Document of The World Bankdocuments.worldbank.org/curated/pt/100861481299660120/... ·...
Transcript of Document of The World Bankdocuments.worldbank.org/curated/pt/100861481299660120/... ·...
Document of
The World Bank
Report No: ICR00003837
IMPLEMENTATION COMPLETION AND RESULTS REPORT
ON A
GRANT
IN THE AMOUNT OF
SDR 1.3 MILLION (US$1.95 MILLION EQUIVALENT)
TO THE
REPUBLIC OF GUINEA-BISSAU
FOR A
BIODIVERSITY CONSERVATION PROJECT (BCP)
November 29, 2016
Environment and Natural Resources Global Practice
Africa Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective May 31, 2016)
Currency Unit = Franc CFA
FCFA 592.0011 = US$ 1.00
US$ 1.00 = SDR 1.00
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
BCP Biodiversity Conservation Project
BT Board of Trustees (the FBG Board) CAFÉ Consortium of African Environmental Funds CAIA Environmental Impact Assessment Unit
(Célula de Avaliação de Impactos Ambientais)
CB Cost Benefit
CBADP Community-based Avoided Deforestation Project in Guinea-Bissau
CBMP Coastal and Biodiversity Management Project
CC Consultative Committee
CDD Community Driven Development
CE Cost Effectiveness
CPAR Country Procurement Assessment Report
CTF Conservation Trust Fund
DC Donors’ Circle (FBG)
EIA Environmental Impact Assessment
ES Executive Secretariat/Secretary
ESMF Environmental and Social Management Framework
ESMP Environmental and Social Management Plan
FIAL Fund for Local Environmental Initiatives
FBG BioGuinea Foundation (Fundação BioGuine)
FCV Fragility Conflict and Violence
FFEM French Global Environment Fund
FISCAP Fisheries Monitoring and Control Institution
FUNBIO Biodiversity Foundation (Brazil)
GA General Assembly
GAC Governance and Anti-Corruption
GCCA Global Climate Change Alliance
GEF Global Environment Facility
G-B Guinea-Bissau
HIPC Heavily-indebted Poor Country
IBAP Institute for Biodiversity and Protected Areas
ICB International Competitive Bidding
ICR Implementation Completion and Results Report
IDA International Development Association
IDF International Development Fund
IFR Interim Financial Report
IMET Institute of Marine and Environmental Technology
IMPAC III International Marine Protected Areas Congress III
ISN Interim Strategy Note
IUCN International Unit for Conservation of Nature
LDCF Least Developed Countries Fund
M&E Monitoring and Evaluation
METT Management Effectiveness Tracking Tool
MRV Monitoring, Reporting and Verification
MSP Medium Size Project
NCB National Competitive Bidding
OP/BP Operational Policy / Bank Policy
PA Protected Area
PNB Boé National Park
PNC Cantanhez National Park
PND Dulombi National Park
PNLC Lagoa de Cufada Natural Park
PNMJVP João Vieira and Poilão Marine National Park
PNO Orango National Park
PNTC Rio Cacheu Natural Park
RAMPAO Regional Network of Marine Protected Areas in West Africa
RAPPAM Rapid Assessment and Prioritization of Protected Area Management
REDD Reduced Emissions from Deforestation and Degradation
REDLAC Latin America and Caribbean Network of Environmental Funds
RF Results Framework
RPF Resettlement Policy Framework
SCD Systematic Country Diagnosis
SISRI Small Island States Resilience Initiative
SNAP National System of Protected Areas
(Sistema Nacional de Áreas Protegidas)
STAR System for the Transparent Allocation of Resources
UEMOA West African Economic and Monetary Union
(Union Economique et Monétaire Ouest Africaine)
UK United Kingdom
UNDP United Nations Development Program
VCS Verified Carbon Standard
WACA West Africa Coastal Areas Initiative
WARFP West Africa Regional Fisheries Program
Senior Global Practice Director: Julia Bucknall
Practice Manager: Benoit Bosquet
Project Team Leader: Maman-Sani Issa
ICR Team Leader: Maman-Sani Issa
Republic of Guinea-Bissau
Biodiversity Conservation Project
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 4
3. Assessment of Outcomes .......................................................................................... 12
4. Assessment of Risk to Development Outcome ......................................................... 20
5. Assessment of Bank and Borrower Performance ..................................................... 21
6. Lessons Learned ....................................................................................................... 23
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 25
Annex 1. Project Costs and Financing .......................................................................... 26
Annex 2. Outputs by Component ................................................................................. 27
Annex 3. Economic and Financial Analysis ................................................................. 50
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 60
Annex 5. Beneficiary Survey Results ........................................................................... 62
Annex 6. Stakeholder Workshop Report and Results ................................................... 63
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 64
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 67
Annex 9. List of Supporting Documents ...................................................................... 68
MAP: IBRD 42532
A. Basic Information
Country: Guinea-Bissau Project Name:
Guinea-Bissau
Biodiversity
Conservation Project
Project ID: P122047 L/C/TF Number(s): IDA-H6700
ICR Date: 11/29/2016 ICR Type: Core ICR
Lending Instrument: SIL Borrower: GOVERNMENT OF
GUINEA-BISSAU
Original Total
Commitment:
XDR 1.30M (USD1.95
M equivalent) Disbursed Amount:
XDR 1.30M (USD 1.95
M equivalent)
Revised Amount: N/A
Environmental Category: B
Implementing Agencies: Guinea-Bissau Institute for Biodiversity and Protected Areas (IBAP)
Co-financiers and Other External Partners:
BioGuinea Foundation
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 07/19/2010 Effectiveness: 07/29/2011 06/21/2011
Appraisal: 01/19/2011 Restructuring(s): 12/03/2014
Approval: 03/17/2011 Mid-term Review: 03/31/2013 10/26/2013
Closing: 05/31/2015 05/31/2016
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Satisfactory
Risk to Development Outcome: Substantial
Bank Performance: Satisfactory
Borrower Performance: Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Satisfactory Government: Satisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies: Highly Satisfactory
Overall Bank
Performance: Satisfactory
Overall Borrower
Performance: Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): No
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): No
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status: Highly Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)*
General agriculture, fishing and forestry sector 100 --
-- Other Agriculture, Fishing and Forestry -- 100
Theme Code (as % of total Bank financing)
Biodiversity
Environment and Natural Resources Management
--Climate Change
----Mitigation
100
--
--
--
50
Renewable Natural Resource Asset Management
--Biodiversity 100 50
*The Bank changed Sector and Theme Code taxonomies as of November 4, 2016. Taxonomy for BCP is
inaccurate - omitting public sector management/institutional development codes – but cannot be changed
E. Bank Staff
Positions At ICR At Approval
Vice President: Makhtar Diop Obiageli K. Ezekwesili
Senior Global Practice
Director/Country Director Julia Bucknall Habib M. Fetini
Practice
Manager/Manager: Benoit Bosquet Idah Z. Pswarayi-Riddihough
Project Team Leader: Maman-Sani Issa John Virdin
ICR Team Leader: Maman-Sani Issa
ICR Primary Author: Anna Roumani
F. Results Framework Analysis
Project Development Objectives (from the Legal Agreement)
The Project Development Objectives (PDO) were to: (i) strengthen the Institute for Biodiversity
and Protected Areas' (IBAP) management of Guinea-Bissau’s national parks; and, (ii) pilot the
operation of a sustainable financing mechanism for the national parks.
Revised Project Development Objectives (as approved by original approving authority)
The PDO was not revised.
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Aggregated Management Effectiveness Tracking Tool (METT) scores for
the 5 existing parks
Value
quantitative or
qualitative)
433 (2009 baseline
aggregate METT score of
which: João Vieira e
Poilão 104; Orango 111;
Cacheu 102; Cufada 67;
Cantanhez 49)
468 507
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Exceeded: 108.3% METT scores were 108.3% of the target and 117% of the
2009 baseline. Disaggregated by Protected Area (PA), the 2015 scores were:
João Vieira e Poilão 116; Orango 119; Cacheu 129; Cufada 83; and, Cantanhez
60. See Main Text 3.2 and Annex 2 for discussion of these results. Of the 5
parks, Cantanhez was the newest and its results were affected by several years
without a Park Director.
Indicator 2 :
BioGuinea Foundation (FBG) legally established and operational in
accordance with the minimum requirements for receiving GEF funds in the
endowment
Value
quantitative or
qualitative)
Not
established/operational
Established and
operational
FBG legally
established and
operational in
accordance with
GEF minimum
requirements.
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Achieved: 100% The FBG was given official non-profit status in both the
United Kingdom (UK) and Guinea-Bissau in 2012. (It was actually legally
established/registered in the UK under the Coastal and Biodiversity Management
Project (CBMP)). The FBG’s executive, management and governance units
became operational under BCP: Executive Secretariat, Board of Trustees,
General Assembly, Consultative Committee and Donors’ Circle. The Investment
Committee is in place and functioning with an approved Investment Policy
Statement. An Investment Manager was appointed for the FBG’s Endowment
Fund. The above meet all minimum requirements for receiving GEF funds in the
endowment. These requirements are detailed in Annex 2.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 :
Component 1:
Number of surveillance and control missions covering the five parks
conducted per year
Value
(quantitative
or qualitative)
Zero (CBMP did not
report # surveillance
missions in parks by
EOP, to establish a
baseline).
300 (12
surveillance and
control missions
per year/park –
60/year for 4
years, extended to
5)
709
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Exceeded: 236% Surveillance and control missions and related events and
activities on the ground involving IBAP staff, institutional partners and
community members/guards totaled 709: 2012 (109); 2013 (134); 2014 (164);
2015 (302).
Indicator 2 : Internal regulations and park-specific Business Plans developed/updated
Value
(quantitative
or qualitative)
Zero (regulations and
business plans)
2 internal
regulations, 3
Business Plans
5 Internal
Regulations; 5
Business Plans
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Exceeded: 250% and 167% Five parks have fully updated internal
regulations subject to further revision/updating by the Park Management
Councils; and five parks each have a Business Plan valid to 2020, subject to
periodic updating.
Indicator 3 : Direct project beneficiaries (of which female)
Value
(quantitative
or qualitative)
Zero
Target was 70,000
(of which 50.6%
female).
43,000 people. See
Comments below
Female
beneficiaries were
estimated at 65% of
direct financing.
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Partially achieved/exceeded: 61% (and 128.5% female) This Core Indicator
was mandatory at appraisal even though the Bank team realized that its
measurement might be difficult as it was not an ideal fit with activities directly
under BCP control. (A Bank-sponsored census of the PA population in 2007
counted about 70,000 people living in/around the parks). Therefore, the Team’s
basic premise at appraisal was that IBAP’s burgeoning capacity to conserve,
protect and stabilize the nation’s biological resources represented a direct benefit
to this population. Based on actual implementation, IBAP conservatively
estimates that the BCP directly benefited around 43,000 people, some 61% of the
target. These included training for 786 IBAP personnel at Headquarters and in
the PAs, plus an estimated 42,200 people who received biodiversity-related
sensitization training, and training targeted at the beneficiaries of IBAP’s micro-
investment financing (leveraged from other donors) under IBAP’s BCP-financed
communications/awareness-building outreach and training programs. An
estimated 65% were women, 128.5% of total. See Main Text Section 3.2,
footnote 29 and Annex 2.
Indicator 4 : Number of protected area staff and community co-managers trained in key
species, protected areas field monitoring and ecotourism guide skills
Value
(quantitative
or qualitative)
Zero 25 (PAD). IBAP
target was 200. 786
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Exceeded: 393% The PAD cumulative target was 25 but this was likely an
error. IBAP’s Final Report defines an annual target of 50/year over 4 years (200)
and this is applied here. The BCP financed training events in a wide range of
relevant subjects including species monitoring, PA field monitoring and
ecotourism guide skills for 786 people (IBAP staff, Park Management Councils,
park communities and partner institutions) from 2012 to 2015. Main Text 3.2 and
Annex 2 matrix.
Indicator 5 :
Component 2:
FBG Board and executive secretariat established and meeting in accordance
with TORs and timetable defined in the Statutes
Value
(quantitative
or qualitative)
Zero
FBG Board
established and
meeting
FBG Board of
Trustees and
Executive
Secretariat were
established and are
meeting based on
TORs and
timetable/Statutes.
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Achieved: 100% Executive Secretariat, Board of Trustees, General Assembly
(a UK governance body), Consultative Committee and Donors’ Circle were
established and are meeting/acting based on TORs, official timetables and
Statutes. (The first FBG Board Meeting occurred on February 18, 2012, attended
by two Trustees, the EC Observer, World Bank as Facilitator and IBAP as
Secretary). Work Plans, annual budgets, annual financial reports are prepared and
presented by the Executive Secretary to the Board of Trustees for approval.
Institutional links are in place between Government and FBG donors. The
Consultative Committee (multi-stakeholder forum) meets annually and ad hoc if
needed. Board meetings coincide with the Donors’ Council annual meetings,
providing IBAP opportunities for joint planning and strategy formulation. See
Annex 2.
Indicator 6 : Comprehensive capitalization strategy under implementation
Value
(quantitative
or qualitative)
Zero (strategy document
does not exist)
Capitalization
strategy under
implementation
Capitalization
strategy under
implementation
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Achieved: 100% Intensive fund-raising efforts have resulted so far in firm
donor pledges to the FBG endowment totaling EUR 4.6 million (G-B
Government EUR 1.00 m, MAVA Foundation EUR 1.3 m, GEF V USD 1.20 m,
equivalent to between EUR 1.00 and 1.20 depending on exchange rate) and,
EUR 1.0 m from FFEM). The VCS-REDD+ pilot is underway and expected to
result in carbon credit sales from emission reductions (ER) averaging 900,000
tCO2/year over 20 years due to avoided deforestation (from Cacheu and
Cantanhez parks) valued at an average US$3.04 m/year/20 years. See Annex 3.
Indicator 7 : Management systems (including fiduciary systems) in place and operational,
producing satisfactory annual and quarterly reports
Value
(quantitative
or qualitative)
Management systems
already in place from
CBMP and GEF
projects.
Management
systems in place
Management
systems are in
place, operational
and producing
satisfactory annual
and quarterly
reports
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Achieved: 100% BCP financed the continuation and upgrading of existing
management systems.
Indicator 8 :
Component 3:
Monitoring systems in place and operational, producing satisfactory annual
and quarterly reports
Value
(quantitative
or qualitative)
Monitoring systems
already in place from
CBMP and GEF
projects.
Monitoring
systems in place
Monitoring systems
established and
operational,
producing
satisfactory annual
and quarterly
reports
Date achieved 03/17/2011 05/31/2015 05/31/2016
Comments
(incl. %
achievement)
Achieved: 100% BCP financed the continuation and upgrading of existing
monitoring systems. BCP also financed design of a SNAP-wide
Monitoring System to track the biological and socio-economic health of
the PAs, an activity not contemplated at appraisal.
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 09/25/2011 Satisfactory Satisfactory 0.43
2 03/19/2012 Satisfactory Satisfactory 0.44
3 10/10/2012 Satisfactory Satisfactory 0.44
4 04/24/2013 Moderately Satisfactory Moderately Satisfactory 0.59
5 11/23/2013 Moderately Satisfactory Moderately Satisfactory 0.88
6 05/18/2014 Satisfactory Satisfactory 1.13
7 12/03/2014 Moderately Satisfactory Moderately Satisfactory 1.29
8 06/08/2015 Satisfactory Moderately Satisfactory 1.70
9 12/20/2015 Satisfactory Moderately Satisfactory 1.95
10 05/31/2016 Highly Satisfactory Satisfactory 1.95
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made DO IP
12/03/2014 MS MS 1.29
Closing Date extended 12
months to compensate for the
Bank’s coup-related suspension
of project activities and
disbursement, and to permit
achievement of PDO.
I. Disbursement Profile
1
1. Project Context, Development Objectives and Design 1.1 Context at Appraisal 1.1.1 Guinea-Bissau is a small West African nation of about 1.45 million people with an
economy based primarily on farming and fishing, which represents some 55 percent of gross
domestic product (GDP).1 At the time of appraisal, agriculture generated about 80 percent of
employment and 90 percent of exports (mainly raw cashew nut). Fishing represented from seven
to ten percent of GDP and 25-40 percent of public revenue. Infrastructure was - and remains –
poor, and social indicators weak: life expectancy of 48 years, 70 percent of the population living
below US$2/day, and 20 percent enduring extreme poverty. Some 60 percent of the population
were <25 years old at that time. The fragility of the state and its institutions has undermined
development of the country’s economic and social infrastructure and its prospects for reducing
widespread poverty. Civil war in 1988-89, a series of military coups, repeated political turmoil
and government turnover have stifled the country’s ability to thrive.
1.1.2 Sector and institutional context: Despite this situation, Guinea-Bissau has enormous
potential. It has the human and natural resources and the geography to grow and provide diverse
sources of income: abundant, high quality land, favorable rainfall, mineral deposits, biodiversity
of global importance, and fishing and tourism potential especially in the coastal zone which is
home to about 80 percent of the population. This unique coastal zone comprising mangroves,
sandbanks and mudflats, shallow estuarine waters and sub-humid Guinean forests, is among the
richest in West Africa for biodiversity: globally significant species of sea-turtles, manatee, goliath
grouper, bottlenose skate, ocean-going hippos, chimpanzees and migratory birds. The João
Vieira and Poilão Marine Protected Area (PA) is a major green turtle nesting site, the third largest
in the Atlantic. Cufada Lakes Natural Park is a designated Convention on Wetlands (Ramsar) site
(while the Bijagós Biosphere Reserve also achieved official Ramsar status in January 2013).
Guinea-Bissau now has four Ramsar sites totaling 1.2 m ha. Such biodiversity and the cultural
tradition it supports are a significant natural asset around which a viable tourism industry could
be built. The coastal zone already provides important ecosystem services: nursery/breeding
grounds for commercial fish stocks, carbon stocks and a buffer against climate change.
1.1.3 Government and its partners, including local and international NGOs such as the
International Union for the Conservation of Nature (IUCN) have, since the 1990s, been working
to conserve and manage the coastal zone upon which the country’s biodiversity depends. The
Coastal and Biodiversity Management Project (CBMP, 2004-2010) financed by the Global
Environment Facility (GEF), the European Union (EU), IUCN and the World Bank, helped the
Government to establish five national parks covering almost 450,000 ha and some 70,000 people,
along with a financially and administratively autonomous agency, the Institute for Biodiversity
and Protected Areas (IBAP).2 Staff and infrastructure were supported for a national headquarters
as well as local park management offices in the five parks, along with awareness-building of local
communities and the development of park management plans. In order for these parks/PAs to
1 At appraisal, Guinea-Bissau ranked 173 out of 182 countries on the United Nations Human Development
Index (2009). 2 The five national parks targeted at appraisal were: Parque Nacional Marinho João Vieira e Poilão
(PNMJVP); Parque Nacional de Orango (PNO); Parque Nacional dos Tarrafes do Rio Cacheu (PNTC);
Parque Natural das Lagoas de Cufada (PNLC); and, Parque Nacional de Cantanhez (PNC). Other parks not
covered by the BCP are also IBAP-managed, e.g., the Urok Community Marine Protected Area.
2
conserve biodiversity and eco-system functions, and to serve as sustainable development poles,
the Government established – under the CBMP – the Fund for Local Environment Initiatives
(FIAL), a mechanism for providing pro-environment block grants to local communities for
initiatives including schools, wells, rice-field rehabilitation, beekeeping, palm oil extraction and
fish processing. Both the strategy and rationale for the CBMP in 2004 entailed Guinea-Bissau
also establishing a private Foundation for Biodiversity in Guinea-Bissau (Fundação BioGuinea -
FBG) with the mandate to manage an expanding endowment fund, sinking funds and revolving
revenue streams to secure financing in perpetuity for, at minimum, management of core recurrent
activities of the country’s network of protected areas and biodiversity conservation efforts.
1.1.4 Rationale for Bank involvement: Sustaining and consolidating these institutions and
achievements have become critical drivers of new Bank-supported operations.3 Two “sister”
Bank-supported projects were conceived to directly capitalize/consolidate IBAP and the FBG and
sustain park management activities during this process: (i) a GEF medium-sized project (MSP)
approved in July 2010 (Guinea-Bissau Biodiversity Conservation Trust Fund Project - BCTF)
supported final steps to secure tax exempt status (in the UK and Guinea-Bissau) for the FBG, its
key operating instruments – a governing Board, executive staff, operational manual, business plan
and capitalization strategy – as well as limited, short-term transition funding for IBAP’s activities
in up to three parks; and, (ii) the IDA-financed Biodiversity Conservation Project (BCP) analyzed
by this ICR, designed to build upon the GEF MSP by financing the core recurrent costs of all five
parks – known as the National System of Protected Areas (SNAP) - until the FBG could be
operationalized and its endowment at least partially capitalized. The goal was to avoid a cessation
of IBAP’s conservation activities and the parks during the near-term transition period which
could reverse a decade’s gains and, to pilot operation of the FBG.4 See Section 2.1.
1.1.5 The BCP would assist Guinea-Bissau to develop/demonstrate capacity to effectively and
transparently manage conservation funds, promoting donor confidence; support initial FBG fund-
raising efforts; and, provide a baseline for a GEF V follow-on in FY12 conceived as seed capital
for the FBG endowment and designed to encourage contributions from other donors. (See para
1.5.1 for Component 1 financing arrangements). Other sources of funding for the FBG
endowment were also envisaged: carbon credits under a REDD (Reduced Emissions from
Deforestation and Degradation) program envisaged to begin in 2013, future park entry fees and
tourism taxes, and debt-for-nature swaps with government creditors. The then recently-approved,
Bank-supported Guinea-Bissau Community Driven Development Project (CDD) was also a
critical part of the picture, designed to continue supporting local communities in/around the parks,
further boosting overall sustainability of the conservation framework.
