DOE/SC CD-1/3a Review · 2017-11-30 · DOE/SC CD-1/3a Review of the High Luminosity LHC...
Transcript of DOE/SC CD-1/3a Review · 2017-11-30 · DOE/SC CD-1/3a Review of the High Luminosity LHC...
OFFICE OF
SCIENCE
DOE/SC CD-1/3a Reviewof the
High Luminosity LHC Accelerator
Upgrade Project (HL-LHC AUP)
Fermi National Accelerator LaboratoryAugust 8-10, 2017
Kurt Fisher
Committee Chair
Office of Science, U.S. Department of Energy
http://www.science.doe.gov/opa/
OFFICE OF
SCIENCE
2
Deliverables – Due Dates
• Closeout report (prepared in PowerPoint)
• Presented Thursday, August 10
• Instructions—slide 13
• Template—slide 15
• Final report draft (prepared in MS Word)
• Due Monday, August 14 to Casey
• Instructions—slide 14
OFFICE OF
SCIENCE
3
DOE EXECUTIVE SESSION AGENDA
Tuesday, August 8, 2017—Wilson Hall, Comitium (WH2SE)
8:00 a.m. DOE Executive Session K. Fisher
8:15 a.m. Program Perspective S. Rolli
8:30 a.m. Federal Project Director Perspective J. Kao
8:40 a.m. Questions
8:45 a.m. Adjourn
DOE Executive Session
Project and review information is available at:
https://web.fnal.gov/organization/OPSS/Projects/HL-LHCAcceleratorUpgradeProject/_layouts/15/start.aspx#/SitePages/DOE%20CD-
1%20-%203a%20Review%20of%20HL-LHC%20Accelerator%20Upgrade%20Project%2C%20August%208-10%2C%202017.aspx
OFFICE OF
SCIENCEReview Committee
Participants
4
Kurt Fisher, DOE/SC, Chairperson
SC1 SC2
Magnets Crab Cavities
* Mark Bird, FSU * Ali Nassiri, ANL
Luisa Chiesa, Tufts Cynthia Keppel, TJNAF
Nicolai Martovetsky, ORNL Joe Preble, TJNAF
SC3 SC4
Cost and Schedule Project Management and ES&H
* Frank Gines, DOE/ASO * Jon Kotcher, BNL
Penka Novakova, BNL Mark Reichandter, SLAC
Katie Martin, ANL Ken Fouts, SLAC
Angus Bampton, PNNL
Observers LEGEND
Mike Procario, DOE/HEP SC Subcommittee
Simona Rolli, DOE/HEP * Chairperson
Jerry Kao, DOE/ASO
Carrie Sauter, ANL Count: 14 (excluding observers)
OFFICE OF
SCIENCE
5
CD-1
Delegation Allowed
S-4 SC-1 SC-1 SC-AD SC-AD SC-AD
Approve Acquisition StrategyReviewed by SC-28
Approved by SC-1
Reviewed by SC-28
Approved by SC-1
Reviewed by SC-28
Approved by SC-2
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Approve Preliminary Project Execution Plan (PEP) S-4 Reviewed by SC-28
Approved by SC-1
Reviewed by SC-28
Approved by SC-2
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Appointment of the Federal Project Director (FPD) S-4 SC-1 SC-1 SC-AD SC-AD SC-AD
Approve Integrated Project Team (IPT) S-4 SC-1 SC-2 SC-AD SC-AD SC-AD
Develop a Risk Management Plan Project Project Project Project Project Project
Comply with the One-for-One Building Space Replacement Project Project Project Project Project Project
Complete a Conceptual Design Project Project Project Project Project Project
Document High Perf. & Sustainable Bldg. & Sustainable
Env. Stewardship considerationsProject Project Project Project Project Project
Conduct a Conceptual Design Review Team external to project Team external to project Team external to project Team external to project Team external to project Team external to project
Complete a Conceptual Design Report Project Project Project Project Project Project
Prepare a Preliminary Hazard Analysis Report Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Develop and Implement an Integrated Safety Management
PlanSite Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Establish Preliminary Quality Assurance Program (QAP) Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Identify general Safeguards and Security requirements for
the recommended alternativeSite Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Complete National Environmental Policy Act
