Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project
Dr. Prem Reddy Health Sciences Building - Project Construction Update - March 2015
-
Upload
justin-gatewood -
Category
Education
-
view
227 -
download
1
Transcript of Dr. Prem Reddy Health Sciences Building - Project Construction Update - March 2015
Structure steel beams set on columns for covered walkway
Stainless steel ducting at South end of cadaver
room.
Cat storage room
Anatomy & Physiology
lab
SIM Center foyer, with observation & control
rooms.
One of the simulation labs walls, with headwall
template and backing, and power conduits
installed
Another shot of Simulation Center foyer,
from opposite area.
Framed structure of one shade structure. Outside
Dean’s office
Support steel beams installed to main covered
walkway columns. Erected structure of tall shade structure to the
right.
East facing exterior of bld, north side.
Electrical room & exit foyer doors installed.
Masonry columns for northern covered
walkway
Looking down corridor 127, from faculty offices to
rotunda.
Main shut offs for HVAC hydronic piping. Inside
Maint. Rm 171
Corridor 127. Storefront framing for glass installed on left side wall along corridor.
Womens student restroom
Men’s student restooms. Overhead
piping.
Insulation installed at west wall nursing
fundamentals
Insulation for corridor 127, other side of wall is nursing
fundamental lab
Insulation installed at West wall of medical
supplies
Wall between utility room and beds & equipment rooms. Washer/dryer
hookups installed
South bldg, west side. Scaffold for framing of
soffits. Plywood sheathing installed to
sloped roof.
In wall plumbing for patient toilet (off Sim Lab)
Janitorial & Maintsupplies room
Trenching for underground conduits to pilasters for
lighting power.
Overhead duct & wall insulation installed in
Physical Science
Chemical balance lab, from exit foyer
Wall insulation, overhead work in Chemistry Lab
Drywall installed in corridor 127, north end
Drywall installed around doorway leading to faculty
offices
Fundamental lab observation room, with nursing fundamental lab
ahead
Overhead work & bracing for operable partition wall
Fundamentals Observation room
Inside hallway in faculty office area. Faculty offices
are getting drywall installed
Ground graded for concrete to be poured
between bldgs
Plumbing shut off valves (will have access panel) in
Cat storage
Workroom near Deans Office
Graded courtyard area, with shade structure
frame work
Landscapers trenching for irrigation, adjacent to
existing bldg
Perforated metal panels for installing at tops of
shade structures.
Electrical equipment installed inside electrical
room (north)
Overhead work, and wall insulation at hallway of
faculty offices
Nursing fundmentals.
Some of the faculty offices. Insulation &
Drywall being installed
Second floor mechanical area louver, PVC roofing
installed
Hydronic HVAC piping in mechanical area upstairs
Steel contractor welding at rotunda – Shields up to
protect others from arc flash
Ducting ran upstairs, decking installed above.
Plywood being fastened to decking on sloped roof,
south side
Looking down at courtyard from southern
roof top
Concrete curb poured along north face of bldg
Overhead piping across front lobby decking
Walls of utility room insulated and backing
installed
Insulation & drywall on walls of Beds &
Equipment. Overhead piping installed
Drywall up on west wall of nursing fundamental lab
Overhead work & drywall installed in chemistry lab
Drywall installed in exit foyer (from chem lab)
Metal decking going up on top of northen covered
walkway
Irrigation piping installed in trench.
Set up of forms for concrete pour in
courtyard.
Drywall along both sides of corridor 127 (north
end)
Trees delivered for installing around site
Deans Office
Study area alcove in corridor 134
Staff restroom
Forms for the color bands in courtyard concrete
Metal decking installed over main entry, and
partial rotunda
Exterior bldg. soffits framed out and lathed for
plaster
Mop sink in Custodian room
Stub outs for wall mounted drinking
fountain in vestibule
Second floor mechanical attic
Looking down on courtyard from roof.
Concrete poured
Glass installed along corridor 127
Metal decking installed on main covered walkway
Finish paint on walls in faculty office area.