Document of The World Bank FOR OFFICIAL USE ONLYdocuments1.worldbank.org/curated/ru/...REPUBLIC OF...

153
Document of The World Bank FOR OFFICIAL USE ONLY Report No: 67296-AFR PROJECT APPRAISAL DOCUMENT ON A PROPOSED CREDIT IN THE AMOUNT OF SDR 93.3 MILLION (US$144.5 MILLION EQUIVALENT) TO THE REPUBLIC OF LIBERIA FOR A WEST AFRICAN POWER POOL (WAPP) - COTE D'IVOIRE, LIBERIA, SIERRA LEONE, AND GUINEA (CLSG) POWER INTERCONNECTION PROJECT AND A PROPOSED GRANT IN THE AMOUNT OF SDR 20.4 MILLION (US$31.5 MILLION EQUIVALENT) TO THE WEST AFRICAN POWER POOL (WAPP) FOR A WAPP INTEGRATION AND TECHNICAL ASSISTANCE PROJECT IN SUPPORT OF THE FIRST PHASE OF THE CLSG POWER SYSTEM RE-DEVELOPMENT SUB-PROGRAM OF THE WAPP APL PROGRAM May 4, 2012 This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Document of The World Bank FOR OFFICIAL USE ONLYdocuments1.worldbank.org/curated/ru/...REPUBLIC OF...

  • Document of

    The World Bank

    FOR OFFICIAL USE ONLY

    Report No: 67296-AFR

    PROJECT APPRAISAL DOCUMENT

    ON A

    PROPOSED CREDIT

    IN THE AMOUNT OF SDR 93.3 MILLION

    (US$144.5 MILLION EQUIVALENT)

    TO THE

    REPUBLIC OF LIBERIA

    FOR A

    WEST AFRICAN POWER POOL (WAPP) - COTE D'IVOIRE, LIBERIA, SIERRA LEONE, AND

    GUINEA (CLSG) POWER INTERCONNECTION PROJECT

    AND A

    PROPOSED GRANT

    IN THE AMOUNT OF SDR 20.4 MILLION

    (US$31.5 MILLION EQUIVALENT)

    TO THE

    WEST AFRICAN POWER POOL (WAPP)

    FOR A

    WAPP INTEGRATION AND TECHNICAL ASSISTANCE PROJECT

    IN SUPPORT OF THE FIRST PHASE OF THE CLSG POWER SYSTEM RE-DEVELOPMENT

    SUB-PROGRAM OF THE WAPP APL PROGRAM

    May 4, 2012

    This document has a restricted distribution and may be used by recipients only in the performance of their

    official duties. Its contents may not otherwise be disclosed without World Bank authorization.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • i

    CURRENCY EQUIVALENTS

    (Exchange Rate Effective March 31, 2012)

    € 1 = US$ 1.33

    SDR 1 = US$ 0.64554

    FISCAL YEAR

    January 1 – December 31

    ABBREVIATIONS AND ACRONYMS

    AfDB African Development Bank

    CEB Communauté Electrique du Bénin (Electric Community of Benin)

    CLSG Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea

    ECOWAS Economic Community of West African States

    EIB European Investment Bank

    EEP ECOWAS Energy Protocol

    ERERA ECOWAS Regional Electricity Regulatory Authority

    ESIA Environmental and Social Impact Assessment

    ESMP Environmental and Social Management Plan

    FIRR Financial Internal Rate of Return

    FMM Financial Management Manual

    FNPV Financial net present value

    JIC Joint Implementation Committee (see also WAPP JIC below)

    HV High voltage

    IDA International Development Association

    IDC Interest during construction

    IPA International Project Agreement

    IPP Independent Power Producer

    GRIDCO Ghana Grid Company Limited

    GWh Giga Watt hours

    KfW Kreditanstalt für Wiederaufbau

    km Kilometer

    kV Kilo Volt

    kWh Kilo Watt hours

    M&E Monitoring and Evaluation

    MW Megawatt

    NEPAD New Partnership for African Development

    NPA National Power Authority (of Sierra Leone)

    NPV Net present value

    OMVG Organisation de Mise en Valeur du Fleuve Gambie (Organization for the

    Development of the River Gambia)

    OMVS Organisation de Mise en Valeur du Fleuve Sénégal (Orgnization for the

    Development of the River Senegal)

    OPGW Optical Fiber Ground Wire

  • ii

    PPA Power Purchase Agreement

    PIPES Planning, Investment Programming and Environmental Safeguards Department at

    the WAPP

    RAP Resettlement Action Plan

    RIAS Regional Integration Assistance Strategy

    RoW Right-of-way

    RTC CLSG Regional Transmission Company

    SCADA Supervisory Control And Data Acquisition

    SIEPAC Sistema de Interconexión Eléctrica de los Países de América Central or Central

    American Electrical Interconnection System

    SOGEM Société de Gestion de l‟Energie de Manantali (Energy Management Company for

    Manantali)

    SONABEL Société Nationale d‟Electricité de Burkina Faso (National Power Company of

    Burkina Faso)

    SPC Special Purpose Company

    SWER Single wire earth return system

    SWS Shield wire system

    TSA Transmission Service Agreement

    TSO Transmission System Operator

    WAPP West African Power Pool

    WAPP JIC West African Power Pool Joint Implementation Committee

    Regional Vice President: Obiageli K. Ezekwesili

    Acting Regional Director:

    Country Director:

    Elizabeth Laura Lule

    Yusupha Crookes

    Sector Director: Jamal Saghir

    Sector Manager: Lucio Monari

    Task Team Leader: Fanny Missfeldt-Ringius

  • iii

    LIBERIA

    West African Power Pool (WAPP) - Côte d'Ivoire, Sierra Leone, Liberia, and Guinea

    Power Interconnection Project

    WAPP

    WAPP Integration and Technical Assistance Project

    TABLE OF CONTENTS

    Page

    I. STRATEGIC CONTEXT .................................................................................................1

    A. Regional Context .......................................................................................................... 1

    B. Sectoral and Institutional Context ................................................................................. 6

    C. Higher Level Objectives to which the Project Contributes .......................................... 8

    II. PROJECT DEVELOPMENT OBJECTIVES ................................................................9

    A. PDO............................................................................................................................... 9

    B. Project Beneficiaries .................................................................................................... 10

    C. PDO Level Results Indicators ...................................................................................... 10

    III. PROJECT DESCRIPTION ............................................................................................11

    A. Project Components .................................................................................................... 11

    B. Project Financing ........................................................................................................ 15

    Lending Instrument ........................................................................................................... 15

    Project Cost and Financing ............................................................................................... 15

    C. Program Objective and Phases.................................................................................... 17

    D. Lessons Learned and Reflected in the Project Design ................................................ 17

    IV. IMPLEMENTATION .....................................................................................................21

    A. Institutional and Implementation Arrangements ........................................................ 21

    B. Results Monitoring and Evaluation ............................................................................ 22

    C. Sustainability............................................................................................................... 23

    V. KEY RISKS AND MITIGATION MEASURES ..........................................................24

    A. Risk Ratings Summary Table ..................................................................................... 24

    B. Overall Risk Rating Explanation ................................................................................ 24

  • iv

    VI. APPRAISAL SUMMARY ..............................................................................................25

    A. Economic and Financial Analyses .............................................................................. 25

    B. Technical ..................................................................................................................... 27

    C. Financial Management ................................................................................................ 27

    D. Procurement ................................................................................................................ 28

    E. Environmental and Social Safeguards ........................................................................ 28

    F. Environmental and Social Issues ................................................................................. 35

    Annex 1: Results Framework and Monitoring for the WAPP CLSG Power Interconnection

    Project ...........................................................................................................................................37

    Annex 2: Results Framework and Monitoring for the WAPP Integration and Technical

    Assistance Project ........................................................................................................................40

    Annex 3: Detailed Project Description .......................................................................................41

    Annex 4: Implementation Arrangements ..................................................................................53

    Annex 5 Operational Risk Assessment Framework (ORAF) ..................................................70

    Annex 6: Implementation Support Plan ....................................................................................73

    Annex 7: Economic and Financial Analysis ..............................................................................78

    Annex 8: Trading Potential and Arrangements ......................................................................102

    Annex 9: Institutional Structure for the CLSG Interconnector ............................................107

    Annex 10: Implementation Status of Projects of the West Africa Power Pool (WAPP)

    Adaptable Lending Program ....................................................................................................115

    Annex 11: Environmental and Social Safeguards ..................................................................121

  • v

    PAD DATA SHEET

    Liberia

    West African Power Pool (WAPP) - Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea

    Power Interconnection Project

    WAPP

    WAPP Integration and Technical Assistance Project

    PROJECT APPRAISAL DOCUMENT .

    Africa

    AFTEG

    .

    Basic Information

    Date: May 4, 2012 Sectors: Power (90%); General Energy Sector (10%)

    Country Director: Yusupha Crookes Themes: Infrastructure services for private sector

    Sector

    Manager/Director:

    Lucio Monari / Jamal Saghir EA Category: A (Full Assessment)

    Project ID: P113266

    Lending Instrument: Adaptable Program Loan Team Leader(s): Fanny Missfeldt-Ringius

    Joint IFC: No .

