Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003648 IMPLEMENTATION COMPLETION AND RESULTS REPORT TF093011, TF099946, TF099943, TF012069, TF015934, TF015935, H‐9920, TF0A1813 ON A GRANT IN THE AMOUNT OF US$ 29.43 MILLION EQUIVALENT TO THE Ministry of Finance & Economic Planning FOR A/THE SOUTHERN SUDAN EMERGENCY FOOD CRISIS RESPONSE PROJECT ( P113586 ) February 22, 2019 Agriculture Global Practice Africa Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08...

Page 1: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

Document of 

The World Bank 

FOR OFFICIAL USE ONLY 

Report No: ICR00003648 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

TF093011, TF099946, TF099943, TF012069, TF015934, TF015935, H‐9920, TF0A1813 

ON A 

GRANT 

IN THE AMOUNT OF US$ 29.43 MILLION EQUIVALENT 

TO THE 

Ministry of Finance & Economic Planning 

FOR A/THE 

SOUTHERN SUDAN EMERGENCY FOOD CRISIS RESPONSE PROJECT ( P113586 ) 

February 22, 2019 

Agriculture Global Practice 

Africa Region 

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

 CURRENCY EQUIVALENTS  

 

(Exchange Rate Effective {Feb 12, 2018}) 

 

Currency Unit  =   South Sudanese Pound 

130.26  =  US$1 

US$ 1.452010    =  SDR 1  

 FISCAL YEAR 

July 1 ‐ June 30                      

 

Regional Vice President: Hafez M. H. Ghanem 

Country Director: Carolyn Turk 

Senior Global Practice Director: Juergen Voegele 

Practice Manager: Mark E. Cackler 

Task Team Leader(s): Melissa Williams 

ICR Main Contributor: Melissa Williams, Behnaz Bonyadian Dehkordi  

Page 3: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

ABBREVIATIONS AND ACRONYMS  

2008 PP  The original Project Paper creating the Emergency Food Crisis Response Project 2011 PP  The first Additional Finance Project Paper dated June 20, 2011 2012 PP  The second Additional Finance Project Paper dated June 15, 2012 2013 PP  The third Additional Finance Project Paper dated October 1, 2013  2014 PP  The fourth Additional Finance Project Paper dated February 28, 2014 2016 PP  The fifth Additional Finance Project Paper dated April 11, 2016 AAH  Africa Action Help ACTED  Agence d'Aide a la Cooperation Technique et au Developpement CMU  Country Management Unit CPA  Comprehensive Peace Agreement CSO  Civil Society Organization EFCRP  Emergency Food Crisis Response Project EFNSP  Emergency Food and Nutrition Security Project EA  Environment Assessment  ESA  Environment and Social Assessment  ESIA  Environment and Social Impact Assessment  ESMF  Environmental and Social Management Framework ESMP  Environmental and Social Mitigation and Monitoring Plan ESSAF  Environmental and Social Screening and Assessment Framework FAO  Food and Agriculture Organization of the United Nations FCV  Fragile, Conflict and Violence  FPCR  Food Price Crisis Response Trust Fund GFRP  Global Food Crisis Response Program GOSS  Government of Southern Sudan/Government of South Sudan IBRD  The International Bank for Reconstruction and Development ICRR  Implementation Completion and Results Report IDA  International Development Association  IPDP  Indigenous Peoples Development Plan IPPF  Indigenous Peoples Planning Framework IRI  Intermediate Results Indicator ISN  Interim Strategy Note ISR  Implementation Status Report  JAM  Joint Aid Management International LICUS  Low‐income Countries Under Stress Grant M&E  Monitor and Evaluation  

MAFS Ministry of Agriculture and Food Security, which previously known as Ministry of Agriculture and Forestry  

M&E  Monitoring and Evaluation NGO  Non‐governmental Organization NPA  Norwegian People’s Aid OP  Operations Manual Policy and Procedures   PCF  Post‐Conflict Funds PDO  Project Development Objective PHRD  Policy and Human Resources Development Fund PIU  Project Implementation Unit  POC  Project Operational Coordinator  

Page 4: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

PMP  Pest Management Plan PP  Project Paper  RAP  Resettlement Action Plan RPF  Resettlement Policy Framework SSTC  Southern Sudan Technical Committee—a technical secretariat within the SSPSC responsible 

for overall coordination and oversight of the project SSTSC  Southern Sudan Technical Steering Committee—an inter‐ministerial, high level Committee 

chaired by the Minister of Agriculture and Forestry and responsible for implementation of the project 

SAFDP  Support to Agriculture and Forestry Development Project TOC  Theory of Change  UN  United Nations  WFP  World Food Programme WVI  World Vision International 

Page 5: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

TABLE OF CONTENTS 

DATA SHEET ........................................................................................................................... 1

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 7 

A. CONTEXT AT APPRAISAL ........................................................................................................... 7 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION ............................................................... 10 

II. OUTCOME ...................................................................................................................... 12 

A. RELEVANCE OF PDOs .............................................................................................................. 12 

B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 13 

C. EFFICIENCY ............................................................................................................................. 21 

D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 22 

E. OTHER OUTCOMES AND IMPACTS (IF ANY) ............................................................................. 23 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 24 

A. KEY FACTORS DURING PREPARATION..................................................................................... 24 

B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 25 

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 28

A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 28 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 29 

C. BANK PERFORMANCE ............................................................................................................. 31 

D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 34 

V. LESSONS AND RECOMMENDATIONS .............................................................................. 35 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 38 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 49 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 51 

ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 52 

ANNEX 5. OVERVIEW OF CHANGES TO THE RESULTS INDICATORS ......................................... 55 

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) ...................................................................... 57 

ANNEX 7. MAP OF PROJECT COUNTIES .................................................................................. 59 

Page 6: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 1 of 60

DATA SHEET 

BASIC INFORMATION

Product Information 

Project ID  Project Name 

P113586 Southern Sudan Emergency Food Crisis Response 

Project 

Country  Financing Instrument 

South Sudan  Emergency Recovery Loan 

Original EA Category  Revised EA Category 

Partial Assessment (B) 

Related Projects 

Relationship  Project  Approval  Product Line 

Additional Financing  P125381‐Southern Sudan Emergency Food Crisis Response Project 

29‐Jun‐2011  Special Financing 

Supplement  P130396‐Southern Sudan Emergency Food Crisis Response Project (AF) 

15‐Jun‐2012  Recipient Executed Activities 

Supplement  P145339‐Southern Sudan Emergency Food Crisis Response Project‐ AF III 

13‐Mar‐2014  Recipient Executed Activities 

Supplement  P149698‐Southern Sudan Emergency Food Crisis Response Project Additional Financing IV 

Recipient Executed Activities 

Supplement  P149700‐Southern Sudan Emergency Food Crisis Response Project AF IV 

13‐Mar‐2014  IBRD/IDA 

Supplement  P151031‐Southern Sudan Emergency Food Crisis Response Project 

12‐Apr‐2016  Recipient Executed Activities 

Page 7: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 2 of 60

Organizations 

Borrower  Implementing Agency 

Ministry of Finance & Economic Planning  Ministry of Agriculture and Forestry 

Project Development Objective (PDO) 

Original PDO 

Increased access to food for consumption by food insecure households or groups living in six of the most distressed counties ofSouthern Sudan. 

Revised PDO 

To support adoption of improved technologies for food production and storage, and provide cash or food to eligible beneficiariesinSouth Sudan. 

PDO as stated in the legal agreement 

See ICR text for elaboration 

Page 8: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 3 of 60

FINANCING 

Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing 

P113586  TF‐93011  5,000,000  5,000,000  5,000,000 

P113586  TF‐99943  1,500,000  1,500,000  1,500,000 

P113586  TF‐99946  700,000  700,000  700,000 

P113586  TF‐12069  3,000,000  2,999,718  2,999,718 

P113586  TF‐15935  3,800,000  3,799,982  3,799,982 

P113586  TF‐15934  3,730,000  3,730,000  3,730,000 

P113586  IDA‐H9220  9,000,000  8,929,337  8,641,597 

P113586  TF‐A1813  2,700,000  2,672,083  2,672,083 

Total  29,430,000  29,331,120  29,043,380 

Non‐World Bank Financing 0  0  0 

Total     0     0     0 

Total Project Cost  29,430,000  29,331,121  29,043,381 

KEY DATES 

Project  Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

P113586  03‐Oct‐2008  27‐Oct‐2008  16‐Feb‐2011  31‐Dec‐2017  31‐Dec‐2017 

P130396  15‐Jun‐2012  31‐Dec‐2017 

P145339  13‐Mar‐2014  31‐Dec‐2017 

P149698  31‐Dec‐2017 

P149700  13‐Mar‐2014  31‐Dec‐2017 

P151031  12‐Apr‐2016  31‐Dec‐2017 

Page 9: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 4 of 60

RESTRUCTURING AND/OR ADDITIONAL FINANCING 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

29‐Jun‐2011  4.95  Additional Financing Change in Project Development Objectives Change in Results Framework Change in Loan Closing Date(s) 

15‐Jun‐2012  7.20  Additional Financing Change in Project Development Objectives Change in Results Framework Change in Loan Closing Date(s) 

01‐Oct‐2013  10.20  Additional Financing Change in Loan Closing Date(s) 

28‐Feb‐2014  11.70  Additional Financing Change in Project Development Objectives Change in Loan Closing Date(s) 

11‐Apr‐2016  17.73  Additional Financing Change in Results Framework Change in Components and Cost Change in Loan Closing Date(s) 

KEY RATINGS 

Outcome  Bank Performance  M&E Quality 

Moderately Satisfactory  Moderately Satisfactory  Modest 

RATINGS OF PROJECT PERFORMANCE IN ISRs 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  24‐Dec‐2008  0 

02  29‐Jun‐2009  Moderately Satisfactory  Satisfactory  .81 

03  22‐Dec‐2009 Moderately 

Unsatisfactory Moderately Unsatisfactory  2.05 

04  04‐Jun‐2010  Satisfactory  Satisfactory  3.08 

05  04‐Apr‐2011  Satisfactory  Moderately Satisfactory  4.70 

06  11‐Mar‐2012  Moderately Satisfactory  Moderately Satisfactory  6.62 

Page 10: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 5 of 60

07  16‐May‐2013  Satisfactory  Moderately Satisfactory  9.64 

08  09‐Dec‐2013  Satisfactory  Moderately Satisfactory  10.20 

09  26‐Jul‐2014  Moderately Satisfactory  Moderately Satisfactory  14.22 

10  02‐Jan‐2015  Moderately Satisfactory  Moderately Satisfactory  21.66 

11  09‐Mar‐2016  Moderately Satisfactory  Satisfactory  26.28 

12  05‐Jul‐2016  Moderately Satisfactory  Satisfactory  26.34 

13  18‐Jan‐2017 Moderately 

Unsatisfactory Moderately Unsatisfactory  26.44 

14  04‐Nov‐2017  Moderately Satisfactory  Moderately Satisfactory  29.04 

SECTORS AND THEMES 

Sectors 

Major Sector/Sector  (%) 

Agriculture, Fishing and Forestry    70 

Crops  60 

Public Administration ‐ Agriculture, Fishing & Forestry  10 

Social Protection    30 

Social Protection  30 

Themes 

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Private Sector Development  100  

Jobs  100 

Human Development and Gender  100  

Nutrition and Food Security  100 

Food Security  100 

Page 11: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 6 of 60

ADM STAFF 

Role  At Approval  At ICR 

Regional Vice President:  Obiageli Katryn Ezekwesili  Hafez M. H. Ghanem 

Country Director:  Kenichi Ohashi  Carolyn Turk 

Senior Global Practice Director:  Juergen Voegele  Juergen Voegele 

Practice Manager:  Karen Mcconnell Brooks  Mark E. Cackler 

Task Team Leader(s):  John Jaramogi Oloya  Melissa Williams 

ICR Contributing Author:  Behnaz Bonyadian Dehkordi 

Page 12: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 7 of 60

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES

A. CONTEXT AT APPRAISAL

Context

1. The Emergency Food Crisis Response Project (EFCRP) was a series of small grants financed through

the Food Price Crisis Response Trust Fund (FPCR), Global Food Crisis Response Program Trust Fund (GFRP),

IDA, and the Policy and Human Resources Development (PHRD) trust fund. It was implemented over 9.5

years between September 2008 and December 2017. The final project cost totaled to $29.43 million. The

components and activities remained largely consistent throughout implementation, with funds shifting to

reflect the increasing food insecurity in the country.  At the time of appraisal, Southern Sudan was just

emerging from 25 years of protracted violent conflict with the Government of the Sudan, and the 2005

Comprehensive  Peace  Agreement  had  established  the  Government  of  Southern  Sudan  (GOSS)  as  an

autonomous entity.1 GOSS’ capacity was still very weak, with few staff in public ministries.

2. Southern Sudan faced continuing residual violence from the previous conflict, returning refugees

following the 2005 Peace Agreement, and structural food insecurity stemming from a combination of: (a)

low  agricultural  productivity;  (b)  poor  state  of  infrastructure;  (c)  the  lost  productivity  ensuing  from

incessant violent conflict; (d) inadequate provision of agricultural services; (e) weak institutions and lack

of  policies  and  regulations;  (f)  inadequately  skilled  human  resources;  (g)  irrational  use  of  natural

resources; and (h) absence of an appropriate land tenure system and land law. Southern Sudan already

relied heavily on  food  imports,2 which were already expensive due  to  fuel and  transport  costs. When

global commodity prices increased, food prices in local markets jumped by as much as 30 percent over a

three‐month period, and local production could not offset expensive imports due to persistent insecurity

in Central, Eastern, and Western Equatoria and in Abyei.

3. The 2008 Project Paper (2008 PP) explained that the EFCRP also demonstrated to donors and the

UN that the Bank was willing to make financial commitments to Sudan. Since re‐engaging in the country

in 2000, Sudan’s arrears prevented the Bank from re‐establishing a normal program. Instead, the Bank

had provided $10 million in IBRD surplus to the two multi‐donor trust funds and funded projects using

Post‐Conflict Funds (PCF) and Low‐income Countries Under Stress (LICUS) grants. The EFCRP, drawing on

Global  Food  Crisis  Response  Program,  addressed  the  criticisms  about  the  Bank’s  commitment  to  the

country.

Theory of Change (Results Chain) 

4. Neither the 2008 PP nor the additional financings were required to explicitly outline a theory of

change. Based on the results framework and descriptions in the project paper, a final overarching theory

of  change  can  be  discerned  and  is  presented  in  table  1.  This  TOC  supported  items  2  and  3  of  the

1 On 9 July 2011, the Government of Southern Sudan became the Government of South Sudan following a referendum on independence.  GOSS refers to both Government of Southern Sudan and Government of South Sudan depending on the time. 2 A 2008 FAO/WFP estimate put the cereal gap at 93 thousand tonnes.2 With approximately 372,000 returnees anticipated in 2008, the gap was expected to increase. 

Page 13: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 8 of 60

Government of Southern Sudan’s 2008 strategy, which called for, inter alia, targeted safety net programs 

and enhancing quick impact agricultural interventions to resource poor farmers to address the price crisis. 

