DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15...

106
DIVISION 15 MECHANICAL

Transcript of DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15...

Page 1: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

DIVISION 15

MECHANICAL

Page 2: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-1 Piping Schedule And General Piping Requirements

AECOM REBID

SECTION 15050A

PROCESS PIPING SCHEDULE AND GENERAL PIPING REQUIREMENTS

PART 1 - GENERAL

1.01 Description

This section describes the application of the Process Piping Schedule shown in the drawings and

the general requirements for selecting piping materials; selecting the associated bolts, nuts, and

gaskets for flanges for the various piping services in the project; and miscellaneous piping items.

This section applies to all piping except Mechanical (plumbing and HVAC) piping.

1.02 Submittals

A. Submit shop drawings in accordance with the General Conditions and Section 01300 and

the following:

B. Submit affidavit of compliance with referenced standards (e.g., AWWA, ANSI, ASTM,

etc.).

C. Submit certified copies of mill test reports for bolts and nuts, including coatings if

specified. Provide recertification by an independent domestic testing laboratory for

materials originating outside of the United States.

D. Submit manufacturer's data sheet for gaskets supplied showing dimensions and bolting

recommendations.

1.03 Definitions of Buried and Exposed Piping

A. Buried piping is piping buried in the soil, commencing at the wall or beneath the slab of a

structure. Where a coating is specified, provide the coating up to the structure wall. Unless

detailed otherwise, coating shall penetrate wall no less than 1 inch. Piping encased in

concrete is considered to be buried. Do not coat encased pipe.

B. Exposed piping is piping in any of the following conditions or locations:

1. Above ground.

2. Inside buildings, vaults, or other structures.

3. In underground concrete trenches or galleries.

1.04 Piping Service

Piping service is determined by the fluid conveyed, regardless of the pipe designation. For

example, pipes designated "Air Low Pressure," "Air High Pressure," and "Air" are all considered

to be in air service.

Page 3: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-2 Piping Schedule And General Piping Requirements

AECOM REBID

1.05 Default Piping Materials

If no material is shown in the drawings or in the Piping Schedule, use the following piping

materials:

Service

Size Range

(inches) Material Specification Section

Buried 3 and smaller Copper 15220

4 DIP 15240

6 and larger DIP 15240

Exposed 3 and smaller Copper 15220

4 DIP 15240

6 and larger DIP 15240

PART 2 - MATERIALS

2.01 Materials Selection and Alternative Materials

A. The Piping Schedule in the drawings lists the material and specification for each piping

service in the project. In locations where the piping material referenced on the Piping

Schedule is not appropriate, the piping material is indicated in the drawings. Materials

called out in the drawings shall govern over materials stated in the Piping Schedule.

B. The Piping Schedule in the drawings may show alternative piping materials for certain

services. In such cases, the same pipe material shall be used for all pipe sizes in all

locations for the given piping service. Do not intermix piping materials.

2.02 Thread Forming for Stainless Steel Bolts

Form threads by means of rolling, not cutting or grinding.

2.03 Bolts and Nuts for Flanges for Ductile-Iron Piping (Specification Sections 15240)

A. Bolts and nuts for Class 125 or 150 flanges (including AWWA C207, Class D) located

indoors, outdoors above ground, and in vaults and structures shall be carbon steel, ASTM

A307, Grade B, hot-dipped galvanized per ASTM F2329.

B. Bolts and nuts for buried or submerged Class 125 or 150 flanges shall be Type 304

stainless steel conforming to ASTM A193 (Grade B8) for bolts and ASTM A194 (Grade 8)

for nuts.

C. Bolts used in flange insulation kits shall conform to ASTM A193 (Grade B7). Nuts shall

conform to ASTM A194 (Grade 2H).

D. Provide washers for each nut. Washers shall be of the same material as the nuts.

Page 4: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-3 Piping Schedule And General Piping Requirements

AECOM REBID

2.04 Bolts and Nuts for Flanges for Carbon Steel and Stainless Steel Piping (Specification Sections

1530, and 15276)

A. Bolts and nuts for flanges shall be Type 304 stainless steel conforming to ASTM A193,

Grade B8 for bolts and ASTM A194, Grade 8 for nuts.

B. Bolts for piping in sodium hypochlorite service shall be titanium, per ASTM F467, Grade

Ti1, Ti2, or Ti7. Nuts shall conform to ASTM F467, same material as the bolts.

C. Hex head machine bolts for use with lugged valves shall comply with ASTM A193, Grade

B8, Class 2.

