DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160...
Transcript of DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160...
![Page 1: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/1.jpg)
Adden
dum #1
KANE COUNTY DIVISION of TRANSPORTATION
Carl Schoedel, P.E. Director of Transportation County Engineer
41W011 Burlington Road St. Charles, IL 60175
Phone: (630) 584-1170 Fax: (630) 584-5265
Section 08-00383-00-BR Peplow Road over Tributary to Virgil Ditch No. 3 Bridge and
Roadway Reconstruction
March 7, 2019
Addendum #1
- The Schedule of Prices has been revised to match the Summary of Quantities
shown in the plans. The reissued Schedule of Prices is attached.
- The Special Provision for Lime Modifier has been revised. The revised Special Provision is attached.
Note: This addendum is hereby declared a part of the proposal documents for the project designated above, and in case of conflict, the addendum shall govern. Bidders shall incorporate in their proposal this addendum in acknowledgement of receipt of the addendum and that it is reflected in the proposal submitted.
![Page 2: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/2.jpg)
Adden
dum #1
RETURN WITH BID
County
Local Public Agency
Section
Route
Total
Item
No.Items Unit Quantity Total
1 TREE REMOV OVER 15 UNIT 130
2 TREE REMOVAL, ACRES ACRE 1.5
3 TEMPORARY FENCE FOOT 250
4 TREE TRUNK PROTECTION EACH 4
5 EARTH EXCAVATION CU YD 35,075
6 REM & DISP UNS MATL CU YD 587
7 CHANNEL EXCAVATION CU YD 730
8 TRENCH BACKFILL CU YD 36
9 POROUS GRAN BACKFILL CU YD 611
10 GEOTECH FAB F/GR STAB SQ YD 1,761
11 TOPSOIL EXC & PLAC CU YD 16,405
12 SEEDING CL 2 ACRE 0.8
13 SEEDING CL 2A ACRE 1.3
14 SEEDING CL 4 ACRE 8.1
15 SEEDING CL 5 ACRE 8.1
16 EROSION CONTR BLANKET SQ YD 48,804
17 TEMP EROS CONTR SEED POUND 3,013
18 TEMP DITCH CHECKS FOOT 1,260
19 AGG DITCH CHECKS TON 14
20 PERIMETER EROS BAR FOOT 7,374
21 INLET & PIPE PROTECT EACH 6
22 INLET FILTERS EACH 3
23 STONE RIPRAP CL A3 SQ YD 24
24 STONE RIPRAP CL A4 SQ YD 1,139
25 FILTER FABRIC SQ YD 1,162
26 CONTRACTOR DESIGNED MOD SOIL LSUM 1
Printed 3/5/2019 Page 4-1 BLR 12200a (01/08/14)
Combination Letter Sections Included in Combinations
SCHEDULE OF PRICES
ADDENDUM NO. 1
Kane
Division of Transportation
08-00383-00-BR
Peplow Road (CH 11)
Schedule for Multiple Bids
Schedule for Single Bid
(For complete information covering these items, see plans and specifications)
Bidder's Proposal for making Entire Improvements
Unit Price
![Page 3: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/3.jpg)
Adden
dum #1
RETURN WITH BID
Item
No.Items Unit Quantity Total
27 PROCESS MOD SOIL 16 SQ YD 11,898
28 LIME TON 393
29 AGG SUBGRADE IMPROVE CU YD 734
30 AGG SUBGRADE IMPR 12 SQ YD 10,710
31 SUB GRAN MAT B 8 SQ YD 610
32 BIT MATLS PR CT POUND 23,586
33 BIT MATLS TACK CT POUND 7,050
34 LEV BIND MM N50 TON 648
35 HMA BC IL-19.0 N50 TON 2,471
36 HMA SC "D" N50 TON 1,364
37 BR APPR PVT CON (FLX) SQ YD 104
38 PAVEMENT REM SQ YD 1,362
39 PAVT PATCH T2 10 SQ YD 20
40 HMA SHOULDERS 8 SQ YD 6,017
41 REM EXIST STRUCT EACH 1
42 PIPE CULVERT REMOV FOOT 92
43 STRUCTURE EXCAVATION CU YD 290
44 FLOOR DRAINS EACH 8
45 CONC STRUCT CU YD 156.0
46 CONC SUP-STR CU YD 141.9
47 BR DECK GROOVING SQ YD 433
48 CONCRETE ENCASEMENT CU YD 4.3
49 PROTECTIVE COAT SQ YD 553
50 CONC SUPSTR APP SLAB CU YD 99.3
51 REINF BARS, EPOXY CTD POUND 94,160
52 FUR M S PILE 14X0.250 FOOT 1,068
53 DRIVING PILES FOOT 1,068
54 TEST PILE MET SHELLS EACH 4