Table 1 EFCRP Final Theory of Change 

Issues/Challenge  Activities  Inputs  Outputs  Outcomes 

Low food production leads to high prices 

Investment support to crop and livestock production 

Improved cereal, vegetable, and pulse seeds 

Increased production and higher yields  

Increased availability of food for local markets and producer households 

Increase agriculture labor opportunities 

Cultivation techniques training 

Mechanization for land preparation  

More land prepared and faster 

Animal restocking/health 

Increased meat, milk, and eggs  

Fishing equipment provision/training 

Increased availability of fish 

Investment support to post harvest management 

Post‐harvest management training 

Decreased food loss Increased food availability into lean season Fish processing training 

Availability of protein for longer period 

Mechanization for processing 

Value addition to agriculture products 

Increased trade in processed flour 

Increased income potential  

Poor infrastructure for agriculture 

Cash for Work/Food 

Grain storage construction  

Increased storage capacity  

Increased food availability over time 

Road repair Improved access to markets  More food arriving 

in local markets 

Households cannot afford food 

Market repair Better facilities for sellers 

Payment for work Increased household income 

More food for households 

5. EFCRP sought to address both the supply and demand challenges in local markets. It promoted

local production of key staple foods, vegetables, and animal products, which fed the producer households

and supplied local markets. It did this by providing technology for production, storage, and processing in

addition  to  training  on  good  farming  and  harvest  practices.  The  cash  for  work  program  invested  in

infrastructure important to farmers (e.g., market access roads, grain storage facilities) and put cash in the

hands of food insecure households so they could purchase food locally. As the project added additional

financings,  the TOC clarified as did the  indicators measuring  it—changing from general goals  (such as,

increased food reserves) to more concrete inputs (such as, fallow land brought under cultivation, storage

capacity added). As the security and hunger situation deteriorated, the project added unconditional cash

transfers and ultimately food aid through WFP for those too ill or old to work or who could not work due

Page 14: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 9 of 60

to conflict  in the area. Two underlying assumptions to the TOC were that the security situation would 

improve  as  would  the  macro‐economic  situation.  Section  IIIB  “Factors  Affecting  Implementation” 

discusses at length how these assumptions did not hold during implementation, and how the scope of the 

security,  economic,  and  food  security  crisis  ultimately  far  exceeded  the  ability  of  EFCRP  to  have  a 

significant and sustainable impact. 

Project Development Objectives (PDOs) 

6. The 2008 Project  Paper  (2008 PP)  PDO  in  the  data  sheet was  “to  increase  access  to  food  for

consumption by the food insecure households living in six of the most distressed counties of the Southern

Sudan”. There were variations in how the PDO was presented between the data sheet, PP text, and the

Grant Agreement  (GA),  but  the  differences were minor  and  still  adhered  to  the  theory  of  change.  In

keeping with World Bank practice,  the  ICR uses  the  text  in  the GA, which  reflects  text  agreed during

negotiations:  “The  objective  of  the  project  is  to  assist  the  Recipient  increase  access  to  food  for

consumption by food‐insecure households and groups in six counties of Southern Sudan.”

7. The 2008 PP defined  food  insecure households  as  those  lacking  assets  and  technical  support,

mostly constituted by smallholder farmers. Implementing NGOs worked with local authorities to identify

those households  in  the project area. The project approach  invested  in:  (a)  supporting an accelerated

supply response of productivity enhancing technologies to increase “own production of staple foods for

own consumption and internal distribution;” and (b) safety net measures that will target food insecure

households  in  the  same  locations  through  public  works.  Some  of  the  technologies  to  be  introduced

included  improved  seeds,  animal  traction, mechanized  land preparation and  crop management,  post‐

harvest mechanization, and storage facilities.

Key Expected Outcomes and Outcome Indicators 

8. The project proposed measuring progress toward the PDO through two indicators: (a) the percent

of  targeted  farmers  adopting  improved  technologies  for  food  production  in  the  targeted  areas,

corresponding  to  the  goal  of  accelerated  production  for  consumption;  and  (b)  percent  of  target

population  receiving  cash  transfers,  corresponding  to  the  safety  net  measures.  While  the  indicators

aligned to the goals of the PDO, they stopped at measuring inputs rather than whether the amount of

food accessible to households for consumption increased. Measuring production increases of different

crops, changes in local market prices, and the actual purchase of food by the safety net beneficiaries would

have provided better measures of PDO achievement.

Components 

9. The project had two technical components and one management component through the fourth

additional  finance,  which  remained  largely  unchanged  in  terms  of  the  activities  they  supported  (see

Section I(B) for additional details). The most frequent change was the addition of funds and the outcome

targets.  The  fifth  additional  finance  added  a  new  component,  which  is  discussed  in  Section  I(B).  The

original project included the following three components:

Component  1:  Support  to  Agricultural  Productivity  (appraisal:  $3.0  million,  project  close:

US$11.43 million) sought to increase farmers’ own production and improve postharvest handling

Page 15: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 10 of 60

and management  of  food  crops.  It  supported  provision  of  inputs  (seeds  and  tools),  technical 

advice on production and postharvest management, and construction of low‐cost food storage 

facilities and granaries at household and community levels.  

Component  2:  Strengthening  Community  Safety  Nets  (appraisal  $1.5  million,  project  close:

US$13.2 million) created temporary job opportunities and income for the food insecure people

to increase their access to food. It supports cash for work activities where target beneficiaries get

cash  transfers  in  exchange  for  labor.  Typical  activities  included  opening  access  roads  to

agriculturally productive areas and construction of grain storage facilities and markets, among

others.

Component  3:  Support  to  Project  Implementation  (appraisal:  $0.50  million,  project  close:

US$2.1 million) designed to finance administrative costs of the Project Coordination Unit (PCU)

including financial management, procurement, environment and social safeguards management,

monitoring, reporting and evaluation of activities under the project.

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION

Revised PDOs

10. The  original  PDO—to  assist  the  Recipient  increase  access  to  food  for  consumption  by  food‐

insecure households and groups in six counties of Southern Sudan—was revised three times. In the first

additional  finance  in  June  2011  (2011  PP),  the  PDO  was  revised  to  “support  adoption  of  improved

technologies  for  food  production  by  eligible  beneficiaries,  increase  storage  capacity  for  staples,  and

provide cash or food to eligible people participating in public works programs in six counties in Southern

Sudan.” This aligned the PDO more closely to the PDO indicators being used by the team and reflected

the changes in geographic targeting agreed in the original negotiations, although it focused the PDO on

activities as opposed to more strategic outcomes.  The restated and amended GA used the same text for

the new PDO.   The  second additional  finance  in  June 2012  (2012 PP)  revised  the PDO  to align  to  the

proposed change in geographical reach of the project and recognize the change in name of the country

after  independence.  The  fourth  additional  finance  in  2014  (2014  PP)  streamlined  the  description  of

Component 1 and reflected the introduction of direct food support to vulnerable people who could not

participate in cash for work programs due to conflict, age, or infirmity.

Revised PDO Indicators and Outcome Targets 

11. The  project  adjusted  its  targets  with  each  additional  finance  made  changes  to  the  project

indicators.  Ultimately,  none  of  the  indicators  from  the  2008  PP  remained  at  the  end  of  the  project.

Changes and additions brought clarity to the indicators and how they were measured.

12. Based  on  instructions  from  the  GFRP,  which  funded  the  project,  the  team  changed  the  PDO

indicators  to  farmers  adopting  at  least  one  improved  technology  for  food  production  (number  and

percentage) and targeted population receiving cash transfers (number instead of percent). These were

agreed with MAFS  and  the  implementing  NGOs  at  a workshop  in  December  2009, which  introduced

indicators specified by the GFRP Secretariat after the 2008 PP had been approved. Annex 5 gives a full

review of the indicators

Page 16: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 11 of 60

Revised Components 

13. The  fifth  additional  financing project  paper  in April  2016  (2016‐PP)  added  a  new  component,

Support to Improved Nutritional Outcomes, that sought to increase the production and consumption of

foods of high nutritional value and build institutional capacity to support nutrition‐sensitive agriculture.

The project PDO did not change with the addition of this component, which had three subcomponents:

Strengthening of farmer groups for  increased diversification of  locally produced foods would

build  the  capacity  of  the  smallholder  farmers  already  supported  under  the  EFCRP  project  in

Nagero,  Tali,  Morobo,  Jur  River,  Juba,  and  Aweil  South  counties  to  diversify  their  local  food

production to include legumes, fruits, vegetables, and small animal products.

Improved Food and Nutrition Practices would improve households’ knowledge and practices of

food and nutrition to improve food consumption patterns—focusing on both farmers and mother

support groups. It also promoted new technologies and incentives to reduce post‐harvest losses,

test labor, and energy saving technologies especially for women as well as address health issues

such as aflatoxins in foods.

Strengthening Institutional Capacity to  Improve Integration of Nutrition  in Agriculture would

build  the capacity of national  institutions  for better nutrition outcomes through  integration of

nutrition  in agriculture and promotion of a multi‐sectoral approach to addressing malnutrition

and exploring the possibility of bio‐fortification to enhance nutrition.

14. Ultimately, implementation of this component was delayed by one year due to another outbreak

of fighting in July 2016, which caused the Bank and most other donors and NGOs to evacuate the country

for several months. The grant was implemented between July 1 and December 31, 2017 but only in Jur

River,  Juba,  and  Aweil  South  counties  due  to  time  constraints  and  remaining  security  restrictions  in

Nagero, Tali, Morobo.

15. From the beginning of the EFCRP to the project closure on 31 December 2017, Component 1 on

agricultural production shifted from being 60 percent of total project cost to 47 percent. The component

on  safety  nets  shifted  from  30  percent  of  project  cost  to  50  percent.  This  shift  in  investment  in  the

components was consistent with the deteriorating humanitarian situation in the country.  By the end of

the project, the final four components were:

Table 1. Project costs by component 

Component 

Original  Project 2008 

Additional Finance (US$ million) 

Total 1 

2011 2 

2012 3 

2013 4 

2014 5 

2016 

Support to Agricultural Productivity  3.00  1.30  1.40  2.73  3.00  ‐  11.43 

Strengthening Community Safety Nets   1.50  0.70  1.50  4.00  5.50  ‐  13.20 

Support to Improved Nutritional Outcomes  ‐  ‐  ‐  ‐  ‐  2.30  2.30 

Support to Project Implementation   0.50  0.20  0.10  0.80  0.50  0.40  2.50 

Total  5.00  2.20  3.00  7.53  9.00  2.70  29.43 

Page 17: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 12 of 60

Other Changes 

16. The  third  Additional  Financing  (2013),  added  upgrading  of  the  Palotaka  Basic  Seed  Center  to

component 1 “Support to Agricultural Productivity”. The fourth Additional Financing (2014), a $5 million

activity for general food distribution through World Food Programme (WFP) was added to Component 2

in response to the worsening food security situation.

Rationale for Changes and Their Implication on the Original Theory of Change 

17. All the changes made to the PDO statement, funding amount, and key performance indicators

were aligned with the original theory of change which had the PDO outcome of increasing the ability of

food  insecure households  to access  food.  The addition of  the  investment  for  the Palotaka Basic  Seed

Center  supported  the  PDO  and  the  goal  of  increasing  production  by  facilitating  the  bulking  and

multiplication of higher yielding seeds thus making them available for farmers because quality seeds are

a major constraint to farmers throughout the country.

II. OUTCOME

A. RELEVANCE OF PDOs

Assessment of Relevance of PDOs and Rating

18. Relevance the PDO is rated substantial. While the PDO wording changed three times, the theory

of change remained constant, and it was very relevant to the food security issues facing Southern/South

Sudan. The significant change in wording came in the 2011 PP, which changed the language to focus more

explicitly on the inputs and activities the project supported. In 2016, new PDO and intermediate outcome

indicators  were  added  to  track  activities  to  improve  nutrition  in  addition  to  food  security.  EFCRP’s

objectives aligned to the World Bank Interim Strategy Note (ISN) of 2008 for Sudan, which, in Southern

Sudan, focused on improved governance and decentralized service delivery to the states, counties, and

communities, drawing on the experiences of the Comprehensive Peace Agreement period (2005‐2011).

Subsequent additional financings were similarly informed by the World Bank's 2011 strategy for Africa,

Africa's  Future  and  the World  Bank's  Support  to  It,  the  2011 World Development  Report  on  Conflict,

Security and Development, and the South Sudan Interim Strategy Note (2013‐2014). The goals remained,

perhaps, even more relevant after closing in December 2017 given the conflict/post‐conflict conditions

prevailing in the country and the high level of food insecurity. Activities like those under EFCRP are being

implemented under the current Emergency Food and Nutrition Security Project (EFNSP) with a greater

emphasis on humanitarian aid.

19. The relevance of  the project design  is  conservatively  rated as  substantial. When  the original

project was designed, Southern Sudan was affected by low production and a dependence on food imports

that resulted in high food prices that were exacerbated by the global food price crisis. EFCRP provided a

rapid intervention that brought assets (seeds and tools) to farmers and created work opportunities for

food insecure households to earn cash for food. The combination of agricultural productivity and cash for

public works should be considered a good practice approach for such conditions because  it addressed

both  the supply side and demand side constraints within a given area. More  food was produced, and

people had more money to buy the food, which increased income for the producers to invest in additional

Page 18: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 13 of 60

production. The simple and modular design—which remained throughout the life of the project—allowed 

it  to  respond  to  the different needs of  project  communities  as  implementation progressed. Once  the 

security situation deteriorated, this also allowed the implementing NGOs to determine what activities to 

focus on given  the  fluid  conditions was also a good decision.  In  interviews with  some NGO staff  they 

indicated they are often limited by other programs to delivering humanitarian aid, even when the targeted 

communities ask for farming assistance over food.  

20. There were some weaknesses in the design decisions that lead to the conservative rating. It may

have  been  better  for  the  grants  to  be  linked  directly  to  the  Support  to  Agriculture  and  Forestry

Development  Project  (SAFDP)  under  the  MDTF‐S  as  additional  financing,  especially  since  the  initial

geographic  targeting  aligned  in  part  to  that  project.  SAFDP was  already  under  implementation when

EFCRP  was  designed,  and  MAFS  was  the  implementing  agency  for  both  projects,  and  the  2008  PP

discussed the complementarities between the two projects. The clear connection in terms of activities is

evident in that the EFCRP activities in Leer and Panyikang counties were ultimately shifted for a time to

the  SAFDP project with  the  2011  PP  using  the  same  implementing  partner—Norwegian  Peoples’  Aid.

Attaching the grant to SAFDP could have facilitated better synergies between the two projects, simplified

monitoring  for  the  stretched  resources  in  MAFS,  and  allowed  the  Bank  and  MAFS  to  reassess  the

continuation of EFCRP when SAFDP closed in 2012. One reason for keeping EFCRP separate was raised in

the 2008 PP, and that was the need to show development partners that the Bank was willing to invest its

own resources, as opposed to MDTF‐S resources, into Southern/South Sudan. At the time, the FPCR trust

fund was perceived as Bank funds.

B. ACHIEVEMENT OF PDOs (EFFICACY)

Assessment of Achievement of Each Objective/Outcome 

21. Efficacy is rated substantial.  Considering the FCV environment, it is extraordinary that over the

life of the project, EFCRP reached 339,433 people, of which 47 percent were women. This fell just short

of the target of 384,500 people, (of which 50 percent women).3 This achievement was made even though

implementation was hampered by increasing insecurity. The assessment looks at project delivery on the

major goals in three phases:

Phase 1: September 2008‐June 2011, which implemented in Yambio, Morobo, Leer, Panyikang,

Raga, and Tonj North counties;

Phase 2:  July 2011‐June 2016 which covers the first through the fourth additional  finance and

implemented in Yambio, Morobo, Leer,4 Jur River, Panyikang, Raga, Tonj North, Terekeka, Maban,

Nagero, and Pochalla; and

Phase 3: July 2016‐December 2017, which added the focus on nutrition and implemented in Jur

River, Juba, and Aweil South counties.5

3 The final progress report from MAFS gives a figure of 442,921, of which 51 percent were women, but the ICRR team used World Bank ISR reporting throughout the report to be consistent.  The more conservative number reported reflects  4 Leer and Yirol ultimately had to be dropped due to insecurity.  5 Nagero, Tali, and Morobo had to be dropped due to insecurity.  

