Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg...

18
Double tracks between Hallsberg and Degerön

Transcript of Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg...

Page 1: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Double tracks betweenHallsberg and Degerön

Page 2: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Ten-T Core Network

Page 3: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Hallsberg

Hallsberg–Stenkumla

Stenkumla–Dunsjö

Dunsjö–Jakobshyttan

Jakobshyttan–Degerön

Jakobshyttan

Page 4: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

2019 2020 2021 2022 2023 2024 2025

Hallsberg

Hallsberg–Stenkumla

Stenkumla–Dunsjö

Dunsjö–Jakobshyttan

Jakobshyttan

Jakobshyttan–Degerön

2026 2027 2028

Page 5: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Hallsberg–Stenkumla

Page 6: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Design and Build Contract. Four bridges in the north.

Estimated cost: EUR 28 million.

Specifications will be publishedin the autumn

of 2021.

Hallsberg–Stenkumla

1stCONTRACT

2ndCONTRACT

3rdCONTRACT

4thCONTRACT

Design and Build Contract. Two bridges in the south.

Estimated cost: EUR 14 million.

Specifications will be published in the spring

of 2022.

Building contract. Two single track tunnels,

soil modificationsand smaller bridges.

Estimated cost: EUR 120 million.

Specifications will be published in the autumn

of 2021.

Building contract. BEST, MBEST Hallsberg

(holding sidings) and connection.

Estimated cost: EUR 140 million.

Specifications will be published in the spring

of 2022.

Page 7: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

13km tracks,

12 km in new terrain.

2,5km tunnel.

two single track tunnels.

Hallsberg–Stenkumla

1,5km rebuilding of

public roads.

Construction and service roads.

11bridges.

2km of rock excavation

Max 12–15 m high.High banks.

Rebuilding and extension of holding sidings.

Noise reduction barriersand screens.

Environmental measures.

Reading in existinginterlocking system, svt 95.

Page 8: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Hallsberg–Stenkumla

Soil from the tunnel, but big barriers: Highway 50, the Western Main Line and electric lines.

Connection to holding sidings.

Building of holding sidings in the Hallsberg rail yard.

Subdivisions to make traffic work during construction.

Two environmental sentences.

Environmentally protected area in the vicinity of the tunnel.

Page 9: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Dunsjö–Jakobshyttan

Page 10: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Dunsjö–Jakobshyttan

Design and Build Contract.

Estimated cost: EUR 33 million.

Specifications will be publishedin the spring of 2020.

1CONTRACT

Page 11: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Dunsjö–Jakobshyttan

3km of new track running

alongside the existing one.

2,5km of double tracks in new terrain.

260m tunnel (double tracks).

Lined tunnel.

Construction and service roads. 2

km of rock excavationMax 16 meters high.

Noise reduction barriers and screens.

Environmental measures.

Reading in existing interlockingsystem, svt 95.

Upgrading of signal box.

Complete design ofconstruction document.

Page 12: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Dunsjö–Jakobshyttan

Construction work within and alongside a line that is open to traffic.

Soil and rock handling in a narrow work area.

Groundwater impact.

Design and construction work incorporate all kinds of rail specific techniques.

Tunnel on turnkey contract.

Lined tunnel, not previously built in Sweden.

Page 13: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Jakobshyttan–Degerön

Page 14: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Jakobshyttan–Degerön

Design and Build Contract.

Estimated cost: EUR 71 million.

Specifications will be publishedin the summer of 2020.

1CONTRACT

Page 15: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Jakobshyttan–Degerön

5km of new track running

alongside the existing one.

6km of double tracks

in new terrain.

1km station withpassing loop.

3new roads,

in total 8 km.

Construction and service roads.

7bridges near the track.

3km of rock excavation

max 10 m high.

Noise reduction barriersand screens.

Environmental measures.

Complete design ofconstruction documents.

Page 16: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Jakobshyttan–Degerön

Construction works within and alongside a line that is open to traffic.

Recreation of meandering river channel.

Groundwater impact.

Design and construction work incorporate all kinds of rail specific techniques.

Page 17: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön
Page 18: Double tracks between Hallsberg and Degerön · 2019 2020 2021 2022 2023 2024 2025 Hallsberg Hallsberg–Stenkumla Stenkumla–Dunsjö Dunsjö–Jakobshyttan Jakobshyttan Jakobshyttan–Degerön

Thank you

Linda [email protected]

+46738172088