1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)
1.2.1 The PDO (as per the Grant Agreement) was to support the Recipient to: (i) strengthen
IBAP’s management of the Recipient’s National Parks; and (ii) pilot the operation of a
3 Design of the FBG was formulated in 2009 by a diverse working group, supported by international
partner institutions, and took global lessons into account. The FBG was legally registered as a private
foundation for public utility under United Kingdom Law in 2011. 4 An endowment of around US$20.0 m was estimated sufficient to finance IBAP and the PAs if financed
solely from investment returns and more modestly, around US$5.0 m would be needed to finance the core
management of at least the two priority PAs in the Bijagós Archipelago (PNO and PNMJVP). Transitional
donor financing however, was still essential.
3
sustainable financing mechanism for the National Parks. The PAD notes that this PDO would
build upon and was consistent with the GEF MSP (approved in 2011).5
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification
1.3.1 Neither the PDO nor the Key Indicators were revised.
1.4 Main Beneficiaries
1.4.1 The PAD describes the project’s primary target group (in the Results Framework
described as “direct” beneficiaries) as including over 70,000 people living in/around the parks
and dependent on park resources for their livelihoods. Longer-term, other beneficiaries – given
the then-current and expected contribution of the PA network to national and regional economic
growth – were national and local authorities (including IBAP), sector ministries, NGOs and the
private sector. The SNAP would also benefit the national population at large by providing the
backbone of a future tourism industry capable of generating substantial public revenue, and
international stakeholders through investment in the existence value of the country’s biodiversity.
Section 2.3 discusses the characterization of beneficiaries.
1.5 Original Components (as approved)
1.5.1 The BCP comprised three components:
Component 1: Consolidation and strengthening of capacity for management of coastal and
marine protected areas and biodiversity (IDA US$1.27 m, 65 percent of total project costs)
financed strengthening of the management of five coastal and marine parks and increasing the
monitoring and conservation of globally significant biodiversity.
Component 2: Pilot the operation of the BioGuinea Foundation (IDA US$0.39 m, 20 percent
of total project costs) supported pilot operationalization of the FBG as a mechanism capable of
financing the core management activities of at least two existing national parks.
Component 3: Project management and monitoring and evaluation (IDA US$0.29 m, 15
percent of total project costs) financed the effective and efficient implementation of project
activities and their coordination with other, related donor initiatives.
1.6 Revised Components
1.6.1 Components were not officially revised (i.e., via restructuring) but as recommended by a
Bank monitoring and evaluation (M&E) specialist conducting an M&E Review of the BCP in
2011, IBAP added activities under Component 3 designed to establish a SNAP-wide Monitoring
System for the longer-term monitoring of the biological and socio-economic health of the parks.
The BCP financed the system’s design, and other donors its implementation (ongoing). See
Section 3.2 and Annex 2.
5 GEF MSP PDO: (i) strengthen the ongoing management and conservation of the Recipient’s selected
National Parks; and, (ii) pilot the establishment of a sustainable financing mechanism for such parks.
4
1.7 Other significant changes
1.7.1 Project design, scope and scale were not changed. However, as a direct result of a
political/military coup on April 12, 2012 which overthrew the Government, the Bank triggered
OP/BP 7.30 (“Dealing with de facto Governments and World Bank Missions”), suspending until
further notice disbursements, Bank missions and the processing of new lending. On December 13,
2012, following the election of a new government, Bank Senior Management authorized the
resumption of all three elements. Also, a Level two restructuring (December 3, 2014), extended
the project closing date by 12 months to May 31, 2016 to compensate for the effects of the eight-
month suspension including to permit further evolution/consolidation of the FBG and its
endowment.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
2.1.1 Soundness of the background analysis: The project was consistent with the Bank’s
assistance strategy for Guinea-Bissau at appraisal. It supported the two pillars of the Interim
Strategy Note (ISN): (i) strengthen economic management and lay the foundation for
improvement in the productive sectors; and, (ii) increase access to basic services, especially for
the rural population. It also supported the ISN’s cross-cutting theme of capacity development and
partnership-building. Specifically, the BCP supported improved management of the natural
resources base on which both then-current livelihoods and future economic development
depended, as well as the enhanced financial capacity to sustain such management into the future.
As such, the BCP responded to the potential of the country’s biodiversity assets to provide the
backbone of a future tourism industry, as outlined in the then-upcoming Country Economic
Memorandum (CEM). It also complemented the then-proposed Bank support for the national and
regional fisheries sector as part of the West Africa Regional Fisheries Program (WARFP).
2.1.2 Assessment of project design: Project objectives were, prima facie, realistic and
achievable in the engagement period, although minor deficiencies in the Results Framework
limited a more ample appreciation of BCP results/achievements (see Section 2.3). The
components supported the PDO but it was agreed with IBAP following effectiveness that
activities would be included under Component 3 to design and establish a SNAP-wide
Monitoring System. This would be an essential complement to the METT scorecard, which was
starting to be regarded in the conservation community as insufficient (on its own) to gauge the
health of ecosystems and species on the ground (Section 2.3). The project’s organizational
framework – as with the CBMP - saw IBAP in the lead, leveraging financial/other support from
many partners and donors (see Annex 2). This was consistent with a strategy using a
programmatic approach involving a spectrum of sector entities, each contributing – in an
organized manner – to achievement of the end-goal. In parallel, the BCP financed the structuring
and staffing of the FBG to take over the financial support of the SNAP from IBAP.
Organizational (and operational) aspects of project design were strengthened by the institutional
continuity, capacity and experience of IBAP’s core leadership/professionals whose continued
growth the BCP financed. The PDO’s social goals were expressed through the expected impact –
direct and indirect - of increasingly more effective and efficient PA management on the socio-
economic and biological health of the parks, which had both local and national implications, and
via the Safeguards triggered: OP/BP 4.01(Environmental Assessment) and OP/BP 4.12
(Involuntary Resettlement).
5
2.1.3 The BCP was another piece of a larger framework – governed by the same over-arching
vision and logic – intended to advance IBAP and the FBG closer to the ultimate goal of a well-
managed and sustainable SNAP. This is and always has been, a process made more difficult by
the short supply of funding. Efforts have been focused on catalyzing, coordinating and
harmonizing all donor projects – including Bank-supported – so that each contributes to
achieving the big picture even if only addressing a portion of it.6 As example, the IDA-financed
BCP and the GEF-financed BCTF were two separate but very similar, closely-coordinated and
mutually reinforcing operations with parallel financing, similar/consistent PDOs and Results
Frameworks and joint supervision. The GEF was a two-year project (as designed) effective in
March 2011, and the BCP was a four-year project (as designed) effective in June 2011. Their
monitoring and evaluation (M&E) was coordinated by IBAP within an integrated MIS, structured
to distinguish clearly between the two operations. The BCP and GEF had separate budgets and
procurement plans but were coordinated through a joint planning process since both operations
were under the IBAP umbrella. Under their respective PDOs: GEF would “pilot the establishment
of a sustainable financing mechanism for such parks” and the BCP “pilot the operation of a
sustainable financing mechanism for the national parks”.7
2.1.4 To avoid overlapping disbursements under Component 1, the BCP Legal Agreement
included a covenant (Schedule 2, Section IV, B1) whereby Component 1 would initially be
financed exclusively by the GEF grant (under its own rubric, not to cost-share the BCP). Only
when Government had fully-disbursed the GEF funds designated for Component 1 (US$613,000
– see Implementation Completion Memorandum (ICM)) would the IDA funds start disbursing.
This situation evolved when the Bank project team saw an opportunity for GEF financing to
follow-on from the successful CBMP and, while the amount was small (US$950,000), it would
provide continuity. Soon after, additional IDA funds became available and the team prepared the
complementary BCP operation. The GEF was to be “limited, transitional, short-term financing
for core park management activities”. The IDA BCP would build upon and complement the GEF-
funded activities by “extending the transition funding for the management of the parks and
supporting the second pilot operational phase of the FBG”.
2.1.5 Lessons from previous operations: Due to the earlier timing of BCP preparation, the
lessons of the CBMP ICR were not yet available so the PAD relied more on observed events and
experiences8 which strongly suggested the need to continue supporting IBAP to manage the parks
successfully and, to collaborate with the Environmental Impact Assessment Unit (CAIA) on the
environmental monitoring of surrounding areas. Viewed retroactively, BCP design foreshadowed
the ICR’s lessons, including: (i) the benefits of multiple, donor-supported interventions over time
for the sustainability of such projects; (ii) the advantages of stable Bank and Borrower/Client
teams especially for technically difficult projects in troubled environments; and, (iii) the fact that
intensive supervision can still be maintained/conducted without a physical presence, i.e., using
electronic means during periods of civil unrest. In the case of the FBG, its concept and design
were informed by the lessons of Bank and external studies of global experiences with
conservation and protected areas trust funds, including in the West Africa Region.
6 At BCP closing, IBAP was managing/executing seven projects totaling EUR 6.5 million, the largest
being the EU-financed, Protected Areas and Climate Change Project (EUR 4.0 million). Two additional
operations totaling EUR 0.5 million had been submitted for approval by the financial entity involved, and
another two projects were at the conceptual stage. See Table 5, Annex 2. 7 “Operation” was not intended to include actual grant-making by the FBG but rather the establishing of
structures/units, staffing, policies and processes and initiation of scheduled meetings and decision-making. 8 See ICR, Report No. 001684 of October 26, 2011.
6
2.1.6 Assessment of risk: Aside from the country risk (political instability and weak macro-
economic situation) which was beyond the scope of the project to address, the two critical risks
identified at appraisal were: (i) that additional donor contributions would not materialize and the
FBG would not secure sufficient funds to sustain even the management of core recurrent
activities of the two marine parks in the Bijagós Archipelago (a risk rated High);9 and, (ii) that
external impacts (e.g., from mining or petroleum exploitation) would compromise or threaten
conservation objectives of one or more of the five parks in the PA network (not rated).10
Efforts
to mitigate the first risk were initiated early on by securing/fostering active involvement of the
donor community in designing the FBG, by piloting the FBG’s operations over the course of the
project, and by launching a financial capitalization strategy for its endowment. For the second
risk cited, mitigation measures were developed under the previous CBMP: preparation of a
national law governing environmental impact assessments and establishing the Environmental
Impact Assessment Unit (CAIA - Célula de Avaliação de Impactos Ambientais) based in the
Prime Minister’s Office, to oversee implementation of the law.
2.1.7 Adequacy of Government’s commitment: Governments in power have consistently
backed IBAP and the SNAP despite the political situation. The BCP grew out of government’s
ongoing commitment to the PAs as the means to conserve biodiversity and eco-system functions
and to serve as “sustainable development poles”. During BCP preparation, the Cufada Park
experience (opening of roads and land clearing inside the park for construction of a future port,
with no Environmental Impact Assessment, EIA) was a milestone in the Government’s
relationship with the Bank, becoming a national governance issue rather than a side-story, and
creating a discussion on how to balance sustainability, safeguards compliance and development,
which government clearly came to own.11
Government also: (i) allocated budget in 2010 for
fisheries surveillance activities – a positive signal of intention to sustain the then-newly-
established system - but was unable to follow through;12
(ii) approved a national Environmental
Impact Assessment Law as the legal basis for mainstreaming environmental and social
considerations into future development and economic growth while legally reinforcing the role of
associated national institutions; and, (iii) successfully designed and piloted – within the CBMP -
the Fund for Local Environmental Initiatives (FIAL – Fundo para Iniciativas Ambientais Locais)
to complement biodiversity conservation and demonstrate tangible benefits to communities
in/around the parks using a participatory approach. A special Bank M&E Support Mission in
2011 found that government’s “ownership of the overall objective and commitment to its
effective implementation are exemplary”.
2.1.8 Participatory processes: Participation has been a hallmark of the Bank-supported,
biodiversity conservation projects. The BCP was founded on an exceptional level of stakeholder
participation, especially by local communities in/around the PAs. Sustainability of the SNAP
depends on it, just as the communities themselves depend on the parks for their livelihoods.
Dialogue and awareness-building have been ongoing for 25 years, paving the way for the creation
and participatory management of the PA system. The national park plans existing at the time of
9 Orango National Park and João Vieira e Poilão Marine National Park
10 See ICR for CBMP, Report #1684 of October 26, 2011 describing such events and their resolution.
11 Ibid. The port was needed to make bauxite extraction in the Boe region viable. To date, this project
has not advanced and cleared forest has been regenerating. 12
Government was unable to honor its promise to allocate regular budget to IBAP due to the fiscal
constraints of maintaining Highly-indebted Poor Country (HIPC) program triggers and the EU’s
unexpected suspension of budget support following political violence in 2010.
7
BCP appraisal resulted from a multi-year participatory process, and their implementation at the
time of CBMP closure was being overseen by Park Management Councils, 50 percent of whose
members were/still are drawn from resident communities and resource users. The BCP saw their
involvement, along with local authorities and technical ministries, as a way to ensure their
continued engagement in the PA system, and their adherence to the idea of the PAs as
development focal points.
2.2 Implementation
2.2.1 The factors affecting project implementation were primarily related to political
instability:
The political/military coup in 2012 and its aftermath affected IBAP’s ability to implement
the project but partner/donor collaboration and commitment mitigated its effects. Guinea-
Bissau’s technical and financial cooperation with its principal development partners (Bank and
GEF) was ruptured. The Bank suspended BCP disbursements (and other Bank projects including
the BCTF/GEF) from April to December 2012 due to the uncertain legitimacy of the transition
government. National fiscal revenues declined and, due to the State’s absence, greater pressure
was exerted on fisheries and forest resources, the latter through the illegal logging and trading of
wood in PA border zones and some attempted incursions into Cantanhez - fended off by the local
population.13
Even so, important activities made progress in this period, importantly because the
EU, MAVA Foundation and UNDP sustained their support to IBAP/SNAP even while
suspending all other portfolio activities. Also, the Designated Account had been replenished right
before the coup, enabling sufficient cash flow to continue key activities. Another positive factor
was proactive Bank supervision, collaborating with IBAP via frequent online and skype
guidance/troubleshooting. The project’s programmatic approach to achieving the higher-level
goals, and IBAP/Bank efforts to harmonize donors and activities, were also positive elements.
FBG’s fund-raising and operational status specifically, were hampered by these same
conditions. Several factors were important: (i) Fund raising/capitalization of the FBG
endowment proved challenging and time-consuming due to donor unwillingness to commit
resources in the aftermath of the coup; (ii) expectations at appraisal under-estimated the time
potentially required to meet fund-raising goals, a lesson for similar projects (but difficult to gauge
at appraisal); and, (iii) salaries could not be paid (most public employees went unpaid in this
period including within IBAP) deterring potential FBG recruits. The resulting delays in launching
the FBG operationally were beyond the BCP’s control, affecting constitution of the Board,
recruitment of the Executive Secretary and Financial Officer, and the transfer of responsibilities
for implementing Component 2 from IBAP to the FBG. Difficulties in finding qualified
candidates for FBG Executive Secretary (ES) saw the Board recruit a consultant as interim ES to
permit a long-term, suitable candidate to be located and groomed without time pressure. This
interim arrangement was subsequently converted to a longer contract.
Presidential and legislative elections in April/May 2014 and the swearing in of a new
government, re-established a fragile normality. Government sponsored in March 2015, an
International Conference of Donors at EU Headquarters in Brussels, presenting a new Strategic
Operational Plan (Terra Ranka, 2015-2020) with an investment program and multi-year action
plan. Biodiversity and natural capital were presented as a “foundation”, and the major cross-
13 Client Completion Report, IBAP, July 2016.
8
cutting sector and development instrument for the entire strategy. From mid-2014 to June 2016
however, political crises had become cyclical with challenges in 2014, the President’s dismissal
of the elected government in 2015 and multiple, unsuccessful attempts since then to put a new
government in place, affecting BCP execution. At the time of ICR preparation, the Government’s
program was still awaiting approval by the National Popular Assembly resulting in partial
paralysis of the state. This recurrent instability impinged upon IBAP’s functionality and growth
due to its partner public agencies in the Government being virtually moribund for extended
periods, and leadership of the State Secretariat of Environment changing repeatedly. Delays
occurred in key operations including the IBAP-managed Global Climate Change Alliance Project
(GCCA+) and the official establishment of the new Boé National Park and Dulombi National
Park under the SNAP.
Surveillance activities in the Cantanhez, Cufada and Orango parks were also affected, even
though the METT scores and SNAP surveillance results indicate that IBAP did regain and
maintain control in affected parks. Cantanhez Park was quite new, lacked operational resources
(suspension-related) for adequate enforcement and control missions from 2012 to 2013, took
three years to recruit a new Park Manager/Director (although Cantanhez did have a director in the
period), and was as a result slower to evolve/consolidate. Management of Cufada Park was also
affected by the suspension, lack of a surveillance vessel and the absence of its new
Manager/Director. In Orango Park, surveillance missions were hampered by burdensome
bureaucratic procedures limiting fuel purchases for public vehicles. Surveillance by 2015
however, had fully recovered and was exceptionally strong for two reasons: (i)
intensive/extensive BCP-financed communications/outreach activities were paying off, prompting
widespread local community involvement/collaboration in park management; and, (ii) IBAP’s
increasing skill in creating financial synergies with institutional partners. This included the
BCP/IDA in cooperation with FISCAP and the Rias do Sul Project (IUCN-UEMOA) enabling
302 missions in six PAs (including AMPC-Urok) of the 312 programmed and, achievement of
96.8 percent of the marine/coastal surveillance program due to the acquisition of new vessels.
Government commitment to the SNAP resulted in substantial budget support for IBAP at a
critical point in the BCP’s final year. The BCP faced a financing constraint from August 2015
because the project contribution to IBAP salaries and operational costs was ending. IDA funds
under Component 1 were fully-disbursed and the costs associated with an additional year of
operations had not been anticipated. The FBG was not yet sufficiently capitalized or mature to
contribute, although at that time three potential sources of funding had been identified/promised.
The Bank team urged the Government to provide support from the national budget, starting in
2016. Government came through, allocating CFA 60.0 million (about US$100,000) for core
IBAP salaries and activities, although this was an exceptional, one-time injection of transitional
funds not associated with a permanent budget line. IBAP confirmed that these promised
resources were released.
2.2.2 Restructuring: The Level two restructuring in 2015 is discussed in Section 1.7.
2.2.3 Mid-term Review (MTR): The MTR was conducted in October 2013 in the post-
coup/pre-election period, a challenging environment both for maintaining regular PA
management activities and the momentum of fund-raising for the FBG endowment. The Bank
team found that IBAP had kept the project largely on track, with some delays: (i) IBAP’s
capacity to manage the SNAP was steadily strengthening and tangible results were being
achieved in the parks – METT scores had already exceeded appraisal targets; (ii) FBG
operationalization was gaining momentum and a Memorandum of Understanding (MOU)
transferring implementation responsibilities for Component 2 from IBAP to the FBG, had been
9
signed; and, (iii) project management continued to be satisfactory with an exemplary degree of
project ownership and fiduciary control at all levels. No major changes were proposed.
2.2.4 Project at Risk status: The Project was not a potential problem project or actual
problem project at any time. However, the country-level risk remained significant throughout,
associated with the unstable political situation and weak macro-economic environment.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
2.3.1 Design: M&E design was built around a Results Framework (RF) comprising two PDO
Indicators and eight Intermediate Outcome Indicators. Project achievement would be measured
primarily by: (i) annual assessment of the management efficiency of the five PAs (continuing the
use of the World Bank/World Wildlife Fund Management Effectiveness Tracking Tool (METT)
scorecards begun under the CBMP);14
and, (ii) legal establishment and operation of the FBG in
accordance with “minimum requirements for receiving GEF funds” (although technically, the
FBG was already legally established under the CBMP and what the BCP planned was to structure
and staff the entity and pilot its operations).15
The RF was generally adequate but had some
deficiencies, noted below. The basic capacity to implement planned M&E activities was already
established in IBAP and would be boosted by specialized technical assistance. As noted earlier,
IBAP used a joint BCTF/BCP Management Information System (MIS) with clear separation of
the two operations. The PAD also notes that key indicators were designed taking into account not
only the information they would provide but also the costs and feasibility of any additional
required data collection, given the small size of the IDA grant.16
IBAP would have primary
responsibility, continuing to monitor national park management activities based on indicators
identified in individual Park Management Plans.
2.3.2 Design deficits were few. The RF included a Core Sector Indicator: “Direct project
beneficiaries (of which female)” with a target of 70,000 people (based on a 2007 CBMP-specific
census of the parks’ population) of which 50.6 percent were expected to be women. The Team
decided that this indicator - which was obligatory but not considered optimal for activities
directly under BCP control - would signal that IBAP’s increasingly strong and astute
management of the PAs had direct (and indirect) short and long-term socio-economic benefits for
the parks’ total population, including female, by stabilizing the physical conditions for their long-
term social and economic survival in place.17
As it turned out, the target was probably the bigger
issue: the BCP actually did finance activities with direct beneficiaries but was never likely to
reach all 70,000 directly. After effectiveness, the need for a more sophisticated system which
14 METT questionnaires were completed by the Park Management Councils every six months and the
IBAP Coordinator and the Monitoring and Planning Unit reviewed the data for quality and consistency.