Page 19: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 14 of 60

Component 1 Goal: Increasing the Supply of Food 

22. Farmers adopting new production technology. Phase one measured the number of farmers that

adopted at least one improved technology for food production, setting a target of 130,000. According to

project reports, the IPs surpassed that target, helping 189,000 farmers adopt an improved technology by

July  2011.  In  phase  2  the  project  continued  to  measure  the  number  of  farmers  adopting  improved

technologies for food production, surpassing the final target of 266,000 by achieving 272,620. Phase 2

also clarified the PDO and indicators, and the technical interventions—seeds and planting materials, small

processing equipment and tools, advisory services, and the goal of expanding current household’s areas

under cultivation to a minimum of five feddans.

23. The  technological  inputs  included  mainly  seeds,

malodas,  toria,  some  ox  ploughs,  and  in  a  few  instances

power  tillers  or  tractors.  According  to  the  2011  project

paper, the impact of this technology on yields was positive—

yields  of  sorghum  on  EFCRP  farmer  field  increased  100

percent in Panyikang, 71 percent in Morobo, and 43 percent

in Yambio. Given that cultivation had decreased or ceased

during  the  war  with  Sudan,  the  significant  increase  is

understandable. Farmers supported by  the project  toward

the end of Phase 1 cultivated an average of 0.43‐1.3 hectares 

of land.6 The distribution of seeds was more equitable than

market‐oriented than originally intended. MAFS wanted to

include farmers with larger farms who could produce more

food for local markets. The support for households working

the  smaller  plots  was  a  trade‐off—more  households

engaged  in  the project, with  just enough  for  food security

and  a  little  surplus  for  local  markets  (at  least  those

cultivating 1.3 hectares).7

24. In Tonj North, WVI also supported crop production

through distribution of seeds, malodas, hoes, and some ox 

ploughs.  It  worked  beyond  staple  crops  and  trained  five  women’s  groups  in  improved  vegetable 

production techniques and installed vegetable gardens. Another group of 25 women received sheep and 

goats, and 50 households received training on fish drying/handling. WVI reported an 80 percent increase 

in  households  with  diversified  income  sources  and  a  40  percent  increase  in  target  households  with 

vegetable gardens and producing green leafy vegetables.8   

25. Expansion of  land under  cultivation. Given  the cultural practices  in  the allocation of  land—in

6 2011 PP 7 MAFS. 2014. Private Sector‐Driven Agricultural Modernization Working Paper 3 for the Agricultural Development and Food Security Project.  8 World Vision. Project completion report Tonj North County, September 2010 ‐ July 2011. Received by ICRR team July 2018.  

Farmer in Ngingo boma, Yambio, with her casava mosaic virus free crop (credit AAH‐I).  

Tonj North Farmer Field Day training (credit WVI) where farmers learn, inter alia, the benefits of planting in rows instead of broadcasting seed for cultivation.  

Page 20: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 15 of 60

some areas, the village head allows people to cultivate land, but ownership does not change hands, so 

the land remains communal. The plot size per household was not tracked; however, new land brought 

under  cultivation was.  By  introducing  labor  saving  equipment  for  land  preparation—e.g.,  ox  ploughs, 

power tillers, tractors—the project surpassed the target of 38,800 hectares of previously fallow land by 

roughly 170 percent to achieve 104,741 hectares.  

26. Introducing  post‐harvest  technology.  Post‐harvest

technology was  supported  in  phase  1,  reaching  approximately

82,000  farmers,  but  it  was  explicitly  tracked  in  the  results

framework  in  phase  2.  In  terms  of  the  number  of  farmers

adopting practices and  initiatives  for postharvest handling and

management, the project surpassed the final target of 100,700

with  the  final  figure  of  125,211.  By  the  project  end,  125,211

farmers  adopted  new  practices  and  initiatives  for  postharvest

handling  and management  after  being  trained  by  the  project,

surpassing the target of 100,700. The project also provided new

machinery  to  facilitate  new  introduction  of  technology, which

the beneficiaries adopted as reported  in the anecdotal  reports

accessed (see photos).

27. Increasing storage capacity. The project was not able to

measure the number of food insecure households in the project

area that had food reserves during phase 1 due to the difficulty

in  establishing  a  baseline  and  difficulty  in measurement  given

that  there  were  investments  in  household  and  community

storage—depending on  the  community demand.  The  indicator

was  revised  for  Phase  2  to  track  the  additional  grain  storage

capacity  created overall. According  to project  ISRs,  the project

exceeded the final target of 8700 metric tons of storage capacity

by  building  11,092  metric  tons  of  storage  capacity  at  the

community  and  household  levels.  In  most  areas,  the  project

supported more rudimentary technology for storage, which was

within the ability of communities to build and maintain and for

which materials were readily available.

28. The  overall  project  impact  on  food  production was  as

follows:

a. Under  the  2008  PP  (2008‐2011),  about  190,000

beneficiaries  cultivated  on  average  about  1.0  feddans  (or  0.425  hectare)  equaling  80,750

hectares.  Based  additional  data  provided  on  beneficiary  cultivation  patterns  in  Yambio  and

Morobo  during  phase  1,  about  83  percent  of  cropping  was  used  for  cereals.  Taking  a  more

conservative estimate of 70 percent of EFCRP cropping area going to cereals, that would mean

Training in fish drying/smoking in Tonj North (credit WVI) 

Food Preparation and Preservation of Vegetable in Tonj North (credit WVI) 

Improved granary in Morobo 

Rice mill in Morobo 

Page 21: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 16 of 60

56,227 hectares were planted with cereals in the project areas. Data from FAO/WFP in the CLIMIS 

database for 2011 show that in the six counties where EFCRP operated, the total area under cereal 

production was 66,268 hectares. Therefore, upwards of 85 percent of cereal production in the 

EFCRP counties in 2011 is attributable to the project. See tables 2 and 3. 

b. During  the  remaining  years  of  the  project  (from  2011‐2016),  an  additional  83,620  farmers

adopted  improved  technology with  the goal of  cultivating 5  feddans per  farmer. Assuming an

average of (1.275 hectares) per beneficiary, 106,616 hectares were added (tables 2 and 3).

c. Up to 2014 when the bulk of project lending for productivity had already occurred, cropped area

and total production maintained a healthy increase over the early years of the project (tables 2

and 3). Due to the conflict, however, area under cereals harvested reduced, resulting in reduced

production (see graph FAOSTAT).

d. The  project  supported  the adoption  of  post‐harvest  technologies  for  125,000  farmers  and  an

additional 11,000 tons of storage capacity to ensure temporal availability of foods, all contributing

to reduced losses and longer availability of processed foods for consumption. According to field

reports  from  IPs,  several  farmers  indicated  that  they  would  construct  their  own  household

granaries after they saw how effective

Table 2 Total cereal production area (hectares) in EFCRP counties during the life of the project 

State  County  2010  2011  2012  2013  2014  2015  2016 

Central Equatoria  

Morobo   10,351  10,060  12,550  13,079  25,099  37,603  9,783 

Terekeka   26,858  18,409  18,961  18,224 

Western Equatoria  

Nagero  2,311  1,731  1,914 

Yambio  25,080  29,251  34,970  36,414  37,770  33,156  22,302 

Lakes   Yirol  28,583  25,594  36,505 

Warrap   Tonj North  22,143  15,065  30,333  25,543  18,736  20,505  22,809 

Western BeG 

Raga   6,406  6,946  7,221  9,553  11,056  11,388  6,260 

Jonglei   Pochalla     6,003  5,007  5,894  6,625 

Unity  Leer  3,536  3,007  2,814  4,105  639 

Upper Nile  

Maban  4,362  4,546  3,461  4,990  5,370 

Panyikang   2,090  1,939  2,016  2,522  ‐  162  680 

69,606  66,268  94,266  128,623  150,432  159,984  131,111 Source: FAO/WFP data in CLIMIS database.  http://www.climis‐southsudan.org/crop/data 

Table 3 Net cereal production (tonnes) in EFCRP counties during the life of the project 

State  County  2010  2011  2012  2013  2014  2015  2016 

Central Equatoria  

Morobo   7,453  7,243  9,036  11,510  32,126  51,140  12,522 

Terekeka     21,486  16,200  10,618  13,122 

Western Equatoria  

Nagero  1,849  1,524  1,684 

Yambio  27,086  30,422  36,369  40,784  45,324  34,483  23,194 

Lakes   Yirol   25,750  24,570  32,125 

Warrap   Tonj North  15,057  7,834  15,773  16,348  14,989  16,404  18,247 

Western BeG 

Raga   6,406  6,946  4,910  7,643  12,383  10,932  6,010 

Jonglei   Pochalla     5,763  5,207  4,715  5,300 

Page 22: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 17 of 60

State  County  2010  2011  2012  2013  2014  2015  2016 

Unity  Leer  1,980  505  900  1,971  1,117  224  358 

Upper Nile  

Maban  2,094  2,182  1,661  3,194  3,437 

Panyikang   1,254  489  968  1,614  N/A  104  435 

101,843  94,829  119,003  133,510  156,606  157,908  116,434 Source: FAO/WFP data in CLIMIS database.  http://www.climis‐southsudan.org/crop/data 

Increasing Income Through Safety Nets 

29. Cash for Work. Project reports cite initial difficulties implementing the safety nets because the

IPs were not familiar with the approach promoted by the project. However, the World Bank team, MAFS,

and the NGOs worked to overcome the confusion, and by the end of phase 1 in June 2011, the project

reached 24,462 people with cash for work, exceeding the PDO target of 20,000.

30. The original project also had some learning

by doing regarding what could be measured under

the circumstances and how. The practice of paying

by  task  instead  of  daily  rates  is  one  example  of

difficulty  in  tracking  data  as  originally  planned  in

project  design.  Similarly,  the  initial  criterion  for

targeting  food  insecure  households  was  not

effective due  to  the  local  culture. Box 1 describes

how  Africa  Action  Help—the  IP  in  Morobo  and

Yambio  counties—entered  communities  and

identified  beneficiaries  for  the  safety  nets

component (see box 1).

31. By  the  end  of  phase  2,  EFCRP  supported

110,000  beneficiaries  with  cash  for  public  works,

averaging 22,000 beneficiaries per year. It had also 

informed the technical design of the Skills Development and Safety Nets Project, which was approved in 

2013. 

32. As agreed with GOSS, the cash for work activities enhanced agricultural productivity in the project

area—e.g., feeder roads, market cleaning/upgrading, grain storage, and the like. For example, in two road

rehabilitation projects, there were 690 individuals (510 men and 180 women) employed to repair 6.5 kms

of the Morobo‐Iraga road and 7 kms of Aboroto‐Yugufe road. Activities included clearance and stumping,

road formation (earth works), drainage, murram digging, and spot murraming.9 In Morobo, 300 people

(198 men  and  102 women) were  employed  to  rehabilitate  23.6  km  of  feeder  road  by  bush  clearing,

excavating, and spreading murram to selected sections, and another 76 people renovated the Karua and

Wuli bridges. In Tali, 225 people (180 M/45 F) were involved in the opening, swamp raising, and gravelling

sections of 11 km feeder road linking Tali center to Pagara Boma.

9 Murram is a gravelly lateritic (clayey) material, often used to surface minor roads in parts of Africa. 

Box  1 Safety nets entry activities by AAH 

To  introduce project public works activities,  the NGO held 

three  Boma  meetings  in  Lujulo,  Panyume  and  Gulumbi 

Payams, which were attended by 54 participants  including 

farmers, chiefs, and local authorities.  The three contractors 

selected  to  manage  the  work  were  introduced  to  the 

construction  sites  through meetings with  local  authorities 

and  the  community,  where  37  participants  attended  the 

meeting. Eligible households for public works were selected 

based on the following criteria: level of food insecurity, idle 

youth  not  involved  in  productive  work,  those  involved  in 

charcoal  burning  and  forestry  destruction,  and  individuals 

capable  of  working.  Feeder  road  formation  training  was 

given to 69 beneficiaries (62 male, 7 female) that formed the 

core  group  for  road  repair.  The  training  covered  road 

alignment,  measurement  for  feeder  road  dimension 

formation and compaction. 

Page 23: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 18 of 60

Rehabilitation of Karua bridge in Morobo county  Installing culverts as part of road rehabilitation in Nagero 

33. Unconditional  food  transfers.  The  2014  PP  started  after  the  civil  war  began  and  added

unconditional food or cash transfers to the project deliverables given the severe food insecurity in the

country.  This  was  the  first  time  that  IDA  funds  were  used  in  EFCRP.  The  unconditional  food  aid—

amounting to $5 million—was managed by WFP. A target of 138,000 beneficiaries provisioned with two

months of food was set  in the project paper.  In the contract with MAFS, however, WFP committed to

reach about 58,000 with four months of provisions. Ultimately, it reached 58,680 beneficiaries with four

months  of  food  supplies,  substantially  achieving  the  overall  target  (138,000  x  2  months=276,000

compared  to  58,680  x  4  months  =  234,720). WFP  reported  efficiencies  in  food  procurement  due  to

exchange rate gains and sourcing commodities  from various sources. Given  the dispersed  locations of

those in need, the “land, transportation, storage, and handling” comprised 63 percent of the contract cost

compared to 17 percent to procure the food. This provides a stark picture of the transport challenges in

the country.

Table 4 General food distribution and BSP by state 

States  Cereals  Pulses  Oil  Salt  Supercereal  Total MT Beneficiaries Aug‐Dec 2014 

Jonglei   697.70   151.50  20.76   71.88   941.84   25,250  

Upper Nile   334.95   12.00   46.81   65.12   458.87   10,401  

Central Equatoria   245.95   14.41   20.05   280.41   16,708  

Eastern Equatoria   0.75   0.75   207  

Unity  350.75   11.70  4.38   366.83   5,846  

Lakes   16.05   16.05   268  

Total  1,645.40   175.20  87.11   20.05   137   2,064.75  58,680 

34. Given the difficulty in getting on the ground in country for supervision once the war broke out,

the team only caught the disconnect by the time of the May/June 2016 ISR, just before the close of the

project. If the indicator tracking the WFP work had not been at the PDO level, the mismatch could have

been corrected relatively easily.

Improved Nutritional Outcomes 

35. Activities related to improving nutrition were the focus of phase 3, which was supposed to begin

in July 2016. The outbreak of violence in July 2016 delayed the start of implementation until July 2017, at

which point the World Bank and MAFS agreed to contract the Food and Agriculture Organization of the

United  Nations  (FAO)  to  manage  implementation.  FAO  subcontracted  World  Concern  Development

Organisation  (WCDO),  Joint  Aid Management  (JAM),  and World  Vision  International  as  implementing

partners.  The phase was originally  supposed  to build  the  capacity of  the  smallholder  farmers  already

Page 24: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 19 of 60

 

supported under the EFCRP in Nagero, Tali, Morobo, Jur River, Juba, and Aweil South counties with the 

codicil that locations could change based on the security situation. When operations resumed in July 2017, 

Nagero, Tali, and Morobo were dropped due to insecurity.   

36. In contrast to the other grant activities under EFCRP, phase 3 had the affirmative goal to impact 

nutrition through dietary diversity,10 and it introduced two new PDO indicators. Against a target of 1800 

households increasing the number of foods they produce, the project achieved 4600 households.  To do 

this, the project collaborated with State Ministries of Agriculture and Health, the Relief and Rehabilitation 

Commission, UNICEF, WFP, International Rescue Committee, Action for Development, and Die Johanniter, 

a  German  humanitarian  organization  operating  in  the  area,  to  sensitize  communities  to  the  project 

activities  and  to  nutrition  through meetings  in  collaboration with  county/payam  administrators,  local 

chiefs, and sultans. Following that, 4600 targeted households were organized into 163 groups (20 in Aweil 

South, 40 in Juba, and 103 in Jur River). FAO procured and distributed about 4.8 tonnes of vegetable 

and  legume  seeds,  including  amaranth,  collard,  cowpea,  eggplant,  okra,  onion,  tomato,  and 

watermelon. Hand tools—including, hoes, rakes, spades, watering cans and plastic buckets—were 

distributed to beneficiaries. Beneficiaries in Jur River also received fishing kits comprising gill nets, 

fishing hooks, and twine. To increase availability of animal protein, the project provided 5000 vulnerable 

households with  investment vouchers to acquire 20,000 chickens and 18,000 sheep or goats from the 

local market, which generated income for  local  livestock sellers. Demonstration plots covering 12.6 ha 

provided training on agronomic practices and animal husbandry.  

