Document Transmittal #: Duke Energy QA CONDITION ...

14
DISPOSIT PRIORITY Normal THE TRAI OTHERW 1) 01749 L C GIBBY - MG01VP 2) 02049 NGO PRA MANAGER EC081 3) 02388 DAVID DZIADOSZ LYNCHBG, VA 4) 02532 MCG NRC INSP MG-ADMIN MAIL RM ION OFTHE ORIGINAL DOCUMENT WILL BE TO NSMITTAL SIGNATURE UNLESS RECIPIENT IS ISE IDENTIFIED BELOW 5) 6) 7) 8) 9) 10) 11) 12) 13) 14) 15) 02546 WC LIBRARY- MG01WC 03044 MCG DOC CNTRL MISC MAN MG05DM 03283 P R TUCKER MG01RP 03614 MCG OPS PROCEDURE GP MG010P 03743 MCG QA TEC SUP MNT QC MG01MM 03744 OPS TRNG MGR. MG03OT 03759 U S NUC REG WASHINGTON, DC 03796 SCIENTECH DUNEDIN, FL 04698 D E BORTZ EC08G 04809 MCG PLANT ENG. LIBR. MG05SE 05162 MCG SHIFT WORK MGRS MG010P Duke Energy DOCUMENT TRANSMITTAL FORM REFERENCE MCGUIRE NUCLEAR STATION RECORD RETENTION # 005893 TECHNICAL SPECIFICATIONS (TS) AND TECHNICAL SPECIFICATIONS BASES (TSB) Date: 10/03/08 Document Transmittal #: DUK082770008 QA CONDITION [: Yes * No OTHER ACKNOWLEDGEMENT REQUIRED N Yes IF QA OR OTHER ACKNOWLEDGEMENT REQUIRED, PLEASE ACKNOWLEDGE RECEIPT BY RETURNING THIS FORM TO: Duke Energy McGuire DCRM MGO2DM 13225 Hagers Ferry Road Huntersville, N.C. 28078 Rec'd By Date Page 2 of 3 _____________________________________________________________________ - _____________ ,- ,- -, ,- r -, ,--, r ~ ~ h 4 1 DOCUMENT NO QA COND REV#/DATE DISTR CODE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL ___________________________________ _______ I. 4 4. 4- 4 4 4 4 4 4 -4- 4 4 4 4 4 -4 TS & TSB MEMORANDUM (1 PAGE) TSB LIST OF EFFECTIVE SECTIONS (4 PAGES) TSB3.6.13 (8 PAGES) NA NA NA --- 09/30/08 091 09/30/08 96 09/26/08 MADM-04B V1 V1 V1 V1 V1 x V1 V1 V1 V3 V8 V1 V1 V2 V1 47 REMARKS: PLEASE UPDATE ACCORDINGLY B H HAMILTON VICE PRESIDENT MCGUIRE NUCLEAR STATION RECIPIENT # 00422 PREVIOUSLY COMPLETED BY: B C BEAVER MG01RC BCB/CMK

Transcript of Document Transmittal #: Duke Energy QA CONDITION ...

Page 1: Document Transmittal #: Duke Energy QA CONDITION ...

DISPOSITPRIORITY Normal THE TRAI

OTHERW

1) 01749 L C GIBBY - MG01VP

2) 02049 NGO PRA MANAGER EC081

3) 02388 DAVID DZIADOSZ LYNCHBG, VA

4) 02532 MCG NRC INSP MG-ADMIN MAIL RM

ION OFTHE ORIGINAL DOCUMENT WILL BE TONSMITTAL SIGNATURE UNLESS RECIPIENT ISISE IDENTIFIED BELOW

5)

6)

7)

8)

9)

10)

11)

12)

13)

14)

15)

