.70Flow (Peak InterpolatedOutput)
Drainage Area
98.00SCS CN (Composite)
ft²32,234.40Area (User Defined)
in0.2Maximum Retention(Pervious)
in0.0Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in8.0Cumulative Runoff Depth(Pervious)
ft³21,382.372Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³21,382.000Volume
SCS Unit Hydrograph Parameters
hours0.17Time of Concentration(Composite)
hours0.02Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s5.03Unit peak, qp
Page 29 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BYPASS DA 1 IMPERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.11Unit peak time, Tp
hours0.44Unit receding limb, Tr
hours0.56Total unit time, Tb
Page 30 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
Synthetic curve1YR
Storm Event
years1Return Event
hours72.00Duration
in1.3Depth
hours0.31Time of Concentration(Composite)
ft²72,745.20Area (User Defined)
hours0.04Computational TimeIncrement
hours1.38Time to Peak (Computed)
ft³/s0.14Flow (Peak, Computed)
hours0.05Output Increment
hours1.40Time to Flow (PeakInterpolated Output)
ft³/s0.14Flow (Peak InterpolatedOutput)
Drainage Area
73.20SCS CN (Composite)
ft²72,745.20Area (User Defined)
in3.7Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in0.1Cumulative Runoff Depth(Pervious)
ft³388.876Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³389.000Volume
SCS Unit Hydrograph Parameters
hours0.31Time of Concentration(Composite)
hours0.04Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s6.04Unit peak, qp
Page 31 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 1YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 1 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.21Unit peak time, Tp
hours0.84Unit receding limb, Tr
hours1.05Total unit time, Tb
Page 32 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
Synthetic curve2YR
Storm Event
years2Return Event
hours72.00Duration
in3.3Depth
hours0.31Time of Concentration(Composite)
ft²72,745.20Area (User Defined)
hours0.04Computational TimeIncrement
hours12.25Time to Peak (Computed)
ft³/s1.32Flow (Peak, Computed)
hours0.05Output Increment
hours12.25Time to Flow (PeakInterpolated Output)
ft³/s1.32Flow (Peak InterpolatedOutput)
Drainage Area
73.20SCS CN (Composite)
ft²72,745.20Area (User Defined)
in3.7Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in1.1Cumulative Runoff Depth(Pervious)
ft³6,416.765Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³6,417.000Volume
SCS Unit Hydrograph Parameters
hours0.31Time of Concentration(Composite)
hours0.04Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s6.04Unit peak, qp
Page 33 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 2YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 2 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.21Unit peak time, Tp
hours0.84Unit receding limb, Tr
hours1.05Total unit time, Tb
Page 34 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
Synthetic curve10YR
Storm Event
years10Return Event
hours72.00Duration
in5.0Depth
hours0.31Time of Concentration(Composite)
ft²72,745.20Area (User Defined)
hours0.04Computational TimeIncrement
hours12.25Time to Peak (Computed)
ft³/s3.00Flow (Peak, Computed)
hours0.05Output Increment
hours12.25Time to Flow (PeakInterpolated Output)
ft³/s2.99Flow (Peak InterpolatedOutput)
Drainage Area
73.20SCS CN (Composite)
ft²72,745.20Area (User Defined)
in3.7Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in2.3Cumulative Runoff Depth(Pervious)
ft³13,925.367Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³13,926.000Volume
SCS Unit Hydrograph Parameters
hours0.31Time of Concentration(Composite)
hours0.04Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s6.04Unit peak, qp
Page 35 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 10YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 10 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.21Unit peak time, Tp
hours0.84Unit receding limb, Tr
hours1.05Total unit time, Tb
Page 36 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
Synthetic curve25YR
Storm Event
years25Return Event
hours24.00Duration
in6.2Depth
hours0.31Time of Concentration(Composite)
ft²72,745.20Area (User Defined)
hours0.04Computational TimeIncrement
hours12.25Time to Peak (Computed)
ft³/s4.29Flow (Peak, Computed)
hours0.05Output Increment
hours12.25Time to Flow (PeakInterpolated Output)
ft³/s4.28Flow (Peak InterpolatedOutput)
Drainage Area
73.20SCS CN (Composite)
ft²72,745.20Area (User Defined)
in3.7Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in3.3Cumulative Runoff Depth(Pervious)
ft³19,852.743Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³19,785.000Volume
SCS Unit Hydrograph Parameters
hours0.31Time of Concentration(Composite)
hours0.04Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s6.04Unit peak, qp
Page 37 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 25YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 25 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.21Unit peak time, Tp
hours0.84Unit receding limb, Tr
hours1.05Total unit time, Tb
Page 38 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
Synthetic curve100YR
Storm Event
years100Return Event
hours72.00Duration
in8.2Depth
hours0.31Time of Concentration(Composite)
ft²72,745.20Area (User Defined)
hours0.04Computational TimeIncrement
hours12.21Time to Peak (Computed)
ft³/s6.58Flow (Peak, Computed)
hours0.05Output Increment
hours12.20Time to Flow (PeakInterpolated Output)
ft³/s6.54Flow (Peak InterpolatedOutput)
Drainage Area
73.20SCS CN (Composite)
ft²72,745.20Area (User Defined)
in3.7Maximum Retention(Pervious)
in0.7Maximum Retention(Pervious, 20 percent)
Cumulative Runoff
in5.0Cumulative Runoff Depth(Pervious)
ft³30,377.295Runoff Volume (Pervious)
Hydrograph Volume (Area under Hydrograph curve)
ft³30,377.000Volume
SCS Unit Hydrograph Parameters
hours0.31Time of Concentration(Composite)
hours0.04Computational TimeIncrement
483.43Unit Hydrograph ShapeFactor
0.75K Factor
1.670Receding/Rising, Tr/Tp
ft³/s6.04Unit peak, qp
Page 39 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Storm Event: Synthetic curve 100YRLabel: BYPASS DA 1 PERVIOUS
Return Event: 100 yearsSubsection: Unit Hydrograph Summary
SCS Unit Hydrograph Parameters
hours0.21Unit peak time, Tp
hours0.84Unit receding limb, Tr
hours1.05Total unit time, Tb
Page 40 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Index
BYPASS DA 1 PERVIOUS (Unit Hydrograph Summary, 25 years)...37, 38
BYPASS DA 1 PERVIOUS (Unit Hydrograph Summary, 2 years)...33, 34
BYPASS DA 1 PERVIOUS (Unit Hydrograph Summary, 100 years)...39, 40
BYPASS DA 1 PERVIOUS (Unit Hydrograph Summary, 10 years)...35, 36
BYPASS DA 1 PERVIOUS (Unit Hydrograph Summary, 1 years)...31, 32
BYPASS DA 1 IMPERVIOUS (Unit Hydrograph Summary, 25 years)...27, 28
BYPASS DA 1 IMPERVIOUS (Unit Hydrograph Summary, 2 years)...23, 24
BYPASS DA 1 IMPERVIOUS (Unit Hydrograph Summary, 100 years)...29, 30
BYPASS DA 1 IMPERVIOUS (Unit Hydrograph Summary, 10 years)...25, 26
BYPASS DA 1 IMPERVIOUS (Unit Hydrograph Summary, 1 years)...21, 22
BASIN DA 1 PERVIOUS (Unit Hydrograph Summary, 25 years)...17, 18
BASIN DA 1 PERVIOUS (Unit Hydrograph Summary, 2 years)...13, 14
BASIN DA 1 PERVIOUS (Unit Hydrograph Summary, 100 years)...19, 20
BASIN DA 1 PERVIOUS (Unit Hydrograph Summary, 10 years)...15, 16
BASIN DA 1 PERVIOUS (Unit Hydrograph Summary, 1 years)...11, 12
BASIN DA 1 IMPERVIOUS (Unit Hydrograph Summary, 25 years)...7, 8