37. The  project  increased  the  dietary  diversity  of  6000  households  (against  a  target  of  1900). 

Interventions  to achieve  this goal  included providing vouchers  to 6000 mothers of children under‐five 

years of age and vulnerable households  to access nutritious  foods  in  the  local market. The NGOs also 

formed and trained 18 mother‐to‐mother support groups with 450 mothers (100 mothers in Juba and 350 

in Jur River) on income generation, business skills and market linkages. It also established small kitchen 

gardens  for  2300  beneficiaries  (79%  women)  and  trained  2500  beneficiaries  (82%  women)  on  food 

processing  and  storage  and  400  beneficiaries  (38%  women)  on  fish  net  braiding,  processing,  and 

10 Other NGOs did provide support to vegetable production—e.g., AAH, WVI, and Mercy Corps.—however, nutrition impacts were not an explicit goal of the other investments.  

   Beneficiaries redeeming their vouchers for poultry pose with the poultry trader 

A beneficiary shows off her tomato crop 

Page 25: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 20 of 60

 

preservation. 

38. Beyond  assets,  the  project  trained  households  on  the  types  of  basic  foods  they  could  grow 

throughout  the year  for dietary diversity and how they could prepare and process/preserve  the  food. 

Beneficiaries  were  trained  on  food  processing,  preparation  and  infant  feeding  practices,  and mother 

support groups were formed and trained in business skills. Awareness‐raising sessions were conducted 

on nutrition sensitive technologies and on energy‐saving technologies—such as, cooking baskets and solar 

drying  for  vegetable  preservation.  Beneficiaries  for  nutrition  education  were  selected  following  a 

participatory  process  with  the  involvement  of,  and  consultation  with,  relevant  stakeholders  in  the 

nutrition  sector.  They  included  households  with  young  children  on  the  verge  of  falling  into  the 

malnutrition  trap  and  children who  have  graduated  from UNICEF  treatment. While  these  households 

benefited  from  nutrition  vouchers  to  buy  healthy  food,  they  also  received  nutrition  education  and 

demonstrations on  cooking,  food preparation,  and preservation;  and  they were  trained on  setting up 

kitchen  gardens  and using energy  and  labor‐saving  technologies.  Radio  programs were designed with 

beneficiaries to improve knowledge of the importance of a diversified diet. Ultimately, 2781 households 

reported adopting healthier eating habits and 2500 households were using improved food processing and 

storage methods and facilities.    

39. The  project  also  conducted  a  national  capacity  assessment  to  review  the  institutional 

environment for nutrition and coordination. State level consultations with relevant stakeholders from the 

State Ministry of Agriculture, Ministry of Health, and the Universities of Juba and Bahr el‐Ghazal were 

held, followed by a workshop to raise awareness among six states of the Greater Bahr el‐Ghazal region 

and  draft  action  plans  to  mainstream  nutrition  in  agriculture.  Given  the  short  timeline  of  the  project 

(essentially  5 months  for  implementation),  the  planned national  stakeholder workshops  could  not  be 

organized  to  build  stakeholder  capacity  for  nutrition mainstreaming.  By  project  close,  40  agriculture 

professionals reported increased understanding of their role in improving nutrition, which falls short of 

the target, but is an impressive achievement given the context and the short implementation timeline.  

Justification of Overall Efficacy Rating  

40. Overall  efficacy  is  rated  substantial  because  the  objectives  of  increasing  food  production  and 

 

 

 A hay solar cooking basket (fireless cooker) is one of the labor saving technologies introduced by the project 

  Children from Marial Ajiith recording a role play at Voice of Hope Radio Station in Wau 

Page 26: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 21 of 60

 

providing  access  to  cash  for  work  were  surpassed,  despite  the  difficulties  presented  by  increasing 

insecurity and poor accessibility. EFCRP was able to substantially achieve or surpass its targets despite the 

challenges of implementing in an area where the government was just being established, the population 

had been traumatized by years of civil war, accessibility due to poor roads was an issue between April and 

November,  and  where  active  conflict  ultimately  engulfed  the  new  country  for  four  years  of  the 

implementation.  

41. As noted in the preceding paragraphs, much of the evidence of the project’s achievements came 

from indirect sources and not the M&E office of the PIU.  This is why the project is rated substantial instead 

of high.   Progress monitoring  in FCV settings  cannot be expected  to  reach  the  levels of  rigor  that are 

achieved  in  non‐FCV  countries,  particularly  in  times  of  active  conflict.  EFCRP  experienced  consistent 

difficulties in monitoring; however, implementing through reputable international NGOs that were able 

to collect data at the local level and were willing to meet with the ICRR team even 6 years after the close 

of  their activity  increased  the confidence  in  the effectiveness of  the project.  In  the early  years of  the 

project the World Bank and MAFS officials made regular visits to the field to validate reporting from IPs, 

which increased the confidence in the reporting that was submitted from the field during the rest of the 

project when field monitoring was limited for MAFS and extremely limited for the World Bank. The ICRR 

team accessed original completion reports from World Vision, Africa Action Help, ACTED, Mercy Corps, 

and  FAO  and  held  a  workshop with  IPs  in  July  2018  to  review  their  implementation  experience  and 

achievements.  This  supplemental  data  verification,  in  addition  to  secondary  sources  and World  Bank 

implementation supervision reports and project papers, helps tell a more plausible story of the project’s 

achievements.  

C. EFFICIENCY 

Assessment of Efficiency and Rating 

42. Overall, the project efficiently managed seven grants over the life of the project with no delays in 

expensing the grants.  Early inefficiencies in the procurement process were resolved, and the PIU brought 

the project in while fully accounting for all funds and receiving clean audit reports. Nevertheless, efficiency 

is conservatively rated as modest largely because of deficiencies in direct project monitoring by carried 

out by the PIU. In addition, the urgency of the crisis response during preparation and the general lack of 

basic data in South Sudan meant that no financial or economic analysis was carried out prior to project 

implementation in 2008, 2011, 2012, or 2013 (original project and the first three additional financings). 

The 2013 PP committed to collecting data for ex‐post computation of financial and economic returns on 

farm  income towards the end of project  implementation; however,  the civil war erupted shortly after 

approval of that additional financing, which delayed implementation for several months and limited field 

data collection necessary for analysis until the end of the project.  

43. Based  on  a  representative  crop  model  for  sorghum  and  maize  that  was  developed  for  the 

preparation of 2014 PP to estimate financial gross margins in the project area. For EFCRP, average prices 

for  maize  and  sorghum  in  December  2015,  six  months  before  the  end  of  the  project  were  used  to 

determine the gross margin. Sorghum prices ranged from SSP 12/kg in Rumbek to SSP 15/kg in Wau. Maize 

prices ranged from SSP 10.3/kg in Wau and to SSP 11.7 in Rumbek. Drawing on the EFNSP analysis, the 

Page 27: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 22 of 60

 

analysis assumes an average of 1 ha/beneficiary. Based on these numbers, the average gross margin six 

months before project close was US$257 for sorghum and US$150 for maize.   

44. While sorghum and maize are the major crops  in South Sudan and a priority  for  food security 

production,  those  two  crops  represent  just  a  part  of  the  cropped  area  under  the  project.  Seeds  and 

cuttings were provided for groundnut, cassava, pulses, vegetables, and sim sim, but data was not available 

to do an adequate analysis of these crops.  Prices were volatile throughout the project, so financial returns 

were similarly volatile. Informal analysis done by one of the implementing NGOs during Phase 1 of the 

project  (around  2010)  showed  a  higher  cost  of  production  that  negatively  affected  gross margins  for 

maize. There was insufficient data to analyze the returns to mechanization—both for land preparation 

and post‐harvest processing, but this was a small element of the project assets introduced.   

45. The analysis of the cash for work program looked to analysis from similar projects for indications 

of the potential returns.  For this, the World Bank’s SNSDP project, which drew on EFCRP for its technical 

design, did provide an analysis that showed it would cost US$2.07 to transfer US$1.00 in wage benefits to 

the intended recipients, which compared well to similar programs. The EFNSP cash for works component 

ultimately  reached  47,595  people  with  an  investment  of  $8.2  million—about  $172  invested  per 

beneficiary. This is averaged over the life of the project, and it includes the cost of materials. Detailed data 

on the number of people reached each year  in each county was not systematically collected, but AAH 

provided full financial data in their 2014‐15 completion report. In Yambio, Nagero, and Tali counties, the 

public works component provided an average of 56 days employment at about $7/day. This was manual 

repair of several kilometers of road and installation of culverts for each community.  Due to the prevalence 

of bartering in South Sudan, the project noted that introducing cash wages would increase purchasing 

power and stimulate demand in local markets. That EFCRP also supported the supply response in local 

market offset the risk of inflation that could have happened in the absence of functioning markets.  

46. The  amount  allocated  for  operations  under  the  nutrition  component  in  phase  3  was  US$2.3 

million.  The  funds  supported 6000 HH,  averaging  roughly  $54 per  person  to  increase  production  and 

dietary diversity, and the households were continuing to produce and even sell surplus in the market six 

months after the close of the project. By comparison, the general food distribution under phase 2, cost 

$5 million to reach 58,680, and average of $85 per person—this is largely due to the expense of delivering 

food support in high conflict areas.  The cash for work generated about US$4.6 million in wages under the 

public works schemes. With 110,000 benefiting from public works, the project paid out US$42 per person 

annually.   

D. JUSTIFICATION OF OVERALL OUTCOME RATING 

47. Based on the strong results on the ground in an increasingly dangerous FCV context, there was a 

good argument to rate the overall outcome as satisfactory; however, the team decided on a the more 

conservative rating of moderately satisfactory due to the lack of traditional evidence and analysis. The 

overall relevance of the PDO was substantial and the design of the project was an excellent response to 

the challenge being addressed—investing  in both the demand and supply‐side constraints  in a project 

area to increase food security.  Based on the robust data available (albeit from indirect sources), EFCRP 

achieved or surpassed its targets for increasing food security: 

Page 28: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 23 of 60

 

272,620 farmers adopting improved technologies for production (102% of the target) 

104,741 hectares of idle land brought under production (270% of target)  

11,092 metric tons of storage capacity built, which increased the time that food was available in 

communities (127% of the target) 

47,595 participants in the cash for work public works program (128% of target)  

4500 households reporting an increase in the number of foods produced (250% of target) 

6000 households reporting increased household dietary diversity (316% of target) 

2500 households using  improved food processing and storage methods and facilities  (161% of 

target).  

48. Having the safety net component focus on improving farm to market roads, increasing storage 

capacity and preparing farm land created a virtuous synergy with the food production component. The 

simple, modular design also allowed relatively easy expansion of the project as the situation on the ground 

deteriorated. Despite this, the difficulties in project implementation caused by steadily increasing conflict 

and  violence,  economic  crises,  weather‐related  site  accessibility,  and  capacity  gaps  that  were  not 

addressed meant that the project simply did not have the data to prove efficacy and efficiency to meet 

the moderately satisfactory threshold.   

E. OTHER OUTCOMES AND IMPACTS (IF ANY) 

Gender 

49. None of the grants had specific goals along the lines of increasing women’s agency—e.g., power 

to  make  decisions  about  how  household  resources  are  allocated,  etc.  —or  reducing  gender‐based 

violence.  The  focus  on women’s  inclusion  varied  across  implementing  partners,  but  all made  sure  to 

include women  in  project  activities—some explicitly  targeted  female  headed  households  (e.g., World 

Vision, Mercy Corps) while others  reported the number of women reached.  In  line with  the emerging 

requirements for the World Bank core indicators, the team started tracking the number of beneficiaries 

disaggregated by gender, and it achieved 47 percent women’s  inclusion against a target of 50 percent 

according to World Bank ISRs. The fifth additional finance, with its focus on nutrition, reached a higher 

proportion of women—e.g., 79 percent of the beneficiaries of kitchen garden training, and 82 percent of 

trainees on food processing and storage.   

Institutional Strengthening 

50. Regardless of the definition of institutional strengthening used, EFCRP was not primarily designed 

to contribute to this goal.  That said, the primary project paper did say that EFCRP would contribute to the 

increased capacity of MAFS and local authorities to manage and monitor projects. Despite a rocky start, 

the project did build a new working relationship between MAFS and the NGOs (see the next section for 

elaboration).    NGOs  report  close  collaboration  with  local  authorities,  including  county  agriculture 

department and payam extension workers, who supported implementation and were provided transport 

facilities to facilitate their work. Local officials participated in trainings to be able to provide support after 

the end of the project. In addition, EFCRP did provide funding to upgrade the Palotaka Seed Center for 

the purposes of producing quality seeds for farmers.   

Page 29: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 24 of 60

Mobilizing Private Sector Financing 

51. The project was not designed to mobilize private sector financing given the emergency nature of

the operation and the fragile context of the country.

Poverty Reduction and Shared Prosperity 

52. As an emergency project designed to meet immediate food security needs, the project did not

focus on poverty reduction or growth, per se. Given the focus on food security through production and

income support, it certainly increased incomes of producers and mitigated the impacts of poverty during

implementation. However, given the continuing conflict, it has been challenging to measure the impact

on either of the twin goals.

Other Unintended Outcomes and Impacts 

53. Early in the project—by June 2010—the team noted that there was impact on youth jobs with

public works providing livelihood opportunities. Anecdotes from the NGOs indicate that the youth were

especially involved in farm mechanization efforts and took the lead in land preparation in some areas and

the  rehabilitation  of  public  roads  and  the  construction  of  storage  facilities. With  the  first  additional

financing,  the  project  started  measuring  youth  participation  in  the  safety  nets  activities  and  it  was

reported that they surpassed their target of 50 percent.

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME

A. KEY FACTORS DURING PREPARATION

54. At the time EFCRP was designed, the Government of Southern Sudan was just forming and had

low human resource capacity to manage development projects. Several ministries had few or no staff on

the  ground.  EFCRP was  designed  shortly  after  the  Support  to  Agriculture  and  Forestry  Development

Project  (SAFDP) which was  financed  by  the Multi‐Donor  Trust  Fund‐South  Sudan  (MDTF‐SS)  and was

managed by the same ministry. These two projects were not the only agriculture/food security projects

under the MDTF‐SS, so the management burden was not small.

55. The management structure followed SAFDP in that the project was  integrated into the normal

operations of the MAF Technical Directorate for Research and Extension with the Director General (DG)

as  Project Operational  Coordinator  (POC)  for  day‐to‐day  coordination.  This meant  that  a  government

official was essentially managing the project in addition to the rest of his or her portfolio, which was sub‐

optimal given the fiduciary, safeguards, and technical issues that needed intense attention.

56. The decision to use technical assistance and implementing partners (NGOs) for EFCRP ran against

the preference of GOSS, but it was a necessity given limited capacity on the ground and the need to act

quickly. Given the government’s aversion to technical assistance, this decision created further challenges

during  implementation  that,  perhaps  the  inclusion  of  capacity  building  activities  for MAFS  staff  (e.g.,

training seminars with visiting staff from the Bank) could have mitigated.

57. The decision to have project sites spread across six states (and later expanded) was a trade‐off in

terms  of  management  efficiency.  The  reason  for  this  is  that  South  Sudan  has  very  weak  transport

Page 30: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 25 of 60

 

infrastructure, with most roads impassable during the rainy seasons, and sporadic insecurity that existed 

even at  the  time of  project  design.  This made management  and monitoring  especially  difficult  for  an 

already stretched Ministry and Bank team.   