D. Provide washer for each nut. Washers shall be of the same material as the nuts.

2.05 Bolts and Nuts for Flanges for PVC, and CPVC, Pipe (Specification Sections 15290and 15292

A. Bolts and nuts for flanges located indoors, outdoors above ground, and in vaults and

structures shall be carbon steel, ASTM A307, Grade B, hot-dipped galvanized per ASTM

F2329.

B. Bolts and nuts for buried and submerged flanges shall be Type 304 stainless steel

conforming to ASTM A193, Grade B8 for bolts and ASTM A194, Grade 8 for nuts.

2.06 Bolts and Nuts for Flanges for Copper Tubing (Specification Section 15220)

A. Connect to flanged valves and fittings with bronze flanges conforming to ASME B16.24,

Class 125 or Class 150, to match the connecting flange. Use solder end companion flanges.

B. When both aboveground adjoining flanges are bronze, use bronze bolts and nuts. Bolts

shall conform to ASTM F468, Grade C65100 or C63000. Nuts shall conform to ASTM

F467, Grade C65100 or C63000.

C. When only one of the aboveground adjoining flanges is bronze, use Type 316 stainless

steel bolts and nuts conforming to ASTM A193 (Grade B8M) for bolts and ASTM A194

(Grade 8M) for nuts.

E. Connect to buried ferrous flanges with flange insulation kits. Bolts used in flange

insulation kits shall conform to ASTM A193, Grade B7. Nuts shall comply with ASTM

A194, Grade 2H. If the adjoining buried flange is bronze, use bronze bolts and nuts as

described above, without a flange insulation kit.

F. Provide washers for each nut. Washers shall be of the same material as the nuts.

2.07 Lubricant for Stainless Steel Bolts and Nuts

Lubricant shall be chloride free and shall be RAMCO TG-50, Anti-Seize by RAMCO, Specialty

Lubricants Corporation Husky Lube O'Seal, or equivalent.

2.08 Gaskets for Flanges for Steel Piping in Water Service (Specification Sections 15253)

A. Gaskets for flat face and raised face flanges shall be 1/8-inch thick and shall be one of the

following nonasbestos materials:

Page 5: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-4 Piping Schedule And General Piping Requirements

AECOM REBID

1. Acrylic or aramid fiber bound with nitrile. Products: Garlock "Bluegard," Klinger

"Klingersil C4400," or equal. Gaskets shall be suitable for a pressure of 500 psi at a

temperature of 400°F.

2.09 Gaskets for Flanges for Steel Piping in Raw Sewage, Sludge, and Scum Service (Specification

Section 15253)

Gaskets shall be full face, 1/8-inch thick, and shall be one of the following nonasbestos materials:

A. Buna-N having a hardness of 55 to 65 durometer. Gaskets shall be suitable for a water

pressure of 200 psi at a temperature of 180°F. Products: Garlock Style 9122 or equivalent.

B. Acrylic or aramid fiber bound with nitrile. Products: Garlock "Bluegard," Klinger

"Klingersil C4400," or equivalent. Gaskets shall be suitable for a water pressure of 500 psi

at a temperature of 400°F.

2.10 Gaskets for Flanges for Ductile-Iron Piping and Fittings in Water Service (Specification Sections

15240

Gaskets shall be full face, 1/8-inch thick, cloth-inserted rubber, with a Shore "A" hardness of 75

to 85. Gaskets shall be suitable for a water pressure of 200 psi at a temperature of 180°F. Gaskets

shall have "nominal" pipe size inside diameters not the inside diameters per ASME B16.21.

Products: Garlock Style 19 or equivalent.

2.11 Gaskets for Flanges for Ductile-Iron Piping and Fittings in Raw Sewage, Sludge, and Scum

Service (Specification Section 15240)

Gaskets shall be full face, 1/8-inch thick, Buna-N having a hardness of 55 to 65 durometer.

Gaskets shall be suitable for a water pressure of 200 psi at a temperature of 250°F. Gaskets shall

have "nominal" pipe size inside diameters not the inside diameters per ASME B16.21. Provide

Garlock Style 9122 or equivalent.

2.12 Gaskets for Flanges for Copper Tubing and Piping for Air and Water Service (Specification

Section 15220)

Gaskets shall be full face, 1/8-inch thick, and shall be one of the following nonasbestos materials:

A. Cloth-inserted rubber with a Shore "A" hardness of 75 to 85. Gaskets shall be suitable for a

pressure of 200 psi at a temperature of 180°F. Products: Garlock Style 19 or equivalent.

B. Acrylic or aramid fiber bound with nitrile. Products: Garlock "Bluegard," Klinger

"Klingersil C4400," or equivalent. Gaskets shall be suitable for a pressure of 500 psi at a

temperature of 400°F.