BASIN DA 1 IMPERVIOUS (Unit Hydrograph Summary, 2 years)...3, 4
BASIN DA 1 IMPERVIOUS (Unit Hydrograph Summary, 100 years)...9, 10
BASIN DA 1 IMPERVIOUS (Unit Hydrograph Summary, 10 years)...5, 6
BASIN DA 1 IMPERVIOUS (Unit Hydrograph Summary, 1 years)...1, 2
B
Page 41 of 4127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/4/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
Appendix E
Water Quality Calculations
Water Quality Calculation Sheet
Basin Drain Time
Slowest Permeability Rate Recorded (SL 1 and 2 Basin Flood) – 1.00 in/hrDesign Permeability Rate – 0.50 in/hrDepth to infiltrate – 1.90 ft = 22.8 inches
22.8 in / 0.50 in per hr = 45.6 hr
Seasonal High Water ClearanceSL #2 – Elevation 104.5Soil Lot Bottom (No Mottles or Water) – Elevation 94.50Basin Bottom Elevation – 99.00Bottom of 6” Sand Layer – 98.50Separation Groundwater and bottom of bmp = 6.00 ft
Subsection: Master Network Summary
Catchments SummaryPeak Flow
(ft³/s)Time to Peak
(hours)Hydrograph
Volume(ft³)
ReturnEvent
(years)
ScenarioLabel
5.911.108,785.0001wqBASIN DA 1IMPERVIOUS
0.111.20208.0001wqBASIN DA 1 PERVIOUS1.871.102,778.0001wqBYPASS DA 1
IMPERVIOUS0.141.40389.0001wqBYPASS DA 1
PERVIOUS5.231.107,771.0001wqEX. DA 1 IMPERVIOUS0.201.35535.0001wqEX. DA 1 PERVIOUS0.031.3579.0001wqEX. DA 1A PERVIOUS
Node SummaryPeak Flow
(ft³/s)Time to Peak
(hours)Hydrograph
Volume(ft³)
ReturnEvent
(years)
ScenarioLabel
0.031.3579.0001wqEX. POA5.241.108,306.0001wqEX. POA (TO BE
REDUCED)1.881.153,167.0001wqPR. POA
Pond SummaryMaximum
Pond Storage(ft³)
MaximumWater
SurfaceElevation
(ft)
Peak Flow(ft³/s)
Time to Peak(hours)
HydrographVolume
(ft³)
ReturnEvent
(years)
ScenarioLabel
(N/A)(N/A)5.951.158,993.0001wqProposedPond (IN)
8,992.000100.890.000.000.0001wqProposedPond (OUT)
Page 1 of 127 Siemon Company Drive Suite 200 WWatertown, CT 06795 USA +1-203-755-1666
6/2/2020
Bentley PondPack V8i[08.11.01.56]
Bentley Systems, Inc. Haestad Methods SolutionCenter200527 Basin Design.ppc
F:\Jobfile\0303M\2019 Project\ENG\COR\Applications\P&F Major Site Plan & Bulk Variance\Soil\2b-Soil Log 1-MKF-kp-4-14-2020.doc
FORM 2-B SOIL LOGS AND INTERPRETATIONSomerset County/Montgomery Township
Applicant's Name CC1377, LLC Block 29002 Lot 45Describe in accordance with 7:9A-5.3 (inches top-bottom) all profile pits
Log ID = SL#1 Date: 4/6/20Depth(inches)Top-Bottom
Munsell Color Name and Symbol; Estimated Textural Class; Estimated Volume % CoarseFragment, If Present; Structure; Moist or Dry Consistence; Mottling - Abundance, Size andContrast, If Present
0 - 8” 5YR 4/3 Loam; Granular, Friable
8 - 70” 5YR 4/4 Loam; Subangular Blocky, Friable
70 - 102” 5YR 4/4 Shale & Rounded Cobbles; 15% Loam
102 - 120” 5YR 4/4 Fractured Shale; 10% Loam
No Mottles
No Water
No Machine Refusal
Depth in Inches:1st Seepage NoneInfiltration None24 Hour Static NoneSHWT Date:Highest Mottling NoneNon-soil 102”
Soil Limiting Zones: Depths as Indicated (In Inches):Fractured Rock Substratum (top) 102”Massive Rock Substratum (top)Excessively Coarse Horizon (top to bottom)Excessively Coarse Substratum (top)Hydraulically Restrictive Horizon (top to bottom)Hydraulically Restrictive Substratum (top)Perched Zone of Saturation (top to bottom)Regional Zone of Saturation – (top)Soil Suitability Class (from table 10.1) IIScType of Field (from table 10.1) SRE
I hereby certify that the information furnished on Form 2B of this application is true and accurate. I am aware that falsification of data is a violation of theWater Pollution Control Act (N.J.S.A.58:10a-1 et seq.) and is subject to penalties as prescribed in N.J.A.C.7:14-8. I further certify that all borings andexcavations on this lot have been properly backfilled for safety purposes.
Signature of Site Evaluator Kyle J. Paterson Date: 4/6/2020
Signature of Professional Engineer Date: 4/8/2020 Michael K. Ford, NJ PE License No. 34722
F:\Jobfile\0303M\2019 Project\ENG\COR\Applications\P&F Major Site Plan & Bulk Variance\Soil\3g-Basin Soil Log1-MKF-kp-4-14-2020.doc
Form 3g - Basin Flood Data SheetSomerset County/Montgomery Township
Applicant's Name CC1377, LLC Block 29002 Lot 45
Description of Pit in Which Test was Conducted: 1 Date Tested: 4/6/20
SL#1 - 90”
BASIN FLOOD ID #: SL#1 AREA OF PIT: 50 sq. ft.
Description of Rock Substratum within Test Zone:
ROCK TYPE: Fractured ; FORMATION: Brunswick ; AVERAGE FRACTURE SPACING: 1” +/-
Type of Fractures (check appropriate category):
open (wide), clean – width of openings (mm)
open (wide), infilled with fines – width of openings (mm) 1 tight (closed)
Orientation of Fractures:
horizontal (parallel to pit bottom) or nearly so inclined vertical (parallel to sides of pit) or nearly so
Hardness of Rock: rippable with hand tools not rippable with hand tools, rippable by machine
*Time/Date of first basin flooding: 9:40am – 4/6/20 Volume of water added (gallons) 400
RESULT OF FIRST BASIN FLOODING:
basin drained within 24 hours – indicate time/date 10:55am – 4/6/20
basin not drained within 24 hours – indicate time/date
*Time/Date of second basin flooding: 11:01am – 4/6/20 Volume of water added (gallons): 400
RESULT OF SECOND BASIN FLOODING:
basin drained within 24 hours – indicate time/date 1:51pm – 4/6/20
basin not drained within 24 hours – indicate time/date
First filling drained in 95 minutes; Second filling drained in 110 minutes
I hereby certify that the information furnished on this form is true and accurate. I am aware that falsification of data is a violation of theWater Pollution Control Act (N.J.S.A. 58:10A-1 et seq.) and is subject to penalties as prescribed in N.J.A.C. 7:14-8.
Signature of Site Evaluator Kyle J. Paterson Date: 4/6/2020
Signature of Professional Engineer Date: 4/8/2020 Michael K. Ford, NJ PE License No. 34722
F:\Jobfile\0303M\2019 Project\ENG\COR\Applications\P&F Major Site Plan & Bulk Variance\Soil\2b-Soil Log 2-MKF-kp-4-14-2020.doc
FORM 2-B SOIL LOGS AND INTERPRETATIONSomerset County/Montgomery Township
Applicant's Name CC1377, LLC Block 29002 Lot 45Describe in accordance with 7:9A-5.3 (inches top-bottom) all profile pits
Log ID = SL#2 Date: 4/6/20Depth(inches)Top-Bottom
Munsell Color Name and Symbol; Estimated Textural Class; Estimated Volume % CoarseFragment, If Present; Structure; Moist or Dry Consistence; Mottling - Abundance, Size andContrast, If Present
0 - 8” 5YR 4/3 Loam; Granular, Friable
8 - 66” 5YR 4/4 Loam; Subangular Blocky, Friable
66 - 120” 5YR 4/4 Fractured Shale; 15% Loam
No Mottles
No Water
No Machine Refusal
Depth in Inches:1st Seepage NoneInfiltration None24 Hour Static NoneSHWT Date:Highest Mottling NoneNon-soil 66”
Soil Limiting Zones: Depths as Indicated (In Inches):Fractured Rock Substratum (top) 66”Massive Rock Substratum (top)Excessively Coarse Horizon (top to bottom)Excessively Coarse Substratum (top)Hydraulically Restrictive Horizon (top to bottom)Hydraulically Restrictive Substratum (top)Perched Zone of Saturation (top to bottom)Regional Zone of Saturation – (top)Soil Suitability Class (from table 10.1) IISType of Field (from table 10.1) SRE
I hereby certify that the information furnished on Form 2B of this application is true and accurate. I am aware that falsification of data is a violation of theWater Pollution Control Act (N.J.S.A.58:10a-1 et seq.) and is subject to penalties as prescribed in N.J.A.C.7:14-8. I further certify that all borings andexcavations on this lot have been properly backfilled for safety purposes.
