DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

25
DOCK C PROJECT: A LOOK AT OPTIONS May 16, 2013

Transcript of DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Page 1: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

DOCK C PROJECT:A LOOK AT OPTIONS

May 16, 2013

Page 2: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Need/Benefit of Dock C Project

• Dock C does not meet ADA requirements• Dock C does not meet DBAW standards creating liability 

issue for City.• Dock C is reaching the end of its service life and is 

deteriorating faster than previously anticipated.• Dock C slip occupants were given commitment that Dock 

would be upgraded in the future.• Glorietta Bay Marina is at 100% capacity and has waiting 

list.  Expansion provides increased recreational berthing opportunities.

• Opportunity to reconfigure dock system for easier access.• Possibility to add public dock component.

2

Page 3: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Dock C Condition

3

Page 4: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Moffatt & Nichol Engineering Study• Hired in 2011 to assess current structural condition of Dock C.• Key Findings:

– 41% of three key components are worn and/or require replacement within 5‐7 years (i.e., by 2015‐18).  Components included: deck boards, stringers/facia and dock connections.

– Floatation system needed to be completely replaced due to cracking and exposed foam.

– 90% of the power pedestals are worn and/or need to be replaced.– A “retrofit” of Dock C would enable it to last another 15‐20 years 

(maximum); – A “rebuild” as wood dock – another 30‐40 years (maximum); 

“rebuild” as concrete dock – another 40‐50 years (maximum).– Conclusion: Simply maintaining dock comes at a cost.  As dock 

gets older, costs to maintain dock will become more expensive as structural integrity diminishes.

4

Page 5: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

GBM Dock System

5

Page 6: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Eel Grass Issue

Photos taken on January 11, 2013 @ 3:00p.m. (‐1.89 MLLW)

6

Page 7: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Existing Dock C Layout34 slips, 1,303 rentable lineal feet

Growing eel grass mound

7

PROJECT OBJECTIVE: Similar to Dock A/B Project, at a minimum, maintain same number of slips and/or rentable lineal footage.  If possible, increase both!  Dock A/B Project resulted in increase of 214 rentable lineal within same footprint.

Page 8: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Retrofit/Rebuild – Loss of Four Slips30 slips, 1,085 rentable lineal feet 

8

Slips 30 feetand Under

Slips Over 30 feet

17 (57%) 13 (43%)

Page 9: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

City of CoronadoMay 16, 2013

EVALUATION OFOPTIONS FOR DOCK C PROJECT

9

Page 10: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Criteria used to determine best option for reconstruction of Dock C

• Compliance with ADA requirements and DBAW standards.• Ability acquire necessary permits and leases from current 

stakeholders.• Highest cumulative “net” slip revenues over new 40‐year 

City‐Port District lease.• Least environmental impact on eel grass and native 

species.• Mitigated increase in total dock area from the current 

Dock C layout.  Goal: <10% increase.

10Source: April 16, 2013 Staff Report

Page 11: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Map of Coronado Local Coastal Program (LCP) Developable Water Area

11

This developable water area is under Port District land/water use and coastal 

permitting jurisdiction.Option 2 

(190 feet beyond leasehold line) 

Page 12: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Port Master Plan Amendment (PMPA)

12

PMPA required to: 1) modify water area between recreational boat berthing and open bay of Precise Plan; and 2) include Dock C Project on Port’s Project List.

Page 13: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Relationship of Dock C to Linear Park

13

140 Feet

190 Feet

Page 14: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 1: Best fit within same footprint34 slips, 1,188 rentable lineal feet

Slips 30 feetand Under

Slips Over 30 feet

23 (68%) 11 (32%)

14

Page 15: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 1‐A: With Public Dock33 slips, 1,086 rentable lineal feet

15

Slips 30 feetand Under

Slips Over 30 feet

23 (70%) 10 (30%)

110‐ft slip is converted to public dock cordoned off by fence.

Page 16: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 2: Optimized mix beyond leasehold linewith public dock

37 slips, 1,450 rentable lineal feet

16

Slips 30 feetand Under

Slips Over 30 feet

19 (51%) 18 (49%)

Page 17: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 2‐A: Smaller Dock System, Larger Public Dock34 slips, 1,360 rentable lineal feet

17

Slips 30 feetand Under

Slips Over 30 feet

16 (47%) 18 (53%)

Public dock increased to 190  lineal feet.  Dock system extension 

beyond leasehold line reduced by 49 feet.  No 

sister slips.