58. As with SAFDP, the design team lacked information on weather, physical conditions, the social 

dynamics of the proposed project areas, and the nature of local markets in the target areas as well.  The 

project  overcame  the  lack  of  capacity  and  information  by  hiring  strong,  reputable  NGOs  for 

implementation—Action Africa Help, Norwegian People's Aid, World Vision, Mercy Corps, HARD‐SSS, and 

ACTED—to implement the project. This prevented the project from adding more detail to the design of 

implementation arrangements and from designing a robust monitoring and evaluation strategy. 

59. The emergency nature of the project combined with delays in contracting the NGOs, fed into the 

failure to sufficiently orient MAFS and NGO staff to the design principles of the project where early on, 

there was confusion over how to implement the safety nets component and how to divide the agriculture 

production activities between subsistence and more market‐oriented farmers (cultivating 5+ feddans).  

This created confusion early on in implementation, which was ultimately overcome, but not without lost 

opportunities.  

B. KEY FACTORS DURING IMPLEMENTATION 

60. EFCRP spanned almost 10 years during which its operating environment changed drastically. It is 

impressive that the project achieved what it did given the circumstances unfolding in the country. This 

section describes the factors that impacted the implementation progress.  

61. Conflict and civil war. The deteriorating security situation ultimately became the defining factor. 

While December 2013 marks the start of a civil war period, intermittent insecurity affected the project as 

early as December 2009, and delayed or prevented implementation in some area (e.g., Pochalla and Yirol 

West).  

62. In December 2013, one month after approval 

of the 2013 PP, civil war broke out, forcing the Bank to 

evacuate the country between 20 December 2013 and 

30 April  2014. During  this  time,  implementation was 

minimal  in  most  locations,  but  given  the  increasing 

need,  the  Bank  pushed  through  a  fourth  additional 

financing in February 2014, which included direct food 

aid through WFP. By the fourth additional financing in 

2014, the project was providing food security support 

in nine counties across seven states (table 4).  

63. The project’s  flexible  implementation model, 

giving  authority  to  the  implementing  partners  to 

determine where and what to implement based on the 

local conditions allowed implementation to continue. The Bank returned to Juba in April 2014, but field 

visits were minimal for the Bank and MAFS due to continued insecurity. A peace agreement was reached 

 A landmine uncovered in Maban county during excavation of a farm pond in 2013 under the grant implementated by Mercy Corps 

Page 31: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 26 of 60

 

in September 2015, after which the Bank, MAFS, and the NGOs made efforts to return to normalcy. The 

2014 PP was set to close in June 2016. Preparations for a fifth additional financing through the PHRD trust 

fund—this time focused on nutrition—commenced and the grant was approved in June 2016. However, 

the peace agreement fell apart  in July 2016, prompting the evacuation of staff from July 2016 to April 

2017.   

64. Economic  turbulence  and  decline.  Economic  crises  at  different  points  of  implementation 

(2008/2009, 2012, and 2016) constrained public sector investment and limited the government’s ability 

to import food.  Very early in the project (2008‐2009), oil prices dropped by around 70 percent, at a time 

when 90 percent of Southern Sudan’s revenue came from oil. Oil prices rebounded somewhat, but a 2012 

dispute over oil with Sudan again restricted the amount of food imported from Sudan and curtailed access 

to fuel by large‐scale mechanized farmers in South Sudan. The situation was exacerbated by an influx of 

refugees and returnees that increased overall food demand. The conflict in December 2013, shut down 

five oil fields, which severely constrained government revenue.  Ultimately, GDP per capita dropped from 

$1,111 in 2014 to less than $200 in 2017. Growing insecurity, low government revenues, and the move to 

monetize  the  debt  led  to  extraordinarily  high  inflation—including  for  food—later  in  project 

implementation.  

Figure 1 South Sudan Consumer Price Index 2011‐2017 with dates of each additional financing 

 

65. Project design elements. The project design had both positive and negative elements. EFCRP was 

simple, with two technical components that could be easily replicated, and adjusted, to work in different 

geographies. The activities were familiar to most NGOs and so could be deployed quickly at various points 

across  the  country.  The  synergy  between  the  two  components multiplied  the  positive  impact  of  the 

project. On  the downside,  the small,  short‐duration grants prevented  the NGOs  from establishing  the 

long‐term  trust  relationship  necessary  to  affect  change.  They  could  not  plan  out  on  a  sufficient  time 

horizon the engagement they think was needed. The many restructurings to add financing to the project 

also created an administrative burden for the project team (dual track approval and reporting), which was 

as different times during implementation, also implementing the SAFDP, preparing a follow‐on agriculture 

project, and preparing and implementing the EFNSP. At the same time, the dispersed nature of the project 

made monitoring difficult, particularly during the rainy season when rain made roads inaccessible.  

Jun‐11100

Jun‐12174

Apr‐13153

Mar‐14153

Jun‐16720

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

Jun‐11

Sep‐11

Dec‐11

Mar‐12

Jun‐12

Sep‐12

Dec‐12

Mar‐13

Jun‐13

Sep‐13

Dec‐13

Mar‐14

Jun‐14

Sep‐14

Dec‐14

Mar‐15

Jun‐15

Sep‐15

Dec‐15

Mar‐16

Jun‐16

Sep‐16

Dec‐16

Mar‐17

Jun‐17

Sep‐17

Dec‐17

Page 32: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 27 of 60

 

66. Accessibility. Aside  from security  issues,  South Sudan  is one of  the most difficult  countries  to 

travel due to the lack of paved roads.  In fact, between April to May and October to November, most roads 

in South Sudan are inaccessible. As insecurity grew during implementation, the costs of monitoring and 

delivering goods increased substantially. At times, logistical issues led to the delayed delivery or loss of 

inputs due to road accidents.   

67. Weather. Weather shocks—including drought, rain, and flood—repeatedly affected accessibility 

to project areas and success of cropping. Early in the implementation, the project learned that drought 

had affected beneficiaries in Upper Nile State, destroying all early planted crops.11  In 2011/2012, delayed 

and erratic rainfall in most parts of South Sudan affected the harvest while drought in the neighboring 

countries limited the availability of food for import. These events coincided with a conflict between Sudan 

and South Sudan over oil that triggered macroeconomic decline that exacerbated the rapidly increasing 

food insecurity in the country.    

68. Implementation through NGOs. EFCRP started when Southern Sudan was an autonomous region 

that  had  only  existed  for  about  three  years.  Government  agencies  were  severely  short  of  staff.  The 

decision  to  implement  through  reputable NGOs,  some  of which were  able  to  provide  their  own  pre‐

financing in anticipation of the funds being reimbursed by MAF, was critical to successful implementation. 

Building trust between the local authorities and the NGOs also took time, which delayed progress at first. 

Trust  was  eventually  established,  and  a  positive  working  relationship  characterized  the  rest  of 

implementation. GFRP ultimately highlighted  the partnership between  the NGOs and  the government 

(see box 2). 

Box  2 Establishing a New Partnership between NGOs and the Government of South Sudan (GoSS) 

Four  international NGOs were  contracted  to  support  the  implementation of  the GFRP South  Sudan Program: Norwegian People’s Aid, World Vision, Africa Action for Hunger International and the Agency for Cooperation in Technical Development. The contractual relationship was defined by an agreement based on Bank procedures that  clearly  identified NGOs  as  consultants  delivering  services  required  by  the GoSS.  The  selected NGOs had working experience in the agricultural sector in South Sudan, extensive knowledge of the local communities, and appropriate  operational  structures  ready  to  be  quickly  scaled  up.  However,  after  the  signature  of  the Comprehensive Peace Agreement (2005) and the subsequent independence in 2011, new working procedures were established. While previously NGOs were only accountable to their donors, they began to be supervised by the new government in place. 

It took some time for the NGOs to adjust to the new reporting requirements; however, they successfully engaged with  the  local  authorities.  They  played  a  crucial  role  in  promoting  awareness  on  important  topics,  especially related  to  gender  issues.  Although  governmental  institutions  remained  structurally  weak,  they  played  an important  role  by  providing  counterparts  to  supervise  the  project;  facilitating  the  exemption  of  taxes  on equipment, materials,  and  inputs  for  the project;  and  disclosing  policy  documents  related  to  agriculture  and forestry development  in South Sudan. Therefore, the relation between NGOs and the GoSS positively evolved during the implementation of the GFRP program. In terms of management, the Internal Coordination Committee, a  forum  in  the Ministry of Agriculture and Forestry, brought  together  the different actors monthly  to discuss implementation of the project and helped in the identification and resolution of key implementation challenges also related to accessibility, logistics, and insecurity. 

Source: World Bank 2012 “Global Food Crisis Response Program (GFRP):  Progress and Lessons Learned” 

11 World Bank. 2009. Implementation Status and Results Report. Sequence 2.  

Page 33: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 28 of 60

 

 

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

A. QUALITY OF MONITORING AND EVALUATION (M&E) 

M&E Design 

69. Monitoring and evaluation was modest. The original project paper outlined more of a supervision 

plan than a monitoring strategy beyond defining the indicators and describing the sources for the data. 

Given the dearth of information about M&E in the 2008 PP (and subsequent additional financings) and 

that EFCRP used the implementation structure and fiduciary systems as defined under the MDTF‐S and 

used for implementation of the SAFDP, it is likely that the project design team planned to build on the 

M&E system defined in the final project paper for SAFDP.  Like SAFDP, EFCRP suffered from the paucity of 

data available to establish baseline values.   

70. Taking a lesson from SAFDP, where “in the absence of a clear plan, a piecemeal approach became 

the actual modus operandi of  the project as  far as M&E was concerned”,12 EFCRP developed a  set of 

indicators  directly  linked  to  the  project  and  held  at  least  two workshops  to  reach  agreement  on  the 

indicators and their measurement. There were, however, changes to the initial indicators once monitoring 

requirements from the FCRP trust fund were communicated after the project was approved.  This led to 

a  disconnect  between  the  2008  project  paper  results  framework  and  the  one  that  was  used  during 

implementation support. Despite the additional preparation, there was some initial confusion over some 

indicators—e.g., what constituted an improved technology—and difficulty measuring other indicators—

e.g., calculating person‐days of labor was not possible due to the nature of assigning and jobs and making 

payment. The original  results  indicators were completely different by the second additional  finance  in 

2012.  

M&E Implementation 

71. M&E remained weak throughout implementation. By the close of the project, there was no M&E 

specialist on staff, and the PIU did not have staff or budget to prepare a borrower completion report. No 

consolidated management  information system database to track physical progress and supplementary 

data was created according to interviews with the Project Director. In the absence of capacity, the PIU 

assembled  the  progress  reports  from  the  NGO  implementers  for  the  World  Bank  team.  Technical 

assistance  was  supposed  to  be  used  throughout  implementation,  which  could  have  bolstered  M&E 

activities; however, the Government was not enthusiastic about outside technical assistance, so coverage 

was patchy. 

72. There was  a missed  opportunity  to  gather  supplementary  data  on,  for  example,  the  types  of 

technology used, the amount and types of seeds distributed, the production levels of crops, the prices 

earned  by  producers,  the  difference  in  prices  in  local  markets  once  the  farmers  began  selling,  the 

kilometers of roads rehabilitated, etc. Enriching data like this was done or not depending on the NGO, and 

12 World Bank.  2013.  Implementation Completion and Results Report for the Support To Agriculture And Forestry Development Project. World Bank: Washington, DC.  

Page 34: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 29 of 60

there was no defined methodology to guide the gathering of the information.  Therefore, good efficiency 

and impact analysis was not possible.  

73. In the early years of the project, regular field missions by the Bank and MAFS could verify the data

provided by the NGOs, and local authorities were also working with the NGOs to do site monitoring. Due

to the outbreak of civil war in December 2013, field missions reduced significantly. While implementation

resumed by March 2014, access to field areas for data validation was constrained. The World Bank team

noted that for most of 2015, MAFS officials were unable to make field visits due to insecurity and could

only resume monitoring visits in early 2016.

M&E Utilization 

74. The indicators finally adopted by the project as of 2012, were enough to gauge progress on project

implementation; however, the World Bank team consistently reported problems with data verification.

Nonetheless, field verification missions that included World Bank staff were possible through 2013, which

adds  a measure  of  confidence  to  the  data  that  the  NGO  partners  were  reporting.  Based  on  project

completion  reports  submitted  by  the  project  implementers—available  from every  implementing NGO

except for one—there was a wealth of data being collected that could have been consolidated and use to

enrich  the  project  knowledge  base.  For  example,  there  are  doubts  about  the  acceptability  of  animal

traction and other mechanization among communities.  EFCRP supported such mechanization and could

have  collected  data  on  adoption  rates  and  qualitative  information  on  issues  limiting  adoption.  Some

implementing NGOs reported on farmers engaging in contracts with private sector buyers in larger cities.

It would have been good to collect data on what farmers and/or cooperatives were able to engage in such

contracts and to gather qualitative data on how these contractual arrangements were formed.

Justification of Overall Rating of Quality of M&E 

75. Quality of M&E is rated negligible because by the end of the project, the paucity of verifiable data

and reports meant  that  the  ICRR  team could not validate any outcomes. The  introduction of  capacity

building  for  PIU  staff  could have helped  increase  the  acceptance of  the  technical  assistance  that was

needed but not readily accepted by the  implementing agency, and  it could have  improved the overall

confidence in the data.

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE

76. Environmental  and  Social.  EFCRP  was  a  Category  B  project  for  environmental  safeguards

throughout the life of the project. The 2008 PP triggered OP 4.01 (Environmental Assessment) and OP

4.09  (Pest Management).  The 2011 PP added OP 4.10  (Indigenous Peoples)  and OP 4.12  (Involuntary

Resettlement,  then the 2012 PP added OP 4.04 on Natural Habitats and OP 4.36 on Forests. Relevant

safeguards  documents were prepared  and disclosed  as  specific  to OPs  as  follows:  Environmental  and

Social Management Framework (ESMF), including a Pest Management Plan (PMP) for OPs 4.01 and 4.04;

an Indigenous Peoples Planning Framework (IPPF) for OP 4.10; and a Resettlement Policy Framework (RPF)

for  OP  4.12.   During  these  updated  PPs,  an  Environmental  and  Social  Screening  and  Assessment

Framework (ESSAF) was prepared for the whole of the South Sudan portfolio in 2012.

77. Despite  capacity  weaknesses  in  safeguards  management  in  the  implementing  agency,  EFCRP

Page 35: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 30 of 60

 

started and ended implementation in safeguards compliance with respect to documentation.  Compliance 

lags occurred in preparation of subsequent management plans – Environmental and Social Management 

Plans (ESMPs) and Resettlement Action Plans (RAPs). At the time of the 2013 PP, a South Sudan Social 

Assessment concluded that most of the people in South Sudan met the criteria for OP 4.10, so an IPP was 

deemed no  longer necessary.  In May 2013, an environmental and social audit conducted by  the Bank 

found  that  safeguards  continued  to be  implemented  satisfactorily  at  the NGO  level. By October 2013 

(when 2013 PP was approved), a consulting firm had been hired by the PIU to manage all safeguard issues. 

That firm, which continued through the end of EFCRP and assured safeguards compliance on the ground. 

According  to  project  reporting,  project  interventions  remained  small  in  scale  and  resulted  in minimal 

safeguard risks that were easily mitigated by the NGO implementers. The collaboration between the NGOs 

and the local authorities was particularly helpful in managing localized conflict between groups. 

78. Financial  Management  and  Audits.  The  implementing  entity  maintained  effective  financial 

management arrangements throughout the life of the project in compliance with the Bank’s policies and 

procedures. A consultant financial management specialist supported the project for the entire duration. 