2.13 Gaskets for Flanges for PVC and CPVC Piping (Specification Sections 15290, and 15294)

Gaskets for flanged joints shall be full faced, 1/8-inch thick, having a hardness of 50 to 70

durometer A. Gasket material for other than sodium hypochlorite service shall be EPR. Gasket

material for sodium hypochlorite service shall be Viton ETP.

Page 6: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-5 Piping Schedule And General Piping Requirements

AECOM REBID

2.14 Gaskets for Flanges for Stainless Steel Piping (Specification Section 15276)

Gaskets shall be full face, 1/8-inch thick. Gaskets shall be one of the following nonasbestos

materials:

A. Cloth-inserted rubber, with a Shore "A" hardness of 75 to 85. Gaskets shall be suitable for

a pressure of 200 psi at a temperature of 180°F. Products: Garlock Style 19 or equivalent.

B. Acrylic or aramid fiber bound with nitrile. Products: Garlock "Bluegard," Klinger

"Klingersil C4400," or equivalent. Gaskets shall be suitable for a water pressure of 500 psi

at a temperature of 400°F.

Remove the raised face of the mating flange.

2.15 Flange Insulation Kits

See Section 13110.

2.16 Insulating Unions

See Section 264213.

PART 3 - EXECUTION

3.01 Installing Pipe Spools in Concrete

Install pipes in walls and slabs before placing concrete. See Sections 03300 and 15062.

3.02 Raised Face and Flat Face Flanges

Where a raised face flange connects to a flat-faced flange, remove the raised face of the flange.

3.03 Installing Aboveground or Exposed Piping

A. Provide pipe hangers and supports as detailed in the drawings and as specified in Section

15064.

B. Install pipe without springing, forcing, or stressing the pipe or any adjacent connecting

valves or equipment.

3.04 Installing Flanged Piping

A. Set pipe with the flange bolt holes straddling the pipe horizontal and vertical centerline.

Install pipe without springing, forcing, or stressing the pipe or any adjacent connecting

valves or equipment. Before bolting up, align flange faces to the design plane within 1/16

inch per foot measured across any diameter. Align flange bolt holes within 1/8-inch

maximum offset.

B. Inspect each gasket to verify that it is the correct size, material, and type for the specified

service and that it is clean and undamaged. Examine bolts or studs, nuts, and washers for

defects such as burrs or cracks and rust and replace as needed.

Page 7: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15050A-6 Piping Schedule And General Piping Requirements

AECOM REBID

C. Clean flanges by wire brushing before installing flanged fittings. Clean flange bolts and

nuts by wire brushing, lubricate carbon steel bolts with oil and graphite, and tighten nuts

uniformly and progressively.

D. Bolt lengths shall extend completely through their nuts. Any that fail to do so shall be

considered acceptably engaged if the lack of complete engagement is not more than one

thread.

E. Do not use more than one gasket between contact faces in assembling a flanged joint.

F. Tighten the bolts to the manufacturer’s specifications, using the recommended cross bolt

pattern in multiple steps of increasing torque, until the final torque requirements are

achieved. Do not over torque.

G. If flanges leak under pressure testing, loosen or remove the nuts and bolts, reset or replace

the gasket, reinstall or retighten the bolts and nuts, and retest the joints. Joints shall be

watertight.

3.05 Installing Blind Flanges

A. At outlets not indicated to be connected to valves or to other pipes and to complete the

installed pipeline hydrostatic test, provide blind flanges with bolts, nuts, and gaskets.

B. Coat the inside face of blind flanges per Section 09900, System No. 7.

3.06 Installing Grooved-End Piping

A. Install grooved-end pipe and fittings in accordance with the coupling manufacturer's

recommendations and the following.

B. Clean loose scale, rust, oil, grease, and dirt from the pipe or fitting groove before installing

coupling. Apply the coupling manufacturer's gasket lubricant to the gasket exterior

including lips, pipe ends, and housing interiors.

C. Fasten coupling alternately and evenly until coupling halves are seated. Use torques as

recommended by the coupling manufacturer.

D. Provide separate hangers and supports at both sides of flexible joints; see Section 15064.

3.07 Installation of Stainless Steel Bolts and Nuts

Prior to assembly, coat threaded portions of stainless steel bolts and nuts with lubricant.

END OF SECTION

Page 8: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-1 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

SECTION 15062

WALL PIPES, SEEP RINGS, AND PENETRATIONS

PART 1 - GENERAL

1.01 Description

This section includes materials, installation, and testing of steel, cast-iron, and ductile-iron wall

pipes and sleeves (including wall collars and seepage rings) and penetrations.