02546 WC LIBRARY- MG01WC

03044 MCG DOC CNTRL MISC MAN MG05DM

03283 P R TUCKER MG01RP03614 MCG OPS PROCEDURE GP MG010P

03743 MCG QA TEC SUP MNT QC MG01MM

03744 OPS TRNG MGR. MG03OT

03759 U S NUC REG WASHINGTON, DC

03796 SCIENTECH DUNEDIN, FL

04698 D E BORTZ EC08G

04809 MCG PLANT ENG. LIBR. MG05SE

05162 MCG SHIFT WORK MGRS MG010P

Duke EnergyDOCUMENT TRANSMITTAL FORM

REFERENCE

MCGUIRE NUCLEAR STATION

RECORD RETENTION # 005893

TECHNICAL SPECIFICATIONS (TS)

AND

TECHNICAL SPECIFICATIONS BASES

(TSB)

Date: 10/03/08

Document Transmittal #: DUK082770008

QA CONDITION [: Yes * No

OTHER ACKNOWLEDGEMENT REQUIRED N Yes

IF QA OR OTHER ACKNOWLEDGEMENT REQUIRED, PLEASEACKNOWLEDGE RECEIPT BY RETURNING THIS FORM TO:

Duke EnergyMcGuireDCRM MGO2DM13225 Hagers Ferry RoadHuntersville, N.C. 28078

Rec'd By

DatePage 2 of 3

_____________________________________________________________________ - _____________ ,- ,- -, ,- r -, ,--, r ~ ~ h 4 1

DOCUMENT NO QA COND REV#/DATE DISTR CODE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL___________________________________ _______ I. 4 4. 4- 4 4 4 4 4 4 -4- 4 4 4 4 4 -4

TS & TSB MEMORANDUM (1 PAGE)

TSB LIST OF EFFECTIVE SECTIONS (4 PAGES)

TSB3.6.13 (8 PAGES)

NANA

NA

--- 09/30/08

091 09/30/08

96 09/26/08

MADM-04B V1 V1 V1 V1 V1 x V1 V1 V1 V3 V8 V1 V1 V2 V1 47

REMARKS: PLEASE UPDATE ACCORDINGLY B H HAMILTON

VICE PRESIDENT

MCGUIRE NUCLEAR STATIONRECIPIENT # 00422 PREVIOUSLY COMPLETED

BY:

B C BEAVER MG01RC BCB/CMK

Page 2: Document Transmittal #: Duke Energy QA CONDITION ...

September 30, 2007

MEMORANDUM

To: All McGuire Nuclear Station Technical Specification, and Technical Specification Bases (TSB)Manual Holders

Subject: McGuire Technical Specifications Bases

REMOVE INSERT

Technical Specification Bases Manual:

TS Bases List of Effected Sections Rev 90

Tech Spec Bases: 3.6.13 Rev 83 (Entire Bases)

TS Bases List of Effected Sections Rev 91

Tech Spec Bases 3.6.13 Rev 96 (Entire Bases)

Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver-Regulatory Compliance875-4180

Page 3: Document Transmittal #: Duke Energy QA CONDITION ...

McGuire Nuclear Station Technical Specification BasesLOES

TS Bases are revised by section

Page Number Revision Revision Date

BASES

(Revised per section)

i Revision 63 4/4/05

ii Revision 63 4/4/05

iii Revision 63 5/25/05

B 2.1.1 Revision 51 1/14/04

B 2.1.2 Revision 0 9/30/98

B 3.0 Revision 81 3/29/07

B 3.1.1 Revision 73 3/6/06

B 3.1.2 Revision 10 9/22/00

B 3.1.3 Revision 10 9/22/00

B 3.1.4 Revision 0 9/30/98

B 3.1.5 Revision 19 1/10/02

B 3.1.6 Revision 0 9/30/98

B 3.1.7 Revision 58 06/213/04

B 3.1.8 Revision 0 9/30/98

B 3.2.1 Revision 74 5/3/06

B 3.2.2 Revision 10 9/22/00

B 3.2.3 Revision 34 10/1/02

B 3.2.4 Revision 10 9/22/00

B 3.3.1 Revision 90 10/30/07

B 3.3.2 Revision 62 1/27/05

B 3.3.3 Revision 71 10/12/05

B 3.3.4 Revision 57 4/29/04

B 3.3.5 Revision 11 9/18/00

B 3.3.6 Not Used - Revision 87 6/29/06

B 3.4.1 Revision 51 1/14/04

B 3.4.2 Revision 0 9/30/98

B 3.4.3 Revision 44 7/3/03

B 3.4.4 Revision 86 6/25/07

B 3.4.5 Revision 86 6/25/07

McGuire Units 1 and 2 Page I Revision 91

Page 4: Document Transmittal #: Duke Energy QA CONDITION ...