Signature of Site Evaluator Kyle J. Paterson Date: 4/6/2020
Signature of Professional Engineer Date: 4/8/2020 Michael K. Ford, NJ PE License No. 34722
F:\Jobfile\0303M\2019 Project\ENG\COR\Applications\P&F Major Site Plan & Bulk Variance\Soil\3g-Basin Soil Log2-MKF-kp-4-14-2020.doc
Form 3g - Basin Flood Data SheetSomerset County/Montgomery Township
Applicant's Name CC1377, LLC Block 29002 Lot 45
Description of Pit in Which Test was Conducted: 2 Date Tested: 4/6/20
SL#2 - 96”
BASIN FLOOD ID #: SL#2 AREA OF PIT: 50 sq. ft.
Description of Rock Substratum within Test Zone:
ROCK TYPE: Fractured ; FORMATION: Brunswick ; AVERAGE FRACTURE SPACING: 1” +/-
Type of Fractures (check appropriate category):
open (wide), clean – width of openings (mm)
open (wide), infilled with fines – width of openings (mm) 1 tight (closed)
Orientation of Fractures:
horizontal (parallel to pit bottom) or nearly so inclined vertical (parallel to sides of pit) or nearly so
Hardness of Rock: rippable with hand tools not rippable with hand tools, rippable by machine
*Time/Date of first basin flooding: 9:05am – 4/6/20 Volume of water added (gallons) 400
RESULT OF FIRST BASIN FLOODING:
basin drained within 24 hours – indicate time/date 9:30am – 4/6/20
basin not drained within 24 hours – indicate time/date
*Time/Date of second basin flooding: 9:50am – 4/6/20 Volume of water added (gallons): 400
RESULT OF SECOND BASIN FLOODING:
basin drained within 24 hours – indicate time/date 10:15am – 4/6/20
basin not drained within 24 hours – indicate time/date
First filling drained in 15 minutes; Second filling drained in 16 minutes
I hereby certify that the information furnished on this form is true and accurate. I am aware that falsification of data is a violation of theWater Pollution Control Act (N.J.S.A. 58:10A-1 et seq.) and is subject to penalties as prescribed in N.J.A.C. 7:14-8.
Signature of Site Evaluator Kyle J. Paterson Date: 4/6/2020
Signature of Professional Engineer Date: 4/8/2020 Michael K. Ford, NJ PE License No. 34722
use consistent units (e.g. feet & days or inches & hours) Conversion TableInput Values inch/hour feet/day
1.0000 R Recharge (infiltration) rate (feet/day) 0.67 1.330.150 Sy Specific yield, Sy (dimensionless, between 0 and 1)
1.00 K Horizontal hydraulic conductivity, Kh (feet/day)* 2.00 4.0054.500 x 1/2 length of basin (x direction, in feet)21.500 y 1/2 width of basin (y direction, in feet) hours days
0.050 t duration of infiltration period (days) 36 1.5010.000 hi(0) initial thickness of saturated zone (feet)
10.333 h(max) maximum thickness of saturated zone (beneath center of basin at end of infiltration period)0.333 Δh(max) maximum groundwater mounding (beneath center of basin at end of infiltration period)
Ground-waterMounding, infeet
Distance fromcenter of basinin x direction, infeet
0.333 00.333 200.333 400.329 500.001 600.000 700.000 800.000 900.000 1000.000 120
Disclaimer
This spreadsheet solving the Hantush (1967) equation for ground-water mounding beneath an infiltrationbasin is made available to the general public as a convenience for those wishing to replicate valuesdocumented in the USGS Scientific Investigations Report 2010-5102 "Groundwater mounding beneathhypothetical stormwater infiltration basins" or to calculate values based on user-specified site conditions. Anychanges made to the spreadsheet (other than values identified as user-specified) after transmission from theUSGS could have unintended, undesirable consequences. These consequences could include, but may not belimited to: erroneous output, numerical instabilities, and violations of underlying assumptions that areinherent in results presented in the accompanying USGS published report. The USGS assumes noresponsibility for the consequences of any changes made to the spreadsheet. If changes are made to thespreadsheet, the user is responsible for documenting the changes and justifying the results and conclusions.
This spreadsheet will calculate the height of a groundwater mound beneath a stormwater infiltration basin. More information can be found in the U.S. Geological SurveyScientific Investigations Report 2010-5102 "Simulation of groundwater mounding beneath hypothetical stormwater infiltration basins".
The user must specify infiltration rate (R), specific yield (Sy), horizontal hydraulic conductivity (Kh), basin dimensions (x, y), duration of infiltration period (t), and the initialthickness of the saturated zone (hi(0), height of the water table if the bottom of the aquifer is the datum). For a square basin the half width equals the half length (x = y).For a rectangular basin, if the user wants the water-table changes perpendicular to the long side, specify x as the short dimension and y as the long dimension. Conversely,if the user wants the values perpendicular to the short side, specify y as the short dimension, x as the long dimension. All distances are from the center of the basin. Userscan change the distances from the center of the basin at which water-table aquifer thickness are calculated.Cells highlighted in yellow are values that can be changed by the user. Cells highlighted in red are output values based on user-specified inputs. The user MUST click theblue "Re-Calculate Now" button each time ANY of the user-specified inputs are changed otherwise necessary iterations to converge on the correct solution will not be doneand values shown will be incorrect. Use consistent units for all input values (for example, feet and days)
In the report accompanying this spreadsheet(USGS SIR 2010-5102), vertical soil permeability(ft/d) is assumed to be one-tenth horizontalhydraulic conductivity (ft/d).
Re-Calculate Now
-0.050
0.000
0.050
0.100
0.150
0.200
0.250
0.300
0.350
0.400
0 20 40 60 80 100 120 140
Groundwater Mounding, in feet
Appendix F
Low Impact Development Checklists
NJD
EP
No
nst
ruct
ura
l S
trat
egie
s P
oin
ts S
yste
m (
NS
PS
)
Ver
sio
n:
Jan
uar
y 31
, 20
06
No
te:
In
pu
t V
alu
es i
n Y
ello
w C
ells
On
ly
Pro
ject
:
Dat
e:M
arch
13,
202
0
Use
r:
No
tes:
Ste
p 1
- P
rovi
de
Bas
ic M
ajo
r D
evel
op
men
t S
ite
Info
rmat
ion
A. S
pec
ify
To
tal A
rea
in A
cres
of
Dev
elo
pm
ent
Sit
e D
escr
ibed
in
Ste
ps
2 an
d 3
=
5.5
A
cres
B. S
pec
ify
by
Per
cen
t th
e V
ario
us
Pla
nn
ing
Are
as L
oca
ted
wit
hin
th
e D
evel
op
men
t S
ite:
Sta
te P
lan
Pla
nn
ing
Are
a:P
A-1
PA
-2P
A-3
PA
-4P
A-4
BP
A-5
To
tal %
Are
a
Per
cen
t o
f E
ach
Pla
nn
ing
Are
a w
ith
in S
ite:
100.
0%10
0.0%
No
te:
See
Use
r's
Gu
ide
for
Eq
uiv
alen
t Z
on
es w
ith
in D
esig
nat
ed C
ente
rs a
nd
th
e N
J M
ead
ow
lan
ds,
Pin
elan
ds,
an
d H
igh
lan
ds
Dis
tric
ts
0303
M
Ste
p 2
- D
escr
ibe
Exi
stin
g o
r P
re-D
evel
op
ed S
ite
Co
nd
itio
ns
A. S
pec
ify
Exi
stin
g L
and
Use
/Lan
d C
ove
r D
escr
ipti
on
s an
d A
reas
: Sp
ecif
y L
and
Use
/Lan
d C
ove
r in
Acr
es f
or
Eac
h H
SG
Sit
e
Seg
men
tL
and
Use
/Lan
d C
ove
r D
escr
ipti
on
HS
G A
HS
G B
HS
G C
HS
G D
Use
/Co
ver
Su
bto
tals
Po
ints
1W
etla
nds
and
Und
istu
rbed
Str
eam
Buf
fers
0.0
02
Law
n an
d O
pen
Spa
ce1.
61.
665
3B
rush
and
Shr
ub0.
00
4M
eado
w,
Pas
ture
, Gra
ssla
nd,
or R
ange
0.0
05
Row
Cro
p0.
00
6S
mal
l Gra
in a
nd L
egum
es0.
00
7W
oods
- I
ndig
enou
s0.
00
8W
oods
- P
lant
ed0.
00
9W
oods
and
Gra
ss C
ombi
natio
n1.
91.
995
10P
onds
, Lak
es, a
nd O
ther
Ope
n W
ater
0.0
011
Gra
vel a
nd D
irt
0.0
012
Por
ous
and
Per
mea
ble
Pav
ing
0.0
013
Dir
ectly
Con
nect
ed I
mpe
rvio
us2.
12.
