Potential Planning that’s not MEDL
• Flagstaff Trails Initiative (FTI) flagstafftrailsinitiative.org/
Trails (and related infrastructure) Planning process
• Idea! This can come from Internally or externally
• Investigation and vetting of the idea
• Prioritization – Internal decision to move forward with the idea
• NEPA- National Environmental Policy Act (the environmental review)
• Decision to accept/change/reject idea founded in the Enviro Analysis
• Implement (need $ and people time)
Construction Costs & construction timelines
• Conservation crew - $6500 for 4 days/ $13K for 8 days
• Heart Trail- Total cost of around 200K for 5 miles of trail
• Timelines- It Depends! On trail class and landscape
• Good soil/terrain = 500’ w/ 5 people in a day.
• Steep rocky terrain = maybe 50’ w/ 8 people on a good day.