Julian From: "Robert Pasternack" <[email protected]> Date: Thursday, July 10, 2014 3:10 PM To: "Doug Gill" <[email protected]> Attach: 014-15 WORK Deliverables_Final w Days Eliminated.docx Subject: FW: 014-15 WORK Deliverables_Final w Days Eliminated Page 1 of 3 8/7/2014 Doug This is the kind of communication that has made our work even more challenging This was JUST received from SPS, and is different from all the communication preceding this, indicative of our beginning Phase 2 of our work in August Give OSPI Approval of the RC-CAP and the need to EXECUTE the Plan approved, I am VERY concerned about this communique and the implication that things will be delayed until Sept, and there could be an interruption in our work with SPS I have asked that they amend our current Contract and add 1/11 th of the $450k we have agreed to for Phase 2, and see what response I get from them But I wanted to make you aware of my grave concern which has arisen after reading what I just received Sorry to trouble you with this, but given your intense interest in SPS, and your commitment to Targeted Monitoring of the RC- CAP, a delay until September (possibly longer) would not be helpful to the Execution of the RC-CAP you have approved Look forward to your advice Let me know if we should chat by phone about this The Honorable Robert H. Pasternack, Ph.D.; NCSP Chief Education Officer Accelify E: [email protected] C: 202-549-4621 From: Anderson, Jennifer R [mailto:[email protected]] Sent: Thursday, July 10, 2014 6:00 PM To: Robert Pasternack Cc: McWilliams, Zakiyyah B; Clancy, Michaela Subject: FW: 014-15 WORK Deliverables_Final w Days Eliminated Importance: High Bob, Thank you for the outline of the contract. I fully understand the enthusiasm to begin the contract as soon as possible however, I need to inform you that we will not have access to the funds until September 1 st . Since the Seattle Public Schools fiscal years begin in September, the Accounting Office will not be able to approve this contract until our FY2014-15 funds are accessible, probably late August. Another contributing factor to the anticipated delay is the contract amount is $450,000 we will need to have SPS Board approval

description

Dr Bob Complains to His OSPI Friend Doug Gill

Transcript of Dr Bob Complains to His OSPI Friend Doug Gill

Page 1: Dr Bob Complains to His OSPI Friend Doug Gill

Julian

From: "Robert Pasternack" <[email protected]>Date: Thursday, July 10, 2014 3:10 PMTo: "Doug Gill" <[email protected]>Attach: 014-15 WORK Deliverables_Final w Days Eliminated.docxSubject: FW: 014-15 WORK Deliverables_Final w Days Eliminated

Page 1 of 3

8/7/2014

Doug

This is the kind of communication that has made our work even more challenging

This was JUST received from SPS, and is different from all the communication preceding this, indicative of our beginning Phase 2

of our work in August

Give OSPI Approval of the RC­CAP and the need to EXECUTE the Plan approved, I am VERY concerned about this communique

and the implication that things will be delayed until Sept, and there could be an interruption in our work with SPS

I have asked that they amend our current Contract and add 1/11th of the $450k we have agreed to for Phase 2, and see what

response I get from them

But I wanted to make you aware of my grave concern which has arisen after reading what I just received

Sorry to trouble you with this, but given your intense interest in SPS, and your commitment to Targeted Monitoring of the RC­

CAP, a delay until September (possibly longer) would not be helpful to the Execution of the RC­CAP you have approved

Look forward to your advice

Let me know if we should chat by phone about this

The Honorable Robert H. Pasternack, Ph.D.; NCSPChief Education Officer

Accelify

E: [email protected]

C: 202­549­4621

From: Anderson, Jennifer R [mailto:[email protected]]

Sent: Thursday, July 10, 2014 6:00 PM

To: Robert Pasternack

Cc: McWilliams, Zakiyyah B; Clancy, Michaela

Subject: FW: 014­15 WORK Deliverables_Final w Days Eliminated

Importance: High

Bob,

Thank you for the outline of the contract.

I fully understand the enthusiasm to begin the contract as soon as possible however, I need to inform you that we will not have

access to the funds until September 1st. Since the Seattle Public Schools fiscal years begin in September, the Accounting Office

will not be able to approve this contract until our FY2014­15 funds are accessible, probably late August.

Another contributing factor to the anticipated delay is the contract amount is $450,000 we will need to have SPS Board approval

Page 2: Dr Bob Complains to His OSPI Friend Doug Gill

prior to us being able to execute the contract. Thus meaning we will need to have it presented to the C&I cabinet first, then

presented to the Board in August and approval on September 3rd.

Seeing as though the original contract runs through August 31, 2014 and we have only executed 2/3rds of the contract would it

be possible to estimate the cost of the August time and possibly add that amount, if it is not too much, to the current contract

and then subtract that amount from the initial amount of $450,000. If we go with this suggestion, we would not have to

withhold services, and just continue work as normal without delay.

Let me know what you think.

Jennifer AndersonSr. Cost [email protected](206) 252-0869FAX: (206) 252-0804

From: Klopfer, Pamela On Behalf Of McWilliams, Zakiyyah B

Sent: Thursday, July 10, 2014 10:56 AMTo: Anderson, Jennifer R

Subject: FW: 014-15 WORK Deliverables_Final w Days EliminatedImportance: High

For contract?

Pamela KlopferSenior Administrative AssistantSpecial Education DepartmentSeattle Public Schools(206) [email protected]

From: Robert Pasternack [mailto:[email protected]]

Sent: Thursday, July 10, 2014 10:51 AMTo: McWilliams, Zakiyyah B

Subject: 014-15 WORK Deliverables_Final w Days Eliminated

Importance: High

Good day Zakiyyah

Please find Attached the Scope of Work for Phase 2 regarding the RC­CAP

You will find the internal Project Management tool eliminated from this version, just showing the Scope; Activities; Deliverables;

and Timeline

Note that the Budget is the amount we have discussed, and the amount contained in the APPROVED RC­CAP

Page 2 of 3

8/7/2014

Page 3: Dr Bob Complains to His OSPI Friend Doug Gill

I await next steps and look forward to executing this Contract prior to the end of July so we can begin our work in August

THANKS for your help