TEMPUS Infra Projects Pvt. Ltd. Chennai CONTRACT SUM: Rs. 23,38,28,194.00 LOI ref: SKCL/PROJ/INFINITE TOWERS/LOA; Dt: 09.04.2014 AS PER CONTRACT UPTO PREVIOUS MONTH CURRENT MONTH (RA 09) CUMULATIVE VALUE OF WORKDONE (INR) (INR) (INR) (INR) 1 Site Prepartion Works 1,53,038.00 1,32,630.40 - 1,32,630.40 2 Civil & Structural Works 841,05,385.00 287,78,288.61 104,52,924 392,31,213.00 3 Archtectural Works 356,96,110.00 - 44,263.44 44,263.44 4 Façade Works 173,75,779.00 - 5 Electrical Works 221,93,224.00 - 6 Diesel Generator System 75,42,638.00 - 7 IBMS Works 26,32,162.00 8 Plumbing & Sanitory Works 46,46,864.00 - 9 Fire Protection Works 54,09,832.00 - 10 HVAC Works 178,32,068.00 - 11 Elevator Works 90,80,000.00 - 12 External Works 59,05,314.00 - 13 Design & Authority Submission 41,28,000.00 7,30,859.15 - 7,30,859.15 14 NT Items 4,59,877.00 4,59,877.00 SUB TOTAL (A) 2167,00,414.00 296,41,778.16 109,57,065 401,38,965.99 ADD VAT / WCT 64,14,112.00 5,92,836.00 2,19,141 8,11,977.30 ADD Service Tax @ 4.944 % 107,13,668.00 14,65,489.00 5,41,717 20,07,206.29 ADD Excise Duty Included - - - ADD Other Taxes Included SUB TOTAL (B) 171,27,780.00 20,58,325.00 7,60,859 28,19,183.58 GRAND TOTAL (C)= (A + B) 2338,28,194.00 317,00,103.16 117,17,923 429,58,149.57 ADD Mobilization Advance 10% @ Contract Sum 233,82,819.00 - ADD Advance Payment against Steel Material Received at site 49,44,864.00 49,44,864.00 LESS Recovery of Advance Payment against Steel paid (39,49,261.00) (9,95,603.00) (49,44,864.00) SUB TOTAL ( D ) 9,95,603.00 -9,95,603 - NET VALUATION (E ) 326,95,706.16 107,22,320 429,58,149.57 LESS Rentention @ 5% of the Workdone Value ( I )= 5% X ( D + E) (15,85,005.16) (5,85,896) (21,70,901.33) LESS Deductions (20,00,000) (20,00,000.00) LESS Sum Previously Certified including RA-8 (K ) (311,10,701.00) (70,85,550.00) (311,10,701.00) SUB TOTAL ( L ) = (326,95,706.16) (96,71,446.17) (352,81,602.33) NET AMOUNT PAYABLE FOR THIS CLAIM 10,50,874.00 Contractor : TEMPUS INFRA PROJECTS PVT LTD Date : DESIGN & BUILD CONTRACT FOR THE PROPOSED INFINITE TOWER OFFICE DEVELOPMENT AT GUINDY,CHENNAI FOR M/S.SRI KAUSALYA CONSTRUCTIONS LIMITED,CHENNAI. S.No DESCRIPTION Authorized Signatory Infinite Tower_SKCL Page 1 of 1 Certificate - IT

description

bnn

Transcript of Draft RA Bill-09

  • TEMPUS Infra Projects Pvt. Ltd. Chennai

    CONTRACT SUM: Rs. 23,38,28,194.00 LOI ref: SKCL/PROJ/INFINITE TOWERS/LOA; Dt: 09.04.2014

    AS PER CONTRACTUPTO PREVIOUS

    MONTH

    CURRENT MONTH

    (RA 09)

    CUMULATIVE VALUE

    OF WORKDONE

    (INR) (INR) (INR) (INR)

    1 Site Prepartion Works 1,53,038.00 1,32,630.40 - 1,32,630.40

    2 Civil & Structural Works 841,05,385.00 287,78,288.61 104,52,924 392,31,213.00

    3 Archtectural Works 356,96,110.00 - 44,263.44 44,263.44

    4 Faade Works 173,75,779.00 -

    5 Electrical Works 221,93,224.00 -

    6 Diesel Generator System 75,42,638.00 -

    7 IBMS Works 26,32,162.00

    8 Plumbing & Sanitory Works 46,46,864.00 -

    9 Fire Protection Works 54,09,832.00 -

    10 HVAC Works 178,32,068.00 -

    11 Elevator Works 90,80,000.00 -

    12 External Works 59,05,314.00 -

    13 Design & Authority Submission 41,28,000.00 7,30,859.15 - 7,30,859.15

    14 NT Items 4,59,877.00 4,59,877.00

    SUB TOTAL (A) 2167,00,414.00 296,41,778.16 109,57,065 401,38,965.99

    ADD VAT / WCT 64,14,112.00 5,92,836.00 2,19,141 8,11,977.30

    ADD Service Tax @ 4.944 % 107,13,668.00 14,65,489.00 5,41,717 20,07,206.29

    ADD Excise Duty Included - - -

    ADD Other Taxes Included

    SUB TOTAL (B) 171,27,780.00 20,58,325.00 7,60,859 28,19,183.58

    GRAND TOTAL (C)= (A + B) 2338,28,194.00 317,00,103.16 117,17,923 429,58,149.57

    ADD Mobilization Advance 10% @ Contract Sum 233,82,819.00 -

    ADDAdvance Payment against Steel Material

    Received at site49,44,864.00 49,44,864.00

    LESSRecovery of Advance Payment against Steel

    paid(39,49,261.00) (9,95,603.00) (49,44,864.00)

    SUB TOTAL ( D ) 9,95,603.00 -9,95,603 -

    NET VALUATION (E ) 326,95,706.16 107,22,320 429,58,149.57

    LESSRentention @ 5% of the Workdone Value

    ( I )= 5% X ( D + E)(15,85,005.16) (5,85,896) (21,70,901.33)

    LESS Deductions (20,00,000) (20,00,000.00)

    LESS Sum Previously Certified including RA-8 (K ) (311,10,701.00) (70,85,550.00) (311,10,701.00)

    SUB TOTAL ( L ) = (326,95,706.16) (96,71,446.17) (352,81,602.33)

    NET AMOUNT PAYABLE FOR THIS CLAIM 10,50,874.00

    Contractor : TEMPUS INFRA PROJECTS PVT LTD

    Date :

    DESIGN & BUILD CONTRACT FOR THE PROPOSED INFINITE TOWER OFFICE DEVELOPMENT AT GUINDY,CHENNAI

    FOR M/S.SRI KAUSALYA CONSTRUCTIONS LIMITED,CHENNAI.

    S.No DESCRIPTION

    Authorized Signatory

    Infinite Tower_SKCL Page 1 of 1 Certificate - IT