The  overall  financial  management  performance  was  rated  Moderately  Satisfactory  for  most  of  the 

implementation period, except for the period between July 2016 and January 2017 when it was rated 

moderately  unsatisfactory  due  to  disruptions  occasioned  by  the  July  2016  conflict.  To  mitigate  the 

heightened  fiduciary  risk  following  the  conflict,  implementation of key project  components under  the 

2016 PP was contracted out to FAO, which had adequate capacity. The project submitted all the interim 

financial reports to the Bank within the timelines stipulated in the legal agreement. It also submitted all 

the audit reports to the Bank on time except the audit report for the financial year ended June 30, 2017 

which  was  delayed.  All  the  audit  reports  expressed  unqualified  opinions  with  no  major  financial 

management issues except the audit report for the financial year ended June 30, 2018 when the auditor 

expressed  a  disclaimer  of  opinion  based  on  inability  to  obtain  documentary  evidence  relating  to 

expenditure of USD 2.5 million incurred through FAO.  Withdrawal applications were submitted to the 

Bank on a regular basis with no major delays in funds flow.  

79. Procurement risk rating remained high throughout project implementation. Challenges included 

the institutional weakness to independently implement project procurement activities and the general 

geographical and political  factors during  implementation period. The 2008 PP was prepared when the 

establishment of government systems were at initial stages with challenges related to overall oversight 

and accountability of procurement decisions. The Ministry of Finance and Planning  issued  in 2006 the 

Interim  Public  Procurement  and  Disposal  Regulations  (IPPDR)  that were  not  generally  adhered  to  by 

institutions. Regulations have no legal framework and to date no Procurement Act has been passed by 

the  government.  The  other  factor  is  the  long  lead  time  in  procurement  process  due  to  both  the 

infrastructural and capacity challenges in the country. At a rate of not less than six months to hire a firm, 

project  procurement  did  at  times  negatively  affected  the  project’s  ability  to  adhere  to  the  cropping 

calendar. Conflict in some project areas especially during the period 2014‐2017 affected the procurement 

and contract management. Project supervision was limited to Juba town as corporate security restricted 

movement of Bank staff beyond Juba town. Procurement and contract management was supported by 

experienced  procurement  consultants.  Post  Procurement  Reviews  conducted  showed  moderately 

Page 36: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 31 of 60

 

satisfactory ratings and though with some challenges, procurement objective(s) were largely met with no 

mis‐procurement activities recorded. Procurement performance is rated as moderately satisfactory. 

C. BANK PERFORMANCE 

Quality at Entry 

80. Quality at entry was satisfactory. The design of EFCRP was particularly strong in that it addressed 

both the supply side and demand side constraints affecting food security. When it was being designed, 

several other programs—financed through the MDTF‐SS were under implementation, many working on 

complementary issues of food production and safety nets. This included the SAFDP, which had been under 

implementation  for a couple of years, was  trying  to address  issues of capacity at  the center and  local 

levels, which would have benefitted EFCRP operations.  

81. Implementation  arrangements  were  complex  at  first,  following  SAFDP,  which  mainstreamed 

project  activities  into  the  operations  of  MAF  Technical  Directorates.  The  Southern  Sudan  Technical 

Steering Committee (SSTSC) was an inter‐ministerial committee chaired by the Minister of Agriculture and 

Forestry was responsible for implementation of the project. The Southern Sudan Technical Committee 

(SSTC) was a technical secretariat at the Undersecretary level within the SSPSC and was responsible for 

overall coordination and oversight of the project. A Director General, who was a member of the SSTC, was 

appointed to provide a link between the national level and the NGO implementers at the decentralized 

level and was to be supported by a short‐term project management and administrative specialist and a 

road engineer as the core personnel for the PIU for the project. The PIU for EFCRP was embedded within 

the Project Coordination Unit of MAF so it could be fully supported by their expertise in the said unit.  

82. EFCRP supplemented the capacity of the government with well‐established international NGOs 

with extensive experience working with the local communities on agriculture and safety nets. This was a 

good decision that impacted the ability of the project to start activities despite delays in establishing the 

contracts for the NGOs, and it paid off in term of safeguards management and implementation in conflict 

areas when the security situation worsened. The project also brought in technical assistance in the PIU to 

complement the government staff working on the project.  

83. EFCRP reflected the lessons that had already been learned through SAFDP. It had a comparatively 

simple results framework with a few indicators that were directly related to the project activities instead 

of broad sector monitoring indicators. The team held workshops on M&E with the implementing agency 

and the NGOs to overcome difficulties experienced in developing the M&E system under SAFDP. Based 

on the quality of EFCRP’s data, more was needed to get a workable system established, such as capacity 

building on database creation and management, data verification, using project data for decision support, 

etc.  

84. The World Bank team planned for rigorous supervision of the project, but the selection of far flung 

implementation sites should have been avoided given the poor transport infrastructure in the country. 

Most of the team was based in the Juba Office and provided direct support and supervision as frequently 

as  required.  In  keeping with  the  practice  of  other  emergency  projects,  a minimum  of  four  intensive 

support missions per year were planned in addition to bimonthly review meetings with the implementing 

Page 37: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 32 of 60

 

agencies. A project review was planned for the end of the first year of implementation to focus on: (a) the 

fiduciary issues; (b) the effectiveness of the coordination mechanisms; and (c) achievements of results. 

Implementing  agencies  were  required  to  produce  technical  audit  reports  every  six  months  and  the 

government was tasked with making regular spot visits to project sites.  

Quality of Supervision 

85. The quality of supervision is conservatively rated moderately satisfactory, especially given the FCV 

context. The World Bank team is to be commended for adhering to a critical pillar of the World Bank’s 

approach  in countries affected by  fragility, conflict, and violence, which  is  to stay engaged.   The team 

worked with MAFS to apply for additional funds to keep the EFCRP operation going, preparing additional 

financing proposals while the staff were evacuated due to insecurity. Ultimately, the experience of EFCRP 

into the design of the Safety Nets and Skills Development Project and the Emergency Food and Nutrition 

Security Project. For the latter, it is highly likely that the relationship established between the World Bank 

and the GOSS through EFCRP facilitated the rapid preparation of that project.  

86. During Phase 1 and the early parts of Phase 2, the World Bank team was in the Juba office and 

worked  closely  with  MAFS  and  the  NGOs  to  monitoring  implementation  progress.  It  also  hired  an 

additional consultant to provide close implementation support to MAFS. The team held workshops with 

MAFS  and  the  NGOs  to  agree  on  monitoring  indicators  and  measurement—although  more  capacity 

building  was  required  to  get  the  M&E  system  functioning—and  it  provided  training  on  safeguards 

implementation.  The World  Bank  team  undertook  regular  field  visits  and  joined  project  coordination 

meetings with MAFS. Given the lack of capacity on the part of such a new government and the lack of 

experience on the part of the NGOs and the Government in working together, it sometimes fell to the 

World Bank team to drive implementation, which they did, by and large.  

87. Once civil war erupted in December 2013, supervision became almost impossible (table 5). The 

Bank offices were twice evacuated to Nairobi: (a) 20 December 2013–30 April 2014; and (b) July 2016‐

April 2017, but the Bank team still arranged for  the 2014 PP during  the first and the follow‐on EFNSP 

during the second.  

88. Insecurity ultimately precluded field visits in some areas—especially by the World Bank team—

and it impeded project implementation in several areas. Given the rapidly changing circumstances in the 

country (both from a security and food insecurity perspective), the World Bank team and MAFS adopted 

a  flexible  approach  to  implementation, where  the  combinations  of  activities  (agricultural  production, 

public works, and direct food support) implemented in a project area were dictated by local circumstances 

and relied on the judgement of the implementing agency.  

Page 38: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 33 of 60

Table 5 EFCRP implementation calendar with security issues 

89. Nevertheless, despite persevering under extremely challenging conditions, there were oversights

and missed  opportunities  that might  have  been  avoided.  For  example,  providing  capacity  building  to

government staff at the national  level could have built more long‐term impact than hiring  in technical

assistance. Even training workshops during supervision, VCs with Bank experts for additional training and

guidance, and mentoring of  staff by Bank  team members  could have be workable. The  reporting and

record  keeping  on  the  part  of  the  Bank  team  was  less  than  optimal.  The  team’s  candor  about  the

implementation issues, including scale of the conflict was weak throughout implementation. There were

14 ISRs for a 9.3‐year project (less than the twice per year guideline), and they sometimes lacked detail

on the nature of the issues being incurred. Finally, the Bank’s handling of two of the additional financings

in 2014 and 2016 created errors that dragged down the ratings of efficacy and relevance. In the 2014 PP,

it’s  not  clear  that  the PDO needed  to be  changed  to  add unconditional  cash  transfers  to  the project,

although this may have been required under the circumstances. The indicator to track that activity did not

need to be at  the PDO  level, since  there was already a beneficiary  indicator, and the other safety net

activities were tracked at the intermediate outcome level. An intermediate outcome indicator could have

been  correctly  quickly  and painlessly  revised once  the  confusion between  the Bank’s  targets  and  the

MAFS‐WFP contract was identified, preventing the shortfall on the target. In the 2016 PP, the failure to

revise the PDO to fit the changed nature of the grant led to a break in the relevance of the design in the

project, even though the activities by themselves were relevant to the context.

Justification of Overall Rating of Bank Performance 

90. Based on the above, while consideration was given to rating overall performance as satisfactory,

the  conservative  rating  of  moderately  satisfactory  was  chosen  for  the  reasons  cited  above.  Project

preparation reflected lessons from ongoing project, but the lack of contextual information on the ground

and lack of capacity for World Bank project management in the implementation agency led to weaknesses

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

2008 PP

2011 PP

2012 PP

2013 PP

2014 PP

2016 PP

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

2008 PP

2011 PP

2012 PP

2013 PP

2014 PP

2016 PP

J F M A M J J A S O N D J F M A M J J A S O N D

2008 PP Active implementation

2011 PP

2012 PP Bank evacuated from Juba

2013 PP

2014 PP Implementation under security restrictions

2016 PP

2016 2017

2014 2015

2008 2009 2010 2011

2012 2013

Page 39: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 34 of 60

 

in  baselines  and  monitoring  systems  that  were  not  overcome.  During  implementation,  the  growing 

insecurity ultimately made field level close supervision impossible. The chaos resulting from the unfolding 

situation in South Sudan during this time, certainly explain the shortcomings; however, the World Bank’s 

failure to catch these issues during preparation and supervision reviews and to bring in the extra resources 

to adequately address them led to important data and lessons being lost.    

D. RISK TO DEVELOPMENT OUTCOME 

91. The risk to development outcome is high. The continued conflict and macroeconomic collapse in 

the  country  have  resulted  in  one  of  the worst  humanitarian  crises  in  the world.  Table  6  provides  an 

overview of how key humanitarian  indicators  have degraded over  time.  The  scale  of  the  conflict  and 

economic collapse where beyond the ability of the project to overcome.  

Table 6 Humanitarian situation in South Sudan at various points of time 

Dec‐12  Apr‐14  Jun‐16  Jun‐17  Jul‐18 

IDPs  183,000  817,700  1,600,000  1,940,000  1,840,000 

POCs  N/A  N/A  170,000  216,956  198,444 

Severely food insecure  2,400,000  3,200,000  6,100,000  7,500,000  7,100,000 

Refugees  N/A  287,600  727,610  1,940,000  2,480,000 

92. Given the insecurity in the country and the ensuing internal displacements, the sustainability of 

project  investments  cannot be  confirmed, and  it  is  likely  that much of  the progress  registered by  the 

project has been  lost due  to displacement and damage or destruction of  infrastructure  in  the conflict 

affected areas. For example, Mercy Corps implemented in Maban County in the payams of Korakimar, 

Bunj and Banachuwa between November 2012 to May 2013. By 2014, sources reported escalating conflict 

in Upper Nile, including in Maban County (Bunj payam) and in Panyikang County. It is unknown how many 

beneficiaries were displaced and how much of the cropping and public works activities survived.13 The 

July 2018 workshop with MAFS and implementing NGOs confirmed that some infrastructure in Yambio 

has survived the conflict, but that many of the farmers had fled the area. Nagero and Morobo counties 

remained  inaccessible. The  investments  in Phase 3 were still operating  in  June 2018, six months after 

project close. Follow up surveys or monitoring have been next to impossible for MAFS and especially for 

Bank staff. 

93. Donor activities in South Sudan now focus almost exclusively on humanitarian aid, including the 

World Bank’s EFNSP, which has supported general  food distribution  through World Food Programme; 

nutrition, health, WASH, and psycho‐social support services through UNICEF; and continued support to 

production for food security through FAO. Despite the loss to conflict, EFCRP did influence the design of 

two follow‐on projects—SNSDP and EFNSP. It also created lessons that will inform the design of future 

recovery and resilience projects in terms of the type of inputs, technology, and other support that should 

be provided.    

13 Radio Tamazuj. 2014. “MAP: Who controls Upper Nile state?” https://radiotamazuj.org/en/news/article/map‐who‐controls‐upper‐nile‐state 

Page 40: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 35 of 60

 

V. LESSONS AND RECOMMENDATIONS 

94. The  following  lessons  learned and  recommendations  from  the project  are  intended  to  inform 

future World Bank finances operations being implemented in the FCV context.  

What worked well 

Working with NGOs. In a context of fragility and conflict, strong, reputable NGOs that are familiar 

with the project area and cultural issues can help overcome lack of information on the part of the 

World Bank and the implementing agency. This is especially true in areas that were isolated for a 

long time due to war. Difficult human relations that arose due to the war are better understood and 

addressed by people who have worked and/or have thorough knowledge about the local setting. 

This can accelerate progress at the beginning of the project as they can hit the ground running. This 

approach  also  has  trade‐offs.  The World  Bank  and  implementing  agency  must  ensure  a  shared 

understanding of project goals, methodologies, and monitoring priorities up front to avoid confusion.   

Working  with  Local  Authorities.  Working  with  local  authorities—including  sector  officers,  local 

administrative officers, and traditional leaders—is critical to managing risk and delivering results on 

the ground. EFCRP benefitted  from County  level  coordinating meetings with officials  that helped 

minimize overlap among donor programs. In addition, local authorities played a key role in resolving 

localized conflicts between groups when they occurred.  

Youth in Agriculture.   Youth do exhibit  interest  in agriculture, and they are especially attracted to 

machinery for land preparation and crop processing,  in addition to road rehabilitation and storage 

construction.  These types of activities can attract more youth in future project and create sustainable 

enterprise opportunities for them.    

Pushing  technical boundaries. NGO partners, working with  government  scientists  to  identify best 

varieties for different locations were able to introduce good quality seeds with traits beneficial to the 

South Sudan context, such as:   Red Beauty groundnut, which  is  tolerant to rosette and  leaf spots; 

NERICA  rice,  which  is  more  resistant  to  environmental  stresses  and  contains  more  protein  than 

traditional varieties; TME 14 variety of cassava for high yields and disease and pest resistance; Longe 

5 maize, for drought‐tolerance and protein content. In addition, seed multiplication in areas of relative 

security was possible and beneficial to continued production.   

Mechanization  is possible  and essential. Even with  small  grant  sizes  and a  short  implementation 

period, EFCRP was able to introduce animal traction, push tillers, some tractors, and machinery for 

post‐harvest processing. Land preparation mechanization is critical to bringing sufficient amounts of 

fallow land under cultivation, so a community can start to tackle food security, and the post‐harvest 

machinery is important to extending storage life of crops.  

Adaptive changes during implementation 

Technical assistance vs.  capacity building. There  is a  trade‐off, particularly when working  in FCV 

countries,  between  achieving  project  goals  in  a  timely manner  through  technical  assistance  and 

building lasting skills on the ground through capacity building. While technical assistance is needed 

up front in low capacity contexts, a strong program of mentoring and capacity building is needed for 

Page 41: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 36 of 60

 

longer‐term  change.  Close  supervision  is  also  needed  to  more  effectively  track  progress, 

communicate and establish teamwork among PIU and donors.  

Maintaining momentum. It is important to counter the impacts of high staff turnover, including by 

staying  in active communication with  changing  country  context and PIU  staff,  and by working  to 

foster capacity of and ownership by incoming stakeholders through dialogue and periodic training 

sessions. 