    Recipient: The Republic of Liberia, The West African Power Pool

    Responsible Agency: The CLSG Regional Transmission Company

    Contact: Shahid Mohammed Title: Chief Executive Officer

    Telephone No.: +231 880 719963 Email: [email protected]

    Responsible Agency: The West African Power Pool (WAPP) Secretariat

    Contact: Amadou Diallo Title: Secretary General

    Telephone No.: +229 21 37 71 44 Email: [email protected] .

    Project Implementation Period: Start Date: May 31, 2012 End Date: June 30, 2017

    Expected Effectiveness Date: For the WAPP CLSG Project - December 1, 2012; For the WAPP Integration and Technical Assistance Project – June

    15, 2012

    Expected Closing Date: December 31, 2017 .

    Project Financing Data(US$M)

    [ ] Loan [ X ] Grant Term:

    Standard IDA credit terms [X] Credit [ ] Guarantee

    For Loans/Credits/Others

    Total Project Cost : US$476 million Total Bank Financing : US$ 176 million

    Total Cofinancing : US$300 million Financing Gap : None .

    mailto:[email protected]:[email protected]

  • vi

    Financing Source Amount(US$M)

    BORROWER/RECIPIENT 21

    IBRD 0

    IDA: New 176

    IDA: Recommitted 0

    Others, of which AfDB

    EIB

    KfW

    279

    133

    105

    41

    Financing Gap 0

    Total 476 .

    Expected Disbursements (in USD Million)

    Fiscal Year FY13 FY14 FY15 FY16 FY17 FY18

    Annual 1 20 40 50 60 5

    Cumulative 1 21 61 111 171 176 .

    Project Development Objective(s)

    The Project development objectives of the WAPP CSLG Project are: (i) to reduce the cost of and increase the electricity supply at utility level; and (ii) to increase the export capability of Côte d'Ivoire.

    The Project development objective of the WAPP Integration and Technical Assistance Project is to increase the technical integration of the WAPP‟s network. .

    Components

    Component Name Cost (USD Million)

    Project 1: WAPP CLSG Power Interconnection 444.4

    Component 1.A: Power interconnection between CLSG 327.5

    Component 1.B: Institutional framework and project oversight 45.4

    Unallocated 71.5

    Project 2: WAPP Integration and Technical Assistance Project 31.5

    Component 2.A: Supply alternatives studies and project preparation support 10.0

    Component 2.B: Technical assistance and integration of WAPP interconnected

    network

    21.5

    .

    Compliance

    Policy

    Does the project depart from the CAS in content or in other significant respects? Yes [ ] No [ X ] .

    Does the project require any waivers of Bank policies? Yes [ X] No [ ]

    Have these been approved by Bank management? Yes [X ] No [ ]

    Is approval for any policy waiver sought from the Board? Yes [X] No [ ]

    Does the project meet the Regional criteria for readiness for implementation? Yes [X] No [ ] .

    Safeguard Policies Triggered by the Project Yes No

    Environmental Assessment OP/BP 4.01 X

    Natural Habitats OP/BP 4.04 X

    Forests OP/BP 4.36 X

  • vii

    Pest Management OP 4.09 X

    Physical Cultural Resources OP/BP 4.11 X

    Indigenous Peoples OP/BP 4.10 X

    Involuntary Resettlement OP/BP 4.12 X

    Safety of Dams OP/BP 4.37 X

    Projects on International Waterways OP/BP 7.50 X

    Projects in Disputed Areas OP/BP 7.60 X .

    Special Conditions for Effectiveness for the WAPP CLSG Power Interconnection Project

    Name Justification

    (a) The Subsidiary Credit Implementation Agreement has been

    executed on behalf of the Recipient and the Regional

    Transmission Company in form and substance satisfactory to the

    Association.

    The Subsidiary Credit Implementation Agreement is expected to be

    entered into between Liberia and the RTC to pass onto the Regional

    Transmission Company the entire proceeds of the credit for the

    implementation of the Project. This agreement is expected to include

    many of the conditions on the use of credit proceeds that would normally

    be part of a Project Agreement with a Project implementing entity, and be

    the vehicle by which Liberia will collect revenue to repay the credit.

    (b) The execution and delivery of the Treaty on behalf of each

    Participating Country has been duly ratified by all necessary

    governmental action.

    The Treaty provides the legal framework under which the entire Project

    will be implemented (including for the Regional Transmission Company,

    which is a creature of this instrument), and its ratification is necessary to

    ensure enforceability of its obligations against each of the Participating

    Countries.

    (c) The execution and delivery of the International Project

    Agreement, in form and substance satisfactory to the

    Association, on behalf of each Participating Country and the

    Regional Transmission Company, has been duly ratified or

    authorized by all necessary governmental and/or corporate

    action.

    While the Treaty provides the legal framework for implementation of the

    Project and the establishment of the RTC, the International Project

    Agreement (IPA) provides all of the detailed mechanics for

    operationalizing the Treaty‟s obligations and making the RTC operational.

    It is an agreement between the Participating Countries and the RTC

    whereby the Participating Countries grant the RTC the rights agreed to in

    the Treaty and obligate the RTC to implement the Project. For example,

    the IPA provides the RTC the right to the real property rights needed for

    implementation of the Project, the protections it needs in the event of

    action by a Participating Country in contravention of the terms of the

    Treaty, the basic tariff methodology that forms the core of the company‟s

    cost recovery, the obligations of the company with respect to the organs

    set up by the Treaty to monitor its implementation for the Participating

    Countries, the obligation of the Participating Countries (with which the

    Association does not have any direct contractual relationship, aside from

    Liberia) to provide the necessary financing for implementing the Project,

    etc.

    (d) The Establishment Agreements have been executed on

    behalf of the Participating Countries and the Regional

    Transmission Company in form and substance satisfactory to the

    Association.

    The Treaty stipulates that the RTC will enter into Establishment

    Agreements with the Participating Countries in which the company will

    establish offices to enable the company to carry out its obligations under

    the IPA. Without such Establishment Agreements in place, it would be

    very difficult, if not impossible, for the RTC to supervise construction of

    the Project.

    (e) The Power Purchase Agreement has been executed on behalf

    of the Utilities in form and substance satisfactory to the

    Association.

    At the heart of the sustainability of the Project is the premise that

    Participating Countries will enter into transactions that use the

    transmission line constructed under Part A.1 of the Project. Although it is

    difficult to stipulate specific conditions for these transactions, at a

    minimum, there should be an anchor transaction agreement – a Power

    Purchase Agreement - between one or more of the Utilities and/or other

    generators in the Participating Countries to demonstrate the viability of

    the Project.

  • viii

    (f) The Transmission Service Agreement has been executed on

    behalf of the Regional Transmission Company and an energy

    user in form and substance satisfactory to the Association.

    This condition relates to (e) above. As the RTC is expected to provide

    transmission service only, there should be a Transmission Service

    Agreement associated with the Power Purchase Agreement.

    (g) Each of the Co-financing Agreements with Liberia has been

    executed and delivered and all conditions precedent to its

    effectiveness or to the right of the Recipient to make

    withdrawals under it (other than the effectiveness of this

    Agreement) have been fulfilled.

    The Project is being developed as a regional one with benefits to all of the

    Participating Countries. As IDA is financing only a portion of the Project,

    it is necessary to ensure that funding for Liberia is secured and available

    for Project start-up.

    (h) The Regional Transmission Company has been duly created,

    established and made operational in the territory of one of the

    Participating Countries, all in form and substance satisfactory to

    the Association. As part of such requirements, there shall be in

    place for the RTC: (i) the paid-in equity contribution pursuant to

    the provisions of the Treaty, including the amount required on

    behalf of each Participating Country to finance the Resettlement

    costs and the Interest During Construction; (ii) the Shareholders‟

    Agreement, in form and substance satisfactory to the

    Association, signed and effective; (iii) the RTC Project

    Implementation Manual, in form and substance satisfactory to

    the Association, adopted; (iv) a financial management

    assessment of the RTC completed to the satisfaction of the

    Association; (v) the representatives of the RTC‟s shareholders

    and the WAPP and two (2) independent directors appointed to

    the RTC‟s Board of Directors; and (vi) its General Manager and

    the key staff recruited, designated and/or appointed, all of them

    under terms of reference and with qualifications and experience

    satisfactory to the Association.

    As a practical matter, the RTC needs to be fully constituted and

    operational in order to undertake the various obligations and activities

    expected of it. For example, in order to execute the IPA and the

    Transmission Service Agreement, the company needs to have officers

    appointed and empowered by the Board of Directors to bind the company.

    Accordingly:

    (a) The Utilities, as the RTC's shareholders, must enter into the

    contemplated Shareholders Agreement that will govern their rights and

    responsibilities as the RTC's shareholders;

    (b) The shareholders must meet to appoint their own Directors to and

    constitute the company‟s Board to allow the company to take corporate

    action in accordance with the terms of its Articles of Association that is

    annexed to the Treaty;

    (c) the RTC Project Implementation Manual must be adopted, in form

    and substance satisfactory to the Association, to allow the RTC to operate

    in accordance with transparent principles and procedures consistent with

    the Bank's requirements;

    (d) The representatives of the RTC‟s shareholders and the WAPP and two

    (2) independent directors must be appointed to the RTC‟s Board of

    Directors; and

    (e) The General Manager (and key staff) of the RTC must be recruited and

    appointed by the Board, and the Board must give the General Manager the

    authority to enter into the various agreements to bind the company.

