Don't Get the Shaft at Work
-
Upload
terry-penney -
Category
Documents
-
view
118 -
download
0
Transcript of Don't Get the Shaft at Work
Don't get the Shaft at Work
Or at least fall down one
P bar Y Safety Consultants Alberta Canada
Lighting in Shafts20 Lux Required for Erecting Scaffold200 Lux for Task Operations
ToeBoards at Each Boarded Lift where the Gapbetween the Scaffold and theWall is Greater than 75mm
It is Possible to Walk Under someShafts at Ground Level, in suchcases Physical Barriers (not just tape)and Warning signs Must be Erected.
Scaffold must beBraced or Tied to theWalls so there is noSway in any Direction
Guard RailBehind Door
Doors Fittedwhere Possible
Toeboard 1.5m
Double Handrails
CONSTRUCTED SHAFTNO WORK INSIDE
CONSTRUCTED SHAFTWORK IN PROGRESS
CONSTRUCTED SHAFTSCAFFOLDING
DANGEROPEN SHAFT
BEHIND DOORPermit to Access Required
site of a competent company manager who is familiar with safety alert re-work in shafts and who will inspect the operation.
Lift shafts and service duct riser entrances must be guarded by threeguard rails to a height of 1.5m plus toeboards and material guards as atemporary measure. Lift shafts and major risers entanceesshouldalways , where possible, be fitted with lockable temporary or permanentdoors with a guard rail behind and a notice stating “DANGER openshaft behind doors permit to access required”.
Tradesmen fixing doors to risers/shafts must work off harnesses unlessthere is a platform inside.
Shaft work must be co-ordinated using permits or marked up sketchesas appropriate.
One trade must not work above another in a shaft. If required, a permitsystem must be introduced together with physical sepatration by a crash deck.
Shafts
P bar Y Safety Consultants Alberta Canada
• Scaffolds erected within shafts MUST be constructed in full compliance with legislation:
– Double guardrails and toe-boards at each boarded lift where gap between scaffold and wall is >75 mm
– Scaffolds must be braced or tied to walls to prevent sway in any direction
Shafts
P bar Y Safety Consultants Alberta Canada
Unacceptable
P bar Y Safety Consultants Alberta Canada
• No scaffolder is to erect or remove a scaffold without the aid of a harness. This MUST be agreed with the contractor before work commences.
• A similar rule applies to ALL OTHER WORKERS where there is no guarded work platform.
• NO LONE WORKING will be allowed in or over shafts.• The practice of boarding over shafts and voids at every
other floor level MUST be discontinued.• Greater attention must be given to solidly fixed edge
protection - double guardrail and toe-board
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
• Lighting in shafts must be carefully considered during erection of scaffold and ongoing work.– 20 lux for erecting scaffold– 200 lux for task operations
• The safe provision of lighting MUST be arranged before any work commences.
• One trade MUST NOT work above another in a shaft.• Where there is any possibility of this happening, a permit
system MUST be introduced.• Physical barriers and warning signs MUST be erected
where it is possible to walk under a shaft at ground level.
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
• Lift shafts and major risers should be provided with lockable temporary or permanent doors.
• Where scaffold barriers are used as a short term measure, a minimum of 3 rails to a height of 1.5m and a toe-board must be solidly fixed.
• A minimum lighting level of 20 lux must be provided at all entrances to a shaft
• Carpenters and others fixing doors to shafts MUST work off harnesses unless there is a platform inside.
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
Unacceptable
P bar Y Safety Consultants Alberta Canada
Unacceptable
P bar Y Safety Consultants Alberta Canada
Unacceptable
P bar Y Safety Consultants Alberta Canada
Safety Information Sheet No 1.
Lift Shaft Protection - Paddington - The Point Kone Lifts Ltd have developed an integral steel frame and sliding door, as protection to lift shaft openings against unauthorised access. Where possible these should be installed by the contractor constructing the lift shaft core as soon as the formwork is struck so that the possibility of a fall of person is eliminated.
Steel frame and Sliding door bolted to reinforced concrete lift shaft core.
Warning notice stating Danger Lift Shaft and Keep Access Clear.
Sliding door lock.
Lift shaft sliding door in the open position showing the double guardrail behind, which is securely fixed to the doorframe.
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
• Working in a riser or shaft must be controlled by a permit system.
