ID Task Name Duration Start Finish 1 Proposed A &A to Existing 5 Story Main Library Building and 4-Story Library Annex Building (phase one) at Singapore polytechnic 219 days Wed 7/1/15 Sat 4/30/16 3 Preliminaries 11 days Wed 7/1/15 Wed 7/15/15 4 Award of Contract 1 day Wed 7/1/15 Wed 7/1/15 5 Purchase of insurance 2 wks Thu 7/2/15 Wed 7/15/15 6 Submission of Equipment / Drawing Submission Schedule 2 wks Thu 7/2/15 Wed 7/15/15 8 Design Stage 30 days Thu 7/2/15 Wed 8/12/15 9 Submission of Mobilization Plan 1 day Thu 7/2/15 Thu 7/2/15 10 Mobilization of site setting up/safety 2 wks Thu 7/2/15 Wed 7/15/15 11 Submission of necessary(Demolition/ Structure) plan for approval 1 wk Thu 7/2/15 Wed 7/8/15 12 Approval of Demolition/ Structure Plan 2 wks Thu 7/9/15 Wed 7/22/15 13 Selection of Material Sample - Phase 2 wks Thu 7/16/15 Wed 7/29/15 14 Submission of Equipment/ Shop Drawings for Approval 2 wks Thu 7/16/15 Wed 7/29/15 15 Approval of equipment 2 wks Thu 7/30/15 Wed 8/12/15 17 Site Construction 185 days Thu 7/9/15 Wed 3/23/16 19 Phase 1(Zones involve in Colours) 40 days Thu 7/9/15 Wed 9/2/15 20 Demolition Works 1 wk Thu 7/9/15 Wed 7/15/15 21 Architectural/Building work - Phase 1 5 wks Thu 7/16/15 Wed 8/19/15 22 M&E Works 2 wks Thu 8/20/15 Wed 9/2/15 23 Fire protection Works 2 wks Thu 8/20/15 Wed 9/2/15 24 Phase 2 ( Zones involve in 1st Story AHUs 1-1,1-2 & stairs 1,Event Space, Wonderland, Café &Reading Area2, 1st story Counter &staircase 3 Colours ) 50 days Thu 9/3/15 Wed 11/11/15 25 Demolition Works 1 wk Thu 9/3/15 Wed 9/9/15 26 Architectural/Building work - Phase 2 4 wks Thu 9/10/15 Wed 10/7/15 27 M&E Works 2 wks Thu 10/8/15 Wed 10/21/15 28 Fire protection Works 2 wks Thu 10/8/15 Wed 10/21/15 29 Finishing work and Furniture Works 3 wks Thu 10/22/15 Wed 11/11/15 30 Phase 3(Zones involve in Colours, Reading Area 5, Return Mahine, Reading Area 4 Exhiition Area Collaborative Zone, mobile Counter, Turnstile Entrance, new Arivals Area, materials Library, reading Area &Gallery) 50 days Thu 11/12/15 Wed 1/20/16 31 Demolition Works 1 wk Thu 11/12/15 Wed 11/18/15 32 Architectural/ Building work - Phase 3 4 wks Thu 11/19/15 Wed 12/16/15 33 M&E Works 2 wks Thu 12/17/15 Wed 12/30/15 34 Fire protection Works 2 wks Thu 12/17/15 Wed 12/30/15 35 Finishing work and Furniture Works 3 wks Thu 12/31/15 Wed 1/20/16 36 Phase 4(Entrance lobby, multimedia Room,kinect rooms, media viewing & Reading Area) 35 days Thu 1/21/16 Wed 3/9/16 37 Demolition Works 1 wk Thu 1/21/16 Wed 1/27/16 38 Architectural/Building work - Phase 4 2 wks Thu 1/28/16 Wed 2/10/16 39 M&E Works 2 wks Thu 2/11/16 Wed 2/24/16 40 Fire protection Works 2 wks Thu 2/11/16 Wed 2/24/16 41 Finishing work and Furniture Works 2 wks Thu 2/25/16 Wed 3/9/16 42 Phase X( Unphased works:- Zones involve in Generator Rooms, Horse reel Tank Rooms, Apron Walkway, Courtyard 2nd story 7linkway, Annex Staircase 4, Annex Stair case 5, Slab over of Stair case 3, lift lobby, Stair Case 1&2, magazine drawers, directors'Room) 175 days Thu 7/23/15 Wed 3/23/16 43 Demolition Works 3 wks Thu 7/23/15 Wed 8/12/15 44 Architectural/building work - Phase X 17 wks Thu 8/13/15 Wed 12/9/15 45 M&E Works 10 wks Thu 12/10/15 Wed 2/17/16 46 Fire protection Works 10 wks Thu 12/10/15 Wed 2/17/16 47 Finishing works 5 wks Thu 2/18/16 Wed 3/23/16 48 Hand Over 28 days Thu 3/24/16 Sat 4/30/16 49 Testing And Commissioning 1 wk Thu 3/24/16 Wed 3/30/16 50 BCA/ FSSD submission 2 wks Thu 3/31/16 Wed 4/13/16 51 Maintenance serving DLP 2 wks Thu 3/31/16 Wed 4/13/16 52 OMM and Warranty 2 wks Tue 4/19/16 Sat 4/30/16 9/2 11/11 1/20 3/9 3/23 Must Finished the Full height Glass works by others before do the ME works! at Entrance lobby Kinect Rooms 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Baseline Baseline Milestone Baseline Summary Progress Deadline Proposed A & A to Existing 5 Story Main Library Building and 4-Story Library Annex Building (phase one) at Singapore polytechnic Master Schedule Page 1 Project: Project Schedule - SP library Date: Thu 6/11/15