    In addition, because the financing plan for the RTC contemplates nominal

    equity contributions by the company‟s shareholders ($17 million) to cover

    the costs of implementing the ESMP and interest during construction, this

    equity needs to be made available for the company to carry out its related

    obligations. The Project assumes these costs to be the responsibility of

    the Participating Countries under Component A-5.

    Disbursement condition for withdrawal of the Credit proceeds

    to finance the construction of the 225kV converter substation in Yekepa, Liberia: the Côte d‟Ivoire Co-financing Agreement

    between Côte d‟Ivoire and the African Development Bank has

    been executed and delivered and all conditions precedent to its

    effectiveness or to the right of Côte d‟Ivoire to make

    withdrawals thereunder have been fulfilled.

    This co-financing is necessary to ensure the Liberia transmission line

    financed by IDA can be operated and import power from Côte d‟Ivoire.

    Special Conditions for Effectiveness for the WAPP Integration and Technical Assistance Project

    WAPP shall have adopted the WAPP Project Implementation

    Manual in form and substance satisfactory to the Association.

    The WAPP Project Implementation Manual must be adopted, in form and

    substance satisfactory to the Association, to allow the WAPP to operate in

    accordance with transparent principles and procedures consistent with the

    Bank's requirements.

  • ix

    Legal Covenants for the WAPP CLSG Power Interconnection Project

    Description Recurrent Due Date Frequency

    The Association may suspend disbursements under the Credit if

    the Guinea Financing Agreement and/or the Sierra Leone

    Financing Agreements shall have failed to become effective.

    No December 31, 2013 Once

    The Recipient shall require the Regional Transmission

    Company (RTC), except as the Association shall otherwise

    agree, to maintain a debt service coverage ratio of at least 1.3

    under terms and conditions that have been agreed upon with the

    Association.

    Yes Following effectiveness Annually

    The Recipient shall cause the RTC to recruit a qualified and

    experienced internal auditor and an accounts officer on the basis

    of terms of reference and with qualifications and experience

    satisfactory to the Association and to acquire and install an

    accounting information system for the Project.

    No 6 months after

    effectiveness

    Once

    The Recipient shall cause the RTC to prepare and furnish to the

    Association as part of the Project Report not later than forty-five

    (45) days after the end of each quarter, interim unaudited

    financial reports for the Project covering the quarter, in form

    and substance satisfactory to the Association.

    Yes Within 45 days after the

    end of the quarter to

    which the IFRs relate

    Quarterly

    The Recipient shall take all action required on its behalf to

    ensure that the Project is implemented in accordance with the

    provisions of the Liberia Environmental and Social Impact

    Assessment (Liberia ESIA), the Liberia Environmental and

    Social Management Plan (Liberia ESMP), and the Liberia

    Resettlement Action Plan (Liberia RAP), all in a manner

    satisfactory to the Association.

    Yes

    Following effectiveness

    Ongoing

    The Recipient shall cause the RTC to collect, compile and

    furnish to the Association reports on the status of compliance

    with the Environmental and Social Impact Assessments

    (ESIAs), the Environmental and Social Management Plans

    (ESMPs), and the Resettlement Action Plans (RAPs) for the

    Participating Countries.

    Yes Within a quarter

    following effectiveness

    Quarterly

    The Recipient shall cause the RTC to acquire and install a

    suitable accounting information system for the Project.

    No 6 (six) months after

    effectiveness

    Once

    The Recipient shall ensure that the RTC employ an operations

    and maintenance contractor under terms of reference and with experience and qualifications satisfactory to the Association.

    No Two (2) months before

    the expected date of

    completion of the

    construction under

    Component 1.A.1

    Once

    The Recipient shall require the RTC to carry out the Project

    with due diligence and efficiency and in accordance with sound

    technical, economic, energy, financial, managerial,

    environmental, and social standards and practices satisfactory to

    the Association, including in accordance with the provisions of

    the ESMPs and the RAPs and pursuant to the RTC Project

    Implementation Manual and the Anti-Corruption Guidelines

    applicable to recipients of loan proceeds other than the

    Recipient.

    Yes Following effectiveness Ongoing

    The Recipient shall ensure that the RTC conclude with the

    WAPP a Control Area Agreement in form and substance

    satisfactory to the Association.

    No Six (6) months before the

    expected date of

    completion of the

    construction under

    Component 1.A.1

    Once

  • x

    The Recipient shall cause the RTC to review with the

    Association the mid-term review report and, thereafter, take all

    measures required to ensure the efficient completion of the

    Project and the achievement of the objectives thereof.

    No On or about January 31,

    2015

    Once

    The Recipient shall exercise its rights and carry out its

    obligations under the Subsidiary Credit Implementation

    Agreement in such manner as to protect the interests of the

    Recipient and the Association and to accomplish the purposes of

    the Credit. Except as the Association shall otherwise agree, the

    Recipient shall not assign, amend, abrogate or waive the

    Subsidiary Credit Implementation Agreement or any of its

    provisions.

    Yes Following effectiveness Ongoing

    Not later than six (6) months after the Effective Date: (i) to set

    up an audit committee under terms of reference and with a

    composition satisfactory to the Association to follow-up with

    management on any issues raised in the annual audits, thereby

    ensuring they properly addressed; and (ii) to develop an anti-

    fraud and anti-corruption policy satisfactory to the Association

    and set up an anti-fraud and anti-corruption committee under

    terms of reference and with a composition satisfactory to the

    Association to handle any fraud and corruption cases

    No 6 months after

    effectiveness

    Once

    No withdrawal shall be made for payments made prior to the

    date of this Agreement, except that withdrawals up to an

    aggregate amount not to exceed SDR 650,000 equivalent may

    be made for payments made prior to this date but on or after

    April 1, 2012, for Eligible Expenditures under Category (1)(b).

    No Disbursement Condition

    Legal Covenants for the WAPP Integration and Technical Assistance Project

    Description Recurrent Due Date Frequency

    Schedule 2, Section IV, B.1: No withdrawal shall be made for

    payments made prior to the date of this Agreement, except that

    withdrawals up to an aggregate amount not to exceed SDR

    1,880,000 equivalent may be made for payments made prior to

    this date but on or after June 20, 2011, for Eligible Expenditures

    under Category (1)

    No Disbursement Condition

    .

    Team Composition

    Bank Staff

    Name Title Specialization Unit

    Fanny Missfeldt-Ringius Senior Energy Economist TTL and Economics AFTEG

    Zayra Romo Energy Specialist Engineering AFTEG

    Franklin Gbedey Energy Specialist Engineering AFTEG

    Issa Diaw Senior Power Engineer Engineering AFTEG

    Tjaarda Storm Van Leeuwen Consultant Inst. Framework & Financial Analysis AFTEG

    Arnaud Braud Financial Analyst Financial Analysis AFTEG

    Dukjoong Kim Financial Analyst Financial Analysis AFTEG

    Marcelino Madrigal Senior Energy Specialist Trading SEGEN

    Maria C. Cruz Lead Social Development

    Specialist

    Social Safeguards AFTCS

    Paivi Koskinen-Lewis Social Development

    Specialist

    Social Safeguards SDV

  • xi

    Robert Robelus Consultant Environmental Safeguards AFTWR

    Allan Rotman Lead Procurement Specialist Procurement AFTPC

    Itchi Ayindo Senior Procurement

    Specialist

    Procurement AFTPC

    Mathias Gogohounga Procurement Specialist Procurement AFTPC

    Patrick Umah-Teteh Senior Financial

    Management Specialist

    Financial management AFTFM

    Alain Hinkati Financial Management

    Specialist

    Financial management AFTFM

    Maxwell Bruku Dapaah Financial Management

    Specialist

    Financial management AFTFM

    Luis M. Schwarz Senior Finance Officer Disbursement CTRLA

    Claudia Pardiñas Ocaña Senior Counsel Law LEGAF

    Sameh Mobarek Senior Counsel Law LEGPS

    Anthony Molle Senior Counsel Law LEGAF

    Anders Jensen M&E Specialist Monitoring and Evaluation AFTDE

    Manuel Berlengiero Energy Specialist Economics AFTEG

    Bipulendu Narayan Singh Operations Analyst Economics SEGES

    Anta Lo-Loum Language Program Assistant Administrative and Client Support AFTEG

    Non Bank Staff

    Name Title Office Phone City

    Fiona Woolf Legal Advisor - London .

    Locations

    Country First Administrative Division Location Planned Actual Comments

    Côte d‟Ivoire Dix-Huit Montagnes Region (Departments of Man and Danane)

    Man to border (Côte d‟Ivoire/Liberia).

    Liberia Counties of Nimba, Grand Bassa, Montserrado,

    Bomi, and Grand Cape Mount.

    Border (Côte

    d‟Ivoire/Liberia) and border

    (Guinea/Liberia) -

    Yekepa – Buchanan – Mount Coffee -

    Monrovia – Mano –

    border (Liberia/Sierra

    Leone).