Training in the use of these instruments was/is continuous. PA directors/staff were also trained to use the
RAPPAM (Rapid Assessment and Prioritization of Protected Area Management, a methodology designed
for broad-level comparison among multiple PAs comprising a PA system or network), and instruments
developed by IMET (Institute of Marine and Environmental Technology, University of Maryland, USA),
for measuring improvements in PA planning and management. 15
See Annex 2 for the minimum requirements for receiving GEF funds. 16
The additional cost burden to the Project of implementing M&E activities was around US$150,000. 17
Small-scale investments became the focus of other CBMP follow-ons: the IDA-financed Rural
Community-driven Development Project (P090712, US$5.0 million equivalent) and the SPF-financed
Participatory Rural Development Project (P117861, US$5.0 million equivalent). The BCP was clearly
expected to catalyze, but not finance, such investments.
10
monitored the long-term biological and socio-economic health of the PAs was acknowledged and
activities were added. See below.
2.3.3 Implementation: An analysis in 2011 concluded that IBAP needed to develop a SNAP-
wide Monitoring System for biodiversity trends in each park.18
While the METT was considered
an adequate proxy for project purposes, at the big picture scale an institution like IBAP needed to
be able to monitor the evolution of the status/health of PA resources in terms of biodiversity
conservation and ecosystem protection on the ground to determine if its management approaches
were/are achieving the desired results or not, i.e., the basis of an adaptive management approach.
This required both a more comprehensive, long-term monitoring system for tracking trends in
biodiversity and socio-economic indicators, established in line with park objectives, combined
with specific research programs to investigate and answer key questions, all well beyond the
scope of the BCP. It was recommended that IBAP: (i) define a set of key indicators relevant to
the monitoring of endangered and threatened species and/or park health status (e.g., population
size, habitat ranges, habitat area); (ii) develop a consistent M&E method with clear data
collection protocols, including standardized forms and measurement schedules for each
species/ecosystem indicator; and (iii) establish an easily accessible database, updated periodically
and harmonized with similar databases in the West Africa region. A BCP-financed, SNAP
Monitoring System was designed and other donors are financing its implementation. Para 3.2.3.
2.3.4 An early proposal to restructure the RF, allowing for a period of implementation, did not
proceed. Subsequent analysis of indicators and targets suggested that formal revision of the RF
was unnecessary due to the minor nature of the few changes proposed, mostly the refining and
clarification of some intermediate indicators to improve measurability. Surprisingly, the issue of
the Core Sector Indicator did not come up, i.e., reducing the target or clarifying its meaning and
measurement. Finally, IBAP prepared a good quality Client Completion Report, reviewed by the
Bank.
2.3.5 Utilization: IBAP prepared reports for domestic and external consumption which were
shared with all project partners/donors – especially for FBG fund-raising campaigns - and clearly
contributed to biodiversity becoming the central, cross-cutting theme of Government’s new 10-
year plan, “Terra Ranka” (English: lift-off, fresh start). The BCP monitored a range of activities
and functions used on an ongoing basis to improve the performance of IBAP and the BCP itself.
2.4 Safeguard and Fiduciary Compliance
2.4.1 Safeguards compliance: The BCP was classified as a Category B operation and
triggered OP/BP 4.01 (Environmental Assessment) and OP/BP 4.12 (Involuntary Resettlement).
The Project was designed explicitly to continue and strengthen a participatory process for the
management and conservation of parks and biodiversity. None of its activities were expected to
produce significant, negative environmental or social impacts and no construction or
rehabilitation/civil works were envisaged. But, to minimize and mitigate any potentially adverse
impacts, an Environmental Assessment (EA) and Environmental and Social Management Plan
(ESMP) were prepared in line with OP 4.01. Similarly, even though the highly participatory
approach to PA management involving multiple stakeholders ensured their engagement in the
parks’ evolution and reinforced the view that the risk of conflict was inherently low, the BCP
18 See Annex 2 of Aide Memoire for mission of October 31, 2011.
11
triggered OP 4.12 and preparation of a Process Framework - widely disseminated and consulted
in the parks - to ensure that any potential risk of restricted resource use would be addressed.
2.4.2 Compliance with the ESMP was satisfactory throughout and no issues emerged. Further,
no issues arose requiring action under OP 4.12. As planned at appraisal, a set of safeguards tools
was included in the FBG’s Operational Manual to ensure that FBG-supported activities explicitly
took into account potential environmental and social impacts, as well as the provisions of the
Resettlement Policy Framework. Further, safeguards provisions were also built into the park
regulations and business plans. The ICR assesses safeguards compliance as Satisfactory.
2.4.3 Financial management/audit: IBAP established and maintained strong financial
management (FM) performance throughout project execution without indications of fraud or
corruption. Internal controls were strengthened, the accounting information system was updated
regularly, compliance with Bank standards and the FM manual was satisfactory throughout, and
financial reporting was regular and of generally good quality. Independent external audits were
uniformly unqualified and any issues detected by auditors were resolved promptly. A Bank
fiduciary mission in 2013 coinciding with a limited re-engagement of the Bank post-coup and
designed to assess the fiduciary capacity of the Bank’s Guinea-Bissau portfolio of active projects
and determine the need for technical assistance, praised IBAP’s FM performance during the risky
aftermath of the coup. The Bank review found that expenditures were well-supported with no
irregularities detected, noting: “This is remarkable and needs to be credited to the (BCP) teams
and authorities”.
2.4.4 Procurement: Procurement performance was supervised regularly by the Bank
Specialist. Procurement management by IBAP was rated Moderately Satisfactory throughout.
Clearly the performance under the BCP was an improvement over the CBMP where IBAP’s lack
of experience with Bank procurement rules and processes, and the Bank’s regional institutional
arrangements for procurement, created issues. Record-keeping under the BCP was good with
some issues in regard to information on payments (actually available in the FM system),
archiving of procurement dossiers, non-publication of contract awards, and delayed procurement
under some activities. Procurement was especially affected by the suspension of disbursements
as most activities foreseen in the Procurement Plan could not be financed, a situation beyond
IBAP’s control. A Procurement Risk Assessment post-coup (March 2012) rated the risk for
procurement processes and contract administration as Substantial and Moderate, respectively,
with overall risk rated Moderate and country risk rated High. There were no outstanding
procurement issues at closing.
2.5 Post-completion Operation/Next Phase
2.5.1 The primary financial instrument to sustain reforms, investments and institutional
capacity is intended to be the FBG - complemented by ongoing donor support - and this is
discussed in detail in Section 3.2 and Annex 2. In terms of follow-on operations, and maintaining
the over-arching vision and logic, a range of options and opportunities was discussed with the
Government prior to closing, including: (i) continued actions to multiply financing for the FBG to
sustain the SNAP in perpetuity; (ii) specific actions in biodiversity protection; (iii) local
economic development through support to artisanal fishing, eco-tourism and other income
generating activities; and, (iv) exploring the theme of the increasing pressure on forest resources.
Following BCP closure, the Bank passed the baton to UNDP/GEF 5 to continue support for FBG
fundraising activities. A separate Global Climate Change Alliance (GCCA+)/EU project is
funding on-the-ground management activities in several SNAP PAs, while other donor-funded
12
projects are supporting different elements of FBG/IBAP operations. This overall approach, led
by the Bank/IBAP is consistent with the long-term vision, realities on the ground and broad
stakeholder agreement/collaboration. See Table 5, Annex 2.
2.5.2 Given the importance and vulnerability of the coastal zone, the Bank recommended that
Government explore potential linkages with the Bank’s coastal resilience efforts under the West
Africa Coastal Areas (WACA) initiative to which Guinea-Bissau could adhere, complemented by
the West Africa Regional Fisheries Program (WARFP) financed by the Bank and GEF in which
Guinea-Bissau already participates. Government has actually requested that the Bank be
implementing agency for a GEF 6 of at least US$ 2.0 million allocated to biodiversity – and a
direct follow-on to BCP activities - under their national STAR (System for the Transparent
Allocation of Resources) allocation and as part of the second phase of the WARFP. The Bank
advised Government to consider preparing a global operation rather than multiple, small projects.
IDA resources could potentially be brought in with GEF resources, while STAR funds could be
combined with other sources such as the Least Developed Countries Fund (LDCF) under its
climate change adaptation window; or, the Small Island States Resilience Initiative (SISRI). A
strategic choice to integrate with SISRI could be justified because a large part of Guinea-Bissau’s
territory is situated in the coastal region with strong biological diversity and marked vulnerability
to climatic variation.
2.5.3 Institutional capacity/growth is considered likely to be sustained but needs ongoing
support from the Bank and other partners. As noted earlier, IBAP has operated for 12 years, has
survived significant instability, is maturing into a skilled and well-organized institution with a
global profile, and has developed notable capacity to leverage donor support for diverse needs of
the SNAP. Much work remains to be done to shore up the SNAP and political instability is
unlikely to end. Therefore, “sustaining reforms and institutional capacity” does not end with the
activation of the FBG but will require sustained Bank leadership and support to ensure that the
institutional framework created thus far is not eroded by the exceptionally difficult political
context. See also Section 4.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Rated: High
3.1.1 The relevance of objectives to current country and global priorities remains high.
Protecting, conserving and managing Guinea-Bissau’s biodiversity and immense natural wealth is
a critical determinant of the nation’s growth potential, and a top priority for the Government as
reflected in its pivotal cross-cutting status in Government’s new National Development Strategy
2020 (Terra Ranka), and in IBAP’s National Strategy for Protected Areas.19
Official ownership is
high. Economically and socially, the country’s abundant natural resources provide diverse
sources of income for a large portion of the country’s population, dependent on them for survival.
Of equal importance, given the globally and regionally significant biodiversity and eco-systems
hosted by Guinea-Bissau, especially in its marine and coastal areas, project objectives remain
relevant and rational, i.e., a two-pronged approach supporting IBAP’s on the ground management
of the parks as the repository of national wealth (carbon stocks, regional fisheries, rare species,
19 Estratégia Nacional para as Áreas Protegidas e a Conservação da Biodiversidade na Guinea-Bissau,
2014-2020, IBAP 2014.
13
mangroves, climate change mitigation through coastal flood control), while constructing a formal
mechanism for self-financing its long-term continuity/survival.
3.1.2 The fundamental thrust of Government’s strategy is echoed in recent Bank strategies. At
the time of project preparation, there was an Interim Strategy Note (ISN) governing the Bank’s
engagement in the country. The project supported the two pillars of the 2009 ISN, namely to: (i)
strengthen economic management and laying the foundations for improvements in the productive
sectors; and, (ii) increase access to basic services, especially for the rural population, as well as its
cross-cutting themes of capacity development and building partnerships. In more recent
documents, among the pillars of the Country Economic Memorandum (CEM, 2015)20
,
strengthening the public sector - and in particular public financial management - is of primary
importance, consistent with the BCP’s objectives for strengthening IBAP and seeking to make the
SNAP self-sustaining through the FBG. The CEM calls for strengthening environmental and
enforcement agencies, citing IBAP and CAIA; and, mobilizing additional fiscal revenue
including by preserving the country’s natural wealth and promoting its efficient management,
specifically fisheries (halting illegal activities, increasing license fees and promoting sustainable
fishing), forests (timber, carbon credits), and natural habitats and ecosystems as sources of
sustainable income. The CEM asserts that securing the ongoing conservation efforts for the
SNAP is critical to preserving ecosystem services and economic opportunities. Second, the
ongoing relevance of BCP objectives to the Systematic Country Diagnostic (SCD, 2016) is strong,
reflected most prominently under the SCD’s challenge of “fragility and weak governance” where
the proposed responses include reforming the management of natural resources as the key to a
more prosperous and sustainable future. This would be effected through: halting forest loss
resulting from cashew and rice expansion, as well as illegal felling; optimal management of
fisheries resources; and, ensuring sustained financing for the SNAP, stressing explicitly the
urgency of capitalizing the FBG. The SCD also concludes that medium-term, policies and
investments geared to harnessing the value of a nature-based economy are key, e.g. eco-tourism.21
3.1.3 The relevance of project design is rated substantial: Design was based on global best
practice and on the lessons of the CBMP, and acknowledged the immense value of Guinea-
Bissau’s natural endowment both nationally and to other regions.22
Government – with Bank
support - has created a national parks system, incorporated coastal and biodiversity management
principles and practices nationally, and supported and approved the tax-exempt status of the FBG.
The FBG is the result of a national strategy and priorities adopted by IDA, GEF and the
Government since 2004 – consistent with the broad, multi-donor approach adopted to achieve an
efficiently managed SNAP, and its design is consistent with the best practice recommendations of
the GEF and Conservation Finance Alliance. It was entirely relevant and essential – through the
BCP (and its sister operation the BCTF/GEF) - to further secure the gains of the CBMP and to
strengthen IBAP’s institutional and human resource capacity to manage the SNAP “under one
roof” while shoring up its financial status long-term by bringing the FBG to operational status.
Project design has, since the beginning, been framed by the modest amounts of financing
accessible to Guinea-Bissau – mandating an incremental approach - and each operation is
designed to consolidate and further advance/expand what already exists.
20 Guinea-Bissau – Country Economic Memorandum – Terra Ranka! A Fresh Start, World Bank Report
# 58296-GW, January 12, 2015. Note that a Country Partnership Framework (CPF) was recently initiated. 21
Guinea-Bissau – Turning Challenges into Opportunities for Poverty Reduction and Inclusive Growth:
Systematic Country Diagnostic (SCD), World Bank Report #106725-GB, 2016. 22
Optimizing Guinea-Bissau’s Natural Wealth, H. Edmundson, World Bank, September 2014.
14
3.1.4 Project components and implementation arrangements were appropriate, given the small
size of the IDA Grant and the sound, successful institutional structure already established.
Components were logical: (i) further boosting IBAP’s institutional capacity to manage the SNAP
and monitor species on the ground (Component 1), reinforced after effectiveness by the inclusion
of activities to design/establish a higher-level, longer-term monitoring system harmonized with
the systems of regional countries; (ii) moving FBG into its operational phase (Component 2); and
(iii) Component 3 was the “anchor” supporting the all-important programmatic approach built
into project design, multi-source budgeting and uniting stakeholders around the table.
Implementation arrangements established under the CBMP remained stable. IBAP maintained its
leadership role and autonomous identity, while the FBG got up and running. The rating of
Substantial takes account of minor flaws in the RF, bringing the rating below High.
3.1.5 The relevance of implementation is rated high. Implementation was flexible depending
on circumstances, much of which under the BCP were completely beyond its control and required
patience and resourcefulness. Component 3 was the window through which the programmatic
approach was consistently pushed. Continuous efforts to harmonize donors and activities proved
crucial during the coup-related suspension of disbursements and activities. The new Government
was fully-supportive,23
with the Bank working with the Client to promote understanding of the
project vision, and with donor partners in national and international fora to always keep them
abreast of where they fit in the big picture and what this entails. Project support helped connect
Guinea-Bissau to the global ecological network and this was effected through many specific
activities/events accessed opportunistically and always with the long-term goal front and center.
3.2 Achievement of Project Development Objectives
Rated: Substantial
3.2.1 The BCP was designed to improve the planning, execution, management and financing of
activities affecting a large geographic area - on the ground - complemented by a significant
portfolio of other donor projects/activities all of which were/are IBAP-managed and moving in
the same direction. IBAP has survived political turbulence, remained stable in its management
and core professional staff, demonstrated strong capacity to expand and improve its technical and
financial management of the SNAP, and is building an international reputation in the sector. The
BCP represented about 80% of IBAP/SNAP’s staff and operational costs but it is important to
bear in mind that IBAP of necessity and in the context of its overall, longer-term strategy receives
multi-donor, integrated, inter-dependent financial/other support. Thus, determining attribution in
the pure sense is not always feasible. The BCP financed all activities planned at appraisal, fully
achieved its two PDO Indicators and, of eight Intermediate Outcome Indicators, three were
exceeded, four fully achieved and one partially achieved. The sustainability outlook is positive
with certain caveats. This is a remarkable achievement in the circumstances. On this basis,
achievement of the PDO is rated Substantial, as evidenced below.
Objective 1: Strengthen IBAP’s management of Guinea-Bissau’s national parks.
Rated: Substantial
23 This latest government was dismissed shortly before the submission of the ICR.
15
3.2.2 The BCP’s transitional financing provided the bulk of the core operational funding for
IBAP (including salaries, fuel, park management committee meetings, surveillance patrols, and
extensive communications/outreach and training activities) without which the management of the
SNAP would have declined significantly both in terms of PA protection and community
sensitization and engagement. The main instrument for measuring the effects on IBAP’s
management of the SNAP was the METT, complemented by other achievements demonstrating
that IBAP’s management of the parks continued to improve throughout BCP execution. METT
score-card results are reported below, along with additional evidence.
METT aggregate Score Card results by end-2015 were 507, 108.3% of the project target
(448), and 117% of the 2009 baseline (433). See footnote 18.
Year PNMJVP PNO PNTC PNLC PNC
2011 106 113 105 74 56
2012 107 115 109 75 56
2013 111 121 122 77 59
2014 114 119 124 81 54
2015 116 119 129 83 60 Source: IBAP/METT Scorecards 2011-2015
Numbers of annual surveillance and control missions covering the five parks exceeded
the 60 missions projected/targeted (12 per park/year). Annual missions increased
steadily: 109 in 2012, 134 in 2013, 164 in 2014, and 302 missions in 2015.
This result is attributed to the following: (i) the 2015 surge in surveillance activities by
organized, resident park communities motivated by IBAP’s effective, BCP-financed
communication, outreach and awareness-building program in the parks. Surveillance
activities became more frequent with the communities’ involvement, and with a new
dynamism associated with stakeholders’ “ownership” of the management and control
instruments/methods; (ii) IBAP’s demonstrated commitment to implementing its PA
Action Plans;24
and, (iii) effective collaboration and synergy among IBAP’s institutional
partners: BCP, the Fisheries Monitoring and Control Institute (FISCAP) and the Rias do
Sul Project (IUCN/West African Economic and Monetary Union -UEMOA). Section 2.2.
Year PNMJVP PNO PNTC PNLC PNC Total
2012 31 45 31 2 0 109
2013 34 64 24 12 0 134
2014 39 39 37 42 13 164
2015 53 53 90 57 24 302 Source: IBAP Surveillance Data, 2012-2015
All five parks received updated Internal Regulations – validated and signed by the
representative PA Management Councils - and Business Plans, exceeding project targets.
Other achievements indicative of IBAP’s growing capacity/influence included the
participatory preparation of clear/simple responsible fishing plans, working with fishing
24 IBAP’s acquisition of four new coastal/marine surveillance vessels (financed by the Life Web Project)
also contributed to its surveillance of the PNO, PNMJVP and PNTC PAs, covering updating of the
maritime zones, coastal enforcement activities, and monitoring of threatened species and habitats.
16
communities in Orango, Cacheu and Cufada PAs; and, the integration of social and
environmental safeguards into the internal regulations for Cufada and Cacheu PAs.
786 IBAP staff, institutional partners and community managers were trained from 2011-
2015, 314.4% based on an aggregated annual target of 50/year defined at appraisal.
Numbers trained annually steadily increased, and training covered a wide range of
relevant subjects, tailored to the needs of each PA.25
IBAP estimates that the BCP directly benefited around 43,000 people, some 61% of the
targeted 70,000 under IBAP’s BCP-financed communications/awareness-building and
direct training activities. These included training for 786 IBAP personnel at Headquarters
and in the PAs, plus an estimated 42,200 people who received biodiversity-related
sensitization training, and training targeted at the beneficiaries of IBAP’s micro-
investment financing (leveraged from other donors) for ecologically-appropriate
technologies and alternative livelihoods. An estimated 65 percent were women.
Sensitization impacts were not formally-studied but anecdotal evidence suggests they
could be substantial. For example, communities: (i) intervened to deter outside interests
from illegal felling/logging of forest on the periphery of several PAs, especially in the
unstable, post-coup period; (ii) sought ways to protect rice fields from hippopotamus
incursions without harming the invaders; (iii) asked Park Rangers for guidance on
humane removal of snakes and other invasive species; (iv) demanded ecologically-
appropriate ovens/fire pits; (v) reported illegal settlements within the PAs to Park
authorities; and, (vi) consulted Park Rangers about saving an injured manatee.
3.2.3 Monitoring of key species: Effective tracking of species on the ground was recognized as
an obvious product of improved SNAP management. Due to the need for a deeper, more global
approach than the plan for species monitoring envisaged at appraisal, and insufficient BCP/IDA
funds for such larger effort, a more encompassing, two-stage plan thinking beyond the project
boundaries and with a different “product” was negotiated with IBAP/donors: a SNAP-wide
Monitoring System tracking the overall biological and socio-economic health of the PAs. The
BCP/IDA would be the catalyst financing the first stage and donors would finance the second
stage under collaborative arrangements. Under Stage I, the BCP/IDA financed the
development/design of the overall approach including databases/indicators on emblematic species
working with forestry, species and social specialists. Participatory diagnoses helped identify key
indicators for each PA, and measurement protocols which could be harmonized with other
regional databases in West Africa. Baselines became the foundation for adaptive management.
IBAP consulted with sub-regional institutions to integrate and harmonize this database with
regional and international systems. Stage I was completed by closing. Stage II – co-financed by
MAVA and the EU – is ongoing, consisting of training in data collection, GIS
design/implementation and equipment. See also 2.3.3.