Page Number

B 3.4.6

B 3.4.7

B 3.4.8

B 3.4.9

B 3.4.10

B 3.4.11

B 3.4.12

B 3.4.13

B 3.4.14B 3.4.14-2B 3.4.14-6

B 3.4.15

B 3.4.16

B 3.4.17

B 3.4.18

B 3.5.1

B 3.5.2

B 3.5.3

B 3.5.4

B 3.5.5

B 3.6.1

B 3.6.2

B 3.6.3

B 3.6.4

B 3.6.5B 3.6.5-2

B 3.6.6

B 3.6.7

B 3.6.8

B 3.6.9

B 3.6.10

B 3.6.11

B 3.6.12

B 3.6.13

B 3.6.14

Amendment Revision Date

Revision 86

Revision 86

Revision 41

Revision 0

Revision 0

Revision 57

Revision 57

Revision 86

Revision 0Revision 5Revision 5

Revision 82

Revision 57

Revision 0

Revision 86

Revision 70

Revision 89

Revision 57

Revision 70

Revision 0

Revision 53

Revision 32

Revision 87

Revision 0

Revision 0Revision 6

Revision 93

Not Used - Revision 63

Revision 63

Revision 63

Revision 43

Revision 78

Revision 53

Revision 96

Revision 64

6/25/07

6/25/07

7/29/03

9/30/98

9/30/98

4/29/04

4/29/04

6/25/07

9/30/988/3/998/3/99

9/30/06

4/29/04

9/30/98

6/25/07

10/5/05

9/10/07

4/29/04

10/5/04

9/30/98

2/17/04

10/4/02

6/29/06

9/30/98

9/30/9810/6/99

04/30/07

4/4/05

4/4/05

4/4/05

5/28/03

9/25/06

2/17/04

9/26/08

4/23/05

McGuire Units 1 and 2 Page 2 Revision 91

Page 5: Document Transmittal #: Duke Energy QA CONDITION ...

Page Number Amendment Revision Date

B 3.6.15 Revision 0 9/30/98

B 3.6.16 Revision 40 5/8/03

B 3.7.1 Revision 0 9/30/98

B 3.7.2 Revision 79 10/17/06

B 3.7.3 Revision 0 9/30/98

B 3.7.4 Revision 57 4/29/04

B 3.7.5 Revision 60 10/12/04

B 3.7.6 Revision 0 9/30/98

B 3.7.7 Revision 0 9/30/98

B 3.7.8 Revision 0 9/30/98

B 3.7.9 Revision 43 5/28/03

B 3.7.10 Revision 75 6/12/06

B 3.7.11 Revision 65 6/2/05

B 3.7.12 Revision 28 5/17/02

B 3.7.13 Revision 85 2/26/07

B 3.7.14 Revision 66 6/30/05

B 3.7.15 Revision 66 6/30/05

B 3.7.16 Revision 0 9/30/98

B 3.8.1 Revision 92 1/28/08

B 3.8.2 Revision 92 1/28/08

B 3.8.3 Revision 53 2/17/04

B 3.8.4 Revision 36 12/17/02

B 3.8.5 Revision 41 7/29/03

B 3.8.6 Revision 0 9/30/98

B 3.8.7 Revision 20 1/10/02

B 3.8.8 Revision 41 7/29/03

B 3.8.9 Revision 24 2/4/02

B 3.8.10 Revision 41 7/29/03

B 3.9.1 Revision 68 9/1/05

B 3.9.2 Revision 41 7/29/03

B 3.9.3 Revision 91 11/7/07

B 3.9.4 Revision 84 2/20/07

B 3.9.5 Revision 59 7/29/04

B 3.9.6 Revision 41 7/29/03

McGuire Units 1 and 2 Page 3 Revision 91

Page 6: Document Transmittal #: Duke Energy QA CONDITION ...