    Sierra Leone Eastern province (Kenema and Kono districts),

    Northern province (Bombali, Kambia,

    Koinadugu and Tonkolili districts), and Southern province (Pujehun district).

    Border

    (Liberia/Sierra

    Leone) – Kenema – Bikongor –

    Bumbuna – Yiben –

    Kamakwie – border (Sierra

    Leone/Guinea).

    Guinea Administrative regions of Kindia (Madina-Oula

    and Sougueta), Labe (Linsan) and Nzerekore

    (Nzerekore and Yalenzou).

    Border

    (Guinea/Liberia) -

    Nzérékoré; and border (Sierra

    Leone/Guinea) –

    Linsan.

    .

  • 1

    Liberia West African Power Pool (WAPP) Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea

    Power Interconnection Project

    And

    WAPP

    WAPP Integration and Technical Assistance Project

    I. STRATEGIC CONTEXT

    A. Regional Context

    Regional Overview

    1. The 15 member states1 of the Economic Community of West African States (ECOWAS) occupy some five million square kilometers and are currently home to about 250 million people.

    Half of the present population lives in poverty, with per capita income barely above US$300 per

    year. Despite the region‟s large energy endowment, the per capita consumption of electricity is

    among the lowest in the world with approximately 171 kWh per capita and year in 2010.

    2. Faced with this power system expansion challenge, ECOWAS Member States have acknowledged that past efforts to achieve national self-sufficiency in electricity supply have been

    uneconomical due to the high cost of establishing power generation and transmission

    infrastructure. They also acknowledge two major shortcomings in the region at the present time:

    (a) low-cost, sizeable, and complex hydro-based power plants and systems are difficult to

    develop in the national context alone, but are key to providing low-cost electricity in a region

    that has among the highest electricity prices in the world, and (b) the lack of adequate

    transmission infrastructure (within and between national power systems) is a key constraint in

    the drive towards greater cooperation in power sector development.

    ECOWAS Vision – West Africa Power Pool

    3. To address these challenges ECOWAS has formed and put in place the West African Power Pool (WAPP) – a cooperative power pooling mechanism for integrating national power

    system operations into a unified regional electricity market – with the expectation that this

    mechanism would, over the medium to long term, assure their citizens a stable and reliable

    electricity supply at affordable cost. To this end, ECOWAS states adopted an ECOWAS Energy

    Policy in 1982 and decided to establish a West African Power Pool (WAPP) in 1999. To

    operationalize this mission, the 29th Summit of the Heads of State and Governments of the

    1 Benin, Burkina Faso, Cape Verde, Côte d‟Ivoire, The Gambia, Ghana, Guinea, Guinea Bissau, Liberia, Mali, Niger, Nigeria,

    Senegal, Sierra Leone, and Togo.

  • 2

    ECOWAS Member States adopted the "Articles of Agreement," which formally set up the

    WAPP Secretariat as a "Specialized Institution of ECOWAS."2

    4. As a “flagship infrastructure project” of the New Partnership for African Development (NEPAD),

    3 the WAPP directly contributes to the broader ECOWAS agenda to establish an open,

    unified, regional economic space in West Africa. The vision for WAPP is also embodied in the

    ECOWAS Energy Protocol (EEP) – that of creating a "level playing field" to facilitate the

    balanced development of diverse energy resources of the ECOWAS Member States for their

    collective economic benefit, through long-term energy sector co-operation, unimpeded energy

    transit and increasing cross-border electricity trade. To this end, the WAPP has been helping

    countries in the ECOWAS region to develop regional priority projects. These priority projects

    are identified through a regional Masterplan, which is regularly updated, and subsequently

    endorsed in WAPP fora. The Masterplan was most recently updated in December 2011.

    5. In July 2006, the "WAPP Organization" was formally inaugurated as an all-inclusive organization of (public and private) electric power utilities based in ECOWAS member states.

    The governance structures of the WAPP organization is constituted of, (i) the General Assembly,

    which comprises representatives of all members and is the highest decision making body; (ii)

    the Executive Board, which consists of six elected members and the Secretary General and is

    responsible for policy, overseeing WAPP operations and planning for future development; (iii)

    the WAPP Organizational Committees, which include the Engineering and Operations, the

    Strategic Planning and the Finance & Human Resources Committees and are composed of

    technical experts of WAPP Membership to provide support and advice to the Executive Board;

    and, (iv) the WAPP Secretariat, which is the administrative organ headed by the Secretary

    General and is responsible for the day-to-day operations of the WAPP.

    6. The Implementation "road map" of the WAPP Infrastructure Program is based on realizing distinct but mutually reinforcing infrastructure sub-programs, which when fully

    realized will converge into a unified, well functioning regional power pooling mechanism in

    West Africa. The five (5) sub-programs being implemented by WAPP are the following (see

    also Graph 1):

    (a) Coastal Transmission Backbone Subprogram (Côte d'Ivoire, Ghana, Benin/Togo, Nigeria): aims to establish a robust interconnection link between the

    ECOWAS Coastal Member States.

    (b) Inter-zonal Transmission Hub Sub-program (Burkina Faso and Mali via Ghana, OMVS via Mali, Liberia-Sierra Leone-Guinea via Cote d'Ivoire): aims to

    establish more secure, reliable transmission corridors for transfer of low cost

    energy to displace diesel-based sources especially in Burkina Faso through Ghana

    and Côte d‟Ivoire, and OMVS through Mali.

    2 ECOWAS/ CEDEAO (2006). 29th Session of the Authority of Heads of State and Government. Decision A/Dec. 18/01/06

    Adopting the Articles of Agreement Relating to the Establishment and functioning of the West African Power Pool, Niamey, 12

    January 2006; and Decision A/Dec.20/01/06 Granting the Status of a Specialized Institution of ECOWAS to the WAPP

    Organization. Niamey, 12 January 2006. 3 NEPAD was established to implement an integrated socio-economic development framework for Africa, and was formally

    adopted at the 37th Summit of the Organisation for African Unity in July 2001.

  • 3

    (c) OMVG/OMVS Power System Development Subprogram (The Gambia, Guinea, Guinea Bissau, Mali, Senegal): aims to interconnect national systems of

    The Gambia, Guinea, Guinea Bissau, Mali, Senegal and secure access to sources

    of low cost energy to be built on the Gambia River, the Senegal River and the

    Konkoure River Basins.

    (d) North-core Transmission Sub-program (Nigeria, Niger, Burkina Faso, Benin): aims to upgrade and extend existing capacity to transfer low cost energy supply to

    Niger, Burkina Faso, and northern Benin and Togo.

    (e) Côte d'Ivoire–Liberia-Sierra Leone-Guinea Power System Re-development Subprogram (Côte d'Ivoire, Liberia, Sierra Leone, Guinea): aims to interconnect

    Côte d'Ivoire, Liberia, Sierra Leone, and Guinea into the WAPP Energy System

    and to develop the hydropower resources in the sub-region.

    Figure 1: Implementation Roadmap of the Core WAPP Programs

    Interconnecting Côte d’Ivoire, Liberia, Sierra Leone and Guinea

    7. In early 2012, Liberia and Sierra Leone are still recovering from the civil wars that have devastated large parts of both countries, and – in the case of Liberia – led to the complete

    destruction of it public power system. Guinea is also only stabilizing after getting to the brink of

  • 4

    civil war in 2010. Cote d‟Ivoire‟s situation only normalized in 2011. Both the power systems in

    Sierra Leone and Guinea are marked by heavy investment needs. Electricity connection rates are

    among the lowest in the world and the cost of generating power in these countries remains high,

    primarily due to the small size of the power systems and the reliance on fossil fuel-based

    generation. The unavailability of public power supply and high costs of power generation are

    recognized to be one of the major impediments to economic recovery and poverty reduction in

    Liberia, Sierra Leone, and Guinea.

    8. Liberia is only slowly rebuilding its power utility Liberia Electricity Corporation (LEC) that had ceased operating during the civil war, and in early 2012 has about 5000 customer. In

    Guinea‟s forest region, no grid-provided power is available. The national power utility,

    Electricité de Guinea (EdG), has been unable to restore service in the forest region since the end

    of the war in the area and there is still heavy load shedding in areas served by EDG. In Sierra-

    Leone, public electricity services are currently only available in selected parts of Sierra Leone

    for about 25 percent of the time only. The operations of the two utilities, the National Power

    Authority (NPA) and the Bo Kenema Power Service Ltd, have been stagnant since the civil war.

    9. However, the efforts that are underway in Liberia, Sierra Leone, and Guinea should both improve the current performance of the of the energy sectors and broaden the electricity access

    rates. In Liberia, a management contractor, Manitoba Hydro International, has been in place

    since July 2011. Since the contractor‟s arrival, both the technical and financial performance of

    LEC has improved, and the number of customers has more than doubled. In addition, an

    investment package in the amount of US$50 million has been made available by the World

    Bank, GPOBA, the Government of Norway, and USAID to support the expansion of customer

    connections to 33,000 by 2015.

    10. In Sierra Leone, the new electricity law ratified in early 2012 should lead to greater financial accountability of the energy sector. In addition, a World Bank financed energy project

    is expected to reach financial closure in early 2013. The proposed project should significantly

    improve the distribution network and increase customer connections of Sierra Leone‟s power

    utility, the National Power Authority (NPA). In Guinea, the Government endorsed a new sector

    strategy in February 2012. With ongoing support from AfDB and new support planned by the

    World Bank, the performance of the power sector is also put on target to improve.