3.2.4 Under its regular species monitoring, the BCP/IDA financed Action Plans for marine
turtles, mangroves and hippopotamus; and, National Integrated Action Plans for 4 bird species of
national and sub-regional importance: Balearica pavonina; Limosa limosa; Phoenicopterus
minor; and Platalea alba. Marine turtle and mangrove Action Plans were finalized and under
25 Training covered: monitoring of protected/threatened species; PA management (enforcement and
vigilance; conservation of humid zones; Logiciel MIRADO for S&A; the laws governing PAs; and
environmental education); eco-tourism; conservation and transformation of halieutic products; local
products and sanitary standards; forest management including inventories, nursery management, fire
prevention and protection, strategic planning and reforestation methods; construction of eco-friendly
stoves; aerial photography, GIS and GPS management; local development and communication.
17
implementation since 2013; the Hippopotamus Action Plan was finalized/validated in 2014 and is
now under execution; and, a monitoring strategy was designed for aquatic/migratory birds as well
as a National Integrated Action Plan for the four bird species named above. Routine monitoring
of marine turtles, marine hippopotamus, and grey parrot in Orango and João Vieira e Poilão parks
show steady increase in numbers, nesting/ovation and sightings (see Table 3, Annex 2).
Objective 2: Pilot the operation of a sustainable financing mechanism for the national parks.
Rated: Substantial
3.2.5 The following demonstrates substantial advancement of the FBG’s operational status:
The FBG was physically established and its operations piloted (in accordance with the
minimum requirements for receiving GEF funds in the endowment – see Annex 2, para
2.7). The FBG Board of Directors was established and was meeting in accordance with
its TORs and the timetable defined in its Statutes; its fourth annual session was conducted
in 2016. An interim Executive Secretary (ES) was converted to full-time for 4-5 years.
The plan is to recruit/train a grants officer to take over the ES position.
FBG management systems (including fiduciary) are in place and operational, producing
satisfactory annual and quarterly reports. The FBG’s Operational Manual (OM) and
manual of procedures were adopted by the FBG Council. The OM includes
environmental and social safeguards instruments.
Formal Board approval was received for the FBG’s Investment Policy Statement and to
competitively appoint a UK-based asset Investment Manager for the FBG’s endowment
fund, with guidance from a BCP-financed, independent, investment management
consultant.26
The SNAP and FBG financing strategy was prepared with support from consultants from
the Brazilian Biodiversity Fund (FUNBIO), also involved in a pilot arrangement to
mentor the FBG.
Government signed a protocol with the FBG giving it full legal rights to operate as a
charity in Guinea-Bissau, with tax-exempt status. The UK also conceded charity status to
the FBG. Actual grant flows have not started. Once the UK bank account is established,
and the funds deposited, investment will start and revenues will start to flow. Annex 2.
A comprehensive capitalization strategy is under implementation. Donor pledges as at
May 31, 2016 totaled some EUR 4.6 m, from: MAVA Foundation (EUR 1.3 m); GEF
V/UNDP (USD 1.22 m, equivalent to around EUR 1.0 – 1.2 million depending on
exchange rate); Government of Guinea-Bissau (EUR 1.0 m); and, EUR 1.0 m from
FFEM. The VCS-REDD+ pilot is underway and expected to result in carbon credit sales
from an average avoided deforestation of 900,000 tCO2/year over 20 years (Cacheu and
Cantanhez PAs) valued at an average US$3.04 m/year over 20 years, a portion of which
will go to the FBG endowment (and portions to monitoring, reporting and verification
(MRV), forest management and community benefits). See Annex 3.
3.2.6 Finally, in regard to the objective of reducing dependence on ad hoc financing/projects,
the strategic choice to use the UNDP/GEF funds to support FBG operations over the next four
years will allow the FBG to apply 100 percent of the revenues to be generated from its
endowment to visible biodiversity conservation activities on the ground. Further, the EUR 1.0
26 See Bio Guinea Foundation Investment Manager Selection and Appointment, August 27, 2016. See also,
Bio Guinea Foundation Investment Policy Statement, August 27, 2016. Finalization of this work will be
co-financed by UNDP/GEF under their follow-on project.
18
million government contribution is for endowment capital, not FBG operating costs, and has been
earmarked within the EU Fisheries Accord. It is not drawn from central government budget and
is thus insulated from the general fiscal situation. Further, 50 percent of that amount has already
been transferred to FBG, and transfer of the balance is considered likely.
3.3 Efficiency
Rated: Substantial
3.3.1 Methodology: A classic economic and financial analysis (cost-benefit (CB) or cost-
effectiveness (CE)) was not conducted at appraisal and remained inappropriate at closing, given
the country context, nature of the BCP and small size of the IDA credit. Based on country
conditions in particular, any quantitative measure to value project benefits (for a CB analysis) or
project effectiveness (CE analysis) would likely be unable to show a true benefit, value or cost
due to systemic distortions and/or conditions of under-financing. The PAD noted that – pending a
concrete assessment of the current and future economic and financial benefits attributable to the
PA network and the ecosystem services it provides - the importance of those benefits could be
inferred. Some positive, updated information is available for several sectors from the World
Bank’s Natural Wealth Study for Guinea-Bissau (Edmundson, 2014) and other sources, with
caveats concerning data reporting, availability and reliability (see Annex 3).
The wealth study conservatively estimates total fishing “potential” at 120,000 tons/year
and total wealth per capita from fishing at some US$305. Further, data shows that the
Government took in public revenue of US$20.0 million in 2015 from fishing activities –
about 25 percent of total government revenues in 2015 - of which US$9.25 million were
license fees from the industrial fishing sector and the remainder were access agreement
payments, mainly from the EU. IBAP continues to monitor/protect the country’s vital
fish breeding and nursery areas lying within the SNAP.
In regard to carbon, the PAD estimated that carbon storage by some 60,000 ha of
protected mangroves in three PAs exceeded 298,000 tons of avoided CO2 emissions/year
with potential to generate around US$5.0 million over seven years. At BCP closing, and
based on the REDD+ Project, this estimate has increased significantly. Carbon credit
sales for just two PAs (Cacheu and Cantanhez) could potentially produce revenues
exceeding US$3.0 million per year, averaged over 20 years. See Annex 3, Box 1.
The potential for eco-tourism noted in the PAD remains high, with solid comparative
advantage resting on its biodiversity and cultural assets. While reaping the benefits
remains well in the future, the BCP’s efforts to further shore up the SNAP’s sustainability
was further “down payment” on that future tourism economy.
Annex 3, Table 1 shows a range of other important benefits flowing from the BCP.
3.4 Justification of Overall Outcome Rating
Rating: Satisfactory
3.4.1 The overall rating of Satisfactory is based on the following:
Relevance: High The PDO was a straightforward statement of well-diagnosed priorities
aligned with past and current Bank and Government policies and strategies.27
Project
design - with minor caveats - was appropriate for achieving those priorities and
27 Country Economic Memorandum: Guinea-Bissau, Terra Ranka! A Fresh Start, World Bank Report No.
58296 Vol. I and II, January 12, 2015; and, Guinea-Bissau 2025: Strategic and Operational Plan for 2015-
2020 – Terra Ranka, Republic of Guinea Bissau, March 2015.
19
thoughtfully complemented other donor-financed and IBAP-executed operations
addressing inter-related portions of the overall vision.
Efficacy: Substantial This rating takes into account the substantial achievement under
both major elements of the PDO and all Intermediate outcome elements, the positive
sustainability outlook (noting country risk), as well as BCP-financed, successful piloting
of FBG operations.
Efficiency: Substantial Many benefits resulted from a modest investment (see Section
3.3 and Annex 3 matrix). All planned project activities were financed (and a vital
monitoring activity was added), and the IDA grant was fully-disbursed. The one-year
extension of the closing date was essential to compensate for the Bank’s coup-related
suspension of disbursements and was not related to inefficient project management.
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
3.5.1 The BCP had no explicit poverty objectives, activities or financing. The BCP’s
complementary alliance with the GEF/BCTF and the CDD project, the latter financing small-
scale socio-economic investments for park and peripheral communities, was part of a broad
vision of the many benefits – including socio-economic - of a well-managed SNAP. Further, as
already noted, while the BCP did not directly finance eco-friendly, alternative livelihood
investments in the PAs, it did finance the training and awareness-building associated with these
investments, as well as the ongoing strengthening of IBAP’s institutional capacity to leverage the
requisite resources. IBAP estimates female beneficiaries at 65 percent of direct beneficiaries.
(b) Institutional Change/Strengthening
3.5.2 IBAP: With BCP support, IBAP demonstrated further institutional growth. IBAP made
significant advances in adopting a programmatic approach via the piloting of integrated, multi-
year planning tools to improve capacity to manage and monitor the SNAP in a coordinated
fashion across diverse financing sources and projects. Further, even though individual donors
generally require that their reporting requirements be met, the move towards an integrated
information management system was designed to improve transparency in the use of funds and to
empower IBAP to manage various funding sources more proactively. Further integration of
project activities into a codified system continued to progress and was finalized in 2014, to
improve the overall efficiency of how SNAP management is implemented and monitored. Its
outreach to PA communities and participatory methods for garnering their engagement in park
management and especially the surveillance effort was increasingly confident and effective, and
the institution acquired a global profile in the conservation sector. It was especially effective in
leveraging financial support from multiple donors. At closing for example, IBAP was managing
eight operations and processing another four (see Annex 2, Table 5). Astute resource leveraging
has become a hallmark of IBAP’s survival strategy, not only plugging financing gaps but helping
to crowd in donors. IBAP, as a maturing, experienced agency benefiting from BCP training and
mentoring, successfully advocated for and managed the incorporation of two new PAs and three
associated biological/wildlife corridors within the SNAP. These parks/corridors were not
financed directly by the BCP but were an indirect benefit of the project through IBAP’s
burgeoning institutional capacity and donors’ growing sense that the SNAP is well-managed.
3.5.3 BioGuinea Foundation (FBG): BCP support enabled the FBG to successfully pilot its
operations, a project objective. Further, human resource and institutional capacity-building of the
FBG Team, its participation in international fora for knowledge exchange and learning, as well as
20
collaboration with and mentoring from other Conservation Trust Funds (CTF) in Africa and
Brazil helped build a transparent, modern institution operating in line with international best
practice and in compliance with UK law. This helped the FBG establish its visibility and
credibility, with multiplier effects vis-à-vis the establishment of collaborative relationships and
support for its endowment which currently stands at EUR 4.6 million (within the parameters
mentioned at appraisal), with strong potential for additional financing from carbon credit sales.
(c) Other Unintended Outcomes and Impacts (positive or negative)
3.5.4 Several unexpected and/or noteworthy developments include:
More regular and frequent park surveillance missions in collaboration with local
communities, and a new dynamism resulting from local ownership of the instruments for
control and management.
Donor/institutional synergies going beyond regular surveillance to other key activities,
e.g., the dismantling by IBAP of unauthorized/illegal settlements within the southern
borders of the Cantanhez and Cufada Parks.
IBAP’s participatory preparation with fishermen in the marine zone, of clear and simple
rules for responsible fishing in Orango and Cacheu Parks.
An easily-managed database, and the valuation and interpretation of field data via GIS
resulted in some reduction of illegal fishing and hunting. Evidence suggests that the
clandestine cutting of large trees was also reduced on the periphery of several PAs.
IBAP assumed managerial responsibility for over 319,400 ha of new PAs and fauna
corridors, expanding the SNAP from 15 percent to 26 percent of the national territory,
and ensuring that it now represents all marine and terrestrial zones. The Bank Team’s adaptation to evolving knowledge and circumstances and going
beyond the original project activities/objectives in promoting the formulation and design
– with IBAP – of the SNAP-wide Monitoring System.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
3.6.1 Within a very small financing envelope, surveys and workshops were not feasible. That
said, the annual METT score card exercise can be considered a proxy for “beneficiary survey,”
asking respondents for their views on a range of indicators of good management performance in
the PAs. Annual and special meetings of donors and other international and national partners
(NGOs, private sector, other government departments) solicited views on SNAP management, the
way forward and their “fit” within the main themes/priorities. Donor/partner recommendations
were influential in guiding IBAP’s approach and evolution. While PA communities were not
formally surveyed, the meetings of the representative Park Management Councils,
communications and dissemination activities in the PAs and the cultural tradition of PA
communities freely voicing their opinions, influenced the cycle of feedback and improvement.
4. Assessment of Risk to Development Outcome Rating: Significant
4.1 The primary justification for rating risk to development outcome as Significant remains
the likelihood of further political unrest and the possibility that this could, over time, erode
IBAP/SNAP, i.e. country risk. This is beyond the control of IBAP, donors or projects. The Bank
has been the lead donor and instigator of annual donor/partner management meetings, creating
synergies. The Bank has facilitated – in cooperation with and through IBAP – specific lines of
21
action designed to mainstream and sustain IBAP and SNAP, with the funding being provided by
other sources, i.e., a continuous process of leveraging financing for a resource-poor state with a
well-defined, high-value endeavor. Such financing is undeniably “drip feeding” but this is the
reality and the Bank has consistently sought to ensure that the donor community understands
where its contributions fit rationally in the overall picture, to avoid duplication and overlap.
Another important sustainability issue is the engagement of a new generation in the SNAP vision
– IBAP has recently taken on younger staff, and maintains a proactive communications outreach
agenda in the PAs which inter alia, targets younger community members. Overall, the
sustainability outlook is quite positive due to the following:
The FBG endowment has secured firm pledges for around EUR4.6 million and, US$3.04
million/year can potentially be obtained from the sale of carbon credits.28
Part of the
former is government’s EUR 1 million, indicating its ownership of the SNAP endeavor,
which has not wavered despite repeated turmoil/turnover. IBAP has consistently demonstrated its ability to navigate this political and operational
environment and is now entering its 12th year. There is strong Bank and donor/partner
awareness of the risks to the SNAP; all parties seek to mitigate those risks through
collaboration, explaining the unusual resilience of the BCP under adverse conditions.
Government followed through on its commitment to keep a portion of IBAP’s core staff
salaries afloat during the transition to FBG financing, transferring some CFA 60.0 million
to IBAP (about US$100,000 equivalent) to help carry it through into 2016.
Medium-term sustainability of IBAP and the SNAP is there. Many donors have come to
the table and there is broad agreement on the importance of the end-goal. Donors are
aware that government has stepped up to assist, signaling its commitment.
Government’s pending parliamentary approval of the expanded SNAP and IBAP’s
demonstrated commitment to managing the new parks/corridors, boosts confidence that
the SNAP is sustainable. Stakeholders are well aware that expansion implies further,
aggressive fund-raising for FBG’s endowment and sustained Bank/donor support.
Longer-term sustainability of IBAP, the FBG and the SNAP is likely, although
vulnerable to donor financing choices and availability, and implying continuing time and
effort to look for funding opportunities.
Biodiversity and natural resource conservation have been successfully inserted and
mainstreamed in national and sector strategies, and feature prominently in new Bank
strategies underpinning its lending priorities for Guinea-Bissau and the region.
Sustainability also translates into replicability, i.e., testing and consolidating the
successful IBAP/SNAP model and its multi-source, programmatic methodology in other
parts of Africa and beyond.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry Rating: Satisfactory
28 A portion of the USD 3.04 million is intended for the FBG endowment (see 3.2.5). Avoided emission
flows in the first year are actually low, increasing over time. Carbon prices may vary widely, as could
IBAP’s ability to manage PA forests, so current numbers are hypothetical and subject to variation. Box 1,
Annex 3.
22
5.1.1 The BCP was prepared rapidly and efficiently by an experienced Bank team to take
advantage of financing unexpectedly available for maintaining the momentum of and
consolidating an important endeavor in a small, poor country. It provided essential
bridge/transitional financing for IBAP’s core operations without which management of the SNAP
could have deteriorated rapidly. Its similarity to the BCTF/GEF was deliberate, designed to apply
additional funding to sets of activities carefully calculated to keep building out each essential part
of the long-term vision for a self-sustaining SNAP. Care was taken to ensure that for essential
activities under Component 1, GEF resources were exhausted before the IDA funds kicked in.
Project design heeded the lessons of the CBMP, was well-aligned to the Bank’s assistance
strategy and country needs, and financed international expertise to ensure that the technical
strategy was correct, which continued throughout the implementation phase. Quality at entry was
enhanced by IBAP’s burgeoning knowledge of Bank requirements, its successful execution of the
CBMP, and its stability as an autonomous public agency, which facilitated the Bank’s preparation
efforts. Project objectives and the Results Framework were well-designed and straightforward
with minor exceptions, and aligned to the modest financing available.
(b) Quality of Supervision Rating: Satisfactory
5.1.2 Bank supervision of the BCP was effective, regular and enhanced by an established
practice of constant online and skype communication with IBAP and project partners. This stood
the project (and IBAP) in good stead generally but especially during the many political upheavals
in the project period. Fiduciary supervision, including safeguards, was regular, comprehensive
and well-reported, with a more intensive focus post-coup. There was a strong effort after
effectiveness to establish systematic data collection and storage and, separate from regular project
monitoring activities, to create an integrated, harmonized database to measure the impact of
modern park management techniques on biodiversity, the ecology and the socio-economic status
of park residents. This was an example of strong project management by the Bank Team,
adapting to evolving knowledge and circumstances and going beyond the original project concept.
The Bank’s decision to suspend disbursements following the coup was correct in the
circumstances, but not without repercussions on timely project execution. The Bank supervision
team worked hard to maintain momentum during this period, and to help the project recover once
the suspension was lifted, which entailed a one-year extension of the closing date. The stability
and experience of the Bank Team undoubtedly contributed to the project’s success and to the
evolution and longer-term sustainability of the IBAP/SNAP vision.
(c) Justification of Rating for Overall Bank Performance Rating: Satisfactory
5.1.2 The rating of Satisfactory is justified by the consistently strong performance of the Bank
team during preparation and supervision, to exploit a programmatic, incremental approach -
attuned to the realities of the country and the modest financing available - to build sustainable,
modern and transparent institutions capable of managing a uniquely valuable natural resource.
5.2 Borrower Performance
(a) Government Performance Rating: Satisfactory
5.2.1 As discussed earlier, the BCP encountered a high degree of political instability during the
course of its implementation with a political/military coup in 2012 and subsequent repeated
turnovers of the national government even after free and fair elections in 2014. Even so,
23
successive, newly-installed administrations supported IBAP, its associated public institution
CAIA, and the SNAP. Government: (i) supported IBAP’s autonomy which in turn catalyzed an
enabling operational environment; (ii) financed a portion of IBAP’s salaries/operational costs
when the BCP essentially ran out of money/was fully-committed in August 2015, the first time
IBAP had received any government funds; (iii) contributed - through a positive dialogue with the
Ministry of Environment and Fisheries - EUR 1.0 million to the FBG endowment from the EU
Fisheries Accord, stimulating hesitant donors to step forward and participate; (iv) showed strong
commitment to the SNAP technically, politically and conceptually, evidenced in biodiversity’s
prominent cross-cutting role in the National Development Strategy (Terra Ranka); (v) convened
an International Donors’ Conference in 2015 to inter alia, galvanize support for the SNAP/FBG;
(vi) acknowledged IBAP’s sector leadership, global profile and demonstrated ability to garner
international support not only for the SNAP but for Guinea-Bissau; and, (vii) supported the
creation of new PAs and biological corridors totaling well over 300,000 ha.
(b) Implementing Agency or Agencies Performance Rating: Highly Satisfactory
5.2.2 IBAP: This institution now has an impressive record of project management in a
complex sector and against high odds. Its performance under the BCP is summarized as follows:
(i) fully-executed all planned project activities and fully-disbursed the credit with a one-year
extension needed to compensate for the Bank’s suspension of disbursements; (ii) exemplary
fiduciary performance throughout the project engagement period drawing special commendation
from the Bank for its FM in the risky post-coup period; (iii) impressive ability to leverage donor
financing for SNAP needs, including immense effort to secure pledges for the FBG; (iv) absolute
commitment to the SNAP vision including the additional parks which represented a high,
unforeseen cost burden. IBAP brought them under the SNAP umbrella to ensure standardized
approaches to their future conservation/protection on the understanding that the SNAP now
represents all ecological areas of Guinea-Bissau, including terrestrial; (iv) skillful use of
communications tools to garner stakeholder support in the parks, nationally and in global forums
among donors, sector partners and NGOs, and to establish and maintain an inclusive, productive
dialogue; and, (v) stable, productive and responsive working relationship with the Bank.
(c) Justification of Rating for Overall Borrower Performance Rating: Satisfactory
5.2.3 The justification for the Satisfactory rating lies in IBAP’s consistently good performance
and sustained commitment – including exemplary financial management – under pressure. This
was complemented by positive actions by government to support IBAP and the SNAP – again,
despite extreme instability – and clear evidence of policy buy-in to the national importance of the
country’s unique natural endowment.
6. Lessons Learned
6.1 The following lessons are among the more important from the BCP experience:
Establishing a conservation foundation is a participatory process the pace of which is
beyond a project’s control. It is overly ambitious to set targets that assume certain
donors/projects will come to the table on time and experience showed that the project was, in any
case, just one part of a longer-term effort. Fund raising takes time and is unpredictable, involving
many steps, decisions and interests. Events can intervene especially in unstable environments.
24
The institutional and administrative structure can be established but securing and formalizing the
funding might take added years. It is recommended that attention be paid to interim financing
needs based on a conservative assessment of how long specific fund-raising targets might take to
materialize.