Proactivity  and  Flexibility  in  Project  Design  and  Implementation.  Projects  in  FCV  face  fluid 

situations—in  terms  of  natural  disasters  and  conflict—requiring  adaptive  risk  management  at  all 

levels—e.g.,  Bank  team,  CMU  and  Senior  Management.    Projects  should  be  flexible  enough  to 

continue operating as circumstances on the ground change. For example, in Northern Bahr el Ghazal, 

when  plans  for  donkey‐powered  traction  clearly  did  not  work  due  to  tse‐tse  fly  infestation,  the 

government and the NGO partner quickly identified alternative activities that would benefit farmers. 

When the insecurity made it next to impossible to go to the field, the World Bank and MAFS agreed 

with the NGO partners on the priorities and to decentralize decision‐making on what interventions 

would  work  in  each  setting.  This  allowed  the  project  to  keep  moving  forward  on  at  least  one 

component until security improved.   

Recommendations for Future Projects in FCV

Learning from experience. This project could serve as an example that despite challenging country 

context, results can be achieved, especially in dire situations such as a food crisis. There is also merit 

in  assessing  the  counterfactual  risk of  not engaging  in  countries needing basic  services.  For  these 

circumstances, a feasible and measurable M&E framework is needed and should be given credence 

when assessing final outcomes.  

Value of better targeting that trades off need and accessibility. Having analysis that would effectively 

measure the accessibility dimension would provide evidence to better support the technical design of 

projects in the future. The demands of this project were especially clear given the grants responded 

quickly  to  the  food  crisis,  however may  have missed  the  potential  of  conjoining  the  accessibility 

dimension for greater impact.    

Pre‐planning and clear fund flows help maintain implementation momentum.  A project operating 

in and FCV context should map out as much as possible,  its  initial procurements and  locations  for 

prepositioning  so  that  supplies—seeds,  construction  materials,  equipment—can  be  purchased, 

imported,  and  pre‐positioned  close  to  the  implementation  sites.    This  will  help  the  project  keep 

moving if weather or conflict block transport. It can also ensure that the seeds and tools for cultivation 

are in place before cropping needs to begin and not delay implementation for a season.  

Longer implementation timelines are needed to achieve impact. All of the NGOs reported that having 

small  grants  over  a  short  period  prevents  planning  for  a  longer  engagement  and  trust  with  the 

communities,  which  need  more  intensive  engagement  to  move  from  humanitarian  to  resilience 

building.  The NGOs could not plan out on a sufficient time horizon the engagement they think was 

needed.  The  many  restructurings  to  add  financing  to  the  project  also  created  an  administrative 

Page 42: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 37 of 60

 

burden for the project team (dual track approval and reporting), which was as different times during 

implementation 

Third‐party monitoring. Having one or more independent agencies monitoring project processes as 

well as implementation progress is important in fragile contexts. These monitors can not only verify 

results, but also  identify  areas where  confusion over approaches or measurement  techniques are 

evident so that additional capacity building or other adjustments can be made quickly.  They can also 

facilitate knowledge sharing across project areas.  

Use technology to enhance M&E. Where interventions are highly dispersed and difficult to access, 

technology such as those offered by GOST, can boost the value of data collected. First,  it provides 

time and GPS tagged data that can be used to ensure project staff are working where they claim to 

be working.  Second, data can be uploaded directly to the PIU and the Bank at any time, allowing for 

closer tracking of project progress. Third,  it makes M&E  interesting—something even youth  in the 

project areas might enthusiastically embrace. Fourth, it can facilitate satellite monitoring of project 

areas.    Finally,  photos  of  the  implementation  locations  can  be  attached  to  records  to  increase 

understanding of the situation of the ground and to provide before and after comparisons of project 

interventions.   .   

Page 43: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 38 of 60

 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

       A. RESULTS INDICATORS  A.1 PDO Indicators       

 Objective/Outcome: Increased access to food for consumption by food insecure households 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of vulnerable persons benefiting from unconditional food or cash transfers 

Number  0.00  138000.00  138000.00  58680.00 

  03‐Feb‐2014  03‐Feb‐2014  03‐Feb‐2014  31‐Dec‐2017  

Comments (achievements against targets): Added in the 2014 PP to capture beneficiaries of direct food distribution from WFP (43% of target achieved). Due to apparent miscommunication between the World Bank team and MAFS, the 2014 PP gave the 138,000 target, but the contract between MAFS and WFP was for the amount achieved. The May/June 2016 ISR noted that “the number of vulnerable households benefiting from unconditional food support (food aid) stands at 58,680 and these accrue primarily from the contract that was issued by the Government to the World Food Program.” The project was not restructured at the time to align the targets.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Direct project beneficiaries  Number  213462.00  215500.00  384500.00  339433.00 

  20‐Jun‐2011  01‐Jun‐2011  11‐Apr‐2016  31‐Dec‐2017  

Female beneficiaries  Percentage  42.00  45.00  50.00  47.00 

Page 44: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 39 of 60

 

 

  20‐Jun‐2011  01‐Jun‐2011  11‐Apr‐2016  31‐Dec‐2017  

 

Comments (achievements against targets): Target (88% achieved). Indicator introduced in 2011 PP as a mandatory core indicator. It replaced "targeted population receiving cash transfers" as a PDO indicator, and participants in public works was tracked for the rest of the project through an intermediate outcome indicator. This indicator will capture beneficiaries under components one and two only (component two beneficiaries disaggregated as an intermediate indicator).      

 Objective/Outcome: Increased production and availability of food in targeted areas 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of farmers adopting improved technologies for food production. 

Number  0.00  189000.00  229800.00  272620.00 

  23‐Sep‐2008  01‐Jun‐2011  16‐May‐2016  31‐Dec‐2017  

Comments (achievements against targets): Target surpassed (102% achieved). The indicator was introduced in 2011 and replaced the indicators "Farmers adopting at least one improved technology for food production (number and percent). It is proxy for reporting on number of farmers targeted for own food production. Original target from 2008 PP was targeted farmers adopting improved technologies for food production in the targeted areas. This was replaced with 2 GFRP indicators in 2009: Farmers adopting at least one improved technology for food production (number and percent). This current indicator was the final version used from the 2011 PP onwards. The target was revised upward with each additional finance until 2016.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Metric tons of storage capacity built 

Metric ton  1636.00  2600.00  8700.00  11092.00 

  01‐Jun‐2011  01‐Jun‐2011  03‐Feb‐2014  31‐Dec‐2017  

Page 45: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 40 of 60

 

 

Comments (achievements against targets): Target surpassed (427% achieved). New PDO indicator in 2011 will report on investments made in response to the demanded post‐harvest storage capacity identified at household and community level. It is a proxy to capture strategies taken by the project to promote increase practices that would reduce household vulnerability to seasonal availability of food for consumption.      

 Objective/Outcome: Increased production and consumption of highly nutritious foods by selected farmers and vulnerable households 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of households reporting an increase in the number of foods produced due to the project 

Number  0.00  1800.00    4600.00 

  11‐Apr‐2016  01‐Jun‐2016    31‐Dec‐2017 

 

Comments (achievements against targets): Target surpassed (250% achieved). This indicator was added under the final grant (PHRD) accessed by the project. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Numbe rof households that report an increased household dietary diversity 

Number  0.00  1900.00    6000.00 

  11‐Apr‐2016  01‐Jun‐2016    31‐Dec‐2017  

Comments (achievements against targets): Target surpassed (316% achieved). This indicator was added under the final grant (PHRD) accessed by the project. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.  

 

 

Page 46: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 41 of 60

A.2 Intermediate Results Indicators

 Component: Component 1 Support to Agricultural Productivity 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of farmers adopting new practices and initiatives for postharvest handling and management. 

Number  0.00  83000.00  100700.00  125211.00 

23‐Sep‐2008  01‐Jun‐2011  01‐Jun‐2016  31‐Dec‐2017 

Comments (achievements against targets): Target surpassed (151% achieved) New indicator in 2011. Introduced to report innovations promoted by the project to improve household consumption through better food management and handling. It will report effects of investments in training, construction of food stores or granaries, processing and other post‐harvest management. It is a subset of the indicator above. 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of hectares of idle land brought back into production 

Hectare(Ha)  0.00  4000.00  38800.00  104741.00 

23‐Sep‐2008  01‐Jun‐2011  01‐Jun‐2016  31‐Dec‐2017 

Comments (achievements against targets): Target surpassed (262% achieved) New indicator in 2011. Introduced to track increased production through expansion of beneficiaries planted area through clearing of idle land. 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percent of targeted food  Text  12%  65%  0  74% 

Page 47: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 42 of 60

 

 insecure households in project areas with food reserves 

  23‐Sep‐2008  01‐Jun‐2011    01‐Dec‐2011 

 

Comments (achievements against targets): Original indicator from 2008 PP was "Numbers of food insecure households in the project area with food reserves" with a target of 1000. This was revised to the current target in 2011 and dropped in 2012 due to difficulty in terms of time and cost in obtaining accurate and reliable data on the indicator, potential problems with attribution of impact to project interventions, and lack of a reliable baseline.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of househjolds using improved food processing and storage methods and facilities 

Number  0.00  0.00  1550.00  2500.00 

  23‐Sep‐2008  23‐Sep‐2008  01‐Jun‐2016  31‐Dec‐2017  

Comments (achievements against targets): Target surpassed (161% achieved) Added in 2016 as part of AF #5 (2.7M PHRD), this is a new indicator associated with the projects new components. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.      

 Component: Component 2: Strengthening Community Safety Nets 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of participants in public works program 

Text  0  25462.00  37300.00  47595.00 

  01‐Jun‐2011  01‐Jun‐2011  01‐Jun‐2016  31‐Dec‐2017  

Percent of which are youth  Text  N/A  50%  70%  62% 

  23‐Sep‐2008  01‐Jun‐2011  01‐Jun‐2016  31‐Dec‐2017 

Page 48: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 43 of 60

 

    

Comments (achievements against targets): Target surpassed (187% achieved) Added in 2011 as requested by the GFRP Secretariat, to report the number of individuals that participated and possibly benefited from cash and/or food from public works. It was simplified to record participation rather than benefits as the latter would require survey, and the original target was set based on elaborate criteria targeting households. Based on the nature of activities selected and the required time for completion, self targeting predominated the selection in 50% of the areas selected.      

 Component: Component 3: Support to Improved Nutritional Outcomes 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of housholds adopting healthy eating practices and using essential nutrition practices 

Number  0.00  0.00  1650.00  2781.00 

  23‐Sep‐2008  23‐Sep‐2008  01‐Jun‐2016  31‐Dec‐2017 

 

Comments (achievements against targets): Target surpassed (169% achieved) Added in 2016 as part of AF #5 (2.7M PHRD), this is a new indicator associated with the projects new components. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of agriculture professionals reporting an increased understaning of their role in improving nutrition and integrated nutrition activities in their work 

Number  0.00  0.00  120.00  40.00 

  23‐Sep‐2008  23‐Sep‐2008  01‐Jun‐2016  31‐Dec‐2017 

Page 49: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 44 of 60

 

   

Comments (achievements against targets): Added in 2016 as part of AF #5 (2.7M PHRD), this is a new indicator associated with the projects new components. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of jopint activities and meetings invloving nutrition and agricutlure/food security coordination mechanisms 

Number  0.00  0.00  5.00  8.00 

  23‐Sep‐2008  23‐Sep‐2008  01‐Jun‐2016  31‐Dec‐2017 

 

Comments (achievements against targets): Target achieved (160% achieved) Added in 2016 as part of AF #5 (2.7M PHRD), this is a new indicator associated with the projects new components. Implementation was delayed due to the outbreak of violence that caused the Bank to evacuate from South Sudan for almost one year.      

 Component: Component 4: Support to Project Implementation 

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Planned implementation progress based on annual work plans is achieved and timely actions taken on implementation problems including fiduciary issues. 

Yes/No  N  Y  Y  Y 

  23‐Sep‐2008  23‐Sep‐2008  31‐Dec‐2017  31‐Dec‐2017 

 

Comments (achievements against targets):  

Page 50: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 45 of 60

 

    

Indicator Name Unit of Measure 

Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Feebacks and follow‐up recorded on fiduciary issues (number) 

Text  4  0  0  0 

  23‐Sep‐2008  23‐Sep‐2008  23‐Sep‐2008  23‐Sep‐2008  

Comments (achievements against targets): Dropped in 2012 in favor of Planned implementation progress based on annual work plans is achieved and timely actions taken on implementation problems including fiduciary issues. However, the ISR template was not updated until the following year.   

           

Page 51: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 46 of 60

 

B. KEY OUTPUTS BY COMPONENT  

Increased access to food for consumption by food insecure households  

Outcome Indicators 1. Number of vulnerable persons benefiting from unconditional food or cash transfers 

2. Direct project beneficiaries 

Intermediate Results Indicators  1. Number of participants in public works program 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 1) 

1. 58,680 people benefitted from unconditional food distribution through WFP (43% of stated target) 

2. 339,433 direct project beneficiaries, of which 47% were women (88% of target)  

3. 47,595 people participated in public works programs (128% of target) of which 62% were youth (89% 

of target) 

Increased production and availability of food in targeted areas 

Outcome Indicators 1. Number of farmers adopting improved technologies for food production  

2. Metric tons of storage capacity built 

Intermediate Results Indicators 1. Number of farmers adopting new practices and initiatives for postharvest handling and management 

2. Number of hectares of idle land brought back into production 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. 272,620 farmers adopted improved technologies for food production (102% of target) 

2. 11,092 metric tons of storage capacity built (127% of target) 

Page 52: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 47 of 60

 

3. 125,211 farmers adopting new practices for post‐harvest management (124% of target) 

4. 104,741 hectares of idle land brought under cultivation (270% of target) 

Support to Improved Nutritional Outcomes14 

Outcome Indicators 1. Number of households reporting an increase in the number of foods produced due to the project 

2. Number of households that report an increased household dietary diversity 

Intermediate Results Indicators 

1. Number of households adopting healthy eating practices and using essential nutrition practices 

2. Number of households using improved food processing and storage methods and facilities 

3. Number of agriculture professionals reporting an increased understanding of their role in improving 

nutrition and integrated nutrition activities in their work 

4. Number of joint activities and meetings involving nutrition and agriculture/food security coordination 

mechanisms 

Key Outputs by Component (linked to the achievement of the Objective/Outcome 2) 

1. 4,500 report increased number of foods produced (250% of target) 

2. 6,000 households reporting increased dietary diversity (316% of target) 

3. 2781 households report adopting healthy eating practices (169% of target) 

4. 2,500 households using improved food processing and storage methods and facilities (161% of target) 

5. 40 agriculture professionals  reporting  increased understanding of  their  role  in  improving nutrition 

(33% of target) 

14 This was not part of the PDO, but was the objective of the phase 3 grant.  See Sections IIA and IIB for explanation.  

Page 53: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 48 of 60

 

6. 8  joint  activities  and  meetings  involving  nutrition  and  agriculture/food  security  coordination 

mechanisms (160% of target) 

  

Page 54: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 49 of 60

 

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

  

A. TASK TEAM MEMBERS 

 

Name  Role 

Preparation 

Supervision/ICR 

Melissa Williams  Task Team Leader(s) 

Ocheng Kenneth Kaunda Odek, Pascal Tegwa  Procurement Specialist(s) 

Stephen Diero Amayo  Financial Management Specialist 

Christine E. Cornelius  Team Member 

Jeeva A. Perumalpillai‐Essex  Team Member 

Tracy Hart  Environmental Safeguards Specialist 

Juvenal Nzambimana  Team Member 

Varalakshmi Vemuru  Social Safeguards Specialist 

Evarist F. Baimu  Counsel 

Srilatha Shankar  Team Member 

Abel Lufafa  Team Member 

Museme Munira Issa  Team Member 

Eric Brintet  Team Member 

John Barakia  Team Member 

Grace Tabu Felix  Team Member 

          

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

Page 55: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 50 of 60

 

FY09  5.573  33,822.36 

FY10  0     0.00 

Total  5.57  33,822.36  Supervision/ICR 

FY09  8.358  32,206.60 

FY10  23.351  111,520.88 

FY11  39.461  117,881.87 

FY12  19.661  47,720.84 

FY13  16.470  123,350.67 

FY14  0  1,737.27 

FY15  1.800  7,914.26 

FY16  0   273.77 

FY18  6.088  39,112.82 

FY19  3.878  23,034.92 

Total  119.07  504,753.90     

  

   

Page 56: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 51 of 60

 

ANNEX 3. PROJECT COST BY COMPONENT  

 

       

Component 

Original Project 

2008 (US$, millions) 

Additional Finance (US$ million) 

Total 1 

2011 2 

2012 3 

2013 4 

2014 5 

2016 

Support to Agricultural Productivity   3.00  1.30  1.40  2.73  3.00  ‐ 11.43 

 

Strengthening Community Safety Nets   1.50  0.70  1.50  4.00  5.50  ‐ 13.2 

 

Support to Improved Nutritional Outcomes 

‐  ‐  ‐  ‐  ‐  2.30  

2.3  

Support to Project Implementation   0.50  0.20  0.10  0.80  0.50  0.40  2.5 

Total  5.00  2.20  3.00  7.53  9.00  2.70  29.43 

  

Page 57: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 52 of 60

 

ANNEX 4. EFFICIENCY ANALYSIS 

 

95. Because of the urgency of the crisis response during preparation and the general lack of basic data 

in South Sudan, no financial or economic analysis was carried out for the project in 2008, 2011, 2012, or 

2013 (original project and the first three additional financings). The 2013 PP committed to collecting data 

for ex‐post computation of financial and economic returns on farm income towards the end of project 

implementation. Within two months of approving the 2013 PP, however, the civil war broke out in South 

Sudan  forcing  the  Bank  to  evacuate  Juba  in  late  December  2013  until  April  2014.  The  2014  PP  was 

prepared while the Bank office was evacuated, so the World Bank team used available data (including 

targets set in the 2014 PP) to provide some preliminary financial and economic analysis while highlighting 

the uncertainties associated with the following estimates:  

Cash wages paid to 37,300 participants in public works projects in the project area were valued 

at US$1.6 million or US$42 per person per year constituting 11 percent of the South Sudan poverty 

line per person per year.   