Page Number

B 3.9.7

Amendment

Revision 88

Revision Date

9/5/07

2

McGuire Units 1 and 2 Page 4 Revision 91

Page 7: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

B 3.6 CONTAINMENT SYSTEMS

B 3.6.13 Ice Condenser Doors

BASES

BACKGROUND The ice condenser doors consist of the inlet doors, the intermediate deckdoors, and the top deck doors. The functions of the doors are to:

a. Seal the ice condenser from air leakage during the lifetime of theunit; and

b. Open in the event of a Design Basis Accident (DBA) to direct thehot steam-air mixture from the DBA into the ice bed, where the icewould absorb energy and limit containment peak pressure andtemperature during the accident transient.

Limiting the pressure and temperature following a DBA reduces therelease of fission product radioactivity from containment to theenvironment.

The ice condenser is an annular compartment enclosing approximately3000 of the perimeter of the upper containment compartment, butpenetrating the operating deck so that a portion extends into the lowercontainment compartment. The inlet doors separate the atmosphere ofthe lower compartment from the ice bed inside the ice condenser. Thetop deck doors are above the ice bed and exposed to the atmosphere ofthe upper compartment. The intermediate deck doors, located below thetop deck doors, form the floor of a plenum at the upper part of the icecondenser. This plenum area is used to facilitate surveillance andmaintenance of the ice bed.

The ice baskets held in the ice bed within the ice condenser are arrangedto promote heat transfer from steam to ice. This arrangement enhancesthe ice condenser's primary function of condensing steam and absorbingheat energy released to the containment during a DBA.

In the event of a DBA, the ice condenser inlet doors (located below theoperating deck) open due to the pressure rise in the lower compartment.This allows air and steam to flow from the lower compartment into the icecondenser. The resulting pressure increase within the ice condensercauses the intermediate deck doors and the top deck doors to open,which allows the air to flow out of the ice condenser into the uppercompartment. Steam condensation within the ice condensers limits thepressure and temperature buildup in containment. A divider barrierseparates the upper and lower compartments and ensures that the steamis directed into the ice condenser.

McGuire Units 1 and 2 B 3.6.13-1 Revision No. 96

Page 8: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

BACKGROUND (continued)

The ice, together with the containment spray, serves as a containmentheat removal system and is adequate to absorb the initial blowdown ofsteam and water from a DBA as well as the additional heat loads thatwould enter containment during the several hours following the initialblowdown. The additional heat loads would come from the residual heatin the reactor core, the hot piping and components, and the secondarysystem, including the steam generators. During the post blowdownperiod, the Air Return System (ARS) returns upper compartment airthrough the divider barrier to the lower compartment. This serves toequalize pressures in containment and to continue circulating heated airand steam from the lower compartment through the ice condenser, wherethe heat is removed by the remaining ice.

The water from the melted ice drains into the lower compartment where itserves as a source of borated water (via the containment sump) for theEmergency Core Cooling System (ECCS) and the Containment SpraySystem heat removal functions in the recirculation mode. The ice (via theContainment Spray System) and the recirculated ice melt also serve toclean up the containment atmosphere.

The ice condenser doors ensure that the ice stored in the ice bed ispreserved during normal operation (doors closed) and that the icecondenser functions as designed if called upon to act as a passive heatsink following a DBA.

APPLICABLE The limiting DBAs considered relative to containment pressure andSAFETY ANALYSES temperature are the loss of coolant accident (LOCA) and the steam line

break (SLB). The LOCA and SLB are analyzed using computer codesdesigned to predict the resultant containment pressure and temperaturetransients. DBAs are assumed not to occur simultaneously orconsecutively.