55 NAME PLATES EACH 1
56 PERM STL SHT PILING SQ FT 67,782
57 PRC FLAR END SEC 12 EACH 3
58 PRC FLAR END SEC 15 EACH 1
59 PRC FLAR END SEC 24 EACH 4
60 PRC FLAR END SEC 30 EACH 1
61 P CUL TEMP FOOT 60
62 P CUL CL A 1 15 FOOT 50
63 P CUL CL A 1 24 FOOT 112
64 P CUL CL A 1 30 FOOT 54
65 P CUL CL C 1 12 FOOT 164
66 STORM SEW CL B 1 8 FOOT 400
67 STORM SEW CL A 1 12 FOOT 155
68 GRANULAR BACKFILL STR CU YD 61
69 GEOCOMPOSITE WALL DR SQ YD 42
70 CONTR LOW-STRENG MATL CU YD 131
71 PIPE DRAINS 12 FOOT 100
Printed 3/5/2019 Page 4-2 BLR 12200a (01/08/14)
Bidder's Proposal for making Entire Improvements
Unit Price
![Page 4: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/4.jpg)
Adden
dum #1
RETURN WITH BID
Item
No.Items Unit Quantity Total
72 PIPE UNDERDRAINS 4 FOOT 2,458
73 PIPE UNDERDRAIN 4 SP FOOT 1,685
74 PIPE UNDERDRAIN 6 SP FOOT 1,755
75 PIPE UNDERDRAIN 8 SP FOOT 1,930
76 CB TC T8G EACH 1
77 MAN TA 4 DIA T1F CL EACH 8
78 MAN TA 5 DIA T1F CL EACH 1
79 INLETS TA T1F CL EACH 8
80 INLET TA SPL F&G EACH 1
81 INLETS TB T1F CL EACH 1
82 SPBGR TY A 6FT POSTS FOOT 2,637.5
83 TRAF BAR TERM T6 EACH 4
84 TR BAR TRM T1 SPL TAN EACH 4
85 GUARDRAIL REMOV FOOT 2,740
86 WOV W FENCE 4 FOOT 54
87 FUR ERECT ROW MARKERS EACH 15
88 ENGR FIELD OFFICE B CAL MO 6
89 MOBILIZATION L SUM 1
90 CHANGEABLE MESSAGE SN CAL DAY 28
91 SIGN PANEL T1 SQ FT 28
92 RELOC SIGN PANEL T1 SQ FT 8
93 RELOC SIGN PANEL T2 SQ FT 12
94 TERMINAL MARKER - DA EACH 4
95 TELES STL SIN SUPPORT FOOT 91
96 MOD URETH PM LTR-SYM SQ FT 147
97 MOD URETH PM LINE 4 FOOT 16,068
98 MOD URETH PM LINE 24 FOOT 39
99 GRDRAIL REF TYPE A EACH 38
100 BARR WALL REF TYPE B EACH 5
101 UNDRGRD C GALVS 1 1/4 FOOT 14
102 UNDRGRD C GALVS 3 FOOT 10
103 HD HANDHOLE EACH 1
104 CONC FDN TY D FOOT 3
105 DET LOOP T1 FOOT 72
106 T-CARYA OVATA 2-1/2 EACH 1
107 T-CELTIS OCCID 2-1/2 EACH 4
108 T-GYMNOCLA DIO 2-1/2 EACH 4
109 T-OSTRYA VIRG 2 EACH 3
110 T-QUERCUS BICOL 3 EACH 2
111 T-QUERCUS IMBR 3 EACH 1
112 CONCRETE PAD REM. SQ YD 6
113 DEWAT AND WATER DIVR LSUM 1
114 TEMP INFO SIGN EACH 2
115 OUTLET SPL EACH 4
116 EXIST FIELD TILE REM FOOT 172
117 WASHOUT BASIN L SUM 1
Printed 3/5/2019 Page 4-3 BLR 12200a (01/08/14)
Bidder's Proposal for making Entire Improvements
Unit Price
![Page 5: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/5.jpg)
Adden
dum #1
RETURN WITH BID
Item
No.Items Unit Quantity Total
118 REM EX SEPTIC TANK EACH 1
119 EXPLOR TRENCH SPL FOOT 100
120 TEMP ACCESS- FLD ENT EACH 5
121 HMA SURF REM VAR DP SQ YD 8,948
122 ABANDON FILL FIELD TILE FOOT 296
123 TRAF CONT & PROT (DETOUR) L SUM 1
124 SIGN SUPPORT SPL EACH 8
125 RELOCATE CONTR CABINT & SOL PWR A LSUM 1
126 GROUTED RIPRAP, CL A3 SQ YD 87
127 WATER WELL TO BE C&A EACH 1
128 PAVEMENT BREAKING SQ YD 3,586
129 STAB CONSTR ENTRANCE SQ YD 111
130 CONSTRUCTION LAYOUT L SUM 1
131 FENCE REMOVAL FOOT 63
132 LONG JOINT SEALANT FOOT 7,687
133 P UNDR FOR STRUCT 4 FOOT 141
134 GUARDRAIL REFLECTIVE PAINT STRIPE FOOT 3,203
135 TRANSVERSE RUMBLE STRIP SQ YD 251
136 SAW CUTTING (FD) FOOT 7,273
137 STAB DRIVEWAYS 10 SQ YD 582
138 TIMBER HDWAL REM FOOT 15
139 FIELD TILE CONNECT TO STR EACH 3
140 PAVEMENT CONTRACTION JOINT FOOT 3,276
141 ITEMS AS ORDERED BY THE ENGINEER UNIT 400,000 $400,000.00
Printed 3/5/2019 Page 4-4 BLR 12200a (01/08/14)
Bidder's Proposal for making Entire Improvements
Unit Price
$1.00
Total Cost