Related to the above, there is a transitional, “dormant” period when a foundation is
structurally, legally and administratively established but its endowment is insufficient to
support financial outflows. Again, given the realistic time-line for a fully-endowed foundation,
this is more likely to happen under negative conditions when donor pushback can be expected
and is complicated by over-optimistic expectations of fund-raising velocity at appraisal, political
factors and the global economy. There is a vulnerable transition period of securing capital for the
endowment, getting the foundation up/running while also funding ongoing management of the
PA system. Donor/partner collaboration in such environments rests on the political context in-
country, not just the technical merits, the former beyond a project’s control. The flow of funds
will always require that donor pledges are honored and in the account, and have reached a
threshold sufficient to generate significant revenues. Even then, they need to be wisely invested
and start generating returns, which may be modest initially and require that transitional donor
financing be sustained.
IBAP’s status as a protected areas management agency – an administratively and
financially autonomous public institution under the jurisdiction of the State Secretariat of
Environment - has sustained it through repeated unrest and government turnover. This
institutional design has been critical to IBAP’s success and credibility. All IBAP staff including
its Director are competitively-recruited and well-qualified for their roles, and not affected by
government turnover. This contrasts with the instability of the more typical project
implementation unit embedded in a responsible agency, with its top echelon politically-appointed.
Acknowledging that not all projects can or should establish a new public agency, it is
recommended that similar projects seek at minimum, to embed the coordination body within a
stable sector agency and include a strategy for institutionalizing its functions and staffing, in situ.
Related to the above, the success of the BCP – in a fragile, politically unstable state – was
not an aberration. The factors which insulated IBAP and the SNAP included: stable Bank
support since the beginning; a sense of solidarity and commitment to the endeavor; IBAP’s
institutional autonomy, and established framework of donors/partners who have stayed involved;
prudent, conservative fiduciary performance despite pervasive governance issues; stable,
communicative relationships with the right entities/people able to get things done, including in
government; and, open, transparent and organized opportunities for planning and trouble-shooting
- stakeholders understood and agreed on their roles. It is recommended that this model be
sustained in Guinea-Bissau, and extended to other African FCV (fragility, conflict and violence)
countries with globally-important biodiversity and potential to supply environmental services.
Stability of the Bank and Client core teams and the depth/mutual trust of their engagement
have been highly advantageous. Such stability can have major advantages over time especially
for technically challenging projects in difficult country conditions. The Bank and Client teams
remain largely in place with a strong commitment to the over-arching vision, an excellent
working relationship based on trust, and the benefit of institutional memory. It is recommended
that this stability be preserved to the extent possible through continued Bank financial support
until IBAP and the FBG are clearly able to walk on their own.
Multi-donor support and an integrated, programmatic approach over a significant time
period are essential to realize/finance “big picture” objectives in fragile countries. Country
25
conditions suggest that donor contributions to this overall effort are likely to remain small but
they can be crucial for securing sustainability. Long-term donor commitment is needed to achieve
the end-goal. While there are disproportionate costs to the Bank (relative to the small size of the
project), the development impact of such interventions can be large. Economies of scale may not
be favorable but on a country basis, the impact justifies the cost to the Bank. It is recommended
that this approach be continued to consolidate the major gains already made and that the end-goal
be carefully defined to support strategy formulation and planning in the interim.
Intense and sustained supervision is appropriate for high-risk environments but does not
need to be costly or always direct, face-to-face encounters with country counterparts and
stakeholders. Regular online/skype contact provides many opportunities for timely
troubleshooting and reassures the Borrower Team that the Bank Team is committed to the joint
resolution of ongoing issues despite the situation on the ground. It is recommended that even for
projects not under pressure from political/civil disturbance, a regular agenda of online/related
consultation can effectively complement the Bank’s standard six-monthly physical supervision
and lead to more timely joint definition and resolution of problems/issues.
METT scorecard results are an important proxy for impact but complementary monitoring
to verify actual impact is essential. Appropriate expertise was included in early supervision
missions to propose an integrated and harmonized SNAP Monitoring System. Designing and
implementing such systems takes time and resources, as shown under the BCP. It is
recommended that projects planning to use the METT, also plan for and ensure the financing of
the more comprehensive system, which is separate from and complementary to standard project
monitoring activities, having a longer-term perspective, wider goals, a science-based approach
and cross-border linkages/implications.
The project demonstrated how to ensure sustainable financing for the conservation of
globally-important biodiversity in a situation of fiscal constraints. Guinea-Bissau is an
emblematic example of uniting donor collaboration around a longer-term vision with the Bank as
catalyst, providing relatively small financing with technical assistance to leverage the
commitment and resources of diverse entities to achieve a weightier result. It is recommended
that the Guinea-Bissau case be used to promote discussion in the Bank on how to ensure
minimum financing for protected areas management in the many African countries where this
continues to be a struggle despite the significant environmental services such areas provide. It is
also recommended, as a product of the ICR management and peer review process, that linking
biodiversity conservation to other agendas receiving more attention, (e.g., climate change and
land restoration), could attract more financing to the former.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/implementing agencies
7.1 The Client’s letter dated November 23, 2016 commenting on the Bank’s draft ICR was
received and inserted in Annex 7. The Client concurred with the ICR’s major findings and ratings.
(b) Co-financiers N/A (c) Other partners and stakeholders N/A
26
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Components Appraisal Estimate
(USD millions)
Actual
(USD millions)
Percentage of
Appraisal
1. Consolidation and strengthened
capacity for management of
coastal and marine protected areas
and biodiversity
1.27 1.27 100.00
2. Pilot operation of the
BioGuinea Foundation 0.39 0.39 100.00
3. Project management, and
monitoring and evaluation 0.29 0.29 100.00
Total Baseline Cost 1.95 1.95 100.00
Physical Contingencies
0.00
0.00
0.00
Price Contingencies
0.00
0.00
0.00
Total Project Costs 1.95 1.95 100.00
Front-end fee PPF 0.00 0.00 .00
Front-end fee IBRD 0.00 0.00 .00
Total Financing Required 1.95 1.95 100.00
(b) Financing
Source of Funds Type of Co-
financing
Appraisal
Estimate
(USD
millions)
Actual/Latest
Estimate
(USD
millions)
Percentage of
Appraisal
Client N/A 0.00 0.00 0.00
International Development
Association (IDA) Grant 1.95 1.95 100.00
27
Annex 2. Outputs by Component 2.1 The following discussion under each Component is intended to complement the output
matrix which shows achievements under all activities slated in the PAD for financing by the BCP.
Component 1: Consolidation and strengthening of capacity for management of coastal and
marine protected areas and biodiversity (US$1.27 m)
2.2 This component, in coordination with donor partners, sought to strengthen the
participatory management and conservation of the existing network of five parks (Protected
Areas) comprising the SNAP during its transition to more permanent, sustainable financing
sources. It would finance the implementation of selected elements of existing Park Management
Plans, as needed:29
Expenditures for Component 1 would be financed by IDA resources only after
the GEF/BCTF resources (US$613,000) for very similar activities were fully-disbursed.
2.3 The METT methodology is a rapid assessment based on a scorecard questionnaire. The
scorecard includes all six elements of management identified in the IUCN-WCPA Framework
(context, planning, inputs, process, outputs and outcomes) with emphasis on the first four items.
It is basic, simple to use and provides a mechanism for monitoring progress towards more
effective management over time. It is used to enable park managers and donors to identify needs,
constraints and priority actions to improve the effectiveness of Protected Area management.
Tracking Tool Indicators/Variables are extensive and have undergone changes over time. The
main assessment form has 30 questions, each with a 4-point scale (0, 1, 2 and 3). This scale
forces respondents to choose whether the situation is acceptable or not. Generally, 0 is equivalent
to no/negligible progress; 1 is some progress; 2 is quite good but with room for improvement; and,
3 is approaching the optimum situation. Four alternative answers are provided for each question
to help assessors judge the level of score given. In addition, three groups of supplementary
questions expand on key themes in the previous questions and provide additional information.
Questions not relevant to the Protected Area are omitted and the scores are adjusted. Scores are
then totaled and the percentage of the possible score is calculated. The Tool’s sponsors are aware
that the “scoring” process is open to distortion, e.g., the assumption that all questions cover issues
of equal weight. Scores provide a better assessment of effectiveness if calculated as a percentage
for each of the six elements of the IUCN-WCPA Framework.
Table 1: Park Management Effectiveness - METT Scores by Protected Area, 2011-201630
Protected
Area31
2011 2012 2013 2014 2015
Score % Score % Score % Score % Score %
PNMJVP 106 63.3 107 66.2 111 76.9 114 77.7 116 79.8
PNO 113 56.1 115 61.8 121 61.8 119 69.8 119 73.4
PNTC 105 56.3 109 48.9 122 59.4 124 64.6 129 69.8
PNLC 74 64.7 75 65.5 77 71.9 81 72.7 83 74.8
PNC 56 n.a. 56 58.3 59 61.5 54 56.3 60 62.5
29 Based on priorities identified during IBAP’s annual work program and budget exercise.
30 Does not include the newest parks/corridors created during BCP implementation as their formal
management was still being established. 31
Respectively: Parque Nacional Marinho João Vieira e Poilão (PNMJVP); Parque Nacional de Orango
(PNO); Parque Natural dos Tarrafes do Rio Cacheu (PNTC); Parque Natural das Lagoas de Cufada PNLC);
and, Parque Nacional de Cantanhez (PNC).
28
2.3 Creation of new parks: Two new terrestrial parks and three biological corridors were
added to the SNAP and are under IBAP management: the national parks of Dulombi and Boé as
well as the three biological corridors of Tchetche, Cuntabane-Quebo and Salifo, established with
GEF/UNDP financing of EUR 1.22 million under the Consolidation of Land-based Protected
Areas Project (2011-2016). While the initial decision to create these new parks was largely
donor-driven with little/no consultation with IBAP, upon discovery IBAP insisted that they
become part of the SNAP even though this presented a major challenge. Total national territory
under the SNAP increased by over 319,000 ha from 15% to 26%. On the positive side, by
creating these terrestrial parks, the SNAP now represents all major national eco-systems. Within
the big picture, this representative SNAP required BCP support to help IBAP think through the
implications of their creation - planning in human and physical terms for the future - although no
BCP financing went directly into establishing the new PAs. Multi-donor budgets and IBAP’s
financial strategy now include these PAs. However, on the negative side, the estimated cost of
managing this larger area – the technical, human resource and financial capacity needs - over the
next 20 years has increased from an estimated EUR 20.0 million to EUR 37.0 million,
underscoring the urgency of the fund-raising effort for the FBG endowment and the challenge
faced by IBAP to establish quality management of these new areas. Expectations have also been
created among the populations living in the new areas.
Table 2: Protected Areas under IBAP Management by end-Project Type of
Area
Protected
Name International
Designation
Area
(ha)
Area
(km2)
% of
Territory
Institution
Responsible
Legal
Statute
National
Park
Parque
Nacional do
Grupo de Ilhas
de Orango
Biosphere
Reserve
158,205 1,582.05 4.4% IBAP Decreto-
Lei
#11/2000
National
Park
Parque Natural
dos Mangais do
Rio Cacheu
Biosphere
Reserve
80,000 800.00 2.2% IBAP Decreto-
Lei #1000
National
Park
Parque Natural
das Lagoas de
Cufada
Local Ramsar 89,000 890.00 2.5% IBAP Decreto-
Lei
#13/2000
National
Park
Parque
Nacional
Marinho João
Vieira e Poilão
Biosphere
Reserve
49,500 450.00 1.4% IBAP Decreto-
Lei #6-
A/2000
Marine
Protected
Area
Area Protegida
Marinha
Comunitaria
das Ilhas de
Urok32
Biosphere
Reserve
54,500 545.00 1.5% IBAP Decreto-
Lei
#8/2005
National
Park
Florestas de
Cantanhez
Biosphere
Reserve
105,767 1,057.67 2.9% IBAP Decreto-
Lei
#8/2011
32 The Project directly-created Cantanhez National Park in parallel with NGO support for the country’s first Marine
Community Protected Area in the UROK Islands, which came to be included in the SNAP. The Urok PA was not financed by the BCP but was managed by IBAP, using the Project methodology, within the SNAP.
29
Type of
Area
Protected
Name International
Designation
Area
(ha)
Area
(km2)
% of
Territory
Institution
Responsible
Legal
Statute
Total: 536,972 5,369.72 14.9%
Additional Protected Areas (Terrestrial) established by IBAP from 2011-2016
National
Park
Dulombi Being defined 98,951 IBAP To be
published
National
Park
Boé Being defined 95,280 IBAP To be
published
Biological
Corridors
Tchetche,
Cuntabane-
Quebo and
Salifo
Being defined 33,604
55,003
36,604
IBAP To be
published
Total: 319,442 3,194.42 10.0%
Source: IBAP/METT, 2016
2.4 Species Monitoring: It became evident that to build IBAP’s institutional capacity,
exploit its collaborative and catalytic potential, and have a longer-term impact, the BCP needed to
think beyond the basic species action plans and monitoring databases/activities, to SNAP-wide,
comprehensive species conservation and monitoring, the results of which would not likely be
evident during the course of one project. Baselines were needed to enable basic, adaptive
management and the project needed to think about how to track the health of and achieve the
objectives – biological and socio-economic – for each PA over time, develop adaptive
management tools and adjust management strategies and approaches accordingly. It was agreed
with IBAP to establish a SNAP-wide Monitoring System and strategy with core indicators
(biological and socio-economic) by PA. Terms of Reference and the overall approach were
developed, working with specialist TA. This was an ambitious goal for which the BCP lacked
adequate resources, so that the original more limited monitoring plan/routine moved ahead in
parallel with the more encompassing, global approach with a different “product” being developed
in two stages. The BCP was the catalyst but with inadequate funds, IBAP had to think beyond
the boundaries of the project - other donors were needed. Stage I (BCP-financed) contracted
forestry, species and social specialists to identify, through participatory diagnoses, core/key
indicators for each PA, and a protocol for their measurement which needed to be harmonized with
other regional species databases. Stage II involves training for data collection, GIS
implementation and equipment, and is still ongoing, financed by other donors. See Table 6.33
33 Some 20 Ecological Indicators and 9 Social Indicators designed under the 1
st Stage, BCP-financed
SNAP Monitoring System include (depending on PA): Abundance and capture of marine turtles on PNO
beaches; Fishing: apprehension by surveillance missions and encounters with resident fishermen; Counting
of hippopotamus in Angor (PNO) lakes and on beaches; Number of resident fishermen, jetties and fishing,
and economic situation; Aquatic birds: Monitoring of Acapa/Imbone (PNO), Imbone lakes and rivers
(during surveillance missions); Counting of Timneh African Grey Parrots at specific points; Marine turtles:
counting in João Vieira e Poilão, Meio and Cavalos; Regular re-survey of people present in PNMJVP
islands and their activities; On-ground measurement and mapping via GPS in PNMJVP; Fishing:
monitoring via “fishing clubs” in Bubaque (size, measurement, photography); Participatory counting of
species (combe, lingron, gandi and oysters); Demographic dynamics in all Parks; Burning-off: number of
fires and area involved; Social facilities in all PA settlements; and, Classification of soil cover. Detailed
matrix available in WB Docs.
30
2.5 Table 3 summarizes the results of routine species monitoring activities during the BCP.
Table 3: BCP-financed Routine Species Monitoring by IBAP PA Indicator Objective Frequency Annual
Estimate
Comment
Marine Turtle: 5 most abundant species of Chelonia mydas
PNMJVP Abundance of
marine turtle
(Chelonia
Mydas).
Number of
sightings
To obtain
data on
long-term
tendency of
turtles to
come to the
4 islands of
PNMJVP to
lay eggs/nest
Campaign
of daily
monitoring
over 5
months
Abundance
.
Index of
night
observation
s: 2000
(7400),
2007
(29,000),
2011-2014
(30,000)
Poilao Island is the 3rd
most
important site for this species
in the Atlantic Region; most
important in Africa; and
among the 12 largest nesting
sites globally.
PNO Abundance of
marine turtle
To obtain
data on
long-term
tendency of
turtles to
come to
PNO to lay
eggs/nest
8 beaches
monitored
once/week
Abundance
. Index of
night
observation
s:
2012/2013:
630
2013/2014:
1279
2014/2015:
1580
Populations of 4 species of
marine turtle lay their eggs in
PNO. This is also the only
known area in Guinea-Bissau
of regular egg-laying/nesting
of Lepidochelys olivacea.
Hippopotamus (Hippopotamus amphibius)
PNO Total number
of
hippopotamus
(adults and
young)
To estimate
the number
of
hippopotam
us that live
in Orango
National
Park
7 beaches,
every 2
years
Minimum
size of
population:
2009 - 109;
2014-114
(average
observation
s per
month)
Monitoring of the
hippopotamus population
seeks to detect (i) changes in
the total number of
individuals; (ii) changes in
the proportion of
males/females; and (iii)
percentage of young
individuals. Monitoring of
this species in Orango Park
is a pre-requisite for
understanding population
dynamics necessary for their
long-term preservation.
Timneh African Grey Parrot (Psittacus erithacus)
PNMJVP Total number
of individuals
and number
of young
To obtain an
index of the
evolution of
parrot
numbers in
the islands
of João
Vieira e
Poilão Park
2 islands
(Meio and
Joao
Vieira),
November-
May on
annual
basis
Population
(Meio-Joao
Vieira):
300
The Timneh Grey Parrot is
one of the few species of
birds nesting in Guinea-
Bissau actually on the IUCN
Red List, where it is
classified under the statute of
Globally Vulnerable.
31
PA Indicator Objective Frequency Annual
Estimate
Comment
Aquatic Birds (Limicola, Group of Species)
PNMJVP
PNO
AMPC
PNLC
PNTC
PNC
Total number
of individual
birds of a
certain
species of
Limicolas and
Aquatic Birds
in PNMJVP
To obtain
indices of
the
evolution of
aquatic bird
numbers and
specific
diversity
Once
annually
(January)
Various
species
counted:
2012:
35,730
individuals
(27
families, 8
species);
2013:
24,527
individuals
(27
families, 8
species);
2014:
19,327
individuals
(30
families, 8
species).
The methodology used today
is polygon-based, where
different areas are estimated
but not counted/included.
These data from just the
PNMJVP islands are under
review according to zone.
The data have been sent to
Birdlife International/
Wetlands for review,
approval of the estimate, and
integration in a global
database. The numbers for
2014 represent only
polygons in PNMJVP/PNO,
and do not include
Cantanhez/Cufada/Cacheu
PAs. Monitoring is
continuing based on the
strategy prepared and agreed.
IBAP has determined that
the birds utilize other
habitats outside the PAs, but
according to expert opinion,
this is a normal dynamic.
Source: IBAP, 2016
2.6 Small-scale community investments: An increasingly stronger IBAP, with BCP
support, leveraged financing from diverse partners/donors for micro-projects in food security,
biodiversity conservation and environment, education and other types (see Table 6), to improve
quality of life in the PAs and peripheral areas. While the BCP did not include direct financing for
small-scale socio-economic and conservation-friendly investments in the parks – and the ICR is
not claiming direct attribution – it did finance an extensive, SNAP-related community outreach
campaign, and training supporting those specific investments, as an essential component of good
SNAP management. It was tacitly-assumed by IBAP and the Bank BCP team that IBAP would
continue these types of investments (mainstreamed under the CBMP) during BCP
implementation by leveraging the needed financing. Such activities were/are considered an
essential component of the parks as “development poles”, enabling people to continue to live and
sustain a livelihood - the socio-economic objectives of the SNAP strategy - in a manner that
protects and conserves park biodiversity. Investment resources were leveraged from the following
projects/donors: (i) Sustainable Management of Forest Resources Project in the Cacheu Park
(EU); Shared Wealth Project (MAVA/IUCN); Rias do Sul Project (UEMOA/IUCN) and national
NGOs (Tiniguena, Palmeirinha). These investments are examples of a larger portfolio of micro-
investments which benefited over 22,000 people living inside and on the periphery of the PAs.
See Table 7 for examples of these investments.
32
Component 2: Pilot the Operation of the BioGuinea Foundation (US$0.39 m)
2.7 While the FBG had already been legally established in the United Kingdom under the
Bank-supported Coastal and Biodiversity Management Project, it had no operational framework,
premises, established policies or staff, all of which were put in place under the BCP. The FBG
became operational in accordance with the minimum requirements for receiving GEF funds into
the conservation endowment. These requirements are defined in the request for a waiver of the
application of disbursement and trust fund policies to GEF-supported conservation funds
approved by the Bank’s Managing Director in March 2002. These conditions are: (i) the Bank
should have a right to request audits of the conservation fund throughout the duration of the
Bank’s supervision of the GEF-financed project, in accordance with standard Bank practice; (ii)
the conservation fund should be subject to the Bank’s procurement and financial management
guidelines throughout the duration of the Bank’s supervision of the GEF-financed project; (iii)
the selection of the Executive Director and/or the composition of the Board of Directors of the
fund (or comparable organ(s)/officer(s) for the administration of the fund) throughout the
duration should be satisfactory to the Bank; (iv) the Bank should be consulted before any changes
regarding the selection of the Executive Director and/or the composition of the Board of Directors
of the fund (or comparable organ(s)/officer(s) for the administration of the fund) throughout the
duration of the Bank’s supervision of the GEF-financed project, and, in any event, for a period of
not less than three years after the latest capitalization of the fund with GEF proceeds, with the
understanding that the Bank should have a right to exercise remedies (or not declare the relevant
GEF Grant Agreement effective) if such changes negatively impact project execution in the
reasonable opinion of the Bank; and (v) the Board of Directors and/or Executive Director of the
fund (or comparable organ(s)/officer(s) for the administration of the fund) should exercise control
over the use of the fund.34
2.8 FBG Structure and Responsibilities: The FBG was piloted in the expectation that it
would, in the medium-term, generate sufficient revenues to sustainably finance the recurrent
management costs of at least two marine national parks in the Bijagos Archipelago, or their
equivalent.35
The following organigram shows the internal structure/organization of the FBG as
at the time of ICR preparation; this may change depending on circumstances and future needs.