1.02 Related Work Specified Elsewhere

A. Concrete Formwork: 03100.

B. Concrete: 03300.

C. Painting and Coating: 09900.

D. Fusion-Bonded Epoxy Linings and Coatings: 09961.

E. Piping Schedule and General Piping Requirements: 15050A.

1.03 Submittals

A. Submit detail drawings for fabricated steel or cast-iron wall and floor pipes and sleeves,

wall flanges, seep rings, and sealing materials. Show dimensions and wall thicknesses.

B. Show flange sizes and the appropriate ANSI or AWWA flange dimensional standard

where flanged end wall pipes or penetrations are used.

C. Show grooved-end dimensions and AWWA grooved-end dimensional standard where

grooved-end wall pipes or penetrations are used.

D. List coating systems to be applied, manufacturer, and dry thickness of coatings. Call out

coatings where coatings are to be applied.

E. List materials of construction, with ASTM material reference and grade.

F. Submit manufacturer's instructions for installing rubber annular hydrostatic sealing

devices.

PART 2 - MATERIALS

2.01 General

A. Use only cast-iron or ductile-iron wall pipes when connecting to cast-iron and ductile-iron

pipe. Use only fabricated steel wall pipes when connecting to steel pipe.

Page 9: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-2 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

B. Cast-iron flanges shall conform to ASME B16.1, Class 125 or 250, to match the flange on

the connecting pipe.

C. Class 150 steel flanges shall conform to AWWA C207, Class D. Flanges shall be flat face.

Flanges shall match the flange on the connecting pipe.

D. See Section 05050 for flange bolts and gaskets.

2.02 Cast-Iron or Ductile-Iron Wall Pipes and Sleeves

A. Provide cast- or ductile-iron wall pipes with ends as shown in the drawings for connection

to adjacent cast-iron and ductile-iron pipe or for containing pipes where they pass through

concrete walls, ceilings, and floor slabs. Provide seepage ring on wall pipes and sleeves

passing through concrete walls and slabs that are to be watertight. Locate collars such that

the collar is at the center of the wall or floor slab, unless otherwise shown in the drawings.

B. Wall pipes and sleeves shall be of the following types:

1. Pipe or sleeve with integrally cast seep ring.

2. Pipe or sleeve with shrink-fit steel collar attached.

3. Pipe or sleeve with steel collar halves bottomed in a groove provided in the pipe or

sleeve.

C. Minimum wall thickness for pipes and sleeves having integrally cast seep rings shall be as

shown in the following table:

Pipe or Sleeve Size

(inches)

Minimum Wall Thickness

(inches)

3 0.48

4 0.52

6 0.55

8 0.60

10 0.68

12 0.75

14 0.66

16 0.70

18 0.75

20 0.80

24 0.89

D. Minimum wall thickness of pipes or sleeves having shrink-fit collars shall be special Class

52. Cut shrink-fit collars from a 1/4-inch-thick steel ring. Attach the collar to a cast-iron or

ductile-iron pipe or sleeve by heating the steel collar and allowing it to shrink over the pipe

at the necessary location. Provide an epoxy bond (Keysite 740 or 742 or Scotchkote 302)

Page 10: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-3 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

between the pipe and collar. Sandblast the area of the pipe to be epoxy coated per SSPC

SP-10.

E. Wall pipes or sleeves having steel collar halves bottomed in a groove shall be ductile iron

Special Class 54 minimum unless otherwise shown. Wall flanges shall consist of 1/4-inch-

thick steel seep ring halves for pipes through 24-inch and 3/8-inch-thick halves for pipe 30

inches and larger, bottomed in a groove provided on the pipe. The pipe groove shall be

machine cut to a depth of 1/16 to 5/64 inch to provide a press fit for the seep ring. Seep

ring halves shall be welded together after fit into groove but shall not be welded to pipe.

Seep rings shall be sealed completely around the pipe with silicon sealant manufactured by

Dow-Corning No. 790, General Electric Silpruf, or equivalent.

F. The material used in cast- or ductile-iron wall flanges, wall sleeves, and wall penetrations

shall conform to ASTM A395, A436, A536, A48 (Class 35), or A126 (Class B).

2.03 Fabricated Steel Wall Pipes and Sleeves

A. Provide fabricated steel wall pipes and sleeves with ends as shown in the drawings for

connection to adjacent steel pipes, or for containing pipes, where they pass through

concrete walls. Provide seepage ring or wall flange on wall pipes and sleeves passing

through concrete walls and slabs that are to be watertight. Wall thickness shall be the same

as the pipe wall thickness when connecting to steel pipe. Minimum wall thickness for

sleeves containing pipes shall be standard weight per ASME B36.10 for sleeves 72 inches

and smaller and 1/2 inch for sleeves greater than 72 inches through 96 inches.