(NEPA)Strategy by issuing a determination (i.e., EIS, EA)Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Conduct Independent Project Review or External
Independent Review
ICE or ICR by PM
& SC-28
ICE or ICR by PM
& SC-28
ICE or ICR by APM
with SC-28SC-28
SC-28
Tailored
SC-28
Tailored
Update PDS, or other funding documents for MIE and OE
projects, and OMB 300s, if applicable.SC-AD SC-AD SC-AD SC-AD SC-AD SC-AD
Hazard Cat. 1,2,3 Nuclear Facility--Update Safety Design
Strategy (SDS)
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
Hazard Category 1, 2, and 3 nuclear facilities, conduct an
Independent Project Review (IPR)PSO PSO PSO PSO PSO PSO
Hazard Cat. 1,2,3 Nuclear Facility--Prepare a Conceptual
Safety Design Report (CSDR)SBAA via the CSVR SBAA via the CSVR SBAA via the CSVR SBAA via the CSVR SBAA via the CSVR SBAA via the CSVR
Hazard Cat. 1,2,3 Nuclear Facility--Prepare Conceptual
Safety Validation Report (CSVR)SBAA SBAA SBAA SBAA SBAA SBAA
Hazard Cat. 1,2,3 Nuclear Facility--Initiate a Code of
RecordProject Project Project Project Project Project
Submit approved CD or equivalent documents to APM SC-28 SC-28 SC-28 SC-28 SC-28 SC-28
Allow expenditure of PED, MIE OR OE funds for project
design. Project Project Project Project Project Project
Submit budget request for the remainder of TPC if CD-2 is
approved w/i 1 year of OMB submissionSC-AD SC-AD SC-AD SC-AD SC-AD SC-AD
Update PARS II with monthly statusProg. Mgr. & FPD
No Earned Value (EV)
Prog. Mgr. & FPD
No Earned Value (EV)
Prog. Mgr. & FPD
No Earned Value (EV)
Prog. Mgr. & FPD
No Earned Value (EV)
Prog. Mgr. & FPD
No Earned Value (EV)
Prog. Mgr. & FPD
No Earned Value (EV)
Continue with Monthly or Quarterly Project
Reporting/Meeting
SC-AD
Invite SC-1 and SC-28
SC-AD
Invite SC-1 and SC-28
SC-AD
Invite SC-2 and SC-28SC-AD to invite SC-28 SC-AD to invite SC-28 SC-AD to invite SC-28
Develop an Acquisition Plan if applicable
Hazard Cat. 1,2,3 Nuclear Facility--Develop a Checkout,
Testing & Commissioning Plan Project Project Project Project Project Project
PO
ST
CD
-1
CD-1--APPROVE ALTERNATIVE SELECTION AND
COST RANGE
PR
IOR
TO
CD
-1--
CO
NC
EP
TU
AL
DE
SIG
N
TOTAL PROJECT COST (TPC) $750M or more Less than $750M to $400M Less than $400M to $100M Less than $100M to $50M* Less than $50M* to $20M Less than $20M to $10M**
DECISION / REQUIREMENTS1 / APPROVAL2
Nu
cle
ar
Fa
cili
tyN
ucl
OFFICE OF
SCIENCE
6
CD-3
Delegation Allowed
SC-1 SC-1 SC-2 SC-AD SC-AD SC-AD
Approve updated CD-2 Project Documentation (PEP, AS,
PDS, etc) if major changes
Reviewed by SC-28
Approved by SC-1
Reviewed by SC-28
Approved by SC-1
Reviewed by SC-28
Approved by SC-2
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Reviewed by SC-28
Approved by SC-AD
Complete Final Design Project Project Project Project Project Project
Incorporate High Performance & Sustainable Bldg. &
Sustainable Env. Stewardship Project Project Project Project Project Project
Conduct a Final Design Review Team external to project Team external to project Team external to project Team external to project Team external to project Team external to project
Complete Final Design Report Project Project Project Project Project Project
Employ a certified EVMS compliant with ANSI/EIA-748A, or
as defined in the contract Certified by SC-28 Certified by SC-28 Certified by SC-28 Certified by SC-28 Contractor N/A
Execution Readiness ReviewICE or ICR by PM if warranted
or IPR by SC-28
ICE or ICR by PM if warranted
or IPR by SC-28
ICE or ICR by PM if warranted