description

A2

Transcript of Document(s) A2

Page 1: Document(s) A2

IDTask Name

Duration Start Finish

1 Proposed A &A to Existing 5 Story Main

Library Building and 4-Story Library Annex

Building (phase one) at Singapore

polytechnic

219 days Wed7/1/15

Sat4/30/16

3 Preliminaries 11 days Wed 7/1/15 Wed 7/15/154 Award of Contract 1 day Wed 7/1/15 Wed 7/1/15

5 Purchase of insurance 2 wks Thu 7/2/15 Wed 7/15/15

6 Submission of Equipment / Drawing Submission Schedule 2 wks Thu 7/2/15 Wed 7/15/15

8 Design Stage 30 days Thu 7/2/15 Wed 8/12/159 Submission of Mobilization Plan 1 day Thu 7/2/15 Thu 7/2/15

10 Mobilization of site setting up/safety 2 wks Thu 7/2/15 Wed 7/15/15

11 Submission of necessary(Demolition/ Structure) plan for approval 1 wk Thu 7/2/15 Wed 7/8/15

12 Approval of Demolition/ Structure Plan 2 wks Thu 7/9/15 Wed 7/22/15

13 Selection of Material Sample - Phase 2 wks Thu 7/16/15 Wed 7/29/15

14 Submission of Equipment/ Shop Drawings for Approval 2 wks Thu 7/16/15 Wed 7/29/15

15 Approval of equipment 2 wks Thu 7/30/15 Wed 8/12/15

17 Site Construction 185 days Thu 7/9/15 Wed 3/23/1619 Phase 1(Zones involve in Colours) 40 days Thu 7/9/15 Wed 9/2/15

20 Demolition Works 1 wk Thu 7/9/15 Wed 7/15/15

21 Architectural/Building work - Phase 1 5 wks Thu 7/16/15 Wed 8/19/15

22 M&E Works 2 wks Thu 8/20/15 Wed 9/2/15

23 Fire protection Works 2 wks Thu 8/20/15 Wed 9/2/15

24 Phase 2 ( Zones involve in 1st Story AHUs 1-1,1-2 &

stairs 1,Event Space, Wonderland, Café &Reading

Area2, 1st story Counter &staircase 3 Colours )

