introducton
Dear Customer,
Please find enclosed the Construction Progress Report of all our projects. Should you have anyfurther queries, please feel free to contact our sales teams.
Thank you
Ananta Singh RaghuvanshiDirector- Sales and Marketing
Bangalore l Chennai Hyderabad Jalandhar Kasauli l Kochi l Lucknow l New Chandigarh l Panchkula l Shimlal l l
nd22 April 2013
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
2/12
External Development
1. Laying of sewer and stormwater pipelines is in progress2. Level difference wall by macceferri in progress3. External electrical work awarded
Construction Status of Independent Floors
1. Total number of cast at various levels - 816
2. Total number of plinths complete - 420
3. Internal electrical and plumbing work is in progress
4. Internal plastering work has begun
slabs
229 acre
Integrated Township
in Panchkula
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
3/12
External Services
1. The laying of sewer and stormwater pipelines - 95% complete2. Electrical work is under progress in R1 and R2.3. Sewage Treatment Plant(STP) in progress.4. The work on parks and horticulture is in progress5. Tubewell boring is almost complete in R1 and R2.
Hyde Park Terraces - Construction by
Shapoorji Pallonji Co. Ltd.
Construction has begun for all floors.
Hyde Park Estate is a229 acres
Integrated Township
in New ChandigarhSE R R A C EE R R A C E A R C A D E
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
4/12
A 250 acres
Integrated Township
in Lucknow
1. Foundation work for electric poles is complete
2. Construction of compound wall in A Block has begun.
3. Laying of services i.e. sewer, stormwater
pipelines and water supply line is in progress.
4. Work for underground water tank and sewage
treatment plant (STP) is in progress.
5. Road work including black top is in progress.
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
5/12
1. Villa reaching completion stage - External finishes in progress
2. External roads and retention walls work in progress
Spread over 58 acres of
forest bed, in Kasauli,
Himachal Pradesh
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
6/12
Luxury cottages in over1.6 acres of cedar forest
in Shimla
S.No. Cottage
No.
Foundation 1st Slab 2
nd Slab 3
rd Slab
1 1, 4, 5, 8, 9, 18,19, 20, 23, 24, 25
Completed
2
21, 22
---
CompletedCompletedCompleted
Completed Completed Completed
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
7/12
External Development
1. Landscaping work in finishing stage
2. Club work finished
3. Squash court work in final stage
4. STP 90% complete
5. Driveways work complete
6. Finishing completed
7. Final coat paint of lobbies in progress
River facing luxury
apartments in
Vytilla, Kochi
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
8/12
External Development
1. STP raft slab & side wall works in progress
2. Macaferri works for entrance road in progress
3. Compound wall and drainage works in progress
4. Tower area slab complete
5. Plastering of walls and ceiling almost complete
6. AC drains in place
7. Kitchen and toilet walls tiling in progress
An Integrated Townshipspread over 26 acres
in Kochi
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
9/12
Structure works
1. LMR (Lift Machine Room), OHT (Over Head
Tank) & structure works completed at Tower
D1 & D2
2. LMR & OHT works in progress at Cluster
A, B & C
3. Non tower upper ground / podiumslab works
in progress at Cluster A, B, C & D
4. Compound wall, underground tank and other
external structure works in progress
Finishing & Services work
1. Block work near completion at all towers and
plastering work in progress
2. External plastering work nearing completion in
Tower D1 & D2.
3. MS railing fabrication and fixing for the Living &
Bedrooms in progress in all towers
4. Toilet waterproofing work in progress in Cluster
A, B, C & D
5. Toilet wall & floor tiling work begun
6. Electrical conduiting and allied works in progress
in all the towers
7. Plumbing & fire fighting work in progress in all
the towers
8. Preliminary works for the lift installation in Tower
D1 & D2 started
High rise apartments in
a 75 acresIntegrated Township
called DLF New Town on
Banerghatta Road,Bengaluru
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
10/12
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
11/12
Luxury Apartments at
Ethiraj Salai, Chennai
L&T is the Construction Partner
-
7/30/2019 DLF India Wide Projects Construction Update 04 2013
12/12
1. Mall structure is ready. Offered units for fit outs.
2. Soft launch of Clubhouse is scheduled by in Aug/ Sep- 2013.th3. PSBB MillenniumSchooloperational upto 10 class
Under Completion of Towers:
1. Entire block of T-34 to T-42 ready. 100 families moved in
2. T-5 is being handed over
3. In T-2, T-3, T-4 and T-6, internal finishing work is under way
and lifts are being fitted
4. In T-24 to 27, internal tiling, electrical and plumbing work is in
progress. Plastering is complete.
with 1700 students
A 52 acre
Integrated Township
on OMR, Chennai