Although the ice condenser is a passive system that requires no electricalpower to perform its function, the Containment Spray System and ARSalso function to assist the ice bed in limiting pressures and temperatures.Therefore, the postulated DBAs are analyzed with respect to EngineeredSafety Feature (ESF) systems, assuming the loss of one ESF bus, whichis the worst case single active failure and results in one train each of theContainment Spray System and the ARS being rendered inoperable.

The limiting DBA analyses (Ref. 1) show that the maximum peakcontainment pressure results from the LOCA analysis and is calculated to

McGuire Units 1 and 2 B 3.6.13-2 Revision No. 96

Page 9: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

APPLICABLE SAFETY ANALYSES (continued)

be less than thecontainment design pressure. For certain aspects oftransient accident analyses, maximizing the calculated containmentpressure is not conservative. In particular, the cooling effectiveness ofthe ECCS during the core reflood phase of a LOCA analysis increaseswith increasing containment backpressure. For these calculations, thecontainment backpressure is calculated in a manner designed toconservatively minimize, rather than maximize, the calculated transientcontainment pressures, in accordance with 10 CFR 50, Appendix K(Ref. 2).

The maximum peak containment atmosphere temperature results fromthe SLB analysis and is discussed in the Bases for LCO 3.6.5,"Containment Air Temperature."

An additional design requirement was imposed on the ice condenser doordesign for a small break accident in which the flow of heated air andsteam is not sufficient to fully open the doors.

For this situation, the doors are designed so that all of the doors wouldpartially open by approximately the same amount. Thus, the partiallyopened doors would modulate the flow so that each ice bay would receivean approximately equal fraction of the total flow.

This design feature ensures that the heated air and steam will not flowpreferentially to some ice bays and deplete the ice there without utilizingthe ice in the other bays.

In addition to calculating the overall peak containment pressures, theDBA analyses include the calculation of the transient differentialpressures that would occur across subcompartment walls during the initialblowdown phase of the accident transient. The internal containment wallsand structures are designed to withstand the local transient pressuredifferentials for the limiting DBAs.

The ice condenser doors satisfy Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO This LCO establishes the minimum equipment requirements to assurethat the ice condenser doors perform their safety function. The icecondenser inlet doors, intermediate deck doors, and top deck doors mustbe closed to minimize air leakage into and out of the ice condenser, withits attendant leakage of heat into the ice condenser and loss of icethrough melting and sublimation. The doors must be OPERABLE to

McGuire Units 1 and 2 B 3.6.13-3 Revision No. 96

Page 10: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

LCO (continued)

ensure the proper opening of the ice condenser in the event of a DBA.OPERABILITY includes being free of any obstructions that would limittheir opening, and for the inlet doors, being adjusted such that theopening and closing torques are within limits. The ice condenser doorsfunction with the ice condenser to limit the pressure and temperature thatcould be expected following a DBA.

APPLICABILITY In MODES 1, 2, 3, and 4, a DBA could cause an increase in containmentpressure and temperature requiring the operation of the ice condenserdoors. Therefore, the LCO is applicable in MODES 1, 2, 3, and 4.

The probability and consequences of these events in MODES 5 and 6 arereduced due to the pressure and temperature limitations of theseMODES. Therefore, the ice condenser doors are not required to beOPERABLE in these MODES.

ACTIONS A Note provides clarification that, for this LCO, separate Condition entry isallowed for each ice condenser door.

A.1

If one or more ice condenser doors are inoperable due to being physicallyrestrained from opening, the door(s) must be restored to, OPERABLEstatus within 1 hour. The Required Action is necessary to returnoperation to within the bounds of the containment analysis. The 1 hourCompletion Time is consistent with the ACTIONS of LCO 3.6.1,"Containment," which requires containment to be restored to OPERABLEstatus within 1 hour.