• Weekly co-ordination meetings must decide who will work within a shaft at any one time to prevent one trade working above another.
• The shaft needs to be dedicated to one trade in writing and marked on a layout plan distributed to all contractors.
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
Permit to Access
• A procedure must be established to prevent operatives working below each other UNLESS the shaft is fitted with a substantial crash deck to provide safe separation.
• Harnesses must be used, attached to the structure or other proved anchor point where there is a risk of falling.
• Contractor working in the shaft will be responsible for the integrity of any edge protection provided.
• Contractors method statement must be carefully checked before approval is given.
• Consider the possibility of the shaft being a confined space.
Working in Riser Shafts etc.
P bar Y Safety Consultants Alberta Canada
Safety Information Sheet No 6.
Method of Installation of Ducting in the Air-conditioning Duct. Paddington - The Point
Rising Duct protected by a double handrail and toe board. Duct void covered by plywood panels, as size of ducts to be installed, supported by metal angle fixed to the sides of the concrete riser.
Underside of plywood panels as size of ducts to be installed supported by metal angle fixed to the sides of the concrete riser. The angle supports have been designed and positioned to support the ductwork when installed.
Safety Information Sheet No 4.
Designed Scaffold Fitting for Fixing Handrails in Riser Duct Reveals Lyndon Scaffolding Ltd. have designed the scaffold fitting shown in the photographs as a robust way of fixing double handrails into the reveal opening of a rising duct.
Double handrail and toe board in front of rising duct.
Designed scaffold fitting.
Designed scaffold fitting.
Scaffold fitting designed by Lyndon Scaffolding Ltd. to fix handrail into a reveal.
Angle slightly less than 900
When the handrail is fixed in the fitting the angle tightens into the reveal. The fittings have been tested to 0.5 Tonnes
P bar Y Safety Consultants Alberta Canada
Page 1
Ductwork installed in the rising duct.
Duct work being installed through the rising duct. Work is under a permit to
work system. Operatives working in the riser
duct wear a safety harness attached back to the handrail.
Relevant plywood removed and ductwork installed in its place.
Ductwork secured to the metal angle that was supporting the plywood panels.
P bar Y Safety Consultants Alberta Canada
1. The objective of the riser shaft co-ordinator is to ensure that only one contractor works in a riser shaft at any one time, unless special engineered crash decks are provided between work operations on a high shaft. Two contractors working on the same level may also be acceptable but this must be strictly controlled with permits.
2. A regular meeting should be held with the contractors requiring access and the risers allocated to specific contractors. This should be immediately marked on a plan or noted in minutes that can be taken away from the meeting, and a permit issued.
Duties Of Riser Shaft Co-ordinator
P bar Y Safety Consultants Alberta Canada
3. The riser shaft co-ordinator should understand the subcontracting arrangements of the contractors, and verify that they have arrangements in place to control access to subcontractors such that one will not be working above the other. Spot checks should be made.
4. On appointment the riser shaft co-ordinator must read carefully safety memorandum 10.03 - Working in Riser Shafts at extreme height.
5 The riser shaft co-ordinator must make arrangements to ensure compliance with safety memorandum 10.03, including daily monitoring.
Duties Of Riser Shaft Co-ordinator
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
Holes up to 600mm wide (any length) are to have A142 structural mesh cast across the hole and a flush 20mm ply covering, with a ‘HOLE UNDER’ notice. Mesh only to be cut as needed to allow services to pass. One square of mesh to be embedded into slab all the way around the hole.
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
Holes 600mm wide - 2 m wide (any length) are to have A142 structural mesh cast across the hole and a full scaffold deck at every floor level, firmly fixed down.
P bar Y Safety Consultants Alberta Canada
Holes over 2m wide are to have a double handrail and toeboard all round and a personnel net and debris net at every second floor.
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
P bar Y Safety Consultants Alberta Canada
• All edge protection and hole coverings inspected daily.
• Inspection by contractor responsible for hole maintenance.
• Spot checks by site managers.
• Written Handover procedure implemented when contractor ceases to be responsible for maintenance of holes.
Protection of Holes
P bar Y Safety Consultants Alberta Canada
If you have any questions, If you have any questions, please ask your supervisorplease ask your supervisor
P bar Y Safety Consultants Alberta Canada