The status of each unit of the FBG is then explained in the table following the organigram below.
34 The terms Board of Director and Executive Director in the GEF requirements are synonymous with
Board of Trustees and Executive Secretary. 35
It should be noted that the concept of the FBG is one of flexibility. The idea is that the funding should
go where it is needed, not be locked into a pre-existing commitment. If the two PAs in the Bijagos
Archipelago have sufficient funding, then the FBG funds could theoretically be directed to another PA
which has a financing gap.
33
Organigram: BioGuinea Foundation
Table 4: Structure and Functions of the BioGuinea Foundation (October, 2016)
Key Units and
Functions
Status Responsibilities
General Assembly of
Members (GA)
In place:
1 founding member is in
place and the decision was
made to expand to a
minimum 2 members.
This is the FBG’s highest office. This
body is a UK governance requirement. Its
members have limited but potent powers
including the ability to dismiss Trustees or
to close down the FBG. It is designed to
provide a counterbalance and check on the
institution. It guarantees the integrity of the
FBG.
Board of Trustees In place:
4 Members
This is the FBG’s apex executive
governance body, responsible for
approving all work plans and budgets. It
ensures that the FBG is administered
according to its statutes, and defines the
FBG’s strategies and policies and their
execution/compliance. It also protects the
FBG against risks which could constrain
execution of its mission and the FBG’s
evolution. It also recruits and supervises
34
Key Units and
Functions
Status Responsibilities
key personnel in the Executive Secretariat.
Executive
Secretariat/Secretary
In place:
The ES drives the FBG functionally and
assures its strategic and day-to-day
operational management; institutional
relations; Board materials; funding levies
(with the Board); human resource
management; marketing and
communications.
Investment
Committee (IC)
In place:
Terms of reference (TOR)
were adopted in July 2016
and IC is in place. This
body supervised the
recruitment of the
Investment Managers.
Its role is to prepare and supervise the
FBG’s investment policy and put into
action the financial resources of the FBG
with Board guidance. This function
includes supervision, and evaluation of the
management of the FBG’s financial
placements by professionals in this field.
Grant Committee To be put in place:
Donors’ Circle In place with TORs adopted:
Actual members: World
Bank (to hold 1st
Presidency); European
Union (Bissau); UNDP
(Bissau); Secretary of State
for Fisheries and Maritime
Resources for Guinea-
Bissau; French World
Environment Fund (FFEM);
Swiss MAVA Foundation.
This unit groups together all donors to the
FBG, permitting them to be updated on the
FBG’s situation, to have exchanges
regarding the vision and strategies with
FBG’s other units and to provide
appropriate counsel in regard to their
experiences and the evolution at their level
and on the international plan.
Consultative
Committee
Informal structure in place: This body is a multi-stakeholder forum
which meets at least once/year – but can be
called on more often if needed - convening
stakeholders from different sectors of
interest to FBG: private sector,
international development agencies and
international and local NGOs. Role is to
keep stakeholders informed and solicit
advice/guidance on specific issues.
Grant Officer (GO) To be recruited.
Part of the Executive
Secretariat. Will be recruited
within the financing of the
GEF V/UNDP and the
French Global Environment
This unit proposes the FBG’s financing
programs and ensures that they are
activated in accordance with the FBG’s
strategic direction/vision.
35
Key Units and
Functions
Status Responsibilities
Fund (FFEM) which is
financing the start of
grant/subsidy activities.
Administrative and
Financial Officers
(AO, FO)
In place
Part of the Executive
Secretariat. Administrative
and Fiduciary Officers/staff
were appointed.
These ensure the management of financial
operations, accounting, administration and
takes into account the development of
internal procedures.
Other functions To be determined based on
needs and resources raised
by the FBG.
Other executive functions might be created
later on (short- and long-term) based on
needs and the FBG’s evolution: e.g.,
monitoring and evaluation; marketing and
communications. Further, consultants
might be contracted as a function of
emerging needs in specific areas. Source: FBG/IBAP, 2016
2.9 Formal FBG Board approval was received for the FBG’s Investment Policy Statement
and recruitment/appointment of an Investment Manager for the FBG’s endowment fund. The
Investment Committee was established to oversee this recruitment process (tender preparation,
short list review and interviews).36
The Foundation Board of Trustees has four members (three
international, one national) none of which represents the Government or is a government official.
The Bank heads a Donor’s Circle which interfaces directly with the Board. Signatories of the
FBG Bank account are Board members and all proceedings are recorded. FBG received its
statute as a UK-registered charity in February 2012 (No. 1146130) and establishing the UK bank
account will occur when the investment advisor agreement is signed. At that point, the account
will receive the funds, invest them and revenues will start to flow.37
There has been experience-
sharing with African Conservation Trust Funds registered in the UK. Meanwhile, the
Government’s contribution is held in the Eco-Bank in Bissau.
2.10 The FBG is entrusted with holding the endowment and will transfer/release funds to
IBAP based on an annual budget proposal. According to the Articles, IBAP is one of many
potential recipients but the SNAP/PAs are identified as the priority for funding. The grant
process has not yet been tested because FBG has not had sufficient funds and currently, is
awaiting the opening of a current account in the UK. Testing may begin soon under follow-on
projects, e.g. the FFEM, which has a specific budget line for this and the GEF V/UNDP if its
disbursement procedures can be revised to permit such transfers through a foundation. IBAP will
be free to continue to leverage other donor and government support. FBG is just one potential
source of financing – it is designed as an instrument to ensure stable, secure flows of financing. It
36 See Bio Guinea Foundation Investment Policy Statement, August 27, 2016; Minutes for approval and
adoption of the Investment Policy Statement; and, Bio Guinea Foundation Investment Manager Selection
and Appointment, August 27, 2016. 37
The accounts needed to service FBG needs are: (i) a Guinea-Bissau-based account for daily
expenditures (established); (ii) a UK charity bank account which could hold cash, make transfers to the
Guinea-Bissau account, receive revenues from the investment account for onward distribution (not yet
established); (iii) the investment account (almost established).
36
does not replace donor projects but complements them to ensure that core activities are financed
so as to reduce the SNAP’s vulnerability to financing gaps.
Component 3: Project Management and Monitoring and Evaluation
2.11 This component was to ensure the effective and efficient implementation of project
activities linked to strengthening the planning and management of IBAP’s protected areas
program, in coordination with other related donor initiatives. Component 3 was of pivotal
importance to the programmatic approach, the place where the Bank could foment “big picture”
thinking, and it financed many intangible activities supporting this. IBAP has to be opportunistic
in terms of where it secures financing but also needs a big vision with clear priorities. The
component financed for example, the annual donor/partner meetings where all could see in a
transparent manner where they fit in this overall vision. It was also a window for the Bank –
working with IBAP – to keep the overall enterprise moving, not just the individual project as
“destination”. It financed essential communications and sensitization activities to promote
commitment to the vision, as well as training and services to support IBAP’s operations and the
consolidation of the FBG. Component 3 enabled the BCP to organize and leverage the financing
needed for many aspects of the core strategy. Part of the programmatic approach is to help IBAP
finance its new, 5-year strategy, avoiding duplication and overlap, and promoting synergies
between donors. The following table shows IBAP’s primary partners and the projects either
under execution during BCP implementation (and since), nearing approval or at the concept
review stage.
Table 5: IBAP’s Main Partners/Donors and Projects
Donor/Financier Projects under Implementation Cost (EUR)
MAVA Foundation Project to finalize the status of the Bijagos
Archipelago as a World Heritage Site (2014-
2015)
10,000
MAVA Foundation Conservation and Research in the PNMJVP
(2013-2016)
497,713
EU/UNDP
WWF/WAMER
Policy and Governance, Wamer Eco-Region (to
2017)
900,000
US Fish and Wildlife
Service
USFWS Marine Turtle Project (2016) 14,000
GEF/UNDP Strengthening the Financial and Operational
Framework of the National PA System in
Guinea-Bissau (2015-2018)
915,700
EU Protected Areas and Climate Change Project
(2016-2020)
4,000,000
FFEM FFEM Support to the Functioning of the PNO
and Urok PAs (2016)
200,000
Total: 6,537,413
Projects pending Approval
Government of
Guinea-Bissau
Budget allocation of the Government of Guinea-
Bissau
100,000
MAVA Foundation Project to Re-launch RBBB in the World
Heritage Site
400,000
Total: 500,000
Projects at Concept Review Stage
IBAP/World Bank Community-Based Avoided Deforestation
Project in Guinea-Bissau
N/A
37
Donor/Financier Projects under Implementation Cost (EUR)
EU Project to Calculate the Macroeconomic Value of
Biodiversity in Guinea-Bissau
245,177
Total: 245,177 (to date)
37
2.13 The following matrix shows project achievements/outputs by Component
Table 6: Outputs by Component at End-Project (May 31, 2016)
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
Component 1: Consolidation and Strengthening of capacity for management of coastal and marine protected areas and biodiversity This component, in coordination with donor partners, sought to strengthen the participatory management and conservation of the existing
network of Guinea-Bissau’s five national parks and biodiversity during this phase of its transition to more sustainable financing sources.
1. Participatory
surveillance and
monitoring of
compliance with
park regulations by
IBAP staff and
community guards
Supervision
Target of 12
supervision
missions per year
in 5 PAs
(60/year) for 4
years (extended
to 5).
Total by EOP:
300
METT Target:
PNMJVP - 111
Orango – 118
Cacheu – 109
Cufada – 74
Cantanhez – 56
Total: 468
Supervision
2012 - 109
2013 -134
2014 - 164
2015 - 302
Total by EOP:
709
METT Actual:
PNMJVP – 116
Orango – 119
Cacheu – 129
Cufada – 83
Cantanhez – 62
Total: 509
Executed:
-- The Project exceeded its surveillance target (236%) and its METT target
(109%)
-- The BCP carried out its planned management and surveillance activities, the
results of which are evident in IBAP/SNAP METT scores.
-- Park management activities included: regular supervision; surveillance
activities in forests and coastal waters; all planned meetings of the Park
Management Councils; discussion and approval of internal regulations; training
and instruction of IBAP personnel and partner entities; adoption of the species
Action Plans and monitoring of targeted species; implementation of
communication and awareness-building instruments/tools.
2. Development or
updates of park
regulations and
park-specific
Business Plans
1 set of internal
regulations per
park
1 Business Plan
per park
1 set of internal
regulations per
park
1 Business Plan
per park
Executed:
-- 5 parks have an updated set of Internal Regulations subject to continuous
revision/updating by meetings of the Park Management Councils.
-- 5 parks have a Business Plan valid to 2020, to be updated annually by the
Park Directors/IBAP when necessary.
38
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
-- In addition, IBAP, with the participation of fishing communities in Orango,
Cufada and Cacheu parks, formulated new, simple/clear rules for responsible
fishing.
3. Meetings of Park
Management
Councils
Two meetings
per park/year
were projected at
appraisal: 1
general meeting
and 1 internal (10
meetings per year
or 40 meetings
over the course of
the planned 4-
year Project)
2012 - 8
2013 - 9
2014 - 12
2015 - 15
Total: 44
Executed:
-- Park Management Councils met 44 times compared to the 40 planned (110%
but 88% based on a 5-year project with 50 meetings).
-- Note that in 2012 and 2013 the number of meetings fell below target due to
the delayed contracting of the Cantanhez Park Director (see Main Text). Once
the director was contracted, regular meetings started. Also, the Project closing
date was extended one year (notionally increasing the target to 50 meetings).
4. Dissemination of
information within
and about the parks
(incl. improved
signage and
communications
materials)
Yes Yes Executed:
IBAP contracted a Director of Communications, resulting in the following:
-- New IBAP website (www.ibapgbissau.org), more accessible, user-friendly,
adaptable for new technologies and for creation of sub-sites.
-- Launch/distribution of communications materials (brochures and folders on
IBAP and FBG; notes and calendars in partnership with Bank of West Africa
(BAO) in 2013 and with the Orange Telecommunications Company in 2016).
-- National radio and TV bulletins about IBAP activities and reporting on
national environmental law, law on PAs, as well as the laws and regulations
affecting forests, hunting and fishing.
-- Organized debates in the PNO, PNTC parks concerning biodiversity
conservation.
-- Environmental education for children and adults; and, training for community
radio operators in PNO and PNTC.
-- Conferences and participation in international forums.
-- Regular publication of IBAP’s “Bemba de Vida” bulletin designed to
39
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
demonstrate to national and international partners and donors the activities
conducted by IBAP in conservation and sustainable management of biological
diversity and natural resources.
-- Article in National Geographic/Portugal on the Bolama Bijagós Archipelago
Biosphere Reserve (author Pedro Narra). See:
http://www.nationalgeographic.pt/ind.../ng-revista/507-bijagos.
-- Signage installed in PNLC to mark the limits of the durable development
zone and zona tampão, and logos designed for new Boé and Dulombi National
Parks.
5. Awareness-
raising and
dialogue with
communities and
other resource
users living in and
around the parks
vis-à-vis park
management
activities and
biodiversity-
friendly alternative
technologies and
alternative
livelihoods
Yes Yes Executed:
-- Awareness-raising and dialogue with park resident communities occurred
regularly in all 5 parks through consultative forums involving all stakeholders
associated directly or indirectly with park services, including resident
communities.
-- Creation of these spaces for consultation served to reinforce and consolidate
the overall management structure, improving its coordination, consistency, and
operations.
-- Among the many subjects addressed, notable aspects include those
guaranteeing the parks’ functionality through the use and sustainable
exploitation of park resources and the form of improvements in living
conditions of the park population resident within and around the parks.
6.
Implementation
of endangered
and threatened
species Action
Plans
3 species
Action Plans
4 species
Action Plans
Executed:
Project outputs exceeded expectations. The BCP financed:
-- Action Plans for marine turtles; mangroves; hippopotamus.
-- National Integrated Action Plans for 4 bird species of national and sub-
regional importance: Balearica pavonina; Limosa limosa; Phoenicopterus
40
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
minor; and, Platalea alba.
-- Chimpanzee, marine turtle and mangrove Action Plans were finalized and
under implementation since 2013; -
-- Hippopotamus Action Plan was finalized/validated in 2014 and is now under
execution.
-- Monitoring strategy was designed for aquatic/migratory birds as well as a
National Integrated Action Plan for the 4 species named above.
-- Databases now exist for marine turtles and hippopotamus in Excel format,
with appropriate variables for statistical analysis and conversion to electronic
format (planned).
-- Monitoring is continuous and species research is underway but requires a
longer-term approach which is unlikely to show measurable species
conservation trends over the course of a single project.
7. Design and
operation of
consolidated
endangered and
threatened species
databases
Yes Yes Executed:
-- IBAP now has a consolidated database on all emblematic species (through its
SNAP-wide Monitoring System).
-- The integrated, cross-border, harmonized system contemplated is still being
negotiated/established. IBAP has had exchanges of knowledge with sub-
regional institutions to harmonize this database with regional and international
systems. The planned integration elements have a high likelihood of being
established.
-- The strategy changed. Due to the need for a deeper, more global approach
than the more limited plan for species monitoring envisaged at appraisal, and
insufficient BCP funds for such larger effort, an additional, more encompassing,
two-stage plan thinking beyond the project boundaries was negotiated with
IBAP/donors. The BCP/IDA would be the catalyst financing the first stage and
donors would finance the second stage under collaborative arrangements.
IBAP’s institutional growth and maturation were key drivers of this process.
41
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
-- Under Stage I, the BCP/IDA financed design of TORs and development of
the overall approach working with specialist TA (forestry, species and social).
Participatory diagnoses helped identify key indicators for each PA, and
measurement protocols which could be harmonized with other regional
databases. Baselines were established as the foundation for adaptive
management. Stage I was completed by EOP.
-- Stage II – co-financed by MAVA and the EU – was launched and is ongoing.
It consists of training for data collection, GIS design and implementation, and
purchase of equipment.
8. Targeted
training, capacity-
building for IBAP
staff and other
stakeholders (e.g.,
training in
participatory
species and
protected area
monitoring
techniques, eco-
tourism guiding
and learning
exchanges between
parks for IBAP
staff, Park
Management
Councils and
community
members
PAD target (see
RF) was 25 staff.
(IBAP’s target
was 100 training
events planned/
projected through
EOP for IBAP
staff, institutional
partners and
community co-
managers).
Some 786
technical staff
and project
partners were
trained during
the Project
period.
2012 -108
2013 - 161
2014 - 221
2015 - 296
Total: 786
Executed/exceeded:
-- The PAD cumulative target was 25, all of which were to be achieved in the
first year, but this was likely an error. IBAP’s final report defines an annual
target for people trained of 50/year over 4 years (200).
-- The BCP financed training events in a wide range of skills for 786 people -
exceeding expectations (393%) – including IBAP staff, Park Management
Councils and park communities. Topics included: participatory species and PA
monitoring techniques; PA supervision and enforcement; PA law; forest
protection and practices; strategic planning; eco-tourism. See Main Text,
footnote 19.
42
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
Technical
assistance for the
development of
annual business
planning tools for
IBAP, and training
in their use
Yes Yes Executed:
-- All updating of the park Business Plans was done by the Park Directors with
collaboration of IBAP Headquarters staff and contracted technical assistance,
and training was provided in the use of the planning tools.
Collaboration and
participation in
regional and
international fori
for biodiversity and
protected area
management issues
Yes Yes Executed:
-- The SNAP/IBAP institutional structure/partners participated regularly
throughout the Project period in regional/international biodiversity and PA
management events, e.g., World Parks Conference in Sydney/Marseille;
IMPAC III Conference (International Congress for Marine Protected Areas,
Marseille, 2013); REDLAC; CAFÉ (Consortium of African Environmental
Funds); Regional Marine Conservation Program meetings; RAMPAO meeting.
Component 2: Pilot the Operation of the BioGuinea Foundation This component sought to support the pilot operation of the FBG, as a mechanism that could, in the medium-term, sustainably finance the
recurrent management costs of at least two marine national parks in the Bijagos Archipelago.
Operational support
to the FBG Board
of Trustees and the
FBG General
Assembly,
including annual
and biannual
meetings, travel,
and communication
Yes Yes Executed:
-- The FBG Executive Secretary, Board of Trustees, General Assembly,
Donors’ Circle and the informal Donors’ Committee received operational
support from IBAP and the Bank Team.
-- All scheduled meetings were conducted, and travel and communications were
facilitated by the BCP.
-- See above table showing structure and functions of the FBG
Support to
Executive
Secretariat to
conduct ongoing
local, national and
Yes Yes Executed:
-- The BCP supported the FBG Executive Secretariat in conducting local,
national and international consultations designed to strengthen the FBG strategy
and priorities, and ensure that the FBG will achieve its objectives.
-- The final draft of the SNAP and FBG financing strategy was prepared by
43
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
international
stakeholders
consultations to
ensure that the
FBG strategy and
priorities were
well-targeted and
achieving desired
objectives
consultants from the Brazilian Biodiversity Fund (FUNBIO), which was also
involved in a pilot mentoring arrangement for the FBG.
-- Specialists in establishing and managing biodiversity foundations supported
the Executive Secretariat as needed for consultation and strategy-formulation.
Design and
preparation of
FBG-specific
communication
materials to raise
awareness of
FBG’s mission and
give visibility to its
activities
Yes Yes Executed: IBAP contracted a Communications Officer to conduct systematic campaigns
in/outside the PAs:
-- Designed an FBG Webpage;
-- Prepared briefing notes, e.g., on the Blue Carbon pilot work; presentations to
international specialist forums including IMPAC III; materials for Bank
presentations on the FBG to leverage donor support.
-- Materials were prepared for presentation at the annual meetings of FBG
partners (Consultative Group meeting with donors, partners, other government
departments, NGOs).
-- The IBAP/FBG teams prepare updates on FBG and its work program as part
of the stakeholder communications strategy.
Travel and
operational costs
for an experienced
conservation
foundation
specialist to
provide ongoing
training and
mentoring support
Yes Yes Executed: -- FUNBIO specialists from Brazil were funded to develop the FBG financing
strategy;
-- Experienced conservation foundation specialists have accompanied FBG
evolution since the beginning and are now supporting the FBG Executive
Secretariat.
-- FBG staff have also travelled to meet and learn from other conservation trust
funds especially the financial side/FM of other similar funds, e.g., Cote d’Ivoire
and Cameroon.
44
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
to the FBG -- CAFÉ and REDLAC trips, designed for learning and knowledge exchange
between other Conservation Trust Funds (CTF)
Technical and legal
assistance as
required in support
of FBG’s day to
day operation
Yes Yes Executed:
-- FBG has on retainer the UK’s top charity legal firm (Bates, Wells and
Braithwaite - BWB). The firm provides legal advice regarding UK law/policies,
issues related to conflict of interest, inputs into grant and policy-making and the
FBG Operational Manual, e.g., compliance issues.