Page 18: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 2‐B: Smaller Dock System, Separate Public Dock34 slips, 1,360 rentable lineal feet

18

Slips 30 feetand Under

Slips Over 30 feet

16 (47%) 18 (53%)

Separate public dock increasing functionality to 220  lineal feet.  Dock system extension beyond leasehold line reduced by 29 

feet.  No sister slips.

Page 19: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 3 – Current layout with additional row of slips41 slips, 1,578 lineal feet

19

Slips 30 feetand Under

Slips Over 30 feet

16 (39%) 25 (61%)

Page 20: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Option 3‐A: With Public Dock40 slips, 1,468 lineal feet

20

Slips 30 feetand Under

Slips Over 30 feet

16 (40%) 24 (60%)

110‐ft slip is converted to public dock cordoned off by fence.  40 and 50‐ft sister slips eliminated.

Page 21: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

City of CoronadoMay 16, 2013

EVALUATION OFDOCK C OPTIONS: SUMMARY

21

Page 22: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

Dock C Option Dimensions: Summary

Option Description

TotalSlips

RentableLinealFootage

TotalDock Area

Rentable LF as % of TotalDock Area

% increase in Total 

Dock Area from 

Current

Slips 30‐ft and Under

Slips Over30‐ft

CURRENT 34 1,303 8,931 14.6% 16 18

1 Best fit within same foot print 34 1,188 8,354 14.2% ‐6.4% 23 11

1‐A Option 1 w/ Public Dock 33 1,086 8,485 12.8% ‐5.0% 23 10

2 Optimized mix w/ Public Dock 37 1,450 9,152 15.8% +2.5% 19 18

2‐AOptimized mix: Smaller Dock System, Larger Public Dock

34 1,360 9,345 14.5% +4.6% 16 18

2‐BOptimized mix: Smaller Dock System, Separate Public Dock

34 1,360 9,506 14.3% +6.4% 16 18

3 Current layout with additional row of slips 41 1,578 9,492 16.6% +6.3% 16 25

3‐A Option 3 w/ Public Dock 40 1,468 9,652 15.2% +8.1% 16 24

22

Page 23: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

23

Option Description

Estimated Cost of 

Construction

Years to Pay offProject

Dock C Projected NET Revenues thru FY 2053

ROI: Cost vs. Net 

Revenue

Increase InNET RevenueCompared to Option 1‐A

Status Quo (Retrofit)

Wood Construction ONLY: Loss of Four Slips

$1,198,239Cost of first.(2 required)

12.5 $1,186,029(after 2 retrofits) 0.6

Status Quo(Rebuild)

Concrete Construction: Loss of Four Slips $2,552,832 15.4 $5,935,538 2.3

1 Best fit within same foot print $2,481,850 14.4 $6,529,346 2.6

1‐A Option 1 w/ Public Dock $2,745,238 18.0 $4,314,287 1.6

2 Optimized mix w/ Public Dock $3,063,224 14.2 $7,725,841 2.5 $3,411,554

2‐A Option 2: Smaller System w/ Larger Public Dock $3,092,199 15.1 $6,806,179 2.2 $2,491,892

2‐B Option 2: Smaller System w/ Separate Public Dock $2,987,089 15.3 $6,813,882 2.3 $2,499,595

3 Current layout with additional row of slips $2,969,997 13.6 $9,061,891 3.1 $4,747,604

3‐A Option 3 w/ Public Dock $3,069,334 15.5 $7,280,206 2.4 $2,965,919

Costs and Revenues: Summary

Page 24: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

NEXT STEPS• Accept additional feedback through end of May.• Forward recommended option for City Council approval.• Initiate CEQA Process

– Port District to serve as Lead Agency– City and Port will enter into agreement.  City to reimburse costs.

• Develop Permit Applications– Port District, Coastal, ACOE, SDRWQCB, U.S. Fish & Wildlife.– Submit after conclusion of CEQA Process.

• Process Port District Master Plan Amendment• Process City‐Port Lease Amendment• Estimated time to complete above steps before 

Construction: Up to 3 years!

24

Page 25: DOCK C PROJECT: A LOOK AT OPTIONS - Coronado Common …

CONTACTS:Jerome Torres

[email protected] Cecil

[email protected]

25