10
14U
ncon
nect
ed Im
perv
ious
with
Sm
all D
/S P
ervi
ous
0.0
015
Unc
onne
cted
Impe
rvio
us w
ith L
arge
D/S
Per
viou
s0.
00
HS
G S
ub
tota
ls (
Acr
es):
0.
00.
05.
50.
0T
ota
l Are
a:
5.5
HS
G S
ub
tota
ls (
%):
0.
0%0.
0%10
0.0%
0.0%
To
tal %
Are
a:
100.
0%
Po
ints
Su
bto
tal:
16
0
To
tal
Exi
stin
g S
ite
Po
ints
:
160
Ste
p 3
- D
escr
ibe
Pro
po
sed
or
Po
st-D
evel
op
ed S
ite
Co
nd
itio
ns
A. S
pec
ify
Pro
po
sed
Lan
d U
se/L
and
Co
ver
Des
crip
tio
ns
and
Are
as: Sp
ecif
y L
and
Use
/Lan
d C
ove
r in
Acr
es f
or
Eac
h H
SG
Sit
e
Seg
men
tL
and
Use
/Lan
d C
ove
r D
escr
ipti
on
HS
G A
HS
G B
HS
G C
HS
G D
Use
/Co
ver
Su
bto
tals
Po
ints
1W
etla
nds
and
Und
istu
rbed
Str
eam
Buf
fers
0.0
02
Law
n an
d O
pen
Spa
ce2.
12.
188
3B
rush
and
Shr
ub0.
00
4M
eado
w,
Pas
ture
, Gra
ssla
nd,
or R
ange
0.0
05
Row
Cro
p0.
00
6S
mal
l Gra
in a
nd L
egum
es0.
00
7W
oods
- I
ndig
enou
s0.
00
8W
oods
- P
lant
ed0.
00
9W
oods
and
Gra
ss C
ombi
natio
n0.
30.
317
10P
onds
, Lak
es, a
nd O
ther
Ope
n W
ater
0.0
011
Gra
vel a
nd D
irt
0.0
012
Por
ous
and
Per
mea
ble
Pav
ing
0.0
013
Dir
ectly
Con
nect
ed I
mpe
rvio
us3.
13.
10
14U
ncon
nect
ed Im
perv
ious
with
Sm
all D
/S P
ervi
ous
0.0
015
Unc
onne
cted
Impe
rvio
us w
ith L
arge
D/S
Per
viou
s0.
00
HS
G S
ub
tota
ls (
Acr
es):
0.
00.
05.
50.
0T
ota
l Are
a:
5.5
HS
G S
ub
tota
ls (
%):
0.
0%0.
0%10
0.0%
0.0%
To
tal %
Are
a:
100.
0%
Po
ints
Su
bto
tal:
10
5
B. C
om
par
e P
rop
ose
d I
mp
ervi
ou
s C
ove
rag
e w
ith
Max
imu
m A
llow
able
Im
per
vio
us
Co
vera
ge:
Tot
al D
irec
tly C
onne
cted
Im
perv
ious
Cov
erag
e =
56%
%
of
Site
Tot
al U
ncon
nect
ed I
mpe
rvio
us C
over
age
with
Sm
all D
/S P
ervi
ous
=0%
%
of
Site
Tot
al U
ncon
nect
ed I
mpe
rvio
us C
over
age
with
Lar
ge D
/S P
ervi
ous
=
0%
% o
f S
iteT
otal
Site
Im
perv
ious
Cov
erag
e =
56%
%
of
Site
Eff
ectiv
e S
ite I
mpe
rvio
us C
over
age
=56
%
% o
f S
ite
Tab
le (
Non
e or
Tab
le)
12%
Po
ints
Su
bto
tal:
0
C. C
om
par
e P
rop
ose
d S
ite
Dis
turb
ance
wit
h M
axim
um
All
ow
able
Sit
e D
istu
rban
ce:
Tot
al P
ropo
sed
Site
Dis
turb
ance
=10
0%
% o
f S
iteM
axim
um A
llow
able
Site
Dis
turb
ance
by
Mun
icip
al O
rdin
ance
=
100%
%
of S
iteP
oin
ts S
ub
tota
l:
0
D. D
escr
ibe
Pro
po
sed
Ru
no
ff C
on
veya
nce
Sys
tem
:
Tot
al L
engt
h of
Run
off
Con
veya
nce
Sys
tem
=
995
F
eet
Leng
th o
f V
eget
ated
Run
off
Con
veya
nce
Sys
tem
=
427
F
eet
% o
f T
otal
Run
off
Con
veya
nce
Sys
tem
Tha
t is
Veg
etat
ed =
43%
Po
ints
Su
bto
tal:
40
E.
Res
iden
tial
Lo
t C
lust
erin
g:
Per
cent
of
Tot
al S
ite A
rea
that
will
be
Clu
ster
ed =
% o
f S
iteM
inim
um S
tand
ard
Lot
Siz
e as
Per
Zon
ing
(Not
e: 1
/2 A
cre
or G
reat
er)
=
Acr
esM
axim
um P
ropo
sed
Clu
ster
Lot
Siz
e (N
ote:
1/4
Acr
e or
Les
s) =
A
cres
Per
cent
of
Clu
ster
ed P
ortio
n of
Site
to
be P
rese
rved
as
Veg
etat
ed O
pen
Spa
ce =
%
of
Clu
ster
ed S
ite P
ortio
n Po
ints
Su
bto
tal:
0
Spe
cify
Sou
rce
of M
axim
um A
llow
able
Im
perv
ious
Cov
erag
e:
Allo
wab
le S
ite Im
perv
ious
Cov
er fr
om M
axim
um I
mpe
rvio
us C
over
Tab
le:
N
ote:
See
Max
imum
Im
perv
ious
Cov
er T
able
Wor
kshe
et f
or D
etai
ls
F.
Will
th
e F
ollo
win
g b
e U
tiliz
ed t
o M
inim
ize
So
il C
om
pac
tio
n?
Pro
pose
d La
wn
Are
as w
ill b
e G
rade
d w
ith L
ight
wei
ght
Con
stru
ctio
n E
quip
men
t:Y
es
(Yes
or
No)
Per
cent
of
Pro
pose
d La
wn
Are
as t
o be
Gra
ded
with
Suc
h E
quip
men
t:10
0%
% o
f La
wn
Are
as
Po
ints
Su
bto
tal:
23
G.
Are
An
y o
f th
e F
ollo
win
g S
torm
wat
er M
anag
emen
t S
tan
dar
ds
Met
Usi
ng
On
ly N
on
stru
ctu
ral
Str
ateg
ies
and
Mea
sure
s?
Gro
undw
ater
Rec
harg
e S
tand
ards
(N
JAC
7:8
-5.4
-a-2
):N
o
(Y
es o
r N
o)S
torm
wat
er R
unof
f Q
ualit
y S
tand
ards
(N
JAC
7:8
-5.5
):N
o
(Yes
or
No)
Sto
rmw
ater
Run
off
Qua
ntity
Sta
ndar
ds (
NJA
C 7
:8-5
.4-a
-3):
No
(
Yes
or
No)
Po
ints
Su
bto
tal:
0
No
te:
If t
he
An
swer
s to
All
Th
ree
Qu
esti
on
s at
G A
bo
ve a
re "
Yes
", A
deq
uat
e N
on
stru
ctu
ral
Mea
sure
s h
ave
bee
n U
tili
zed
.
To
tal
Pro
po
sed
Sit
e P
oin
ts:
16
8
Rat
io o
f P
rop
ose
d t
o E
xist
ing
Sit
e P
oin
ts:
10
5%
Req
uir
ed S
ite
Po
ints
Rat
io:
94
%
No
nst
ruct
ura
l P
oin
t S
yste
m R
esu
lts:
Pro
po
sed
No
nst
ruct
ura
l M
easu
res
are
Ad
equ
ate
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
Low Impact Development Checklist A checklist for identifying nonstructural stormwater management
Strategies incorporated into proposed land development
Municipality: Montgomery Township
County: Somerset Date: August 22, 2019
Review board or agency: Montgomery Township Planning Board and the Somerset
County Planning Board.
Proposed land development name: Preliminary & Final Site Plan
Lot(s): 45 Block(s): 29002
Project or application number: 0303M
Applicant’s name: CC1377, LLC
Applicant’s address: 36 Brower Lane, Hillsborough, NJ 08844
Telephone: 908-359-3276 Fax: 908-359-3998
Email address: [email protected]
Designer’s name: Michael K. Ford, P.E. c/o Van Cleef Engineering Associates
Designer’s address: 32 Brower Lane, PO Box 5877, Hillsborough, NJ 08844
Telephone: 908-359-8291 Fax: 908-359-1580
Email address: [email protected]
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
Part 1: Description of Nonstructural Approach to Site Design
In narrative form, provide an overall description of the nonstructural stormwater management
approach and strategies incorporated into the proposed site’s design. Attach additional pages as
necessary. Details of each nonstructural strategy are provided in Part 3 below.
