DRAFT 06.03.09
Madison Valley Stormwater Project Phase 2
Seattle Design CommissionJune 4, 2009
Seattle City HallBoards and Commissions Room, L2-80
DRAFT 06.03.09
Three Stormwater Pipeline Alignment Options
BaselineBaseline Open-CutOpen-CutTrenchlessTrenchless
DRAFT 06.03.09
Selected Stormwater Pipeline Alignment
= Proposed shaft location = Stormwater pipeline
DRAFT 06.03.09
Existing Conditions in Washington Park
Looking toward southwest corner of Washington Park
Mixed-use building on E Madison St
E Madison St streetscape Batting cage and south slope from lower lawn
View down into site from E Madison St
DRAFT 06.03.09
Conceptual Landscape DetailsBALUSTRADE / ORNAMENTAL RAILING
Concrete or Cast Stone Balustrade
Metal Railing on Low Wall
Metal Railing on Curb
DRAFT 06.03.09
Conceptual Landscape DetailsEXISTING STORAGE TANK FACADE
Natural Stone
ShotcreteStone Work in Washington Arboretum Stone Veneer
Synthetic Stone
Stone Façade on Tank
Overlook with Ornamental Railing
Upper Lawn
Rain Garden and Drainage Grate
Sunken Lawn Meadow with Wooded Hillside Beyond