-- For strictly local issues, local legal expertise is contracted as needed.
Technical
assistance and
operating costs for
the development of
key FBG
operational policies
as needed
Yes Yes Executed: -- BWB handled (and still handles) specific aspects of the FBG policy work,
e.g., conflict of interest policy.
-- Senegalese consultant developed the Operational Manual.
-- UK specialist developed the Investment Policy Statement.
-- TA was contracted to prepare recruitment/tender documents.
-- FUNBIO developed the FBG financial strategy.
-- All of the above conducted in consultation with the FBG Secretariat, and
other key partners/IBAP in the case of the financial strategy.
Recruitment of a
UK-registered
agent (responsible
for preparing and
filing required
documentation with
the UK Charity
Commission and
Tax Authorities on
an ongoing basis)
Yes Yes Executed:
-- BWB was recruited for this function as Company Secretary (a UK
legal/administrative function)
Technical Yes Yes Executed:
45
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
assistance and
operating costs for
the development
and implementation
of a monitoring and
evaluation program
for the FBG
-- An M&E program was developed/operational for the then-current level of
activities but the grant-making stage needed a more complex system.
-- While no FBG grants had been made by closing, FM and audit M&E systems
for the FBG are in place.
-- Design of another layer of M&E was underway at closing for the active grant
stage.
Technical
assistance and
operating costs to
support ongoing
FBG fund-raising
efforts
Yes Yes Executed: -- The FBG endowment fund-raising effort, with BCP TA and operational
support, has been successful so far with firm pledges totaling EUR 4.3 m and an
average US$3.20 million/year expected from carbon credit sales (averaged over
the 20 year project period). Annex 3.
-- Fund-raising is done through the Executive Secretariat, and annual partner
meetings which define opportunities moving forward, project proposals (FFEM,
MAVA etc). TA supports all such efforts.
-- FUNBIO (Brazilian Biodiversity Fund) consultants conducted a financial
analysis of IBAP/SNAP to identify the main elements of a financing strategy to
mobilize long-term funding. The strategy was concluded and presented to the
FBG Consultative Committee, Board of Trustees, other partners.
-- BCP also financed TA for the pilot carbon financing effort.
Participation in
international
conservation trust
fund meetings,
including Africa
Conservation Trust
Fund Working
Group, REDLAC
etc.
Yes Yes Executed: (See also Component 1 above: similar activity)
-- The SNAP/IBAP institutional structure/partners participated regularly
throughout the Project period in regional/international biodiversity and PA
management events, e.g., World Parks Conference in Sydney/Marseille;
IMPAC III Conference (International Congress for Marine Protected Areas,
Marseille, 2013); REDLAC; CAFÉ (Consortium of African Environmental
Funds); Regional Marine Conservation Program meetings; RAMPAO meeting.
46
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
Component 3: Project management, and monitoring and evaluation This component sought to ensure effective and efficient implementation of project activities, in coordination with the other related donor
activities.
Recruitment of a
full-time IBAP
Procurement
Officer
Yes Yes Executed:
Procurement Officer recruited for IBAP and operating according to the
Operational Manual.
Technical
assistance to
monitor the
implementation of
environmental and
social safeguards in
collaboration with
CAIA
Yes Yes Executed:
-- Safeguards were triggered to be conservative/cautious. The preparation of
internal regulations for the PAs was the only activity, in reality, which could
potentially have had an impact.
-- IBAP prepared a report, in collaboration with CAIA, to analyze the situation
on the ground in the PAs
Operating costs of
donor and partner
coordination
meetings
Yes Yes Executed:
-- The Project financed annual coordination meetings between IBAP and its
strategic donor partners to analyze progress including on the FBG and its
endowment, and agree on future strategy.
-- Donors also provided valuable feedback to IBAP on the format and content
of these meetings to increase their utility to all stakeholders.
Recruitment of an
Operations and
Monitoring Officer
Yes Yes Executed:
-- An Operations and Monitoring Officer was recruited for IBAP to head
IBAP’s Department of Monitoring and Evaluation, a permanent, functioning
unit involved in planning and monitoring IBAP’s activities and
operations/projects, production of quarterly and annual reports/other.
Technical
assistance and
operating costs to
develop and
implement an
Yes Yes Executed/ongoing:
-- BCP financed the regular monitoring of emblematic species and habitats
considered threatened whether locally or globally: Action Plans for marine
turtles and mangroves were updated and are under implementation, and for
hippopotamus were finalized and validated in 2014; strategy for migratory birds
47
Activity by
Component (PAD)
Target Achieved by
End of Project
Description/Observations
M&E program for
the protected areas
network (SNAP)
was developed in 2013 and an integrated Action Plan covering 4 species was
also prepared. Databases now exist for all key species in Excel, suitable for
research work.
-- In 2015, IBAP/BCP initiated the conceptualization and development of a
separate SNAP Monitoring System, an integrated system with key indicators for
monitoring ecological, social and sustainable development of the SNAP.
-- The initial proxy is the METT – measuring management effectiveness – but
IBAP needs to go beyond the METT to measure what is happening on the
ground, and had by end-Project and with BCP financing/TA, identified a set of
indicators and objectives for each PA within the SNAP.
-- A 1st stage/system tracks the health of a particular species population and
steps needed to avert/avoid its extinction, looking at anthropogenic or natural
causes of death or simple illness. The system would track the population to
assess whether it is growing, shrinking, and/or changing behavior as the basis
for adaptive management. BCP financed the design and capacity-building
aspects (training people to execute system requirements), participatory selection
of core indicators, protocol formation and definition. All work planned under
the 1st stage was completed by closing.
-- Harmonization efforts have started, with IBAP participating in knowledge
exchanges with regional institutions. Consolidation and further development of
this system is ongoing.
-- An inter-linked 2nd
stage/system – financed by other donors and well
underway before closing - will measure whether the PAs are achieving their
objectives - ecological, social (related to local communities in the parks).
Measurement of the achievement of PA objectives becomes more complex and
involves longer-term monitoring to detect declines or improvements over time.
48
2.14 Table 7 shows examples of small-scale investments in the PAs, using financing leveraged
by IBAP during the life of the BCP. As noted earlier, it was understood that IBAP would
continue to develop its role as lead agency for the SNAP by sustaining the activities initiated
under the CBMP to engage local populations in the PAs in a long-term commitment to the parks’
ecological and socio-economic health. The BCP financed extensive outreach campaigns and
training within and around the PAs, and IBAP leveraged the financing for direct micro-
investments on-the-ground which benefited from IBAP’s training.
Table 7: Local Development Initiatives implemented within SNAP, 2012 to 2015
Initiatives Developed by IBAP with Leveraged Funds Park Financier/Donor
2012
In 2012 (January to September), the PNMJVP brought
together 9 groups from Canhabaque Island, comprising 73
young people, 47 women and 81 children. The manufacture
of fiber mats, harvesting of tubers and forest fruits and
extraction of palm oil were reinstated as the main activities
of these temporary migrants. They produced around 2,250
liters of palm oil, 82 fiber mats, 7 50 kg sacks of inhame
and 6 sacks of cabaceira for sale.
PNMJVP IBAP, NOÉ-
Conservation
To minimize the damage caused by hippopotamus in rice
fields, a program financed the fencing off of fields in the
mangrovebolanhas of Cubampor and Suzana (PNTC),
Bissorã in the Oio region and the agriculture center of
Carantaba in the east of the country, zones where
hippopotamus are common. In Cubompor about 10.6 ha
were fenced and in Suzana about 49 ha. This initiative
financed/supported by CBD-Habitat sought to replicate
successful experiences in the Orango park as well as to
contribute to reducing conflicts between man and animals,
and reduce rural poverty.
PNO
PNTC
Bissorã
(outside
the PA)
CBD-Habitat, IBAP
With the support of NOÉ-conservation, basic informatics
training was administered for Park Rangers in Orango park.
This training allowed a better understanding of informatics
and its functions and introduced Rangers to Microsoft
software. Discussion of texts in Word and of Excel tables
was accompanied by practical exercises. The 11 Rangers
trained are now expected to prepare their reports and create
databases on their surveillance/enforcement missions in
Orango park.
PNO NOÉ-Conservation
An agreement was signed between IBAP and WFP to
promote learning activities in the regions of Bafatá and
Gabu, namely: Promotion of Ecologically appropriate
Stoves, Improved Food/Diet, and Fruit Development.
PNB PND World Food Program
(WFP) and IBAP
A partnership between IBAP, ECOBANK, DGFF and DGA
resulted in the preparation and financing of a micro-project
to protect (54 ha) and re-constitute (2 ha) degraded forest
ecosystems in the Bissorá sector.
Bissorã ECOBANK, IBAP,
Director General for
Forests and Wildlife
and Director General
for Agriculture.
49
Initiatives Developed by IBAP with Leveraged Funds Park Financier/Donor
2013
Construction of a community radio station in Cacheu Park PNTC MAVA, IUCN
Rehabilitation of a Health Post in Orango Park PNO N/A
Electrical fencing to resolve human-hippopotamus conflict. PNO
PNTC
CBD-Habitat, IBAP
Construction of a plant nursery in Cacheu Park. PNTC EU, Monte Ace,
IBAP
2014
Rehabilitation of 215 ha of bolanhas (mangrove ricefields)
in Apilho, Djendem
PNTC EU, Monte Ace,
IBAP
Support for extraction of solar salt saw 42 women trained
and provided with required materials and equipment. The
women’s group has already produced 560 kg of salt for sale
and is building a fund for future expenditures.
PNTC AD, IBAP, IUCN
Supporting fishing activities, the Rias do Sul Project
provided materials and equipment at a reasonable price for
responsible fishing in the Cacheu, Cufada and Orango
Parks.
PNO,
PNLC
PNTC
IUCN, UEMOA
(Rias do Sul Project)
Micro-project to aid transportation: acquisition of a canoe
for crossing the Ambuduco River
PNO IBAP
Support to a “Knowledge Exchange for Youth” program in
Orango Park.
PNO IBAP
Under a basic sanitation investment, a well for potable
water was constructed in An-or.
PNO IBAP
Under a micro-project for basic health, in partnership with
CBD-Habitat, a Basic Sanitation Unit in Ambuduco was
rehabilitated and equipped with medications.
PNO CBD-Habitat
2015
Installation of 2 Ice-making Plants to support fish
conservation in Cacheu, Buba.
PNLC
PNTC
UEMOA, UICN
Rehabilitation of a primary school in Djopá, Cacheu Park PNTC IBAP
Rehabilitation of an Advanced Enforcement Post in
Imbone, Orango Park
PNO IBAP
Rehabilitation of wells in three PAs PNO
PNLC
PNTC
IBAP
Provision of materials for sustainable fishing under the Rias
do Sul Project
PNLC
PNC
PNTC
UEMOA, IUCN
Community Hostel in Anhôr was put into operation with
capacity to host 16 people, with 8 double rooms, interior
sanitation, and 24-hour electricity and water supply. Such
investments can potentially support eco-tourism.
PNO MAVA, IUCN
50
Annex 3. Economic and Financial Analysis 3.1 A classic economic and financial analyses (e.g., cost-benefit or cost-effectiveness) was
not conducted at appraisal and remained inappropriate at closing, given the country context –
summarized in the Main Text Section 1 and spelled out in recent Bank strategies - the nature of
the Project and the small size of the IDA credit. Based on the country conditions in particular, any
quantitative measure to value the project benefits (for a cost-benefit analysis) or the project
effectiveness (for a cost-effectiveness analysis) is likely to be under-estimated and unable to show
a true benefit, value or cost due to systemic distortions and/or conditions of under-financing.
3.2 In the case of e Cost-Benefit (CB) analysis, it is highly unlikely that the substantial
benefits derived from the project could be valued. For example, it is difficult to associate an
economic value to the Project as enabler or catalyst for conservation initiatives. Without the
project financing, it is more likely that the areas intended for conservation would have
experienced persistent degradation of high-value, unique biodiversity and natural resources and a
subsequent loss of opportunities for sustainable coastal and forest management. Likewise, it is
also challenging to provide a value regarding the Project’s role in keeping the protected area
system up/running within a context of political instability and severe resource limitations. The
country is and has been for some time characterized by weak governance, grossly inadequate
provision of basic public goods and services and limited economic opportunities. Public
institutions are geared towards providing private goods to elites – political and military – rather
than public goods to citizens (see Guinea-Bissau Country Economic Memorandum (CEM) and
Systematic Country Diagnostic (SCD)). Even more difficult is attributing apparent benefits to the
Bank’s project in some cases, especially where some achievements represent cases where benefits
derive from a number of different factors catalyzed by the Project.
3.3 In the case of a Cost-Effectiveness (CE) analysis, under an extremely constrained
budgetary situation, any analysis might indicate substantial results when compared to comparable
projects from other countries/realities with similar conservation objectives, due to the extreme
budget constraints in the Guinea-Bissau case. The project implementation agency IBAP
submitted annual requests for budget support from 2012 through 2015 totaling EUR 1.371
million, and only in 2015 was the Government able to allocate resources to IBAP (EUR
100,000).38
Yet, despite this situation, and the very small size of the BCP Grant, the Project
substantially achieved its objectives. Taking into account the project background/context, a Cost-
Effectiveness analysis would require a set of heroic assumptions since it would be virtually
impossible to measure all the elements necessary for such analysis. The cost-effectiveness of the
analysis itself, given search and processing costs under such conditions, is also an important
consideration in this case.
3.4 The PAD economic and financial analysis did not include a CE or CB assessment. At
appraisal, it was noted that while a concrete assessment of the current and future economic and
financial benefits attributable to the PA network and the ecosystem services it provides had yet to
be undertaken, the importance of these benefits could be inferred. Some positive, updated
38 IBAP requested an aggregate EUR 1.371 million over four years, as follows: 2012 EUR 275,000; 2013
EUR 228,000; 2014 EUR 299,000; and 2015 569,000. Only in 2015 was government able to allocate some
part of the request - EUR 100,000.
51
information/data is available for several sectors from the World Bank’s Natural Wealth Study for
Guinea-Bissau (Edmundson, 2014) and other sources, but caveats apply regarding data reporting,
availability and reliability:
First, the potential for eco-tourism noted in the PAD – especially in the PAs of the
Bijagos Archipelago - remains high, with solid comparative advantage resting on its
biodiversity and cultural assets. IBAP’s income from touristic activities in the PAs is still
modest – around EUR 10,000 – 11,000/year. Deficient infrastructure and political
instability means reaping the expected benefits remains well in the future but BCP’s
efforts to shore up the PA’s sustainability was a further “down payment” on that future
tourism economy.
Second, in regard to fishing, the PAD estimated total annual fish production as 250,000
tons (based on Economic and Sector Work in 2003) with an estimated gross value of
between US$60-90 million and if managed well, a projected future value of US$119
million. The wealth study does not re-estimate current fish production nor attempt to
assign a gross value. However, with the caveat that fishing data is commonly under-
reported and outdated, the study conservatively estimates total fishing “potential” at
120,000 tons/year, and total wealth per capita from fishing at around US$305. A World
Bank report still under preparation shows that the Government of Guinea-Bissau took in
public revenue of US$20.0 million in 2015 from fishing activities, of which US$9.25
million were license fees from the industrial fishing sector (converted at USD1=578.31 F
CFA) and the remainder were access agreement payments, mainly from the EU.39 IBAP
continues to protect the country’s vital fish breeding and nursery areas lying within the
SNAP.
Third, in regard to carbon, at appraisal it was estimated that carbon storage by some
60,000 ha of protected mangroves in three of the PAs equaled 298,126 tons of avoided
CO2 emissions per year with potential to generate around US$5.0 million over seven
years at an average price (at that time) of US$3.50/ton of CO2. At BCP closing, and
based on the REDD+ Project, this estimate has increased significantly. Carbon credit
sales for just two PAs (Cacheu Mangrove Forest National Park and Cantanhez Forest
National Park) could potentially produce revenues of just over US$3.0 million per year
averaged over 20 years at US$3.30/ton of CO2, the 2015 average market price for carbon
(see Box 1).
3.5 At a broader level, the wealth study suggests that the total natural wealth in Guinea-
Bissau could be up to US$ 3,874 per capita (in 2010 prices) where US$305 per capita comes from
biodiversity/Protected Areas, not including mangrove ecosystem services. Likewise, the 2011
natural wealth valuation for Cacheu Protected Area (a coastal and marine PA) alone is in the
order of US$ 190 per capita. If 70,000 people live in and on the periphery of the PAs, the total
conservative value associated with the PAs alone represents around US$21.35 million, about 8%
of the total valuation of Guinea-Bissau’s natural wealth.40
39 West Africa’s Coastal Bottom-Trawl Fishery: The Case of Trade in Foreign Fishery Services, World
Bank, report pending. 40
Wealth accounting is a larger number than GDP because it includes the valuation of non-tradable goods
or goods which lack market prices (e.g., carbon storage, flood protection). In the case of Guinea-Bissau,
there is a very strong dependence on natural resources (e.g., fishing, cashew nut). GDP per capita is
US$563.70 (current USD), but comparing monetary values over time (Power Purchase Parity or PPP) it is
52
3.6 Table 1 presents a comprehensive accounting of BCP benefits, while Box 1 discusses the
expected benefits of the World Bank ESSD Trust Fund and BCP-financed Reduced Emissions
from Deforestation and Forest Degradation (REDD+) Project.
US$1,367.30. While the natural wealth valuation is US$3,874/per capita (in 2010 prices) - or three times
GDP- for the PAs alone it is US$190/per capita.
53
Table 1: Project Characteristics, Identified Benefits and Achievements
Project
Components Objective Main Activities
Identified
Direct/
Indirect
Benefits
Achievements by BCP
Component 1:
Consolidation
and
strengthened
capacity for
management
of coastal and
marine
protected areas
and
biodiversity
(US$1.27 M).
Enable IBAP to
continue the
participatory
management and
conservation of
Guinea-Bissau’s
protected areas
and biodiversity
during the first
phase of the
transition to
more sustainable
financing
sources. It will
focus on
strengthening the
management of
five coastal and
marine national
parks and
increasing the
monitoring and
conservation of
globally
significant
biodiversity.
Support and
finance, in each
of the five
national parks
as needed,
operating costs,
development of
park
regulations,
dissemination
activities and
awareness-
campaigns,
implementation
of endangered
and threatened
species actions
plans; design
and operation of
consolidated
endangered and
threatened
species
databases,
among others.
Effective
conservation
of globally
important
ecosystem and
threatened
species.
The project has served as key enabler and corner stone for upcoming
conservation initiatives. Bank support via the BCP could be regarded as the
‘keystone’, enabling project support from other donors to be leveraged and around
which other donors designed and harmonized their activities. The larger scale
follow on GEF 5 (UNDP), GCCA+ (EU), and FFEM projects all build upon the
activities and achievements of the BCP, seeking to complement and further
consolidate these. There were also other, smaller scale activities such as those
financed through MAVA and other NGOs which complemented the BCP.
Guinea Bissau’s natural capital is substantial with solid comparative advantages.
Its comparative advantage in tourism rests with its biodiversity and cultural assets.
The World Bank’s Guinea-Bissau Natural Wealth study (Edmundson, 2014)
provides an estimate of the potential wealth per capita of natural resources
(estimated at US$ 3,874) of which biodiversity/protected areas is US$ 305 per
capita, without including mangrove ecosystem services (and based on a 50%
opportunity cost for agriculture). Likewise, the 2011 natural wealth valuation for
Cacheu Protected Area (a coastal and marine PA) alone is in the order of US$ 190
per capita (based on a different methodology with actual values for PA goods).
Based on these estimates, the BCP has effectively managed to maintain Guinea
Bissau’s natural capital (and valuation), despite chronic political instability.
Effective
development
and fostering
economic
activities in
line with
conservation
efforts.
Bank support via the BCP has contributed to preserving and enhancing future
economic opportunities for the country at a national and local level. The SNAP
is regarded as the backbone of a future tourism industry for the country. Nature-
based tourism is identified as the core element of one of the four growth poles
identified in Terra Ranka – the country’s 10-year development strategy. Guinea
Bissau’s tourism potential rests on its rich, globally significant biodiversity and
ecosystems, its varied and attractive landscapes, and on its cultural diversity
(cuisine, festivals, traditional dance and music, and handcrafts). Therefore,
conserving the SNAP and its globally significant biodiversity, preserves this option
for future development by the private sector and communities alike.
Guinea Bissau is endowed with considerable natural capital and it is important
for its economy. The economy of Guinea-Bissau today is based entirely on this
natural capital, which represents 47% of per capita wealth, the highest proportion in
West Africa.
54
Project
Components Objective Main Activities
Identified
Direct/
Indirect
Benefits
Achievements by BCP
It has significant water resources, a rich maritime territory, and exceptional
biodiversity, which provides significant ecosystem services to the whole of West
Africa (e.g., almost 10% of the land mass is covered in mangroves, the highest
proportion in the world; 13% of the land and sea territory is under conservation to
protect biodiversity – a proportion which is in process of increasing to 26% due to
the recent inclusion of new parks and biological corridors).
Strengthened
institutions at
regional,
national, and
local levels
through
targeted
capacity
building for
planning,
management
of national
biodiversity
conservation.
The project has provided important management tools and strengthened national
institutions. Bank support via BCP has strengthened institutions at different levels
(local, regional, national) building capacity and fostering the ongoing dialogue and
partnership with local stakeholders. The project has also supported specific
investments in improving the management of the PAs such as training, the
participatory preparation of the PA’s Internal Regulations and Business Plans, and
the design of a SNAP-wide Monitoring System. Similarly, the Project financed the
bulk of the core operational costs for IBAP (including salaries, fuel, park
management committee meetings, surveillance patrols, communications campaigns
and training). Without this finance, the management of the SNAP would have
declined significantly both in terms of PA protection and community sensitization
and engagement, the latter essential to PA sustainability.