Multiple low impact development BMPs have been used in the design of the proposed site plan.
Landscape and soil disturbance has been minimized by maintaining a significant difference in
elevation between the eastern and western portions of the property with the help of a retaining
wall. The open spaces on-site will provide low maintenance landscaping and will minimize the
use of fertilizers and pesticides.
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
Part 2: Review of Local Stormwater Management Regulations
Title and date of stormwater management regulations used in development design:
Montgomery Township Stormwater Ordinance
Do regulations include nonstructural requirements? Yes: X No:
If yes, briefly describe: A total of nine (9) strategies are to be used to meet the groundwater
recharge stormwater quality and stormwater quantity requirements prior to utilizing structural
stormwater management measures. These nine strategies are listed in the Drainage Report
List LID-BMPs prohibited by local regulations: ______________________________
Pre-design meeting held? Yes: Date: No: X
Meeting held with:
Pre-design site walk held? Yes: Date: No: X
Site walk held with:
Other agencies with stormwater review jurisdiction:
Name: Somerset-Union Soil Conservation District________________________
________________________________ ________________________
Required approval: Certification __________________
Name: Somerset County Planning Board
Required approval: Conditional Approval
Name:
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
Part 3: Nonstructural Strategies and LID-BMPs in Design
3.1 Vegetation and Landscaping
Effective management of both existing and proposed site vegetation can reduce a development’s adverse
impacts on groundwater recharges and runoff quality and quantity. This section of the checklist helps
identify the vegetation and landscaping strategies and nonstructural LID-BPMs that have been
incorporated into the proposed development’s design to help maintain existing recharge rates and/or
minimize or prevent increases in runoff quantity and pollutant loading.
A. Has an inventory of existing site vegetation been performed? Yes: X No:
If yes, was this inventory a factor in the site’s layout and design? Yes: X No:
B. Does the site design utilize any of the following nonstructural LID-BPMs?
Preservation of natural areas? Yes: X No: If Yes, specify % of site: 2.3%
Native ground cover? Yes: No: X If Yes, specify % of site: ___
Vegetated buffers? Yes: No: X If Yes, specify % of site: ___
C. Do the land development regulations require these nonstructural LID-BMPs?
Preservation of natural areas? Yes: No: X If Yes, specify % of site: __
Native ground cover? Yes: No: X If Yes, specify % of site:
Vegetated buffers? Yes: No: X If Yes, specify % of site:
D. If vegetated filter strips or buffers are utilized, specify their functions:
Reduce runoff volume increases through lower runoff coefficient: Yes: No: X
Reduce runoff pollutant loads through runoff treatment: Yes: No: X
Maintain groundwater recharge by preserving natural areas: Yes: X No:
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
3.2 Minimize Land Disturbance
Minimizing land disturbance is a nonstructural LID-BMP that can be applied during both the development’s
construction and post-construction phases. This section of the checklist helps identify those land disturbance
strategies and nonstructural LID-BMP’s that have been incorporated into the proposed development’s design to
minimize land disturbance and the resultant change in the site’s hydrologic character.
A. Have inventories of existing site soils and slopes been performed? Yes: X No:
If yes, were these inventories factors in the site’s layout and design? Yes: X No:
B. Does the development’s design utilize any of the following nonstructural LID-BPMs?
Restrict permanent site disturbance by land owners? Yes: No: X
If yes, how:
Restrict temporary site disturbance during construction? Yes: X No:
If yes, how: Site disturbance during construction will be minimized by using current soil erosion
and sediment control practices.
Consider soils and slopes in selecting disturbance limits? Yes: No: X
If yes, how:
C. Specify percentage of site to be cleared: NA_________ Regraded: 97.7
D. Specify percentage of cleared areas done so for buildings: NA
For driveways and parking: NA For roadways: NA
E. What design criteria and/or site changes would be required to reduce the percentages in C and D above?
The site plan has been designed to limit development to eastern portion of site. There are no other changes
that could reduce the percentages.
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
F. Specify site’s hydrologic soil group (HSG) percentages:
HSG A: HSG B: HSG C: 100 HSG D:
G. Specify percentage of each HSG that will be permanently disturbed:
HSG A: HSG B: HSG C: 97.7 HSG D:
H. Locating site disturbance within areas with less permeable soils (HSG C and D) and minimizing disturbance
within areas with greater permeable soils (HGS A and B) can help maintain groundwater recharge rates and
reduce runoff volume increases. In light of the HSG percentages in F and G above, what other practical
measures if any can be taken to achieve this?
NA: 100% Type C Soil in area of disturbance
I. Does the site include Karst topography? Yes: No: X
If yes, discuss measures taken to limit Karst impacts:
_________________
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
3.3 Impervious Area Management
New impervious surfaces at a development site can have the greatest adverse effect on groundwater
recharge and stormwater quality and quantity. This section of the checklist helps identify those
nonstructural strategies and LID-BPMs that have been incorporated into a proposed development’s design
to comprehensively manage the extent and impacts of new impervious surfaces.
A. Specify impervious cover at site: Existing: 41.2% Proposed: 60.1%
B. Specify maximum site impervious coverage allowed by regulations: 70%
C. Compare proposed street cartway widths with those required by regulations:
Type of Street Proposed Cartway
Width (feet)
Required Cartway
Width (feet)
Residential access-low intensity
Residential access-medium intensity
Residential access-high intensity with parking 24’ 24’
Residential access-high intensity without
parking
Neighborhood
Minor collector-low intensity without parking
Minor collector-with one parking lane
Minor collector-with two parking lanes
Minor collector-without parking
Major collector
D. Compare proposed parking space dimensions with those required by regulations:
Proposed: 9 x 18 Regulations: 9 x 18
E. Compare proposed number of parking spaces with those required by regulations:
Proposed: 229 Regulations: 225
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
F. Specify percentage of total site impervious cover created by buildings: 37.9
By driveways and parking: 62.1 By roadways: N/A
G. What design criteria and/or site changes would be required to reduce the percentages in F above?
Reduce the number of parking spaces by two. The cartway widths and the remaining parking spaces are
based on the Residential Site Improvement Standards and are required for the residential use proposed.
____________
H. Specify percentage of total impervious area that will be unconnected:
Total site: 0 Buildings: 0 Driveways and parking: 0 Roads: 0
I. Specify percentage of total impervious area that will be porous:
Total site: 0 Buildings: 0 Driveways and parking: 0 Roads:
J. Specify percentage of total building roof area that will be vegetated: 0
K. Specify percentage of total parking area located beneath buildings: 0
L. Specify percentage of total parking located within multi-level parking deck: 0
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
3.4 Time of Concentration Modifications
Decreasing a site’s time of concentration (Tc) can lead directly to increased site runoff rates which, in turn,
can create new and/or aggravate existing erosion and flooding problems downstream. This section of the
checklist helps identify those nonstructural strategies and LID-BMPs that have been incorporated into the
proposed development’s design to effectively minimize such Tc decreases.
When reviewing Tc modification strategies, it is important to remember that a drainage area’s Tc should
reflect the general conditions throughout the area. As a result, Tc modifications must generally be applied
throughout a drainage area, not just along a specific Tc route.
A. Specify percentage of site’s total stormwater conveyance system length that will be:
Storm sewer: 100 Vegetated swale: 0 Natural channel: NA
Stormwater management facility: Other:
Note: The total length of the stormwater conveyance systems should be measured from the site’s
downstream property line to the downstream limit of sheet flow at the system’s headwaters.
B. What design criteria and/or site changes would be required to reduce the storm sewer percentages and
increase the vegetated swale and natural channel percentages in A above?
In order to provide swales the limit of disturbance would be increased
C. In conveyance system subareas that have overland or sheet flow over impervious surfaces or turf
grass, what practical and effective site changes can be made to:
Decrease overland flow slope: NA ____________
Increase overland flow roughness: NA
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
3.5 Preventative Source Controls
The most effective way to address water quality concerns is by pollution prevention. This section of the
checklist helps identify those nonstructural strategies and LID-BMPs that have been incorporated into the
proposed development’s design to reduce the exposure of pollutants to prevent their release into the
stormwater runoff.