B.1 and B.2

If one or more ice condenser doors are determined to be partially open orotherwise inoperable for reasons other than Condition A or if a door isfound that is not closed, it is acceptable to continue unit operation for upto 14 days, provided the ice bed temperature instrumentation is monitoredonce per 4 hours to ensure that the open or inoperable door is notallowing enough air leakage to cause the maximum ice bed temperatureto approach the melting point. The Frequency of 4 hours is based on thefact that temperature changes cannot occur rapidly in the

McGuire Units 1 and 2 B 3.6.13-4 Revision No. 96

Page 11: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

ACTIONS (continued)

ice bed because of the large mass of ice involved. The 14 dayCompletion Time is based on long term ice storage tests that indicate thatif the temperature is maintained below 270F, there would not be asignificant loss of ice from sublimation. If the maximum ice bedtemperature is > 270 F at any time or if the doors are not closed andrestored to OPERABLE status within 14 days, the situation reverts toCondition C and a Completion Time of 48 hours is allowed to restore theinoperable door to OPERABLE status or enter into Required Actions D.1and D.2. Ice bed temperature must be verified within the specifiedFrequency as augmented by the provisions of SR 3.0.2.

C.1

If Required Actions B.1 or B.2 are not met, the doors must be restored toOPERABLE status and closed positions within 48 hours. The 48 hourCompletion Time is based on the fact that, with the very large mass of iceinvolved, it would not be possible for the temperature to increase to themelting point and a significant amount of ice to melt in a 48 hour period.

D.1 and D.2

If the ice condenser doors cannot be restored to OPERABLE status withinthe required Completion Time, the plant must be brought to a MODE inwhich the LCO does not apply. To achieve this status, the plant must bebrought to at least MODE 3 within 6 hours and to MODE 5 within36 hours. The allowed Completion Times are reasonable, based onoperating experience, to reach the required plant conditions from fullpower conditions in an orderly manner and without challenging plantsystems.

SURVEILLANCE SR 3.6.13.1REQUIREMENTS

Verifying, by means of the Inlet Door Position Monitoring System, that theinlet doors are in their closed positions makes the operator aware of aninadvertent opening of one or more doors. The Frequency of 12 hoursensures that operators on each shift are aware of the status of the doors.

McGuire Units 1 and 2 B 3.6.13-5 Revision No. 96

Page 12: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

SURVEILLANCE REQUIREMENTS (continued)

SR 3.6.13.2

Verifying, by visual inspection, that each intermediate deck door is closedand not impaired by ice, frost, or debris provides assurance that theintermediate deck doors (which form the floor of the upper plenum wherefrequent maintenance on the ice bed is performed) have not been leftopen or obstructed: In determining if a door is impaired by ice, the frostaccumulation on the doors, joints, and hinges are to be considered inconjunction with the lifting force limits of SR 3.6.13.7. The Frequency of7 days is based on engineering judgment and takes into considerationsuch factors as the frequency of entry into the intermediate ice condenserdeck, the time required for significant frost buildup, and the probabilitythat a DBA will occur.

SR 3.6.13.3

Verifying, by visual inspection, that the top deck doors are in place andnot obstructed provides assurance that the doors are performing theirfunction of keeping warm air out of the ice condenser during normaloperation, and would not be obstructed if called upon to open in responseto a DBA. The Frequency of 92 days is based on engineering judgment,which considered such factors as the following:

a. The relative inaccessibility and lack of traffic in the vicinity of thedoors make it unlikely that a door would be inadvertently left open;

b. Excessive air leakage would be detected by temperaturemonitoring in the ice condenser; and

c. The light construction of the doors would ensure that, in the eventof a DBA, air and gases passing through the ice condenser wouldfind a flow path, even if a door were obstructed.

SR 3.6.13.4

Verifying, by visual inspection, that the ice condenser inlet doors are notimpaired by ice, frost, or debris provides assurance that the doors arefree to open in the event of a DBA. For this unit, the Frequency of18 months is based on door design, which does not allow watercondensation to freeze, and operating experience, which indicates thatthe inlet doors very rarely fail to meet their SR acceptance criteria.Because of high radiation in the vicinity of the inlet doors during poweroperation, this Surveillance is normally performed during a shutdown.