    11. Nevertheless, the energy sectors of Liberia, Sierra Leone, and Guinea in their own right are too small to be able to lower the cost of electricity to levels that are internationally

    competitive. By interconnecting these small systems, however, this structural challenge can be

    overcome.

    12. In recognition of these benefits and following the return to peace in Liberia and Sierra Leone, the 2005 WAPP Master Plan already retained the interconnections between Man (Côte

    d‟Ivoire) – Monrovia (Liberia) and Conakry (Guinea) – Bumbuna (Sierra Leone) on the priority

    list of projects. In 2006, the WAPP undertook a detailed review of the power systems in Liberia,

    Sierra Leone, and Guinea, which led to the drafting of the “Concept for Liberia, Sierra Leone,

  • 5

    Guinea Power System.”4 Under this review, these individual projects were aggregated into a

    single transmission line project to interconnect Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea,

    and to develop the systems of these three countries as a single network and within one sub-

    program. The wider WAPP LSG concept seeks the following outcomes:

    Provide residents of the greater Monrovia area in Liberia; Bo, Kenema and Western Areas in Sierra-Leone; and, the Forest Region of Guinea, with improvements in power

    supplies in the short term.

    Pursue a regional infrastructure developmental approach that will provide over the medium to long term adequate electricity to the people in a more efficient and cost

    effective way, boosting economic and social development.

    Establish a regional regulatory framework for the sector that is conducive to the participation of private/strategic partners in the development of the power sector. The

    participation of the private sector and strategic partners is critical to obtaining the

    required capital investment and effective management for the electricity sector. This will

    also enable Government to concentrate on other social needs; and

    Ensure the technical capacity, management competence and the financial viability of the institutions of the electricity sub-sector for the sustainable provision of services and

    specifically, the viability of those agencies that are responsible for operating an open

    access transmission network and associated support services that enable competitive

    delivery of power to consumers.

    13. The project will contribute to economic recovery and poverty reduction through improved access to essential power supplies in the LSG area. This will be accomplished through

    the re-construction of essential infrastructure and strengthening of institutional capabilities to

    plan, procure, operate, maintain and sustainably manage these services. It will provide support

    for targeted critical investments with the aim of developing the most economic power resources

    in the LSG area and making services available from a regional power system that overcomes the

    structural inefficiencies presented by the small sizes of the individual economies. The realization

    of the CLSG Power Network will also interlink the WAPP Coastal Transmission Backbone and

    the OMVG/OMVS Power System. The proposed CLSG Power Network project was confirmed

    as one of the high priority projects in the revised WAPP Master Plan (2011).

    14. The regional context of the program will have a transformational impact in the national power systems by building its own backbone transmission line. While the CLSG

    interconnector transmission line represents the initial stage for enabling energy trade in the

    region, the project will also transform the domestic power systems by building the backbone

    transmission lines in Liberia and Sierra Leone at the time when both domestic generation and

    distribution infrastructure are limited in these countries. The small size of the power sector

    prevents economies of scale, making it difficult for governments to afford and operate large

    infrastructure investments while the nascent national systems emerge from emergency response

    mode. In turn, the combined regional and domestic impacts will support the transition to

    4 Arthur Energy Advisors (2006). Concept for LSG Power System covering Liberia, Sierra Leone, and Guinea.

    Commissioned by the WAPP Secretariat.

  • 6

    normally functioning power utilities in these countries with lower cost, more sustainable

    generation and more effective means to control and optimize system expansion and operations.

    15. Grid connection of mining sites would allow a number of alternative power supply models to be developed. The CLSG countries are endowed with vast areas of world class iron

    ore deposits that once developed could represent a major demand on the CLSG line. Once the

    CLSG Regional Transmission Company (RTC) is established and the CLSG line constructed, the

    cost of extending the transmission grid to connect the major mining sites would be low. Indeed

    the CLSG line goes closely past the most significant mining areas and the potential amount

    traded by the mining companies is high. If mining demand were interconnected to the grid,

    different supply arrangements could be developed that would allow the energy supply surplus

    from mining to be sold to the grid (either bilateral or to the utilities) or allow the development of

    large supply generation plan to meet the mining demand while using the CLSG line. Taking into

    consideration the impact of the mining demand on the design of the line, a two phase

    construction approach was adopted. The line is expected to be upgraded by 2020 with the second

    circuit equipped (i.e. an additional capacity of 145 MW) to accommodate higher demand.

    16. In recognition of the benefits that this project will bring to the CLSG countries, it was singled out by the G20 as a priority project at the 2011 Cannes meetings.

    World Bank Support of the WAPP

    17. On June 30, 2005, the World Bank's Executive Board of Directors endorsed the application of the adaptable program lending (APL) instrument, within the framework of the

    World Bank's Regional Integration Assistance Strategy (RIAS) for West Africa, as the vehicle

    for providing IDA credit support to the WAPP initiative. The Bank earmarked US$350 million

    in IDA resources under the IDA Regional Pilot Program to put in place a multi-year

    programmatic framework to help close the financing gap and thereby ensure timely

    implementation of priority WAPP investments and technical assistance activities of the Revised

    WAPP Master Plan.

    18. The APL instrument provides the framework for the IDA credit support to the original set of WAPP priority projects. It is a useful and relevant tool, as it reinforces policies through

    dedicated policy triggers, such as country commitments and ratification of the ECOWAS Energy

    Protocol. The APL original umbrella envelope of US$350 million has been depleted.

    19. Future WAPP priority projects that are being considered for World Bank financing include the Mount Coffee Hydropower Plant Rehabilitation in Liberia, the Adjarala Hydropower

    Plant between Benin and Togo, and the Gouina Hydropower Plant in Mali. Annex 10 provides

    an overview of the implementation status of projects of the WAPP APL program.

    B. Sectoral and Institutional Context

    20. The Heads of State of Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea (CLSG) project have entrusted the preparation of the CLSG power interconnection project to the WAPP

    Secretariat. The Energy Ministers then established the WAPP Joint Implementation Committee

    (JIC), which gathers representatives from all four countries‟ ministries in charge of energy and

    the power utilities. Following the adoption of the WAPP Cote d‟Ivoire Liberia-Sierra Leone-

  • 7

    Guinea (LSG) sub-program and the setting up of the WAPP JIC in 2007, the four countries have

    jointly pursued the preparation of this project, which has been considered a high priority project

    for the sub-region. Once constructed, it will constitute the first interconnection of power systems

    ever among these four countries.

    21. The WAPP JIC has overseen the preparation of the project‟s feasibility study, the Environmental and Social Impact Analyses (ESIAs), and the institutional studies that have

    defined the institutional framework for the project. They have endorsed final reports and studies,

    as well as concepts for moving forward.

    22. In 2008, the ECOWAS Heads of State endorsed the establishment of “Special Purpose Companies” (SPC) as a major vehicle for the implementation of WAPP regional priority

    projects. A few examples of such SPCs exist in the ECOWAS region. These include SOGEM,

    which runs the Manantali (and soon also the Felou) hydropower plants in Mali, which are jointly

    owned by Mauritania, Senegal and Mali. This also includes the CEB, which owns and operates

    key generation plant and transmission lines for the Governments of Benin and Togo. The

    experience of these SPCs in the ECOWAS region has been mixed, and the WAPP JIC is aiming

    to take the lessons learned from these experiences to setting up a better structured SPC for the

    WAPP CLSG project (see below discussion in the lessons learned section).

    23. After the technical and safeguard studies were well underway, the WAPP JIC began to tackle the setting up of the SPC (CLSG Regional Transmission Company or “RTC”) in 2011. In

    a first instance, the WAPP JIC adopted in Guinea in June 2011 an interim institutional

    mechanism, the Project Implementation Unit (PIU), which would initially be located with the

    WAPP Secretariat, and then will be strengthened and transferred to the RTC, once the later is

    established. At the WAPP, the PIU is to have a “light” structure. Once the RTC is established,

    and presumably construction of the line has begun, the PIU would be reinforced and merged into

    the RTC to ensure the construction can properly supervised. The PIU would not only be directly

    responsible for the management of the Contractor(s) of the line, but also for the management of

    the Owner‟s Engineer, who in turn will directly oversee the Contractors‟ work.

    24. In 2011-2012, the WAPP and JIC began developing the legal framework for implementation of the CLSG Transmission Line. As discussed in more details in Annex 9, this

    structure is primarily based on creating a RTC by treaty among the States to design, construct,

    own, operate, maintain, and develop the line. The RTC, a supranational entity with commercial

    character, would be set up based on articles of association annexed to the treaty that provide for

    the entity's governance structure. An international project agreement (IPA) implements the

    provisions of the treaty by agreement among the CLSG states and this RTC.

    25. The IPA provides for the countries' obligations towards the RTC and gives the RTC the mandate to implement the CLSG Transmission Line. The RTC's shareholding will be divided in

    equal shares among the national utilities designated for the role by the States and subject to a

    shareholders' agreement that governs the utilities' respective rights and responsibilities. Users of

    the CLSG transmission line are expected to enter into power purchase agreements for the sale

    and purchase of power, and use the line to move the power pursuant to a transmission service

    agreement with the RTC. The ownership structure of the RTC is illustrated in the graph below.