A. Trash Receptacles
Specify the number of trash receptacles provided: Two (2) trash enclosures are proposed
Specify the spacing between the trash receptacles: 649 ft
Compare trash receptacles proposed with those required by regulations:
Proposed: 2 Regulations: NA
B. Pet Waste Stations
Specify the number of pet waste stations provided: NA
Specify the spacing between the pet waste stations: NA
Compare pet waste stations proposed with those required by regulations:
Proposed: Regulations:
C. Inlets, Trash Racks and Other Devices that Prevent Discharge of Large Trash and Debris
Specify percentage of total inlets that comply with the NJPDES storm drain inlet criteria: 100
D. Maintenance
Specify the frequency of the following maintenance activities:
Street sweeping: Proposed: Private Regulations:
Litter collection: Proposed: Private Regulations:
Identify other stormwater management measures on the site that prevent discharge of large trash and
debris:
Regular property care by owner.
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
E. Prevention and Containment of Spills
Identify locations where pollutants are located on the site and the features that prevent these pollutants
from being exposed to stormwater runoff:
Pollutant: NA-None Location:
Feature utilized to prevent pollutant exposure, harmful accumulation or contain spills:
Pollutant: NA Location:
Feature utilized to prevent pollutant exposure, harmful accumulation or contain spills:
Pollutant: NA Location:
Feature utilized to prevent pollutant exposure, harmful accumulation or contain spills:
Pollutant: NA Location:
Feature utilized to prevent pollutant exposure, harmful accumulation or contain spills:
Pollutant: NA Location:
New Jersey Stormwater BMP Manual . Appendix A: Low Impact Development Checklist . Final Draft . December 2003
F:\Jobfile\0303M\_ENG\Hydrology\Low Impact Development Checklist-180717.doc
Part 4: Compliance with Nonstructural Requirements
of NJDEP Stormwater Management Rules
1. Based upon the checklist responses above, indicate which nonstructural strategies have been
incorporated into proposed development’s design in accordance with NJAC 7:8-5.3(b):
No. Nonstructural strategy Yes No
1 Protect areas that provide water quality benefits or areas particularly
susceptible to erosion and sediment loss.
X
2 Minimize impervious surfaces and break up or disconnect the flow of
runoff over impervious surfaces.
X
3 Maximize the protection of natural drainage features and vegetation.
X
4 Minimize the decrease in the pre-construction time of concentration
X
5 Minimize land disturbance including clearing and grading.
X
6 Minimize soil compaction.
X
7 Provide low maintenance landscaping that encourages retention and
planting of native vegetation and minimizes the use of lawns, fertilizers
and pesticides.
X
8 Provide vegetated open-channel conveyance systems discharge into and
through stable vegetated areas.
X
9 Provide preventative source controls.
X
2. For those strategies that have not been incorporated into the proposed development’s design, provide
engineering, environmental and/or safety reasons. Attached additional pages as necessary.
See Stormwater Management Report for further discussion of Low Impact Development Techniques.
Appendix G
Pipe Calculations
Block 29002 Lot 45Montgomery Township0303M6/25/20
INLET DRAINAGE AREACOMPOSITE "C" CALCULATIONS
DRAINAGE AREA
Catch Basin I.D. AREA (SF) IMP. O.S. Composite "C" AREA (Ac.)
0.99 0.51
DA-1 CB-1 2,966 1,717 1,249 0.79 0.07DA-2 CB-2 2,166 1,236 930 0.78 0.05
DA-3 CB-3 38,553 34,892 3,661 0.94 0.89DA-4 CB-4 14,052 9,573 4,479 0.84 0.32DA-5 CB-5 13,418 10,640 2,778 0.89 0.31DA-6 CB-6 14,829 13,462 1,367 0.95 0.34DA-7 CB-7 2,589 2,137 452 0.91 0.06DA-8 CB-8 13,466 10,326 3,140 0.88 0.31DA-9 CB-9 10,087 9,463 624 0.96 0.23DA-10 CB-10 7,737 4,202 3,535 0.77 0.18DA-11 CB-11 3,866 3,456 410 0.94 0.09DA-12 CB-12 2,153 1,309 844 0.80 0.05DA-13 CB-13 2,771 1,860 911 0.83 0.06DA-14 CB-14 19,485 286 19,199 0.52 0.45DA-15 CB-15 12,173 169 12,004 0.52 0.28DA-16 CB-16 2,967 0 2,967 0.51 0.07DA-16A CB-16A 2,389 0 2,389 0.51 0.05DA-17 CB-17 8,305 4,847 3,458 0.79 0.19DA-18 CB-18 2,786 0 2,786 0.51 0.06DA-19 CB-19 433 0 433 0.51 0.01DA-20 CB-20 1,799 0 1,799 0.51 0.04DA-21 CB-21 25,249 24,130 1,119 0.97 0.58DA-22 CB-22 2,677 957 1,720 0.68 0.06DA-23 CB-23 2,534 1,188 1,346 0.74 0.06
PIPE CALCULATIONS
Start Node Stop Node Invert (Start) (ft) Invert (Stop) (ft) Length (ft) System Intensity (in/h) System CA (acres) Upstream Inlet Area (acres) Upstream Inlet C Slope (%) Manning's n Diameter (in) Flow (cfs) Capacity (Full Flow) (cfs) Velocity (ft/s) HGL (In) (ft) HGL (Out) (ft)STORM MH-2 EX. L.I. 96.20 94.59 26 6.22 1.34 (N/A) (N/A) 6.2 0.013 24 16.59 56.29 15.58 97.67 95.48
CB-15 CB-16 118.25 113.62 185 6.52 0.43 0.28 0.52 2.5 0.013 15 2.82 10.21 7.11 118.92 114.07CB-1 CB-2 118.76 118.10 66 6.60 0.06 0.07 0.79 1.0 0.013 15 0.37 6.46 2.85 119 118.31CB-2 CB-3 118.00 111.63 157 6.52 0.09 0.05 0.78 4.1 0.013 15 0.62 13.02 5.45 118.31 112.63CB-14 CB-15 121.38 118.35 121 6.58 0.28 0.45 0.52 2.5 0.013 15 1.88 10.23 6.36 121.93 118.92CB-13 CB-14 121.92 121.48 17 6.60 0.05 0.06 0.83 2.5 0.013 15 0.33 10.21 3.82 122.14 121.93CB-3 CB-5 111.53 104.73 170 6.43 1.20 0.89 0.94 4.0 0.013 15 7.77 12.91 11.01 112.63 105.84CB-4 CB-3 112.29 111.63 66 6.60 0.27 0.32 0.84 1.0 0.013 15 1.79 6.46 4.5 112.82 112.63CB-22 CB-23 110.81 110.67 28 6.60 0.04 0.06 0.68 0.5 0.013 15 0.27 4.57 2.04 111.01 110.98CB-23 CB-17 110.57 110.20 74 6.55 0.09 0.06 0.74 0.5 0.013 15 0.56 4.57 2.53 110.98 110.97CB-18 CB-19 107.51 105.95 52 6.32 0.76 0.06 0.51 3.0 0.013 15 4.82 11.19 8.78 108.4 106.53CB-19 CB-20 105.85 102.71 78 6.30 0.76 0.01 0.51 4.0 0.013 15 4.84 12.91 9.77 106.74 103.24CB-17 CB-18 110.10 107.61 83 6.35 0.73 0.19 0.79 3.0 0.013 15 4.65 11.19 8.69 110.97 108.17CB-20 CB-21 102.61 100.35 57 6.27 0.78 0.04 0.51 4.0 0.013 15 4.95 12.91 9.83 103.51 101.38CB-5 CB-7 104.63 103.51 34 6.38 1.80 0.31 0.89 3.3 0.013 15 11.56 11.72 10.89 105.84 104.56CB-6 CB-5 105.39 104.73 66 6.60 0.32 0.34 0.95 1.0 0.013 15 2.15 6.46 4.73 105.97 105.84CB-21 STORM MH-2 100.25 96.30 112 6.25 1.34 0.58 0.97 3.5 0.013 15 8.48 12.13 10.69 101.38 97.67CB-7 CB-8 103.26 100.40 141 6.36 1.85 0.06 0.91 2.0 0.013 18 11.89 14.96 9.39 104.56 101.41CB-8 CB-10 99.90 99.71 38 6.31 2.35 0.31 0.88 0.5 0.013 24 14.94 15.71 5.69 101.42 101.11CB-9 CB-8 101.31 100.65 66 6.60 0.22 0.23 0.96 1.0 0.013 15 1.47 6.46 4.26 101.78 101.42CB-10 STORM MH-1 99.61 99.45 27 6.29 2.49 0.18 0.77 0.6 0.013 24 15.76 17.52 6.31 101.11 100.99CB-12 STORM MH-1 99.70 99.45 18 6.56 0.12 0.05 0.80 1.4 0.013 15 0.82 7.64 0.67 100.99 100.99
STORM MH-1 HW-1 99.45 99.00 74 6.28 2.61 (N/A) (N/A) 0.6 0.013 24 16.52 17.64 6.38 100.99 100.47CB-11 CB-12 99.84 99.70 27 6.60 0.08 0.09 0.94 0.5 0.013 15 0.56 4.57 2.53 100.99 100.99OCS STORM MH-2 98.33 97.35 39 6.60 0.00 (N/A) (N/A) 2.5 0.013 18 8.16 16.65 9.38 99.44 98.13
CB-16 CB-16A 113.52 111.41 105 6.43 0.47 0.07 0.51 2.0 0.013 15 3.02 9.16 6.69 114.22 112.13CB-16A CB-17 111.41 110.2 61 6.38 0.49 0.05 0.51 2 0.013 15 3.16 9.11 6.75 112.13 110.97
Roof Drain Sizing Sheet Roof Drain Sizing
Building Number Roof Area (SQ. FT.) Size (Inches) Slope (Inch/Foot)
1 24,129 12 1/8
2 24,148 12 1/8
Please note that all roof drains have been sized per the 2015 National Standard Plumbing Code Chapter 13 Section 13.1.10.1 Primary Roof Drainage. See Table 13.6.2 Part 1 enclosed in this appendix. A rainfall rate of five inches per hour was utilized per NJAC 5:23-3.15(b)11.ii, which states that “rainfall rates shall be applied so that the applicable rainfall rate for Burlington and Ocean Counties and all counties south shall be six inches per hour and for Mercer and Monmouth Counties and all counties north, the applicable rainfall rate shall be five inches per hour.” This site is located north of Mercer and Monmouth Counties.
