DNV Lifting Spreadsheet Rev 0

29
Job-CTR Project: DNV 4-Point Lift Rigging Calculations Sheet 1 Rev 0 Asset: By KPP Subject: Date 9/25/2009 Checked VM PRELIMINARY INFORMATION ON LIFTING AND CODES The DNV standard Rules for Planning and Execution of Marine Operations, Pt2, Ch5, Lifting, 1996, is specifically for lifts greater than 50T. The 2009 release of this standard will cover lifts down to 5T. This spread sheet should only be used for lifts >50T until the it is updated with information from the 2009 release. Engineering Pty Ltd ACN 009 171 528

description

c

Transcript of DNV Lifting Spreadsheet Rev 0

Page 1: DNV Lifting Spreadsheet Rev 0

Job-CTRProject: DNV 4-Point Lift Rigging Calculations Sheet 1 Rev 0Asset: By KPPSubject: Date 9/25/2009

Checked VM

PRELIMINARY INFORMATION ON LIFTING AND CODESThe DNV standard Rules for Planning and Execution of Marine Operations, Pt2, Ch5, Lifting, 1996, isspecifically for lifts greater than 50T.The 2009 release of this standard will cover lifts down to 5T.This spread sheet should only be used for lifts >50T until the it is updated with information from the 2009 release.

Engineering Pty Ltd ACN 009 171 528

Page 2: DNV Lifting Spreadsheet Rev 0

Job-CTRProject: DNV 4-Point Lift Rigging Calculations Sheet 2Asset: By KPPSubject: Date 9/25/2009

Checked VM

INSTRUCTION FOR USE OF SPREADSHEETGeneral InformationThis spreadsheet calculates the rigging required for a 4-point lift according to DNV standard, Rules forPlanning and Execution of Marine Operations, Part 2, Chapter 5 for lifts >50T.

Refer to ASSUMPTIONS on Design Report page in addition to this information.Note that symmetry is not required and padeyes can be place at any x,y and z coordinates.

Limitations1) 4 leg lift only2) IWRC GR1770 wire rope and Green Pin shackles and masterlinks only

3) Wire rope diameter is only calculated for the critical sling and UC is based on this sling

4) Above water/ offshore/ onshore/ on-platform/ inshore lifts only

5) Single hook lift only

Coordinate System yCOG is at the origin 2

z axis is verticalx and y axis are in the horizontal planeLifting points are labelled anti-clockwise starting from the positive x and y quadrant 3

Inputs requiredAll inputs are in blueThe title block needs to be completed on the first page of the design report onlyInputs

1 Type of lift- Select as applicable (Offshore, On-platform, Inshore, Onshore)

2 Lift weight, to nearest 0.1T

3 Rigging weight, zero initally

4 D/d ratio must be greater than or equal to 4 (DNV Pt2, Ch5, Section 3.1.3), if no bending enter 4

5 Minimum sling angle (must be >= 60 deg)

6 Configuration and tolerance

7 Lifting point coordinates defined with COG at origin

8 Skew factor data, only required for 4 point, approximately double symmetric lifts

9 Sling details are used to determine sling safety factors

10 Override rigging selection

The spreadsheet will determine the rigging with UC's closest to 1

If a lower UC is desired input larger rigging size 11 Splicing reduction factor. Equivalent to termination factor in WEL standard.12 Padeye UC from padeye spreadsheet

SOLVINGDefine all required inputs as above. Solve without rigging weight and then increase weight by including rigging weight to determine UC's. If original UC's are close to 1 the rigging required may change and the process repeated. If the approx UC is used for the SKL calculation this should be checked against the results and iterated if required.

Engineering Pty Ltd ACN 009 171 528

Page 3: DNV Lifting Spreadsheet Rev 0

Job-CTRRev 0 Project: DNV 4-Point Lift Rigging Calculations Sheet

KPP Asset: By9/25/2009 Subject: Date

Checked

Other Relevant InformationInput 1 Type of lift: Inshore, Onshore/ On-platform or Offshore

This spreadsheet calculates the rigging required for a 4-point lift according to DNV standard, Rules for Input 4 If no bending insert a number greater than 4Input 6 The rigging configuration and tolerance effects the SKL.