  • 8

    26. On 5 and 18 March 2012 the draft treaty was initialed by the Ministers of Energy of the CLSG states. By the end of April 2012 the outstanding legal documents are to be finalized, and

    the Heads of State are expected to sign the treaty by the end of May 2012. The treaty is expected

    to be ratified by the CLSG parliaments by early September 2012. The RTC is expected to be

    fully staffed by end 2012.

    Figure 2: Ownership Structure of the CLSG Regional Transmission Company

    C. Higher Level Objectives to which the Project Contributes

    27. The project is aligned with the goals and strategies of relevant regional and sub-regional organizations—namely, NEPAD, ECOWAS and the WAPP Organization. The

    WAPP is part of NEPAD‟s development strategy toward regional integration of electricity

    networks. As a result of this strategy, the WAPP aims to create an open, unified regional

    economic space through the integration of markets for infrastructure services. The WAPP‟s

    regional infrastructure development program for ECOWAS states fully aligned with the goals of

    NEPAD. It provides the power utilities of the region with a vehicle to achieve the vision

    embodied in the ECOWAS Energy Protocol –that of creating a “level playing field” to facilitate

    the balanced development of diverse energy resources of the ECOWAS Member States for their

    collective economic benefit, through long-term energy sector cooperation, unimpeded energy

    transit and increasing cross-border electricity trade. The CLSG countries have shown their

    commitment to the project by endorsing the updated WAPP Master Plan (2011) that identifies

    the proposed project as a priority project for the sub-region.

    CLSG Regional Transmission Companya supranational entity with a commercial character

    Énergies de Côte d'Ivoire

    (CI-Energies)

    Liberia Electricity Corporation

    National Power Authority

    Electricité de Guinée

    S H A R E H O L D E R S

    SHAREHOLDERSAGREEMENT

    CLSG TREATY

    ARTICLES OF ASSOCIATION

  • 9

    28. The Project is consistent with the criteria of engagement and selectivity set out in key assistance strategies. These include the World Bank‟s Regional Integration Assistance

    Strategy (RIAS),5 which under its Pillar 1 recognizes the need for improving access to clean

    energy and improving supply reliability. The Program also meets the three key criteria for

    regional projects: (a) involvement of more than two countries (b) economic benefits that will

    accrue to several countries, and (c) evidence of regional ownership and commitment of the

    participating countries and provision of a platform for policy harmonization in power sector

    development.

    29. The Project will reduce greenhouse gas emissions. The interconnection results in reduced use of hydrocarbon fuels in the four countries and helps avoid more than 5.6 million

    tons of carbon over the lifetime of the project in comparison to the “without” project scenario.

    Assuming a damage cost value of US$20 per ton, overall gains from avoided carbon emissions

    can be valued at US$62.5 million in net present value (NPV) terms.

    II. PROJECT DEVELOPMENT OBJECTIVES

    A. PDO

    30. The Project development objectives of the WAPP CSLG Project are: (i) to reduce the cost of and increase the electricity supply at utility level; and (ii) to increase the export capability

    of Côte d'Ivoire.

    31. The Project development objective of the WAPP Integration and Technical Assistance Project is to increase the technical integration of the WAPP network.

    32. While all CLSG countries will benefit of reduced costs and increased electricity supply over the lifetime of the investment of the CLSG transmission line, the impact of the CLSG

    project over the five-year lifetime of the present project is more differentiated as follows: (i)

    Liberia and Sierra Leone are expected to exhibit reduced costs of electricity supply at the utility

    level; and (ii) Liberia, Sierra Leone, and Guinea are expected to experience an increase of

    electricity supply at the utility level.

    33. The WAPP CLSG project will increase Côte d'Ivoire's capacity of exporting electricity by interconnecting Côte d'Ivoire with Liberia, and through Liberia with Sierra Leone and Guinea

    as well. Export could initially come both from Côte d'Ivoire and Ghana. The increased revenue

    stream from exports to Côte d'Ivoire's power sector would be a combination of revenue of sale of

    electricity and transmission wheeling charges. In the medium term, the project would also help

    unlock Guinea‟s large hydropower potential. It is estimated that with the Project Guinea would

    add about 2,800 MW of hydropower capacity and generate an additional 133,400 GWh over the

    period of 2012-2030. Without the project, there would be lower demand for hydropower from

    Guinea, and only 1,600 MW of Guinea‟s potential would be developed generating about 67,500

    GWh over the same period.

    5 Regional Integration Assistance Strategy, IDA and IBRD, April 2008.

  • 10

    34. For the WAPP Integration and Technical Assistance Project, increasing the technical integration of the WAPP network means enhancing the synchronization of the WAPP

    transmission network by installing equipment to enhance such trades and to provide technical

    assistance to the WAPP to ensure better operation of networks.

    B. Project Beneficiaries

    35. The WAPP CLSG Power Interconnection Project. The project beneficiaries are the existing and future customers of the power utilities in Côte d‟Ivoire, Liberia, Sierra Leone, and

    Guinea, who will be provided with more and lower cost power. This cost reduction will help

    make electricity more affordable for households and along with greater security of supply, will

    improve the competitive edge of firms in Liberia, Sierra Leone and Guinea to create jobs and

    spur economic growth. At the end of the project‟s life, a total addition of 5.2 million people is

    expected to benefit from the electricity provided through the line, of which 2.6 million are

    women. Both men and women are expected to benefit equitably from the proposed project.

    36. In Côte d‟Ivoire, revenues from electricity exports will help the newly created Énergies de Côte d'Ivoire (CI-Energies) to increase its income substantially.

    37. The WAPP Integration and Technical Assistance Project. The direct beneficiaries of this project are the power utilities in the ECOWAS region, which will benefit from more

    efficient electricity trades, in turn rendering their own operation more efficient.

    C. PDO Level Results Indicators

    38. The key PDO Level Results Indicators for the WAPP CLSG Power Interconnection Project are the following:

    Annual electricity supply from CLSG imports at utility level (GWh) disaggregated by Liberia, Sierra Leone, and Guinea.

    Annual weighted cost of electricity supply at power utility level in Liberia and Sierra Leone (USD/kWh).

    Cote d‟Ivoire export capability to CLSG countries (MW).

    Direct project beneficiaries (number), of which female (%).

    39. The key PDO Level Results Indicators for the WAPP Integration and Technical Assistance Project are the following:

    WAPP Master Plan Priority projects prepared to financial closure (number).

    Ratio of annual total hours of synchronization of WAPP Zone A against total hours in a year within TCN-CEB-GRIDCO interconnection (%)

    40. Annex 1 presents the detailed results framework for project 1, and Annex 2 provides the detailed results framework for project 2.

  • 11

    III. PROJECT DESCRIPTION

    A. Project Components

    41. Two Projects are presented under this phase of the Program, each of them being implemented independently. The first project is dedicated to the implementation of the WAPP

    CLSG Power Interconnection, while the second project is dedicated to the implementation of the

    supply and technical integration of the WAPP network. Total costs are respectively US$444

    million and US$31.5 million (project 1 includes US$71 million for physical and price

    contingencies). The overall cost is therefore US$476 million (excluding duties and taxes), of

    which IDA is financing US$176 million. A detailed project description is presented in Annex 3.

    The WAPP CLSG Power Interconnection Project

    Component 1.A: Power interconnection between Côte d’Ivoire, Liberia, Sierra Leone, and

    Guinea (US$321.9 million, of which IDA US$84.8 million, AfDB US$106.9 million, EIB

    US$82.9 million, KfW US$37.0 million, CLSG Governments US$10.1 million)

    42. Under this component, the infrastructure of the 1,349 km transmission interconnection between Côte d‟Ivoire, Liberia, Sierra Leone, and Guinea is being financed. The component will

    be implemented by the CLSG Regional Transmission Company (RTC), and it will be co-

    financed by AfDB, EIB, KfW, and IDA. The co-financing structure is based on parallel

    financing. A coordinated procurement strategy for the structuring of the bidding process and

    bidding documents has been adopted.

    Sub-Component 1.A-1: Transmission and Distribution Interconnection

    43. This component will finance the construction of 1,349 km of 225kV double circuit overhead transmission line interconnecting Côte d‟Ivoire, Liberia, Sierra Leone and Guinea. The

    line will have a transmission capacity of 290 MW once completed (see detailed explanation in

    Annex 3). This component is estimated to cost about US$193 million excluding contingencies,

    taxes and duties. The line will be co-financed by AfDB, EIB, and IDA.

    44. The IDA credit will finance the sections of this transmission line within Liberia, from Yekepa, to Buchanan, and onwards to Mount Coffee up to the border with Sierra Leone in Mano.

    The IDA credit will also finance the construction of two lines totaling a total length of 50 km of

    66kV overhead distribution lines in Liberia from Mount Coffee to Monrovia. The agreed

    financing plan foresees for the remaining co-financiers6 the following breakdown: (i) the EIB

    will finance the transmission line between Yiben (Sierra Leone) to the border between Sierra

    Leone and Liberia; (ii) the AfDB will finance the remaining transmission lines as follows: from

    Linsan (Guinea) to Yiben (Sierra Leone), from Nzérékoré (Guinea) to Yekepa (Liberia), and

    from Yekepa (Liberia) to Man (Côte d‟Ivoire).