![Page 6: DIVISION of TRANSPORTATION...conc supstr app slab cu yd: 99.3 51 reinf bars, epoxy ctd: pound 94,160 52: fur m s pile 14x0.250 foot: 1,068 53 driving piles: foot 1,068 54: test pile](https://reader034.fdocuments.in/reader034/viewer/2022042216/5ebf057fcb616a244063c826/html5/thumbnails/6.jpg)
Adden
dum #1
Peplow Road Over Tributary CH 11 to Virgil Ditch No. 3 Sec. 08-00383-00-BR Kane County
30
DIVISION 300
CONTRACTOR DESIGNED MODIFIED SOIL Description: This item of work will require the Contractor to design the percent of lime in the soil to obtain the maximum compressive strength to be used in the processing of modified soil.
Minimum Testing Procedure. Take one soil sample for every 500 cubic yards of soil, one per major type of soil, or a minimum of three soil samples per project, whichever is greater. Take soil samples in locations, such as in the shoulder area of a subgrade to be stabilized, and at approximate equal intervals along the project work. Determine the percent of lime by using compressive strength tests performed on the soil lime cylinders prepared according to ASTM D 5102, Method B. Perform the compressive strength test on cylinders using a 5-day cure. Use a percentage of lime by dry weight of the soil of 0, 4, 6, and 8 for each soil sample. Make three soil cylinders for each percentage at the optimum moisture of the lime-soil mixture. Recommend the percentage of lime for the project that obtains the maximum strength in 5 days.
Submit four (4) copies of a report from the Contractor or his geotechnical consultant with all the data suitably presented to the Engineer for acceptance. The Contractor or his geotechnical consultant will make a formal recommendation to the Engineer for approval of the percentage to be used on the project. The Engineer may increase the percentage of lime chosen by the laboratory data by 1 percent to meet field variations.
Basis of Payment: The work to provide all sampling, testing, a documentation to provide the field verified percent of lime to be used in the soil modification will be paid for at the contract unit price Lump Sum for CONTRACTOR MODIFIED DESIGNED SOIL.
HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH Description. This work shall consist of removing, by rotomilling, with a machine and automatic grade control, according to Articles 440.03 and 440.04 of the Standard Specifications, the necessary existing bituminous material from the existing surface at locations indicated in the plans. The purpose of grinding is to remove the rutting in the existing bituminous surface and re-establish the required cross slope prior to paving the surface course. The milling limits and approximate depths of cuts are shown in the plans. It shall be the responsibility of the Contractor to verify the depth of cuts prior to the milling operation.
Basis of Payment. This work will be paid for at the contract unit price per Square Yard for HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH.
LIME MODIFIER Description. This work shall consist of providing a Lime soil modifier material determined as part of the Contractor mix design to be used in the processing of the modified soil.
Materials: The soil; modifiers materials shall be in accordance with the applicable portions of Section 1001, 1002, and 1012 of the Standard Specifications.
Lime shall be “Non-Hydrated Lime (Lime Kiln Dust)” in accordance with Section 1012.03 of the
Standard Specifications.
Basis of Payment: Supplying the material to be used in the soil modification processing will be at the contract unit price per Ton for LIME.