Three rigging configurations and SKL calculation methods as below: i) Symmetrical and within specified tolerance, SKL=1.25, section 2.3.2.5ii) Approximately symmetrical, outside tolerance, SKL calculated as per section 2.3.2.7iii) Any unusual geometry, SKL calculated assuming one leg inactive at a time

Input 8 The SKL is dependent on the sling load, and diameter so cannot be directly calculated.A best estimate of fabrication tolerance and UC is required. The lower the UC the higher the SKL, therefore the design should not be too conservative.

Wire rope diameter is only calculated for the critical sling and UC is based on this sling Input 9

Rigging Design Options1 OPTION 1: The spreadsheet will determine the rigging with UC's closest to 1.

x OPTION 2: Manually input the rigging at the bottom of page 1 of the design report and check rigging UC's.

4

D/d ratio must be greater than or equal to 4 (DNV Pt2, Ch5, Section 3.1.3), if no bending enter 4

Define all required inputs as above. Solve without rigging weight and then increase weight by including rigging weight to determine UC's. If original UC's are close to 1 the rigging required may change and the process repeated. If the approx UC is used for the SKL calculation this should be checked against the results and

Engineering Pty Ltd ACN 009 171 528

If the weight is well controlled and skew thoroughly considered, f=1.2, otherwise 1.3

If the slings is for single use, w=1.0, if multiple use and sling in good condition,

If wire rope is new,m=1.35, if used,

m=1.5

Page 4: DNV Lifting Spreadsheet Rev 0

3 Rev 0KPP9/25/2009VM

Symmetrical and within specified tolerance, SKL=1.25, section 2.3.2.5Approximately symmetrical, outside tolerance, SKL calculated as per section 2.3.2.7Any unusual geometry, SKL calculated assuming one leg inactive at a time

The SKL is dependent on the sling load, and diameter so cannot be directly calculated.A best estimate of fabrication tolerance and UC is required. The lower the UC the higher the SKL,

OPTION 2: Manually input the rigging at the bottom of page 1 of the design report and check rigging UC's.

=1.2, otherwise 1.3

=1.0, if multiple use and sling in good condition, w=1.1

Page 5: DNV Lifting Spreadsheet Rev 0

Job-CTRProject: DNV 4-Point Lift Rigging Calculations Sheet 4 Rev 0Asset: By KPPSubject: Date 9/25/2009

Checked VM

DESIGN CODE COMPLIANCEDNV Rules for Planning and Execution of Marine Operations, Part 2, Chapter 5, Lifting (1996)

All possible CoG positions should be considered

ASSUMPTIONS4 leg, single hook, above water lifts onlyFor unusual geometry, skew is accounted for by conservatively assuming any individual leg is inactive at a time. This case is not referred to in the code.Design load for shackles and padeyes excludes rigging weightMasterlink design method assumed the same as for shackles

NOMENCLATURE/ ABBREVIATIONS

COG Centre of GravityD Bending diameter of slingsDAF Dynamic Amplification FactorDHL Dynamic Hook Loadd Diameter of sling

Maximum sling loadMBL Minimum Breaking LoadP Nominal dynamic sling load

Padeye design loadSKL Skew Load FactorSWL Safe Working LoadUC Utilisation CoefficientW Weight of object

Weight of rigging

Sum of sling and padeye tolerance divided by sling length

Bending reduction factor

Consequence factor

Design factor for lift point

Load factor

Material factor

Bending or splicing reduction factor

Splicing reduction factor

Nominal safety factor for slings

Wear factor

Engineering Pty Ltd ACN 009 171 528

Psling

Ppadeye

Wrig

Average sling strain caused by Psling

0

b

c

design

f

m

r

s

sf

w

Page 6: DNV Lifting Spreadsheet Rev 0
Page 7: DNV Lifting Spreadsheet Rev 0

Job-CTRProject: DNV 4-Point Lift Rigging Calculations Sheet 1 Rev 0Asset: By KPPSubject: Date 5/25/2010

Checked VM

LIFT RIGGING DESIGN TO DNV STANDARD This calculation determines the lift rigging required for a 4-point symmetric or unsymmetric lift >=50T

Design Code

DNV Rules for Planning and Execution of Marine Operations, Part 2, Chapter 5, Lifting, (1996)

Assumption

4 leg, single hook, above water lifts only

For unusual geometry, skew is accounted for by conservatively assuming any individual leg is inactive at a

time. This case is not referred to in the code.