or IPR by SC-28 SC-28 SC-28 SC-28
Conduct a Technology Readiness Assessment, where
significant CTE modification occursN/A N/A N/A N/A N/A N/A
Update the Hazard Analysis Report Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Prepare Construction Project Safety and Health Plan Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Update the Quality Assurance Program Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Finalize the Security Vulnerability Assessment Report, if
necessarySite Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab Site Office or Lab
Hazard Cat. 1,2,3 Nuclear Facility--Update Safety Design
Strategy (SDS)
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
SBAA & FPD, w/ CNS or
CDNS concurrence, as
appropriate
Hazard Cat. 1,2,3 Nuclear Facility--Prepare a Preliminary
Documented Safety Analysis 4 that updates the PSDRSBA Authority via the SER SBA Authority via the SER SBA Authority via the SER SBA Authority via the SER SBA Authority via the SER SBA Authority via the SER
Hazard Cat. 1,2,3 Nuclear Facility--Prepare a Safety
Evaluation Report (SER)SBAA w/ FPD concurrence SBAA w/ FPD concurrence SBAA w/ FPD concurrence SBAA w/ FPD concurrence SBAA w/ FPD concurrence SBAA w/ FPD concurrence
Hazard Cat. 1,2,3 Nuclear Facility--Revise the Code of
RecordProject Project Project Project Project Project
Submit approved CD or equivalent documents to APM. If
applicable, any PB BCP to APMSC-28 SC-28 SC-28 SC-28 SC-28 SC-28
Allow expenditure of TPC funds. Update budget document
and OMB 300s if applicable.SC-AD SC-AD SC-AD SC-AD SC-AD SC-AD
Update PARS II with monthly statusProg. Mgr., FPD, and
Contractor
Prog. Mgr., FPD, and
Contractor
Prog. Mgr., FPD, and
Contractor
Prog. Mgr., FPD, and
Contractor
Prog. Mgr., FPD, and
Contractor
Prog. Mgr. & FPD
No Earned Value (EV)
Continue with Monthly or Quarterly Project
Reporting/Meeting
SC-AD
Invite SC-1 and SC-28
SC-AD
Invite SC-1 and SC-28
SC-AD
Invite SC-2 and SC-28SC-AD to invite SC-28 SC-AD to invite SC-28 SC-AD to invite SC-28
Perform EVMS surveillance review Bi-annually by SC-28
Annually by Contractor
Bi-annually by SC-28
Annually by Contractor
Bi-annually by SC-28
Annually by Contractor
Bi-annually by SC-28
Annually by ContractorAnnually by Contractor N/A
Submit Lessons Learned regarding up-front planning and
design 90 days after CD-3FPD FPD FPD FPD FPD FPD
SC-AD Request Annual Project Peer Review by PMSO SC-28 SC-28 SC-28 SC-28 SC-28
Tailored
SC-28
Tailored
CD-3--APPROVE START OF CONSTRUCTION
PR
IOR
TO
CD
-3--
FIN
AL
DE
SIG
NP
OS
T C
D-3
TOTAL PROJECT COST (TPC) $750M or more Less than $750M to $400M Less than $400M to $100M Less than $100M to $50M* Less than $50M* to $20M Less than $20M to $10M**
DECISION / REQUIREMENTS1 / APPROVAL2
Nu
cle
ar
Fa
cil
ity
OFFICE OF
SCIENCE
7
SC Organization
OFFICE OF
SCIENCE
8
Charge Questions
1. Does the acquisition strategy document a carefully considered analysis of
alternatives that supports the preferred alternative?
2. Does the conceptual design satisfy the performance requirements? Does the
conceptual design report and supporting documentation adequately justify the
stated cost range and project duration? Is the need, technical justification and
schedule justification sufficient to approve early materials procurement?
3. Does the proposed project team have adequate management experience, design
skills, and laboratory support to produce a credible technical, cost, and schedule
baseline?
4. Are the ES&H aspects of the project being properly addressed and is the ES&H
planning currently sufficient for this stage of the project?