http://epubs.iapmo.org/NSPC/2015/mobile/index.html#p=340
2 of 3 4/11/2019, 12:22 PM
Tailwater > .5 Do (2)
RIPRAP APRON DATA SHEETPROJECT NAME: 1377 US-206 Job #: 0303M
STORM FREQENCIES: 25-Year DATE: 4/21/2020
BY: KH
OUTLET YEAR Q PIPE PIPE TAILWATER La W (beg) W (end) d50
STRUCT. STORM (cfs) HEIGHT (in) WIDTH (in) (ft) (ft) (ft) (ft) (in)
HW-1 25 16.27 24 24 2.72 17.3 6.0 12.9 1.1
Page 1
Appendix H
Emergency Spillway Design
1377 US-206, Montgomery NJ 08558
Project: 1377 US-206 Date: 08/23/19Location: Montgomery Township, Somerset County By: KH
Emergency Spillway
Basin 1
Emergency Spillway - NJDEP Criteria
Peak 100 Year Inflow to Basin = 18.82 cfs
100 Year Inflow Plus 50% = 28.23 cfs
Emergency Spillway = 70.00 LF Broad Crested Weir at Elev = 103.95
Weir Equation: Q = CLH^1.5
Solving for H: = (Q/CL)^0.67
Where: Q = 28.23 cfs L = 70.00 feet C = 2.70 ( Discharge Coefficient ) H = Hydraulic Head over Spillway
Hydraulic Head H = 0.28 ft
Velocity Over Spillway : V = Q/A
Where: Q = 28.23 cfs A = L x H = 19.58 sf
Velocity V= 1.44 fps
Emergency Water Surface Elevation = 103.95 + H = 104.23
Top of Berm = 104.23 + 1 ft (Freeboard)= 105.23
Set Top of Berm Elevation = 105.30
F:\Jobfile\1231H.01\ENG\Hydro\Drainage Report 10-1-18.doc
Appendix I
Recharge Analysis
Annu
al G
roun
dwat
er R
echa
rge
Anal
ysis
(bas
ed o
n G
SR-3
2)Pr
ojec
t Nam
e:
Sele
ct T
owns
hip↓
Aver
age
Annu
al P
(in)
Clim
atic
Fact
orD
escr
iptio
n:
SOM
ERSE
T CO
., M
ONT
GO
MER
Y TW
P46
.01.
50An
alys
is D
ate:
10/0
5/17
Land
Segm
ent
Area
(acr
es)
TR-5
5 La
nd C
over
Soil
Annu
alRe
char
ge(in
)
Annu
alRe
char
ge(c
u.ft)
Land
Segm
ent
Area
(acr
es)
TR-5
5 La
nd C
over
Soil
Annu
alRe
char
ge(in
)
Annu
alRe
char
ge(c
u.ft)
12.
07Im
perv
ious
are
asRo
yce
0.0
-1
3.08
Impe
rvio
us a
reas
Roy
ce0.
0-
21.
62W
oods
Royc
e12
.573
,625
21.
99O
pen
spac
eRo
yce
12.3
88,8
883
1.38
Ope
n sp
ace
Royc
e12
.361
,641
30
Woo
dsPe
nn-
-4
0O
pen
spac
eBi
rdsb
oro
--
40
Ope
n sp
ace
Klin
esvi
lle-
-5
0W
oods
Bird
sbor
o-
-5
Ope
n sp
ace
Lans
dow
ne-
-6
0R
esid
entia
l 1/2
acr
e or
1 a
cre
Keyp
ort
--
6W
oods
Bird
sbor
o-
-7
0Im
perv
ious
are
asLa
nsdo
wne
--
7R
esid
entia
l 1 a
cre
or 2
acr
eKe
ypor
t-
-8
0G
rave
l, di
rtLa
nsdo
wne
--
80
Brus
hAd
elph
ia V
aria
nt-
-9
0br
ush
Adel
phia
--
90
Brus
hAd
elph
ia-
-10
0br
ush
Adel
phia
--
100
Brus
hAb
botts
tow
n-
-11
0Br
ush
Abbo
ttsto
wn
--
110
Brus
hAb
botts
tow
n-
-12
0Br
ush
Abbo
ttsto
wn
--
120
Brus
hAb
botts
tow
n-
-13
0Br
ush
Abbo
ttsto
wn
--
130
Brus
hAb
botts
tow
n-
-14
0Br
ush
Abbo
ttsto
wn
--
140
Brus
hAb
botts
tow
n-
-15
0Br
ush
Abbo
ttsto
wn
--
150
Brus
hAb
botts
tow
n-
-
Tota
l =
5.1
Tota
lAn
nual
Rec
harg
e(in
)
Tota
lAn
nual
Rec
harg
e(c
u-ft)
Tota
l =
5.1
Tota
lAn
nual
Rec
harg
e(in
)
Tota
lAn
nual
Rec
harg
e(c
u.ft)
7.3
135,
266
4.8
88,8
88
Proc
edur
e to
fill
the
Pre-
Dev
elop
men
t and
Pos
t-Dev
elop
men
t Con
ditio
ns T
able
s%
of P
re-D
evel
oped
Ann
ual R
echa
rge
to P
rese
rve
=10
0%
Tota
lIm
perv
ious
Area
(sq.
ft)13
4,16
5
For e
ach
land
seg
men
t, fir
st e
nter
the
area
, the
n se
lect
TR
-55
Land
Cov
er, t
hen
sele
ct S
oil.
Sta
rt fro
m th
e to
p of
the
tabl
ePo
st-D
evel
opm
ent A
nnua
l Rec
harg
e D
efic
it=46
,378
(cub
ic fe
et)
and
proc
eed
down
ward
. Don
't le
ave
blan
k ro
ws (w
ith A
=0) i
n be
twee
n yo
ur s
egm
ent e
ntrie
s. R
ows
with
A=0
will
not
be
disp
laye
d or
use
d in
cal
cula
tions
. For
impe
rvio
us a
reas
out
side
of s
tand
ard
lots
sel
ect "
Impe
rvio
us A
reas
" as
the
Land
Cov
er.
RW
C=
3.53
(in)
DR
WC
=3.
53(in
)
Soil
type
for i
mpe
rvio
us a
reas
are
onl
y re
quire
d if
an in
filtra
tion
faci
lity
will
be b
uilt
with
in th
ese
area
s.ER
WC
=0.