Design load for shackles and padeyes excludes rigging weightMasterlink design method assumed the same as for shackles

zInut Data Masterlink

1) Type of Lift Onshore/ On-platform2) Lift weight 50.0 T 53) Rigging weight 1.00 T

4) D/d ratio 4

5) Minimum sling angle 60 deg

6) Configuration/tolerance 4 point, symmetrical lift within tolerance y

7) Lifting point data 2

Point x (mm) y(mm) z(mm) 3

1 1000 1000 0 COG2 -1000 1000 03 -1000 -1000 0 x4 1000 -1000 0 4

Dynamic Applification 1.10 (DNV Pt.2 Ch.5 Lifting, Table 2.1)8)

0.25 % (Fabrication tolerance Section 3.1.4.2)

1 (Assumed design UC)

800 MPa (MBL/A for GR1770)

30000 MPa (DNV Pt.2 Ch.5 Lifting, Section 2.3.2.7)

SKL= 1.25 min 1.1 (DNV Pt.2 Ch.5 Lifting, Section 2.3)

9) Sling DetailsQuestion ResponseWell controlled weight and skew thoroughly considered noSling use multiple use, good conditionSling condition new

(DNV Pt.2 Ch.5 Lifting, Section 3.1.2.1)

Override rigging selectionWire rope size: Use calculated valueShackle size: Use calculated valueMasterlink size: Use calculated value

Engineering Pty Ltd ACN 009 171 528

P1

P2

P3

P4

Skew Factor (Only required for approximately double symmetric)

0=

UCapprox

=

Fu sling

=

Esling

=

Page 8: DNV Lifting Spreadsheet Rev 0
Page 9: DNV Lifting Spreadsheet Rev 0

1

Page 10: DNV Lifting Spreadsheet Rev 0
Page 11: DNV Lifting Spreadsheet Rev 0

Job-CTR 0Project: DNV 4-Point Lift Rigging Calculations Sheet 2Asset: 0 By KPPSubject: 0 Date 5/25/2010

Checked VM

Results Operating caseOnshore/ On-platform 50-100T

Safety Factors

1.3 (DNV Pt.2 Ch.5 Lifting, Section 3.1.2.1)

1.3

1.33 1.33 (Effectively termination factor, can be

1.1 1.33 1.1 if going off 0.9 as in Woodside)

1.35

3.35

Design Load

DHL= 56.10 T

Sling LoadsLoad (T)

20.24 (Max individual sling loads for including SKL or one leg inactive)

20.24

20.24

20.24

20.24

20.24 T

Master link height 2449 mm

4 point lifting sling set comprising of:Item Size Mass(kg) Length(mm) UC4x Green pin bow safety shackle 25.00 T 60.0 0.91

1x Green pin master link assembly 63.0 T 67.6 0.72

Sling 1 IWRC GR 1770 wire rope 34.0 mm 13.0 2828 0.81

Sling 2 13.0 2828

Sling 3 13.0 2828Sling 4 13.0 2828Total 180 11314

Rigging SWL 51.0 TPadeye SWL 18.04 T

Engineering Pty Ltd ACN 009 171 528

f=

c=

r=

s=

w=

b=

m=

sf=

sf=max(3,

f

c

r

w

m)

DHL=DAF(W+Wrig

)

P1

P2

P3

P4

Pmax

Psling

=

Page 12: DNV Lifting Spreadsheet Rev 0
Page 13: DNV Lifting Spreadsheet Rev 0

Job-CTRRev 0 Project: DNV 4-Point Lift Rigging Calculations Sheet

KPP Asset: 0 By5/25/2010 Subject: 0 Date

Checked

Lift Rigging DesignSpecific Design Requirements for Rigging

The SWL of the sling assembly shall be calculated from the following equation:

(DNV Pt.2 Ch.5 Lifting, Section 3.1.2.3)

Design of Wire Rope

(Effectively termination factor, can be 20.24 T (maximum load in sling)

1.1 if going off 0.9 as in Woodside)

664.51 kN

Diameter required= 34.0 mmMBL= 728 kN

Weight= 460 kg/100mUC= 0.91

Design of ShacklesShackle allowable load, minimum of SWL*DAF and MBL/3.3 (DNV Pt.2 Ch.5 Lifting, Section 3.2.1.2)