5. Is the documentation required by DOE O413.b for CD-1 approval complete and in
good order?
OFFICE OF
SCIENCE
9
Agenda
Tuesday, August 8, 2017—Wilson Hall, Comitium (WH2SE)
8:00 am DOE Full Committee Executive Session Fisher
8:45 am Fermilab Welcome – One West (WH1W) Lockyer
8:50 am U.S. Contribution to HL-LHC Project Rossi
9:20 am HL-LHC AUP: Project Overview Apollinari
10:05 am HL-LHC AUP in Fermilab Context Belomestnykh
10:13 am HL-LHC AUP in BNL Context Lissauer
10:21 am HL-LHC AUP in LBNL Context Leemans
10:30 am Break – Outside of One West
10:45 am 302.1 - Project Management Carcagno
11:10 am 302.1 - 2 Magnet System Ambrosio
11:50 am 302.1 – 3 Crab Cavities Ristori
12:10 pm Lunch – 2nd Floor Crossover
1:00 pm Reviewers/Observers Photo – 1st Floor Atrium
1:10 pm Subcommittee Breakout Sessions
Breakout 1a – Magnets – Black Hole (WH2NW)
Breakout 1b – Management – Comitium (WH2SE)
Breakout 1c – Crab Cavities and CD-3a Drill-Down– Snake Pit (WH2NE)
2:45 pm Break – Outside of Comitium
3:00 pm Subcommittee Breakout Sessions (cont)
5:15 pm DOE Full Committee Executive Session
6:00 pm Adjourn
OFFICE OF
SCIENCE
10
Agenda (cont’d)
Wednesday, August 9, 2017
8:30 am LARP as Precursor for HL-LHC AUP - Curia II (WH2SW) Sabbi
9:00 am CD-3a Needs for Strand Procurement Apollinari
9:25 am CD-3a Functional and Technical Readiness Ambrosio
9:55 am CD-3a Procurement and QA Readiness Cooley
10:30 am Break – Outside of Curia II
10:45 am Tour of TD Magnet Assembly Site – Meet Buses in front of Wilson Hall
12:00 pm Lunch – Outside Comitium for Reviewers and Observers
1:00 pm Q&A Session, Executive Session – Comitium (WH2SE)
2:45 pm Break – Outside of Comitium
3:00 pm DOE Full Committee Executive Session, Initial Report Writing
Thursday, August 10, 2017
8:00 am Exec Session/Q&A Follow up/Report Writing – Comitium (WH2SE)
10:00 am Break – Outside of Comitium
10:15 am DOE Full Committee Executive Session/Dry Run
12:00 pm Lunch – Box Lunches Provided for Reviewers and Observers
1:00 pm Close-Out Presentation – Curia II (WH2SW)
2:00 pm Adjourn
OFFICE OF
SCIENCE
11
Report Outline/Writing
Assignments
Executive Summary .....................................................................................................Fisher
1. Introduction ....................................................................................................... Lavine*
2. Technical Systems Evaluation (Charge Questions 1, 2, 3, 5)
2.1 Magnets ............................................................................................... Bird*/SC-1
2.1.1 Findings
2.1.2 Comments
2.1.3 Recommendations
2.2 Crab Cavities ................................................................................... Nassiri*/SC-2
3. Cost and Schedule (Charge Questions 1, 2, 3, 5) ....................................... Gines*/SC-3
4. Project Management and ES&H (Charge Questions 1, 3, 4, 5) .............. Kotcher*/SC-4
*Lead
OFFICE OF
SCIENCE
12
Closeout Presentation
and Final Report
Procedures
OFFICE OF
SCIENCE
13
Format:
Closeout Presentation
OFFICE OF
SCIENCE
14
Format:
Final Report
Please Note: Recommendations are approved by the full committee and presented at the review closeout briefing.
Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report.
(Use MS Word / 12pt Font)
2.1 Use Section Number/Title corresponding to writing assignment list.
2.1.1 Findings – What the project told us
Include a brief narrative description of technical, cost, schedule, management information
provided by the project. Each subcommittee will emphasize their area of responsibility.