McGuire Units 1 and 2 B 3.6.13-6 Revision No. 96

Page 13: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

SURVEILLANCE REQUIREMENTS (continued)

SR 3.6.13.5

Verifying the opening torque of the inlet doors provides assurance that nodoors have become stuck in the closed position. The value of 675 in-lb isbased on the design opening pressure on the doors of 1.0 lb/ft2. For thisunit, the Frequency of 18 months is based on the passive nature of theclosing mechanism (i.e., once adjusted, there are no known factors thatwould change the setting, except possibly a buildup of ice; ice buildup isnot likely, however, because of the door design, which does not allowwater condensation to freeze). Operating experience indicates that theinlet doors usually meet their SR acceptance criteria. Because of highradiation in the vicinity of the inlet doors during power operation, thisSurveillance is normally performed during a shutdown.

SR 3.6.13.6

The torque test Surveillance ensures that the inlet doors have notdeveloped excessive friction and that the return springs are producing adoor return torque within limits. The torque test consists of the following:

1. Verify that the torque, T(OPEN), required to cause opening motionat the 400 open position is < 195 in-lb;

2. Verify that the torque, T(CLOSE), required to hold the doorstationary (i.e,, keep it from closing) at the 40' open position is> 78 in-lb but < 250.6 in-lb; and

3. Calculate the frictional torque, T(FRICT) 0.5 {T(OPEN) -T(CLOSE)}, and verify that the T(FRICT) is > - 40 in-lb but < +40 in-lb.

The purpose of the friction and return torque Specifications is to ensurethat, in the event of a small break LOCA or SLB, all of the 24 door pairsopen uniformly. This assures that, during the initial blowdown phase, thesteam and water mixture entering the lower compartment does not passthrough part of the ice condenser, depleting the ice there, while bypassingthe ice in other bays. The Frequency of 18 months is based on thepassive nature of the closing mechanism (i.e., once adjusted, there areno known factors that would change the setting, except possibly a buildupof ice; ice buildup is not likely, however, because of the door design,which does not allow water condensation to freeze). Operating

McGuire Units 1 and 2 B 3.6.13-7 Revision No. 96

Page 14: Document Transmittal #: Duke Energy QA CONDITION ...

Ice Condenser DoorsB 3.6.13

BASES

SURVEILLANCE REQUIREMENTS (continued)

experience indicates that the inlet doors very rarely fail to meet their SRacceptance criteria. Because of high radiation in the vicinity of the inletdoors during power operation, this Surveillance is normally performedduring a shutdown.

SR 3.6.13.7

Verifying the OPERABILITY of the intermediate deck doors providesassurance that the intermediate deck doors are free to open in the eventof a DBA. The verification consists of visually inspecting the intermediatedoors for structural deterioration, verifying free movement of the ventassemblies, and ascertaining free movement of each door when liftedwith the applicable force shown below:

Door Lifting Force

a. Adjacent to crane wall < 37.4 lbb. Paired with door adjacent to crane wall < 33.8 lbc. Adjacent to containment wall < 31.8 lbd. Paired with door adjacent, to containment < 31.0 lb

wall

The 18 month Frequency is based on the passive design of theintermediate deck doors, the frequency of personnel entry into theintermediate deck, and the fact that SR 3.6.13.2 confirms on a 7 dayFrequency that the doors are not impaired by ice, frost, or debris, whichare ways a door would fail the opening force test (i.e., by sticking or fromincreased door weight).

REFERENCES 1. UFSAR, Chapter 6.

2. 10 CFR 50, Appendix K.

3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

4. DPC-1201.17-00-0006 "Design and Licensing Basis for IceCondenser Lower Inlet Doors Technical Specification SurveillanceRequirements, 400 Opening, Closing and Frictional Torques".

5. MCS-1558.NF-00-0001 "Design Basis Specification for the NFSystem".

McGuire Units 1 and 2 B 3.6.13-8 Revision No. 96