Strengthened
monitoring and
conservation
of specific
endangered
and threatened
species.
Bank support via the BCP contributed to preserving and enhancing conservation
of endangered and threatened species. Guinea-Bissau hosts biodiversity and
ecosystems of global significance, particularly those in the coastal and marine areas
(mangroves, green turtles, sawfish, migratory birds, chimpanzees, carbon stocks
and regional fisheries, among others). Bank support through the BCP ensured the
core functioning of IBAP and progressively increased effectiveness of the
management of coastal and marine PAs, especially those where endangered and
threatened species live.
Strengthened
partnerships at
all levels,
providing
opportunities
to better
collaborate and
communicate
Bank support via the BCP strengthened IBAP’s programmatic management of
the SNAP and catalyzed and facilitated dialogue and the building of partnerships
between the stakeholders. IBAPs communications materials and efforts
(participation in international meetings, brochures, publications, websites and
community meetings, radio shows, among others) helped to share knowledge
internationally, and to raise awareness both nationally and locally.
The BCP further strengthened IBAP’s institutional capacity and reputation to
55
Project
Components Objective Main Activities
Identified
Direct/
Indirect
Benefits
Achievements by BCP
the exchange
of good
practices.
leverage funding from a wide range of donors/partners and to proactively
coordinate where it is spent. IBAP established and maintained strong financial
management performance without indications of fraud and corruption, and it also
has an impressive record of project management in a complex and usually under-
funded sector. With Bank support, IBAP leveraged significant donor financing for
the SNAP, developed the capacity to coordinate multiple donor projects
simultaneously, and took on the responsibility of new parks within the national
system.
Strengthened
conservation
of mangrove
forests
Bank support via the BCP contributed to preserving and enhancing conservation
of mangrove forests. Nearly 10% of Guinea Bissau’ land mass is covered in
mangroves and approximately 70 percent of the population lives in the low-lying
coastal area which is highly vulnerable to storm surges and rising sea levels. In the
context of climate change, for which Guinea Bissau ranks second only to
Bangladesh on the 2014 Climate Change Vulnerability Index (CCVI), mangroves
have great relevance due to their capacity to protect against storms and sea level
rise, making them indispensable for coastal communities in their fight against
climate change. Mangroves may be particularly effective in rural areas where
populations are widely dispersed and the construction of hard infrastructures like
seawalls may not be economically feasible over long coastlines.
Component 2:
Pilot the
operation of
the BioGuinea
Foundation
(US$0.39 M).
Support the pilot
operation of the
BioGuinea
Foundation in
Guinea-Bissau
(FBG) as a
mechanism that
would eventually
be capable of
financing the
core
Support and
finance
operational
support to the
FBG Board of
Directors, its
members, and
the Executive
Secretariat to
conduct
stakeholders
Leverage
resources and
sustainable
financing for
conservation
BCP through its focus on building and operationalizing the FBG and fund
raising efforts, helped to secure seed capital totaling around EUR 4.60 million
for the endowment.41
BioGuinea was designed to manage various funding
mechanisms (sinking, revolving, and endowment) but the key to sustainability lies
with securing an endowment capital with sufficient revenue streams to meet SNAP
recurrent costs. So far, the project has directly secured seed capital commitments to
the endowment fund from GOGB (EU Fisheries Accord and future REDD+
revenues), MAVA Foundation, GEF5, FFEM.
Strengthened
capacity
building at all
BCP support has enabled human resource and institutional capacity building of
the FBG team. The project has improved FBG capacity, and has enabled
participation in international fora for knowledge exchange and learning,
41 GEF contribution is USD 1.22 million, valued in EUR between EUR1.00 and EUR1.20 million, depending on the rate of exchange.
56
Project
Components Objective Main Activities
Identified
Direct/
Indirect
Benefits
Achievements by BCP
management
activities of at
least two of the
country’s
existing national
parks.
consultations;
technical
assistance and
operating costs
to support
ongoing
fundraising
efforts of the
foundation
levels,
providing
opportunities
to leverage
resources for
conservation.
collaboration and mentoring with other CTFs in Africa and Brazil, helping build a
transparent institution operating in line with international best practice and in full
compliance with UK law, which has helped increase the FBG’s visibility and
credibility with knock-on effects vis-à-vis establishment of collaborative
relationships and project and endowment support.
Increase global
awareness for
conservation
finance.
BCP support enabled the operationalization of BioGuinea as an example of
conservation finance. Taking into account political instability in Guinea-Bissau,
conservation finance is a central opportunity to achieve long term goals for the
sustainable financing of the SNAP. BioGuinea was created under English law and
legally recognized in Guinea-Bissau as a private, secular, non-profit organization
established for public benefit. BioGuinea represents a significant illustration/model
of conservation finance at the country level.
57
Box 1: Conservation Financing and the REDD+ Project
The BioGuinea Foundation (FBG) was established in March 2011 as an instrument for the sustainable financing
of biodiversity conservation, with an emphasis on the management of the National System of Protected Areas
(SNAP) and the promotion of sustainable social development. The FBG is designed to manage various funding
mechanisms (sinking, revolving and endowment) with its key strategy for sustainability lying with gradually
securing an endowment capital with sufficient revenue streams to meet SNAP’s recurrent costs.
An innovative financing option relates to REDD+ (Reduced Emissions from Deforestation and Degradation)
through the sale of carbon credits (currently priced at an average US$ 3.30 per ton)42
. With this in mind, IBAP
and the FBG are piloting and initiative to explore the potential role which carbon finance can play in supporting
broader biodiversity conservation. With support from the World Bank ESSD Trust Fund and the BCP, a
Reduced Emissions from Deforestation (REDD) project was developed to help secure financing to protect the
forest and biodiversity in Cacheu and Cantanhez National Parks. This innovative blue carbon REDD project,
entitled the Community Based Avoided Deforestation Project in Guinea-Bissau (CBADP) seeks to demonstrate
how carbon finance can contribute to Guinea-Bissau’s short, medium and longer-term conservation financing
strategy, helping finance ongoing forest management in the short and medium-term and to gradually build up the
endowment resources needed to mitigate financial uncertainties in the medium and long-term.
The CBADP was independently validated under the Verified Carbon Standard (VCS) with a baseline year of
2011. The carbon emissions reduction potential for the two Protected Areas, i.e., Cacheu Mangrove Forest
National Park (74,700 ha) and Cantanhez Forest National Park (106,500 has) is estimated to average 920,426 ton
per year over 20 years43
, (approximately 18 million tCO2e) which at an average price of US$ 3.30/ton, could
potentially create long-term revenues of approximately US$60.0 million. (See table below.) Taking into account
Guinea-Bissau’s political instability, finding a buyer might be challenging, nevertheless the pilot and the
estimates indicate that the coastal forests have significant economic and financial potential that could potentially
finance the FBG, the management of protected areas by IBAP, community sustainable development activities
and help build the FBG’s endowment for future protected areas.
Now, five years into the pilot, FBG and IBAP need to undertake the first monitoring to quantify the actual
avoided emissions, complete the verification audit and issue the first VCUs. FFEM (confirmed) and MAVA (in
the approval process) propose to finance this process, enabling the monitoring and independent third party
verification required to be able to quantify and issue the VCUs. It will additionally build IBAP and FBG's
capacity to manage carbon projects, and prepare them to engage with the carbon market. At the end of this
process FBG is expected to be able to engage in the carbon market, commercialize these VCUs and realize its
carbon revenues.
Expected Impacts:
The first direct impacts expected of completing the first Independent Verification of the blue carbon REDD
project are that FBG and IBAP will have a verified carbon asset (VCU) that can be traded. While actual
emissions reduction over the past five years will depend upon the degree to which IBAP and its partners have
managed to reduce deforestation in the two designated Protected Areas, the CBADP Project Document (PD)
nevertheless indicated a potential for avoiding 785,921 tCO2e by 2016. Using the 2015 average VCU market
price of USD 3.30 (Hamrick and Goldstein, 2016), this could potentially generate USD 2.50 million. These
resultant carbon revenues would trigger a package of relevant social, environmental, economic and institutional
impacts that are further detailed below. The second direct expected impact relates to building FBG's capacity to
trade carbon, operate a carbon registry and perform the required bureaucratic steps. The project will provide
42 Forest Marketplace (2016). Raising Ambition – State of the Voluntary Carbon Market 2016. 43 Community Based Avoided Deforestation Project in Guinea-Bissau (2015): Winrock International, IICT, and the World Bank.
58
FBG and IBAP staff with the necessary knowledge, training and materials to perform deals in the carbon market.
Carbon finance revenues will be distributed in accordance with a benefit-sharing arrangement, the broad
principles of which are already agreed, namely, funds would be provided to: (i) IBAP in support of immediate,
ongoing management of these two PAs, including for monitoring, verification and issuance of VCUs: (ii) local
communities (via a sinking fund managed by the FBG) in support of participatory sustainable development
initiatives, e.g., similar to those developed under the FIAL; (iii) the FBG endowment fund, to build up the
capital base for generating future sustainable revenue flows after the end of the CBADP; and, (iv) to other
implicated partners, like the State Secretariat for Environment and NGOs.
The increased flow of funds from the sale of VCUs is also expected to have the following impacts:
Environmental: The project will materialize the conservation efforts in Cacheu and Cantanhez National Parks,
delivering emission reductions estimated at around 785,921 tCO2e in the first monitoring period. This
demonstrates the global impact of forest and biodiversity conservation on climate change mitigation, reinforcing
the role of local communities. Furthermore, the project supports a broader national climate policy (National
Determined Contribution - NDC) and the national development strategy (“Terra Ranka”) by supporting the
protection of 145,698 ha of forest and the biodiversity it contains. Finally, in a country that is considered to be
the second most vulnerable to climate change after Bangladesh (Maplecroft, CCVI 2015), the preservation of
these biomes guarantees the maintenance of a natural infrastructure that provides double dividends for the
country and the communities, delivering both emissions mitigation and climate adaptation returns.
Social: The project demonstrates how participatory management and sustainable local development can work
together to support forest and biodiversity conservation. The carbon revenues will permit small grants and
microfinance initiatives, based on the lessons derived from the Fund for Local Environmental Initiatives (FIAL),
to be operationalized. Such programs can impact over 50,000 people living inside the project area. More
importantly, sharing the benefits from REDD will provide communities with a clear message of how they can
benefit from changes in behavior by assessing tangible returns from forest conservation. This supports a
paradigm change since PAs should not be seen as a constraint on their livelihoods, reinforcing their buy-in into
protected areas as whole. Finally, the REDD project is a milestone and basis for a virtuous cycle for future
generations, in which the relationship between community and natural resources is mutually beneficial.
Economic: The main economic impact relates to a new financial source for FBG and IBAP, both for short and
long term conservation financing. From a broader perspective, the project is the first of its kind in Guinea-Bissau
and will allow the country to be inserted into an international carbon payment mechanism. Another relevant
impact relates to supporting capitalizing the endowment and the overall FBG sustainable financing strategy. The
project further demonstrates to the Government of Guinea-Bissau and other West African countries how smart
climate financing that supports tangible social and environmental positive impacts is a reality, providing an
economic value for maintaining standing forests.
Institutional: The experience gained through implementation of this demonstration project is expected to build
institutional capacity in IBAP, FBG and other local partners. The practical experience and lessons learned with
both implementing carbon projects, and operating in carbon markets will also help reinforce the Government's
participation in the ongoing high-level debate on climate issues and related international negotiations.
The ultimate goal of the project is to avoid deforestation in two protected areas of Guinea Bissau (GB), thus
reducing carbon emissions and improving the protection of globally important biodiversity sites. The CBAD
project aims to contribute to the realization of Guinea Bissau's long term vision of sustainable financing for
conservation of biodiversity by leading pilot activities that, while autonomous, can later be nested into national
level developments. To this end, the proposed Independent Verification project activities seek to enable FBG
and IBAP to take the next step in the implementation of the overarching pilot VCS CBAD project, supporting
the first verification of carbon emission reductions (ERs) and issuance of associated VCUs, facilitating benefit-
sharing arrangements and strengthening the capacity to market carbon credits. See table of estimated carbon
credit revenues below.
59
Estimated Revenues from Carbon Credit Markets
Years
Estimated GHG
Emission Reductions
or Removals (tCO2e)
Value (US$) at 2015
Average Price
2013 75,251 248,328
2014 153,844 507,685
2015 235,776 778,061
2016 321,050 1,059,465
2017 409,664 1,351,891
2018 501,619 1,655,343
2019 596,914 1,969,816
2020 695,550 2,295,315
2012 797,527 2,631,839
2022 902,845 2,979,389
2023 978,096 3,227,717
2024 1,056,688 3,487,070
2025 1,138,621 3,757,449
2026 1,223,895 4,038,854
2027 1,312,509 4,331,280
2028 1,404,464 4,634,731
2029 1,499,759 4,949,205
2030 1,598,395 5,274,704
2031 1,700,372 5,611,228
2032 1,805,690 5,958,777
Total Estimated 18,408,529 60,748,146
Total Years 20
Average per
year 920,426 3,037,407
60
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit Responsibility/
Specialty
Lending
John Virdin Sr. Natural Resource Management
Specialist/TTL AFTEN Task Team Leader
Liba Feldblyum Operations Officer AFTEN Task Team Leader
Tanya Yudelman Consultant/Environment Specialist AFTEN Environment and
Biodiversity
Virginie Vaselopoulos Program Assistant AFTEN Team member
Osval Rocha Romao Sr. Financial Management Specialist AFTFM Financial
Management
Cheick Traore Procurement Specialist AFTPC Procurement
Wolfgang Chadab Sr. Finance Officer LOAFC Financial
Management
Luz Meza-Bartrina Sr. Counsel LEGAF Legal Counsel
Daniela Junqueira Counsel LEGAF Legal Counsel
Gayatri Kanungo Global Environment Facility (GEF) AFTEN Environment
Barry Spergel Consultant AFTEN Conservation Trust
Funds
Alberto Ninio Lead Counsel LEGEN Environmental Law
Amadou Konare Environmental Safeguard Specialist AFTEN Environmental
Safeguards
Cheikh Sagna Social Safeguard Specialist AFTCS Social Safeguards
Supervision/ICR
Liba Feldblyum Operations Officer/TTL AFTEN Task Team Leader
Maman-Sani Issa Regional Safeguards Advisor/TTL OPSPF Safeguards
Tanya Yudelman Consultant/Environment Specialist GEN07 Environment and
Biodiversity
Jayne Angela Kwengwere Program Assistant GEN07 Team member
Cheik Traore Sr. Procurement Specialist GGO07 Procurement
Fatou Fall Samba Financial Management Specialist GGO25 Financial
Management
Anna Roumani Consultant GSULN Rural Development
Juan Jose Miranda Montero Environmental Economist GENGE Environmental
Economics
61
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY10 3.60 27.80
FY11 2.87 34.64
Total: 6.47 62.44
Supervision/ICR
FY12 16.74 92.90
FY13 15.68 81.88
FY14 16.03 103.24
FY15 12.55 88.89
FY16 4.38 53.67
FY17 7.00 18.03
Total: 72.38 438.61
62
Annex 5. Beneficiary Survey Results 5.1 The METT Scorecard involved annual interviews with stakeholders including
communities residing in/on the periphery of the parks. Scores are reported in this ICR and the
full questionnaires can be obtained from IBAP. No other beneficiary surveys were conducted.
63
Annex 6. Stakeholder Workshop Report and Results
N/A
64
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR A. Executive Summary of Client’s final Completion Report (Informal Translation)
The Biodiversity Conservation Project - (BCP) was financed by IDA Credit HH 6700 for an
amount of SDR 1.3 million, equivalent to USD 1.90 million. The BCP was executed in five years,
between June 2011 and May 2016. The Project Development Objectives were to reinforce the
management of IBAP in the five Protected Areas (PA), and operationalize the BioGuinea
Foundation, for which three components were implemented.
Component 1: Strengthen and consolidate the capacity for management of coastal and marine
protected areas and biodiversity
The five parks are more effective and efficient in their participatory management according to the
METT scores which totaled 507 compared to 454 at the beginning of the project (2011): PMJVP
went from 106 to 116; PNO from 113 to 119; PNTC from 105 to 129, PNLC from 74 to 83, and
PNC from 56 to 60. The participatory management plans, and the Business Plans and internal
regulations were updated and approved by the Park Management Councils in all five parks.
Participatory surveillance exceeded 60 missions per year in all five parks: 2012-109 missions;
2013-134; 2014-164 and in 2015- 302 including the AMPC Urok. Thanks to the BCP and
complementary activities of IBAP partners, illegal encampments on the maritime/coastal limits
of the PNC and PNLC were dismantled, infiltration of the parks by non-resident fishermen was
reduced, along with the use of single-line nets and consequently reduction in illegal and
irresponsible fishing practices. During the BCP’s four years, the capacity of 786 people was
strengthened both domestically and through overseas training visits, including IBAP staff,
technicians from partner institutions, community co-managers and the communities themselves,
exceeding the target of 200 for the four years. About 43,000 people were trained overall
including through the project’s communications and awareness-building campaigns and other
diverse types of training.
Component 2: Pilot the operation of the BioGuinea Foundation
The BioGuinea Foundation is operational with its governance organs instituted and functioning,
with operational manuals and procedures adopted. Fund-raising activities, institutional linkages
and negotiations with the Government and Donors are permanent/ongoing for capitalization of
the FBG. The Government provided EUR 1.0 million through its Fisheries Accord with the EU,
and with strategic partners such as the MAVA Foundation (EUR 1.3 million), FFEM (EUR 1.0
million), and GEF 5 contributed USD 1.3 million.
Component 3: Project management and monitoring and evaluation
The management, coodination and monitoring of the projec was conducted under the direction of
IBAP and its technical and financial team, through the operationalization of a monitoring and
evaluation system, through the presentation of plans, reports, the application of performance
measurement instruments, to assess management effectiveness in the Protected Areas, and
through the utilization of software - Hi Project - for accountability/fiduciary. Bank supervision
missions were always timely and useful.
The most prominent negative factor not under the control of IBAP was the recurrent
political/military and government instability which influenced the implementation of various
activities on the ground. Other factors were managed in a positive way by IBAP due to its
65
institutional autonomy and the stability of its management, the culture of being results-driven, by
its rigorous and transparent management of allocated resources, and by the overall quality of its
interventions in managing the PAs, with the strong involvement of the communities and by the
diversity and quality of the activities/interventions of IBAP’s partners: the gains and successes
and the growth of the PAs in effectiveness and efficiency; in the strengthened capacity of their
human resources including community agents; in the greater involvement, participation and
decision-making of the communities; and the complementary and synergistic actions of IBAP’s
various strategic partners.
Lessons Learned: The importance of the following: participatory, transparent and democratic
governance; co-management of resources in terms of ownership and responsibility; strengthening
the capacities of IBAP’s technical and administrative personnel, partner institutions and the
communities in the PAs, creating greater “horizontality” in the dialogue among
stakeholders/actors; proactive communication concerning the execution of activities in the PAs,
contributing to constructing a positive image and visibility for IBAP and its activities; and, in the
operationalization of the BioGuinea Foundation, that a medium to long-term perspective is
needed to guarantee/ensure a mechanism for the sustainable financing of activities in the PAs.
66
B. Client’s Letter commenting on the Bank’s draft ICR
67
Annex 8. Comments of Co-financiers and Other Partners/Stakeholders
N/A
68
Annex 9. List of Supporting Documents Project Appraisal Document (PAD)
Financing Agreement, Grant #H670-GW
Supervision Aide Memoires
Implementation Supervision Reports (ISR)
Procurement Post Reviews
Financial Management Supervision Reports
Annual Reports of Client
Correspondence
Client Contacts
Restructuring Documents
Systematic Country Diagnosis (SCD): “Turning Challenges into Opportunities for Poverty
Reduction and Inclusive Growth”, World Bank Report #106725-GB, June 2016
Country Economic Memorandum – Guinea-Bissau: Terra Ranka! A Fresh Start, World Bank,
Report # 58296, Vols. I and II, January 12, 2015
Optimizing Guinea-Bissau’s Natural Wealth, H. Edmundson, World Bank, September 2014
Guinea Bissau 2025: Strategic and Operational Plan for 2015-2020 – Terra Ranka (Eng),
Republic of Guinea Bissau, March 2015
Estratégia Nacional para as Áreas Protegidas e a Conservação da Biodiversidade na Guiné-Bissau,
2014-2020, Instituto da Biodiversidade e das Áreas Protegidas (IBAP), 2014
Progress Report: Validation Audit of the Community-based Avoided Deforestation Project in
Guinea-Bissau, World Bank/SCS Global Services, May 24, 2013 (REDD study)
Relatório Final: Projeto da Conservação da Biodiversidade (PCB), Unidade de Gestão do
Projeto/IBAP, October 2016
Implementation Completion and Results Report: Guinea-Bissau Coastal Biodiversity
Management Project, Report # 00001684
Implementation Completion Memorandum (ICM): Guinea-Bissau Biodiversity Conservation
Trust Fund (BCTF), Trust Fund # TF098994, July 2, 2014
69
Map: Guinea-Bissau Biodiversity Conservation Project (P122047)