2.1.2 Comments – What we think about what the project told us
Descriptive material assessing the findings and making observations and conclusions
based on the findings. The committee’s answer to the charge questions should be
contained within the text of the Comments Section. Do not number your comments.
2.1.3 Recommendations – What we think the project needs to do
1. Beginning with an action verb, provide a brief, concise, and clear statement with a due date.
2.
Cost and schedule subcommittee should provide attachments for approved project cost breakdown and schedule. Management
subcommittee should provide attachment for approved project organization and names of personnel.
OFFICE OF
SCIENCE
15
Closeout Report on the
DOE/SC CD-1/3a Review of the
High Luminosity LHC Accelerator
Upgrade Project (HL-LHC AUP) Fermi National Accelerator Laboratory
August 8-10, 2017
Kurt Fisher
Committee Chair
Office of Science, U.S. Department of Energy
http://www.science.doe.gov/opa/
OFFICE OF
SCIENCE
16
2.1 Magnets
M. Bird, FSU / Subcommittee 1
• Findings
• Comments
• Recommendations
1. Does the acquisition strategy document a carefully considered analysis of
alternatives that supports the preferred alternative?
2. Does the conceptual design satisfy the performance requirements? Does the
conceptual design report and supporting documentation adequately justify the
stated cost range and project duration? Is the need, technical justification and
schedule justification sufficient to approve early materials procurement?
3. Does the proposed project team have adequate management experience, design
skills, and laboratory support to produce a credible technical, cost, and schedule
baseline?
5. Is the documentation required by DOE O413.b for CD-1 approval complete and
in good order?
OFFICE OF
SCIENCE
17
2.2 Crab Cavities
A. Nassiri, ANL / Subcommittee 2
• Findings
• Comments
• Recommendations
1. Does the acquisition strategy document a carefully considered analysis of
alternatives that supports the preferred alternative?
2. Does the conceptual design satisfy the performance requirements? Does the
conceptual design report and supporting documentation adequately justify the
stated cost range and project duration? Is the need, technical justification and
schedule justification sufficient to approve early materials procurement?
3. Does the proposed project team have adequate management experience, design
skills, and laboratory support to produce a credible technical, cost, and schedule
baseline?
5. Is the documentation required by DOE O413.b for CD-1 approval complete and
in good order?
OFFICE OF
SCIENCE
18
3. Cost and ScheduleF. Gines, DOE/ASO / Subcommittee 3
1. Does the acquisition strategy document a carefully considered analysis of
alternatives that supports the preferred alternative?
2. Does the conceptual design satisfy the performance requirements? Does the
conceptual design report and supporting documentation adequately justify the
stated cost range and project duration? Is the need, technical justification and
schedule justification sufficient to approve early materials procurement?
3. Does the proposed project team have adequate management experience, design
skills, and laboratory support to produce a credible technical, cost, and schedule
baseline?
5. Is the documentation required by DOE O413.b for CD-1 approval complete and
in good order?
• Findings
• Comments
• Recommendations
OFFICE OF
SCIENCE
19
3. Cost and ScheduleF. Gines, DOE/ASO / Subcommittee 3
PROJECT STATUS
Project Type MIE / Line Item / Cooperative Agreement
CD-1 Planned: Actual:
CD-2 Planned: Actual:
CD-3 Planned: Actual:
CD-4 Planned: Actual:
TPC Percent Complete Planned: _____% Actual: _____%
TPC Cost to Date
TPC Committed to Date
TPC
TEC
Contingency Cost (w/Mgmt Reserve) $ _____% to go
Contingency Schedule on CD-4b ______months _____%
CPI Cumulative
SPI Cumulative
OFFICE OF
SCIENCE
20
4. ManagementJ. Kotcher, BNL / Subcommittee 4
1. Does the acquisition strategy document a carefully considered analysis of
alternatives that supports the preferred alternative?
3. Does the proposed project team have adequate management experience, design
skills, and laboratory support to produce a credible technical, cost, and schedule
baseline?
4. Are the ES&H aspects of the project being properly addressed and is the ES&H
planning currently sufficient for this stage of the project?
5. Is the documentation required by DOE O413.b for CD-1 approval complete and
in good order?
• Findings
• Comments
• Recommendations