(Max individual sling loads for including SKL or one leg inactive) Green pin FOS= 6 (Green Pin Grade S shackle manufactures data sheets)

DNV FOS= 5.45 (Max(Green pin FOS/DAF,3.3))

19.85 T

Convert WLL in shackle table to WLL for DNV standard, divide by:

k = 1.10 (= Green pin FOS / DNV FOS)

18.04 T

Shackle required= 25.00 TShackle weight= 14.99 kg

UC= 0.72

Design of Masterlink AssemblyFOS Green pin FOS= 4 (Green Pin Masterlink assemblies manufactures data sheets)5.45 DNV FOS= 3.64 (Max(Green pin FOS/DAF,3.3))

3.64 56.10 T (DHL)

3.35 Convert WLL in shackle table to WLL for DNV standard, divide by:

k = 1.10 (= Green pin FOS / DNV FOS)

51.00 TMasterlink required= 63.00 T

Masterlink weight= 67.60 kgUC= 0.81

PadeyesLifting points should be designed for maximum sling loads (DNV Pt.2 Ch.5 Lifting, Section 4.1.3.1)Lateral load > 3% maximum sling load (DNV Pt.2 Ch.5 Lifting, Section 2.4.3.4)

19.85 T

1.7 (DNV Pt.2 Ch.5 Lifting, Table 4.1)

33.74 TPadeye SWL= 18.04 T

Refer to "PADEYE SHEET V6" ICON in-house spreadsheet for padeye design.UC= INSERT UC

Engineering Pty Ltd ACN 009 171 528

SWL < MBL/sf.g

g = gravity (9.81 m/s2)

SWLreq

>

MBLreq

> SWLreq

sf.g

MBLreq

>

SWLreq

> (Psling

factored to exclude rigging weight)

Mod SWLreq

> (= SWLreq

/ k)

SWLreq

>

Mod SWLreq

> (= SWLreq

/ k)

Ppadeye= (Psling factored to exclude rigging weight)

design

=

Mod Ppadeye

= (Ppadeye

x design

)

Page 14: DNV Lifting Spreadsheet Rev 0
Page 15: DNV Lifting Spreadsheet Rev 0

03 Rev 0 Project: DNV 4-Point Lift Rigging CalculationsKPP Asset: 05/25/2010 Subject: 0VM

Sling Arrangement

The SWL of the sling assembly shall be calculated from the following equation:

(DNV Pt.2 Ch.5 Lifting, Section 3.1.2.3)

Shackle allowable load, minimum of SWL*DAF and MBL/3.3 (DNV Pt.2 Ch.5 Lifting, Section 3.2.1.2)

(Green Pin Grade S shackle manufactures data sheets)

(Green Pin Masterlink assemblies manufactures data sheets)

Lifting points should be designed for maximum sling loads (DNV Pt.2 Ch.5 Lifting, Section 4.1.3.1)Lateral load > 3% maximum sling load (DNV Pt.2 Ch.5 Lifting, Section 2.4.3.4)

Engineering Pty Ltd ACN 009 171 528

factored to exclude rigging weight)

factored to exclude rigging weight) -1500 -1000 -500 0 500 1000 1500

0

500

1000

1500

2000

2500

3000

1; 2,449

Elevation

x (mm )

z (mm )

-1500 -1000 -500 0 500 1000 1500

-1500

-1000

-500

0

500

1000

1500

1; 10002; 1000

3; -1000 4; -1000

5; 1000

Plan

x (m m)

y (mm )

Page 16: DNV Lifting Spreadsheet Rev 0
Page 17: DNV Lifting Spreadsheet Rev 0

Job-CTR 0Sheet 4 Rev 0By KPPDate 5/25/2010Checked VM

-1500 -1000 -500 0 500 1000 1500

0

500

1000

1500

2000

2500

3000

1; 2,449

Elevation

x (mm )

z (mm )

-1500 -1000 -500 0 500 1000 1500

-1500

-1000

-500

0

500

1000

1500

1; 10002; 1000

3; -1000 4; -1000

5; 1000

Plan

x (m m)

y (mm )