88(in
)ED
RW
C=
0.88
(in)
Pre-
Dev
elop
ed C
ondi
tions
Post
-Dev
elop
ed C
ondi
tions
Rec
harg
e Ef
ficie
ncy
Para
met
ers
Cal
cula
tions
(are
a av
erag
es)
Annu
al R
echa
rge
Req
uire
men
ts C
alcu
latio
n↓
New
Jer
sey
Gro
undw
ater
Rech
arge
Spre
adsh
eet
Vers
ion
2.0
Nov
embe
r 200
3
Proj
ect N
ame
Des
crip
tion
Anal
ysis
Dat
eB
MP
or L
ID T
ype
Rec
harg
e B
MP
Inpu
t Par
amet
ers
Roo
t Zon
e W
ater
cap
acity
Cal
cula
ted
Para
met
ers
Rec
harg
e D
esig
n Pa
ram
eter
sPa
ram
eter
Sym
bol
Valu
eU
nit
Para
met
erSy
mbo
lVa
lue
Uni
tPa
ram
eter
Sym
bol
Valu
eU
nit
BMP
Area
ABM
P42
93.0
sq.ft
Empt
y Po
rtion
of R
WC
und
er P
ost-D
Nat
ural
Rec
harg
eER
WC
1.23
inIn
ches
of R
unof
fto
cap
ture
Qde
sign
0.99
in
BMP
Effe
ctiv
e D
epth
,th
is is
the
desi
gn v
aria
ble
dBM
P22
.8in
ERW
C M
odifi
ed to
cons
ider
dEX
CED
RW
C1.
23in
Inch
es o
f Rai
nfal
lto
cap
ture
Pdes
ign
1.20
in
Upp
er le
vel o
f the
BM
Psu
rface
(neg
ativ
e if
abov
egr
ound
)dB
MPu
-22.
8in
Empt
y Po
rtion
of R
WC
und
er In
filt.
BMP
RER
WC
0.96
inR
echa
rge
Prov
ided
Avg.
ove
r Im
p. A
rea
27.5
in
Dep
th o
f low
er s
urfa
ce o
fBM
P, m
ust b
e>=d
BMPu
dEXC
0.0
inR
unof
f Cap
ture
dAv
g. o
ver i
mp.
Are
a30
.7in
Post
-dev
elop
men
t Lan
dSe
gmen
t Loc
atio
n of
BM
P ,
Inpu
t Zer
o if
Loca
tion
is d
istri
bute
dor
und
eter
min
ed
SegB
MP
2un
itles
s
BM
P C
alcu
late
d Si
ze P
aram
eter
sC
ALC
UL
ATI
ON
CH
ECK
MES
SAG
ESAB
MP/
Aim
pAr
atio
0.04
unitl
ess
Volu
me
Bala
nce-
>So
lve
Prob
lem
to s
atis
fy A
nnua
l Rec
harg
eBM
P Vo
lum
eVB
MP
8,15
7cu
.ftdB
MP
Che
ck---
>O
KPa
ram
eter
s fro
m A
nnua
l Rec
harg
e W
orks
heet
Syst
em P
erfo
rman
ce C
alcu
late
d Pa
ram
eter
sdE
XC C
heck
--->
OK
Post
-D D
efic
it R
echa
rge
(or d
esire
d re
char
gevo
lum
e)Vd
ef46
,378
cu.ft
Annu
al B
MP
Rec
harg
eVo
lum
e23
3,25
2cu
.ftBM
P Lo
catio
n--->
OK
Post
-D Im
perv
ious
Are
a(o
r tar
get I
mpe
rvio
us A
rea)
Aim
p10
1,93
0sq
.ftAv
g BM
P R
echa
rge
Effic
ienc
y89
.6%
Rep
rese
nts
% In
filtra
tion
Rec
harg
edO
TH
ER
NO
TE
S
Roo
t Zon
e W
ater
Cap
acity
RW
C4.
90in
%R
ainf
all
beca
me
Run
off
78.0
%%
Pdes
ign
is a
ccur
ate
only
afte
r BM
P di
men
sion
s ar
e up
date
d to
mak
e re
ch v
olum
e= d
efic
it vo
lum
e. T
he p
ortio
nR
WC
Mod
ified
toco
nsid
er d
EXC
DR
WC
4.90
in%
Run
off
Infil
trate
d85
.5%
%of
BM
P in
filtra
tion
prio
r to
fillin
g an
d th
e ar
ea o
ccup
ied
by B
MP
are
igno
red
in th
ese
calc
ulat
ions
. Res
ults
are
Clim
atic
Fac
tor
C-fa
ctor
1.50
no u
nits
%R
unof
fR
echa
rged
58.2
%%
sens
etiv
e to
dBM
P, m
ake
sure
dBM
P se
lect
ed is
sm
all e
noug
h fo
r BM
P to
em
pty
in le
ss th
an 3
day
s. F
or la
nd
Aver
age
Annu
al P
Pavg
46.0
in%
Rai
nfal
lR
echa
rged
45.4
%%
Segm
ent L
ocat
ion
of B
MP
if yo
u se
lect
"im
perv
ious
are
as" R
WC
will
be m
inim
al b
ut n
ot z
ero
as d
eter
min
ed b
y
Rec
harg
e R
equi
rem
ent
over
Imp.
Are
adr
4.1
inth
e so
il ty
pe a
nd a
sha
llow
root
zon
e fo
r thi
s La
nd C
over
allo
win
g co
nsid
erat
ion
of la
tera
l flo
w a
nd o
ther
loss
es.
How
to s
olve
for d
iffer
ent r
echa
rge
volu
mes
:By
defa
ult t
he s
prea
dshe
et a
ssig
ns th
e va
lues
of t
otal
def
icit
rech
arge
vol
ume
"Vde
f" an
d to
tal p
ropo
sed
impe
rvio
us a
rea
"Aim
p" fr
om th
e "A
nnua
l Rec
harg
e" s
heet
to "V
def"
and
"Aim
p" o
n th
is p
age.
Thi
s al
low
s so
lutio
n fo
r a s
ingl
e BM
P to
han
dle
the
entir
e re
char
ge re
quire
men
t ass
umin
g th
e ru
noff
from
ent
ire im
perv
ious
are
a is
ava
ilabl
e to
the
BMP.
To s
olve
for a
sm
alle
r BM
P or
a L
ID-IM
P to
rech
arge
onl
y pa
rt of
the
rech
arge
requ
irem
ent,
set V
def t
o yo
ur ta
rget
val
ue a
nd A
imp
to im
perv
ious
are
a di
rect
ly c
onne
cted
to y
our i
nfilt
ratio
n fa
cilit
y an
d th
en s
olve
for A
BMP
ordB
MP.
To
go b
ack
to th
e de
faul
t con
figur
atio
n cl
ik th
e "D
efau
lt Vd
ef &
Aim
p" b
utto
n.
10/0
5/17
00
F:\Jobfile\1231H.01\ENG\Hydro\Drainage Report 10-1-18.doc
Appendix J
Drainage Area Maps
Land Surveying Professional Planning Landscape Architecture
Engineering Associates, LLC
FILE No. 3476-L
Consulting Civil, Environmental & Municipal Engineering
Van Cleef
F:\JOBFILE\0303M\_ENG\DWG\EXISTING DA.DWG
ONE
WAY
D
D
S S
D
FL 1SL1
SL 2
FL 2
FL 3
FL 4
FIRE LANEFIRE LANE
FIRE LANE
SHEET FLOW
100 FT. @4.0%
T
c
PATH (TYP) CHANNEL FLOW
881 FT
SHALLOW
CONCENTRATED FLOW
183 FT. @4.6%
SHEET FLOW
100 FT. @3.8%
SHALLOW CONCENTRATED FLOW
50 FT. @20.1%
CHANNEL FLOW
712 FT
Land Surveying Professional Planning Landscape Architecture
Engineering Associates, LLC
FILE No. 3476-L
Consulting Civil, Environmental & Municipal Engineering
Van Cleef
F:\JOBFILE\0303M\_ENG\DWG\PROPOSED DA.DWG
ONE
WAY
D
D
S S
S
D
FL 1SL1
SL 2
FL 2
FL 3
FL 4
FIRE LANEFIRE LANE
FIRE LANE
DA-4
0.32
DA-15
0.28
DA-23
0.06
DA-21
0.58
DA-16
0.07
DA-1
0.07
DA-14
0.45
DA-13
0.06
DA-17
0.19
DA-3
0.89
DA-2
0.05
DA-5
0.31
DA-7
0.06
DA-6
0.34
DA-9
0.23
DA-8
0.31
DA-11
0.09
DA-12
0.05
DA-10
0.18
DA-22
0.06
DA-18
0.06
DA-19
0.01
DA-20
0.04
DA-16A
0.05
Land Surveying Professional Planning Landscape Architecture
Engineering Associates, LLC
FILE No. 3476-L
Consulting Civil, Environmental & Municipal Engineering
Van Cleef
F:\JOBFILE\0303M\_ENG\DWG\PROPOSED DA.DWG