    45. To ensure the sizing of the transmission line responds to the actual needs on the ground and to reduce the initial investment costs, a two-stage implementation of the proposed

    6 Co-financiers include all multilateral and bilateral institutions involved in the project (AFDB, EIB, KfW, and WB).

  • 12

    component has been adopted. The CLSG interconnection transmission line will be built as a 225

    kV double circuit line with one circuit equipped and with a capacity of 145 MW. The

    transmission towers will be built to support a double circuit line. Under phase 2 the line will be

    upgraded to include the second circuit, with a total transmission capacity of 290 MW. The

    second phase is expected to be undertaken about 3 years after operation of the line is initiated,

    when the load on the line is expected to increase. The financing for this second circuit is not part

    of the present project.

    46. The transmission line has a provision of Optical Fiber Ground Wire (OPGW) in Sub-Component 1-A-1. As per the normal international practice for OPGW, supply, installation, and

    commissioning will be part of electricity wire tender. The AfDB is considering exploring the

    feasibility of using the line for purposes of telecommunications as part of its financing, which

    could add to the revenue of the line.

    Sub-Component 1.A-2: Substations

    47. This sub-component will finance the construction of 11 225kV substations in Yekepa, Buchanan, Mount Coffee and Mano in Liberia; in Kenema, Benkongor, Bumbuna, Yiben, and

    Kamakwie in Sierra Leone; and in Linsan and Nzérékoré in Guinea. Additionally, this

    component will provide financing to the required compensation system. The feasibility study

    identified that compensation equipment would need to be installed in the substations of Mount

    Coffee (Liberia), Bumbuna (Sierra Leone), Linsan (Guinea), and Man (Côte d‟Ivoire). The

    Owner‟s Engineer will verify the location of the compensation equipment as part of his

    assignment.

    48. The financing plan for the construction of the 11 substations, compensation system and reinforcement of specific substations has been confirmed as follows: (i) the World Bank will

    finance Yekepa sub-station in Liberia; (ii) KfW will finance Mano, Monrovia, and Buchanan

    substation in Liberia; (iii) EIB will finance Bikongor, Kenema, and Bumbuna Substations in

    Sierra Leone; and (iv) AfDB will finance Linsan and Nzérékoré sub stations in Guinea,

    Kamakwie and Yiben substations in Sierra Leone, and Man substation in Côte d‟Ivoire.

    Sub-Component 1.A-3: Supervisory Control and Data Acquisition (SCADA)

    49. This sub-component will finance the procurement and installation of the supervisory control and data acquisition (SCADA) system that will monitor and control the interconnected

    transmission line in the four countries to ensure proper exchange of power and operating control

    of the system. The estimated cost of the SCADA is US$6.4 million and will be financed by

    AfDB. The finances will go towards the financing of a new control center in Guinea, and

    towards the upgrading of the capabilities of the SCADA system and control center in Côte

    d‟Ivoire so that it can accommodate operation of the WAPP CLSG transmission line.

    Sub-Component 1.A-4: Installation and Supply of Compensation and Frequency Regulation

    Equipment

  • 13

    50. This sub-component will finance measures to enhance compensation and frequency control along the CLSG transmission line, which are to be determined by the Owner‟s Engineer

    at a time closer to commissioning of the transmission line. This would include measures to

    minimize reactive power and enhance frequency control in transit situations. This sub-

    component is financed by IDA.

    Sub-Component 1.A-5: Implementation of the Environmental and Social Management Plans

    (ESMPs) and Resettlement Action Plans

    51. The cost of implementation of the Environmental and Social Management Plans (ESMPs) (which includes the cost of the Resettlement Action Plans or RAPs) in the amount of

    US$ 10.1 million will be covered by the respective Governments as part of their counterpart

    financing. The costs of the implementation of the environmental mitigation measures under the

    ESMPs will be almost entirely included in the contractor contract, while the costs of the social

    mitigation measures will be directly born by the CLSG Governments. The measures to be

    adopted in relation to the ESMPs are discussed in the section pertaining to safeguards further

    below as well as in Annexes 4 and 11.

    Component 1.B: Institutional framework and project oversight (US$45.4 million, of which

    IDA US$45.0 million, AfDB US$0.4 million)

    52. Under this component key institutional features of the project will be supported and developed that will ensure the sound implementation of the WAPP CLSG transmission

    interconnector. The component will be implemented or administered by the Regional

    Transmission Company (RTC) and it will be financed by IDA and EIB.

    Sub-Component 1.B-1. Establishment of the Regional Transmission Company

    53. This sub-component will cover the operating costs of the RTC during the construction of the line. It will cover support for the development of the institutional framework of the RTC, the

    setting-up of the RTC, including setting up of systems such as procurement and financial

    management systems and recruitment of staff, and the operational costs during the construction

    phase of the CLSG power interconnection. The AfDB will finance part of the auditing costs.

    Sub-Component 1.B-2. Implementation support through the Owner’s Engineer

    54. The proposed project will finance an Owner‟s Engineer to assist the RTC with (i) overall project management and supervision of the procurement, design, construction and preparation

    for operation and maintenance of the complete investment, including the full transmission line,

    construction and upgrade of substations; (ii) supervision and monitoring of the implementation

    of the Environmental and Social Management Plans (ESMPs) and the Resettlement Action Plans

    (RAPs), based on an agreed monitoring plan; (iii) the carrying out of a compensation and

    frequency regulation studies and measures, to re-evaluate the compensation requirements for the

    line, including reactive power and frequency control in transit situations, and further dimension

    the scope and the scale of compensation and frequency regulation required; and (iv) the carrying

    out of the audits of the Regional Transmission Company.

  • 14

    55. The pre-award (pre-construction) activities for the Owner‟s Engineer will be financed by the EU-Africa Infrastructure Trust Fund through the European Investment Bank (EIB) under a

    single contract and will be lump-sum. Funding for post award (construction) activities of the

    Owner‟s Engineer will be provided by IDA under a separate single contract. This contract will be

    time-based. As agreed with the EIB, the overall assignment for the Owner‟s Engineer will be bid

    out as a single procurement, and World Bank procurement rules will be used. Moreover, the

    World Bank will provide no objections to the client during the recruitment process. Only if the

    Owner‟s Engineer is performing well under the first phase will the firm‟s contract for the second

    phase be signed. This type of contracting is standard best practice for Owner‟s Engineer‟s

    contracts.

    The WAPP Integration and Technical Assistance Project

    Component 2.A: Supply Alternatives Studies and Project Preparation Support (US$10 million,

    all of which financed by IDA)

    56. Under this component a key studies will be conducted to ensure that in the medium to long-term the generation capacity along the line will be developed in a timely manner and in

    accordance with least cost principles. More specifically, technical assistance will be provided for

    preparatory institutional, legal, pre-feasibility/feasibility, and environmental and social impact

    assessment studies for the CLSG transmission line and potential hydropower plant candidates

    along the transmission line. The potential hydropower plant candidates may include (i) Bikongor

    hydropower plant (Sierra Leone); (i) Kassa B hydropower plant (Guinea); and (iii) Souapiti

    hydropower plant. These project sites have been identified as part of the least cost expansion

    plan along the WAPP CLSG interconnection through the updated WAPP Masterplan (2011).

    This component will be implemented by the WAPP Secretariat, and it will be financed by IDA.

    In addition, this component will support project preparation, including the WAPP CLSG JIC,

    through studies and support of decision meetings, training, staffing and outfitting of a Project

    Implementation Unit (PIU).

    Component 2.B: Technical Assistance and Integration of WAPP network (US$21.5 million,

    all of which financed by IDA)

    57. This component financed by IDA proposes to support the integration of WAPP networks and to provide technical assistance.

    Sub-Component 2.B-1: Technical Integration of WAPP Network

    58. The establishment of a sub-regional market for electricity is conditioned by the interconnection and synchronous operation of transmission networks. Frequency and load/supply

    control is one of the challenges of a synchronous interconnection. The proposed synchronization

    component will address this issue, thereby reducing supply costs and increasing supply volume

    in the WAPP. The WAPP will implement this component in at least five power utilities in the

    ECOWAS region. An updated feasibility study will determine the equipment needs. Then a

    single contractor will install the equipment. WAPP will retain ownership of this equipment and

  • 15

    lease it on a „gratis‟ basis to the power utilities subject to them adequately undertaking the O&M

    of the equipment.

    Sub-Component B-2: Strengthening of the WAPP

    59. This sub-component aims to speed up WAPP project implementation by strengthening the Planning, Investment Programming and Environmental Safeguards (PIPES) Department and

    for the Information and Coordination Center and build capacity. Technical assistance will also

    include supporting the certification process of network operators and will assist the development

    of standardized market operating rules for the WAPP zone.

    60. The project costs (see further below) also include provision for an unallocated amount, which reflects both physical and price contingencies for the project.