Page 18: DNV Lifting Spreadsheet Rev 0
Page 19: DNV Lifting Spreadsheet Rev 0

ReferencesWire rope Unirig lifting and morring equipment, J:\Reference\Product Catalogue\Unirig CatalogueShackles Unirig lifting and morring equipment, J:\Reference\Product Catalogue\Unirig CatalogueMasterlinksVan Beest Catalogue 2005, J:\Reference\Product Catalogue\Green Pin

WIRE ROPE LOOK UP TABLE TO DETERMINE SIZELookup rounds down so size colum shifted up to compensate

Min. breakWeight Size (mm)force kN kg/100m

0 0 13106 67.3 14124 78 16161 102 18204 129 19227 144 20252 159 22305 193 24363 229 26426 269 28494 312 30567 358 32645 408 34728 460 36817 516 38910 575 40

1010 637 421110 702 441220 771 451280 806 481450 917 521700 1080 582121 1340 642580 1630 672830 1790 703090 1950 773740 2360 804030 2550 864660 2940 905100 3220 965810 3670 1026560 4140

WIRE ROPE LOOK UP TABLE FOR MBL AND WEIGHT

Size (mm)Min. breakWeightforce kN kg/100m Fu

13 106 67.3 798.614 124 78 805.518916 161 102 800.748318 204 129 801.669319 227 144 800.624320 252 159 802.140922 305 193 802.351424 363 229 802.4062

Page 20: DNV Lifting Spreadsheet Rev 0

26 426 269 802.366928 494 312 802.270830 567 358 802.140932 645 408 801.991734 728 460 801.832536 817 516 802.651838 910 575 802.387840 1010 637 803.732542 1110 702 801.188144 1220 771 802.351445 1280 806 804.813148 1450 917 801.300952 1700 1080 800.483458 2121 1340 802.776864 2580 1630 801.991767 2830 1790 802.688370 3090 1950 802.920477 3740 2360 803.156780 4030 2550 801.74386 4660 2940 802.230490 5100 3220 801.669396 5810 3670 802.6825

102 6560 4140 802.8116798.6

GREEN PIN SHACKLE LOOK UP TABLESWLL Weight

0 3.253.25 4.75 0.794.75 6.5 1.266.5 8.5 1.888.5 9.5 2.789.5 12 3.8712 13.5 5.2613.5 17 6.9417 25 8.7925 35 14.9935 42.5 20.6542.5 55 29.0155 85 41.0585 120 62.24120 150 110150 200200 250250 300300 400400 500500 600600 700700 800800 900900 10001000

GREEN PIN MASTERLINK LOOK UP TABLE

Page 21: DNV Lifting Spreadsheet Rev 0

WLL Weight0 2.4

2.4 4.3 1.164.3 6.7 2.226.7 10 3.3610 17 6.0217 21.2 9.99

21.2 26.5 18.926.5 32 23.3

32 40 25.840 50 35.250 63 4763 67.6

Page 22: DNV Lifting Spreadsheet Rev 0
Page 23: DNV Lifting Spreadsheet Rev 0
Page 24: DNV Lifting Spreadsheet Rev 0
Page 25: DNV Lifting Spreadsheet Rev 0
Page 26: DNV Lifting Spreadsheet Rev 0
Page 27: DNV Lifting Spreadsheet Rev 0
Page 28: DNV Lifting Spreadsheet Rev 0

ICON Engineering Pty LtdSpreadsheet Revision HistoryDescription: DNV 4-Point Lift Rigging Calculations

Revision Date Description ByA 25-Sep-09 DNV 4-Point Lift Rigging Calculations KPP

Notes:1) The spreadsheet revision history shall be put on a tab called "Rev".2) Revisions noted, A, B, ...Z are not approved for use without normal checking (ie the output must be checked as if the spreadsheet was developed as new)3) Revisions noted 0 and higher are approved for use, output does not need to checked. Input must be checked. Each subsequent revision must be approved for use.

Page 29: DNV Lifting Spreadsheet Rev 0

Chk App

Notes:1) The spreadsheet revision history shall be put on a tab called "Rev".2) Revisions noted, A, B, ...Z are not approved for use without normal checking (ie the output must be checked as if the spreadsheet was developed as new)3) Revisions noted 0 and higher are approved for use, output does not need to checked. Input must be checked. Each subsequent revision must be approved for use.