50 days Thu 9/3/15 Wed 11/11/15

25 Demolition Works 1 wk Thu 9/3/15 Wed 9/9/15

26 Architectural/Building work - Phase 2 4 wks Thu 9/10/15 Wed 10/7/15

27 M&E Works 2 wks Thu 10/8/15 Wed 10/21/15

28 Fire protection Works 2 wks Thu 10/8/15 Wed 10/21/15

29 Finishing work and Furniture Works 3 wks Thu 10/22/15 Wed 11/11/15

30 Phase 3(Zones involve in Colours, Reading Area 5,

Return Mahine, Reading Area 4 Exhiition Area

Collaborative Zone, mobile Counter, Turnstile

Entrance, new Arivals Area, materials Library,

reading Area &Gallery)

50 days Thu 11/12/15 Wed 1/20/16

31 Demolition Works 1 wk Thu 11/12/15 Wed 11/18/15

32 Architectural/ Building work - Phase 3 4 wks Thu 11/19/15 Wed 12/16/15

33 M&E Works 2 wks Thu 12/17/15 Wed 12/30/15

34 Fire protection Works 2 wks Thu 12/17/15 Wed 12/30/15

35 Finishing work and Furniture Works 3 wks Thu 12/31/15 Wed 1/20/16

36 Phase 4(Entrance lobby, multimedia Room,kinect

rooms, media viewing & Reading Area)

35 days Thu 1/21/16 Wed 3/9/16

37 Demolition Works 1 wk Thu 1/21/16 Wed 1/27/16

38 Architectural/Building work - Phase 4 2 wks Thu 1/28/16 Wed 2/10/16

39 M&E Works 2 wks Thu 2/11/16 Wed 2/24/16

40 Fire protection Works 2 wks Thu 2/11/16 Wed 2/24/16

41 Finishing work and Furniture Works 2 wks Thu 2/25/16 Wed 3/9/16

42 Phase X( Unphased works:- Zones involve in

Generator Rooms, Horse reel Tank Rooms, Apron

Walkway, Courtyard 2nd story 7linkway, Annex

Staircase 4, Annex Stair case 5, Slab over of Stair

case 3, lift lobby, Stair Case 1&2, magazine drawers,

directors'Room)

175 days Thu 7/23/15 Wed 3/23/16

43 Demolition Works 3 wks Thu 7/23/15 Wed 8/12/15

44 Architectural/building work - Phase X 17 wks Thu 8/13/15 Wed 12/9/15

45 M&E Works 10 wks Thu 12/10/15 Wed 2/17/16

46 Fire protection Works 10 wks Thu 12/10/15 Wed 2/17/16

47 Finishing works 5 wks Thu 2/18/16 Wed 3/23/16

48 Hand Over 28 days Thu 3/24/16 Sat 4/30/16

49 Testing And Commissioning 1 wk Thu 3/24/16 Wed 3/30/16

50 BCA/ FSSD submission 2 wks Thu 3/31/16 Wed 4/13/16

51 Maintenance serving DLP 2 wks Thu 3/31/16 Wed 4/13/16

52 OMM and Warranty 2 wks Tue 4/19/16 Sat 4/30/16

9/2

11/11

1/20

3/9

3/23

Must Finished the Full height Glass works by others before do the ME works! at Entrance lobby Kinect Rooms

8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 121518212427 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9June 2015 July 2015 August 2015 September 2015 October 2015 November 2015 December 2015 January 2016 February 2016 March 2016 April 2016 May 2016

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Baseline

Baseline Milestone

Baseline Summary

Progress

Deadline

Proposed A & A to Existing 5 Story Main Library Building and 4-Story Library Annex Building (phase one)

at Singapore polytechnic Master Schedule

Page 1

Project: Project Schedule - SP libraryDate: Thu 6/11/15