In EFCRP, ultimately 47,595 people participated in the public works program; however, payment in some areas followed a daily wage rate while other used a task‐based rate, which incentivized rapid completion of works.  According to analysis in the 2011 PP using 2009 data, the payments were equivalent to daily rates ranging from SDG 13‐15 SSP per day in Yambio and Morobo to SDG 20‐25 per day in Raja.  

Direct  food support  to 138,000 people  for 2 months was valued at US$7.6 million at a rate of 

US$27.5 per person per month equivalent to 86 percent of the poverty line.  

As pointed out in section IIB, due to miscommunication between the World Bank team and the PIU,  the assumption of 138,000 beneficiaries served  for  two months was  inaccurate.   The PIU contracted with WFP to provide GFD for 58,680 beneficiaries over a period of four months. GFD represented 17 percent of the project cost, so the analysis below looks at the financial returns for the support to agriculture production, which was 39 percent of the project.  

The economic benefit cost ratio of increased community grain storage was estimated at 1.3 with 

an economic NPV of US$1 million and an ERR of 20 percent.  

The data and assumptions used to arrive at these figures were not available to the ICRR team, so a follow up analysis was not done.   

96. While  the  NGOs  were  able  to  restart  with  implementation  after  March  2014  and  the  Bank 

returned to Juba one month later,  insecurity throughout the country preventing the collection of solid 

data  for  analysis.  This  ICRR  provides  some  financial  analysis  of  the  support  to  agriculture  production 

(component 1) using a  representative crop model  for  sorghum and maize  that was developed  for  the 

preparation of the 2014 PP. It also draws on project documents and evaluations of similar projects inside 

and outside of the Bank to get a sense of the returns to investments to public works programs (component 

2) like those under EFCRP. 

97. EFNSP  used  a  representative  crop model  for  sorghum  and maize  that was  developed  for  the 

preparation of 2014 PP to estimate financial gross margins in the project area. For EFCRP, average prices 

Page 58: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 53 of 60

 

for  maize  and  sorghum  in  December  2015,  six  months  before  the  end  of  the  project  were  used  to 

determine the gross margin. Sorghum prices ranged from SSP 12/kg in Rumbek to SSP 15/kg in Wau. Maize 

prices ranged from SSP 10.3/kg in Wau and to SSP 11.7 in Rumbek. Drawing on the EFNSP analysis, the 

analysis assumes an average of 1 ha/beneficiary. Based on these numbers, the average gross margin six 

months before project close was US$257 for sorghum and US$150 for maize.   

Table 7 Financial analysis of sorghum and maize production under EFCRP 

   Unit  Sorghum  Maize 

Yield  kg/ha  900  800 

Crop price  US$/kg  0.73  0.5 

Operating costs by Project  US$/ha  200  125 

Operating costs by farmer  US$/ha  200  125 

Gross Margin  US$/ha  257  150 

98. There are a few caveats to the analysis. The final reported number of farmers adopting improved 

technologies for production under EFCRP is 272,620, and while sorghum and maize are the major crops in 

South Sudan and a priority for food security production, those two crops do not represent 100 percent of 

the cropped area. Seeds and cuttings were provided for groundnut, cassava, pulses, vegetables, and sim 

sim, but the project did not track the number of hectares dedicated to each crop across seasons. It should 

also be noted that prices were volatile throughout the project, so financial returns were similarly volatile. 

Financial analysis of production for maize and groundnut done by one of the implementing NGOs during 

Phase 1 of the project (around 2010) showed a higher cost of production, particularly for maize in Yambio 

county. However, this data had not been validated, and some details were missing, so the analysis could 

not be included.  

99. There was insufficient data to analyze the returns to mechanization—both for land preparation 

and post‐harvest processing, but this was a relatively small element of the project assets introduced.   

100. The analysis of the cash for work program looked to analysis from similar projects for indications 

of the potential returns.  For this, the World Bank’s SNSDP project, which drew on EFCRP for its technical 

design, did provide an analysis that showed it would cost US$2.07 to transfer US$1.00 in wage benefits to 

the intended recipients, which compared well to similar programs. The EFNSP cash for works component 

ultimately  reached  47,595  people  with  an  investment  of  $8.2  million—about  $172  invested  per 

beneficiary. This is averaged over the life of the project, and it includes the cost of materials. Detailed data 

on the number of people reached each year  in each county was not systematically collected, but AAH 

provided full financial data in their 2014‐15 completion report. In Yambio, Nagero, and Tali counties, the 

public works component provided an average of 56 days employment at about $7/day for average annual 

wage of $414. This was manual repair of several kilometers of road and installation of culverts for each 

community.   

Component 1 

Agriculture 

Component 2 

Safety Nets 

Component 3 

Management 

Number of people 

employed  Mandays 

Average days/ person 

Total Wage Bill 

Average daily wage 

Yambio  37.2%  24.9%  37.9%  276  14,691  53.23  112,059.07  7.63 

Page 59: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 54 of 60

 

Component 1 

Agriculture 

Component 2 

Safety Nets 

Component 3 

Management 

Number of people 

employed  Mandays 

Average days/ person 

Total Wage Bill 

Average daily wage 

Tali  40.6%  17.2%  42.2%  225  13,667  60.74  99,638.96  7.29 

Nagero  42.6%  25.2%  32.2%  568  31,150  54.84  224,081.00  7.19 

101. Noting the prevalence of bartering in South Sudan, the project noted that introducing cash wages 

would increase purchasing power and stimulate demand in local markets. That EFCRP also supported the 

supply response in local market offset the risk of inflation that could happen in the absence of functioning 

markets. The public works supported by EFCRP had multiplier effects as well.  For example, the focus on 

farm to market road rehabilitation would have contributed to lowering the cost for transport to market 

by  farmers,  which  would  have  increased  access  to  relatively  affordable  food  in  local  markets.  The 

monitoring  system  for  the  project  did  not  systematically  record  the  kilometers  of  road  that  were 

rehabilitated, and no baseline data on the cost of transport to market was collected.  A review of a World 

Food  Programme  feeder  road  project  (an  activity  supported  by  EFCRP  as  well)  did  not  perform  an 

economic or financial analysis. 

  

Page 60: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 55 of 60

 

ANNEX 5. OVERVIEW OF CHANGES TO THE RESULTS INDICATORS 

 

Line Item  Type  Indicator  Introduced 

Dropped or 

Replaced  Comments 

1  PDO  % of targeted farmers adopting improved technologies for food production in the targeted areas 

Sep‐08  Dec‐09  Replaced by GFRP indicators (#2 and #3)  

2  PDO  Farmers adopting at least one improved technology for food production (number of farmers) 

Dec‐09  Jun‐11  Replaced by simplified #4 in June 2011 

3  PDO  Farmers adopting at least one improved technology for food production (% of farmers targeted)3 

Dec‐09  Jun‐11  Replaced by #4 

4  PDO  Number of farmers adopting improved technologies for production 

Jun‐11  N/A    

5  PDO  % of target population receiving cash transfers 

Sep‐08  Dec‐09  Replaced by #6 

6  PDO  Targeted population receiving cash transfers (number)3 

Dec‐09  Jun‐11  Replaced by #9 

7  PDO  Number of vulnerable persons benefiting from unconditional food or cash transfers 

Feb‐14  N/A  Added in 2014 to capture beneficiaries of direct food distribution from WFP 

8  PDO  Metric tons of storage capacity built  Jun‐11  N/A    

9  PDO  # of project beneficiaries (% of which are female) 

Jun‐11  N/A  Captured all beneficiaries under components one and two.  

10  PDO  Number of households reporting an increase in the number of foods produced 

Jun‐16  N/A  Exclusive to the PHRD grant 

11  PDO  Number of households that report an increased household dietary diversity 

Jun‐16  N/A  Exclusive to the PHRD grant 

12  IOI  Food insecure households in the project area with food reserves 

Sep‐08  Jun‐11  Replaced by #17 

13  IOI  Number of food insecure households in the project area that participate in public works 

Sep‐08  Jun‐11  Reformulated in 2011 and merged with number of participants of public works program  

14  IOI  Beneficiaries of public work programs (number of individuals) 

Dec‐09  Jun‐11  Replaced by #18 

15  IOI  Person‐days provided in labor intensive public works (number) 

Dec‐09  Jun‐11  Difficulties in measurement as some areas of South Sudan paid by task rather than by day.  

16  IOI  Feedbacks and follow‐up recorded on fiduciary issues (number) 

Sep‐08  Jun‐12  Replaced by #21 

Page 61: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 56 of 60

 

Line Item  Type  Indicator  Introduced 

Dropped or 

Replaced  Comments 

17  IOI  Percent of targeted food insecure households in project areas with food reserves 

Jun‐11  Jun‐12  Dropped due to difficulty in gathering data  

18  IOI  Number of participants in public works program (% of which are youth) 

Jun‐11  N/A    

19  IOI  Number of farmers adopting new practices and initiatives for postharvest handling and management. 

Jun‐11  N/A  Introduced to track additional focus on post‐harvest management.  

20  IOI  Number of hectares of idle land brought back into production 

Jun‐11  N/A    

21  IOI  Planned implementation progress based on annual work plans is achieved and timely actions taken on implementation problems including fiduciary issues. 

Jun‐12  N/A    

22  IOI  Number of households adopting healthy eating practices and using essential nutrition practices 

Jun‐16  N/A  Exclusive to the PHRD grant 

23  IOI  Number of households using improved food processing and storage methods and facilities 

Jun‐16  N/A  Exclusive to the PHRD grant 

24  IOI  Number of agriculture professionals reporting an increased understanding of their role in improving nutrition and integrated nutrition activities in their work 

Jun‐16  N/A  Exclusive to the PHRD grant 

25  IOI  Number of joint activities and meetings involving nutrition and agriculture/food security coordination mechanisms 

Jun‐16  N/A  Exclusive to the PHRD grant 

    

Page 62: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

  Page 57 of 60

 

ANNEX 6. SUPPORTING DOCUMENTS (IF ANY) 

 

World Bank. 2008. Sudan ‐ Southern Sudan Emergency Food Crisis Response Project (ISDS). Washington, DC: World Bank. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=9817324 

World Bank. 2011. Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 05 . Washington, D.C. : World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=14004193 

World Bank. 2012. Main report  Vol. 1 of South Sudan ‐ Emergency Food Crisis Response Project : environmental assessment. South Sudan ; s.n.. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=17736742 

Lufafa, Abel. 2012. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 06 . Washington, D.C. : World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=16898647 

Lufafa, Abel. 2013. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 07 . Washington, D.C. : World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=17721318 

World Bank. 2013. Environmental and social management framework  Vol. 3 of South Sudan ‐ Emergency Food Crisis Response Project : environmental assessment. South Sudan ; s.n.. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=17747304 

World Bank. 2013. Environmental and social assessment report  Vol. 2 of South Sudan ‐ Emergency Food Crisis Response Project : environmental assessment. South Sudan ; s.n.. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=17747175 

Lufafa, Abel. 2013. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 08 . Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=18622981 

Lufafa, Abel. 2014. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 09 . Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=19892291 

World Bank. 2011. Sudan ‐ Additional Financing for the Southern Sudan Emergency Food Crisis Response Project . Washington, DC: World Bank. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=14450486 

0000A8056. 2015. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 10 . Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=23141880 

World Bank. 2013. South Sudan ‐ Additional Financing for the Emergency Food Crisis Response Project. Washington DC: World Bank. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=18367768 

Lufafa,Abel. 2016. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project : P113586 ‐ Implementation Status Results Report : Sequence 11 . Washington, D.C. : World Bank Group. 

Page 63: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 58 of 60

https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=26047282 

Lufafa, Abel. 2016. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project: P113586 ‐ Implementation Status Results Report: Sequence 12 . Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=26550495 

World Bank. 2016. Sudan ‐ Southern Sudan Emergency Food Crisis Response Project: Implementation support mission ‐ May 16 to 20, 2016. Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=26534091 

World Bank. 2014. Official Documents‐ Recommendation of Statutory Committee for Grant H922‐SS, TF015934 and TF015935 (Closing Package) . Washington, DC: World Bank. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=19427303 

World Bank. 2014. South Sudan ‐ Additional Financing for the Emergency Food Crisis Response Project: restructuring. Washington DC; World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=19221266 

Lufafa, Abel. 2017. South Sudan ‐ Southern Sudan Emergency Food Crisis Response Project: P113586 ‐ Implementation Status Results Report: Sequence 13. Washington, D.C.: World Bank Group.  https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=27109736 

World Bank. 2017. South Sudan/AFRICA‐ P113586‐ Southern Sudan Emergency Food Crisis Response Project ‐ Procurement Plan. Washington, D.C.: World Bank Group.  https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=27895515 

National Audit Chamber. 2016. South Sudan ‐ Emergency Food Crisis Response Project: audited financial statement ‐ year ending June 30, 2015. South Sudan.  https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=27041391 

Lufafa,Abel. 2017. Disclosable Version of the ISR ‐ Southern Sudan Emergency Food Crisis Response Project ‐ P113586 ‐ Sequence No: 14. Washington, D.C.: World Bank Group. https://hubs.worldbank.org/docs/ImageBank/Pages/DocProfile.aspx?nodeid=28133885 

Page 64: Document of The World Bank...07 16‐May‐2013 Satisfactory Moderately Satisfactory 9.64 08 09‐Dec‐2013 Satisfactory Moderately Satisfactory 10.20 09 26‐Jul‐2014 Moderately

The World Bank Southern Sudan Emergency Food Crisis Response Project ( P113586 )

Page 59 of 60

ANNEX 7. MAP OF PROJECT COUNTIES The project implemented in select payams within each operational county.