    B. Project Financing

    Lending Instrument

    61. The proposed lending instrument is an Adaptable Program Lending (APL). This project is a natural continuation of the previous West African Power Pool (WAPP) Adaptable Program

    Lending (APL) that was developed in 2006 as part of the World Bank‟s support to the regional

    program of the WAPP. It is a horizontal APL4, which covers the sub-region of the CSLG

    countries and connect previously not yet interconnected countries in the sub-region. It is also the

    first phase of a vertical APL. Phase 2 of the APL 4 is expected to be the Mount Coffee

    Hydropower Plant, which is a regional hydropower resource located in Liberia along the CLSG

    Power Interconnection. Principles for advancing to the next phase of an APL within the

    geographical area that delineates the APL‟s (for example APL 4 covers the CLSG countries), are

    (i) the readiness of the subsequent project; (ii) the level of advancement of the preceding phases

    within the geographical area; and (iii) the adherence to WAPP principles, such as the ECOWAS

    Energy Protocol (EEP).

    Project Cost and Financing

    62. The table below presents a summary of the project costs in thousand US$ and the percentage contribution of IDA financing per component. Annex 3 includes a more detailed cost

    breakdown by component. The co-financiers for this project are AfDB, EIB, and KfW. The

    Governments will also contribute to the project.

    Table 1: Project Cost and Financing

    Project Components Project Cost

    (US$ thousand)

    IDA Financing

    (US$ thousand)

    % Financing

    Project 1

    Component 1.A: Power interconnection

    between Côte d‟Ivoire, Liberia, Sierra Leone,

    and Guinea.

    321,948

    8

    84,800

    26%

  • 16

    Component 1.B: Support for the institutional

    framework and project oversight.

    Project 2

    Component 2.A: Supply Alternatives Studies

    and Project Preparation Support.

    Component 2.B: Technical Assistance and

    Integration of WAPP Network.

    Total Baseline Costs

    Physical and Price Contingencies

    45,420

    10,000

    21,500

    398,867

    77,018

    45,070

    10,000

    21,500

    161,370

    14,630

    99%

    100%

    100%

    40%

    19%

    Total Project Costs 475,885 176,000 37%

    63. The table below gives a more detailed breakdown of the project costs and the financing by respective co-financier.

    Table 2: Breakdown of Project Costs and Financing

    64. Indicative terms for the financing are shown in the table below:

    Table 3: Indicative terms of Financing

    Lender Amount

    (US$ 000)

    Tenor

    (Years)

    Grace Period

    (Years)

    Interest

    Rate

    Service

    Charge

    On-lending

    Term

    EIB 105,180 18 5 1.4% 2 Mil

    Euro Same as

    Gov.

    AfDB(Loan) 28,831 50 10 0.75% 0% Same as

    Gov.

    AfDB EIB KfW WB Governments Total

    [kUS$] [kUS$] [kUS$] [kUS$] [kUS$] [kUS$]

    Component 1.A

    Power interconnection between Côte

    d‘Ivoire, Liberia, Sierra Leone, and Guinea 106,986 82,951 37,067 84,800 10,143 321,948

    1-A-1 Transmission Interconnection 58,793 60,748 0 73,200 0 192,740

    1-A-2 Substations 41,773 22,204 37,067 10,100 0 111,144

    1-A-3 SCADA 6,420 0 0 0 0 6,420

    1-A-4 Compensation and frequency control measures 0 0 0 1500 0 1,500

    1-A-5 Implementation of the ESMPs and RAPs 0 0 0 0 10,143 10,143

    Component 1.B

    Institutional framework and project

    oversight 350 - - 45,070 - 45,420

    1-B-1

    Establishment of the Regional Transmission

    Company 350 0 0 19,170 019,520

    1-B-2 Owner's Engineer 0 0 0 25,900 0 25,900

    25,758 22,228 3,707 14,630 10,695 77,018

    133,094 105,180 40,774 144,500 20,837 444,385

    Component 2.A Studies and Project Preparation Support 0 0 0 10,000 0 10,000

    Component 2.B

    Technical Assistance and Integration of

    WAPP Network 0 0 0 21,500 0 21,500

    2-B-1 Technical Integration of WAPP Network 0 0 0 18,000 0 18,000

    2-B-2 Technical Assistance to WAPP 0 0 0 3,500 0 3,500

    0 0 0 31,500 0 31,500

    133,094 105,180 40,774 176,000 20,837 475,885

    Note: The project financing costs include 10% of phys ica l contingencies and 4.5% of price contingencIes for the World Bank financed parts .

    Component Activity

    WAPP CLSG Power Interconnection Project

    WAPP Integration and Technical Assistance Project

    Total Costs WAPP Int. and Tech. Assist. Project

    Unallocated and Interest During Construction

    Overall Costs

    Total Costs WAPP CLSG Power Interconnection Project

  • 17

    Lender Amount

    (US$ 000)

    Tenor

    (Years)

    Grace Period

    (Years)

    Interest

    Rate

    Service

    Charge

    On-lending

    Term

    AfDB (Grant ) 104,263 - - - - -

    IDA 176,000 40 10 0% 0.75% Same as

    Gov.

    KfW 40,774 - - - - -

    65. The four governments have agreed to finance the cost of implementation of the Environmental and Social Management Plans (ESMPs), including the Resettlement Action Plans

    (RAPs) (US$ 10.1 million), and the Interest During Construction (IDC) (US$5.5 million) as part

    of their counterpart financing. The Government of Liberia will also provide about US$5.1

    million for cost contingencies. The table below shows the indicative amount per country and the

    expected timeline for disbursement:

    Table 4: Counterpart Financing

    Country ESMP

    (US$ mil.)

    IDC

    (US$ mil.)

    Unallocated

    (US$ mil.)

    Cote d‘Ivoire 2.19 1.38 -

    Liberia 2.39 1.38 5.15

    Sierra Leone 3.40 1.38 -

    Guinea 2.16 1.38 -

    C. Program Objective and Phases

    66. The project is part of a wider program by the Bank to support the WAPP priority projects. The goal of the WAPP APL program is as stated earlier, to establish a well-functioning,

    cooperative, power pooling mechanism for West Africa, as a means to increase access of the

    citizens of ECOWAS to stable and reliable electricity at affordable costs. The WAPP has a

    rigorous process of selecting priority projects on the basis of a regional Masterplan (last updated

    in 2011), which uses least cost expansion principles.

    67. Support under the program is accorded in four WAPP zones as follows: (i) WAPP zone A core countries; (ii) WAPP zone B core countries; (iii) interconnection of zone A and zone B

    countries; and (iv) targeted support of most vulnerable WAPP countries. The WAPP CLSG

    project inscribes itself in the support of the most vulnerable countries. Next WAPP possible

    candidate projects include the Mount Coffee Hydropower Plant in Liberia, the Adjarala

    Hydropower Plant between Benin and Togo, and the Gouina Hydropower Plant in Mali.

    D. Lessons Learned and Reflected in the Project Design

    68. The WAPP CLSG project has been designed taking into account broad lessons from the the setting up of the SIEPAC project in Central America (Sistema de Interconexión Eléctrica de

  • 18

    los Países de América Central or Central American Electrical Interconnection System), which

    has similarities with the proposed WAPP CLSG project, especially with regard to the

    arrangements for the creation of a cross-border transmission infrastructure. In addition, lessons

    learned from the design of comparable Bank financed regional APLs for Southern Africa Power

    Pool (SAPP), the Energy Community of South East Europe (ECSEE), and the existing WAPP

    program have been applied. The project has also benefitted from lessons learned from a five

    decades long evolution of the best known regional power market - the Nordic power market

    which is operated by NordPool.

    69. Lack of transmission line usage: lessons of experience from projects show that the construction of cross-border transmission line is a necessary condition for trades to take place,

    but not a sufficient condition to enable the flow of trades when excess power is not available to

    be traded on the line. The demand-supply balance for Côte d‟Ivoire and Ghana indicate that both

    countries would be able to export power in direction of Liberia, Sierra Leone, and Guinea.

    Moreover, Côte d‟Ivoire‟s Minister of Energy confirmed in a joint Memorandum of the four

    CLSG Ministers of Energy dated 5 and 18th

    of March 2012 the availability of 83 MW for the

    export along the transmission line once the construction is complete. In the medium term, Guinea

    can also become a large exporter through development of its hydropower resources. Annex 8

    gives a detailed breakdown of availability of power along the CLSG line.

    70. Even if supply is available in principle, as the demand-supply balance seems to indicate, the question is how power trades can best be incentivized due to a sound institutional framework

    and market design. Beyond the mere availability of trade, the WAPP JIC is envisaging the

    incorporation of the following mechanism in the institutional framework in order to incentivize

    trade:

    Establishing a clear and transparent framework for trades along the line with required use of a standardized Transmission Service (TSA) by including a standard form for this

    agreement in the International Project Agreement of the RTC;

    A simple, yet effective, method to price transmission whose main objective to ensure transmission cost are recouped. The more complex the tariff methodology, the more

    difficult it is for future investors in power generation to anticipate transmission costs. A

    postage-stamp methodology is easier to understand and apply by the entity determining

    prices. A postage stamp tariff methodology has indeed been adopted to determine

    transmission usage costs under the WAPP CLSG Project.

    As part of the tariff methodology, the Gove