B. Wall flanges shall be in the form of a steel wall collar welded to the steel sleeve or

penetration. Cut welded wall collars from a 1/4-inch steel ring. Attach the collar to a steel

wall pipe or sleeve with full circle, 3/16-inch fillet welds. Welding procedures shall be in

accordance with ASME B31.3, Chapter V.

C. Steel pipe used in fabricating wall sleeves containing pipes shall comply with ASTM A53

(Type E or S), Grade B; ASTM A135, Grade B; ASTM A139, Grade B; or API 5L or 5LX.

Wall pipes connecting to steel pipe shall be of the same material as the connecting pipe.

Wall collar material shall comply with ASTM A36, A105, A181, or A182.

2.04 Rubber Annular Hydrostatic Sealing Devices

A. Rubber annular hydrostatic sealing devices shall be of the modular mechanical type,

utilizing interlocking synthetic rubber links shaped to continuously fill the annular space

between the pipe sleeve and the passing pipe. Assemble links to form a continuous rubber

belt around the pipe, with a pressure plate under each bolthead and nut.

B. Materials of construction shall be as follows:

Compound Material

Pressure plate Delrin plastic or reinforced nylon polymer

Bolts and nuts for links Type 303 or 316 stainless steel

Sealing element Nitrile rubber

Page 11: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-4 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

C. The size of the wall sleeve needed to accommodate the passing pipe shall be as

recommended by the rubber annular seal manufacturer.

D. Provide centering blocks in 25% of the sealing elements on pipelines larger than 12 inches

in diameter.

E. The rubber annular hydrostatic sealing devices shall be Link Seal as manufactured by

Thunderline Corporation; Innerlynx as manufactured by Advance Products & Systems,

Inc.; or equivalent.

2.05 Bolts, Nuts, and Gaskets for Flanged-End Wall Pipes

See Section 15050A.

2.06 Polyethylene Foam Filler for Pipe Penetrations

Packing foam shall be an extruded closed-cell polyethylene foam rod, such as Minicel backer rod,

manufactured by Industrial Systems Department, Plastic Products Group of Hercules, Inc.,

Middletown, Delaware; Ethafoam, as manufactured by Dow Chemical Company, Midland,

Michigan; or equivalent. The rod shall be 1/2 inch larger in diameter than the annular space.

2.07 Polyurethane Sealant for Pipe Penetrations

Sealant shall be multipart, polyurethane sealant, to cure at ambient temperature, for continuous

immersion in water. Install as recommended by the manufacturer. Products: SIKA Sikaflex 2C or

equivalent.

2.08 Painting and Coating

A. Coat penetrations and sleeves exposed, above ground, or in vaults and structures in

accordance with Section 09900, System No. 10 unless fusion-bonded epoxy coatings per

Section 09961 are shown in the drawings or specified elsewhere.

B. Coat submerged sleeves and penetrations per Section 09900, System No. 7 unless fusion-

bonded epoxy coatings per Section 09961 are shown in the drawings or specified

elsewhere.

C. Coat buried sleeves and penetrations per Section 09900, System No. 7 or with fusion-

bonded epoxy per Section 09961.

D. Do not coat stainless steel sleeves and penetrations.

PART 3 - EXECUTION

3.01 Location of Pipes and Sleeves

A. Provide a wall or floor pipe where shown in the drawings and wherever piping passes

through walls or floors of tanks or channels in which the water surface is above the pipe

penetration.

Page 12: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-5 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

B. Provide a floor sleeve where shown in the drawings and wherever plastic pipe, steel, or

stainless steel pipe 3 inches and smaller or stainless steel or copper tubing passes through a

floor or slab. Provide a rubber annular sealing device in the annular space between the

sleeve and the passing pipe or tubing.

C. Provide wall sleeves where shown in the drawings and wherever plastic, steel or stainless

steel pipe 3 inches and smaller, or stainless steel or copper tubing passes through a wall.

Provide a single rubber annular seal when the wall is 8 inches thick or less. Provide two

rubber annular seals (one at each end of the sleeve) when the wall is more than 8 inches

thick.

D. Where wall sleeves are installed in which water or soil is on one or both sides of the

channel or wall, provide two rubber annular seals (one at each end of the sleeve).

E. Where pipes pass through walls or slabs and no sleeves or wall or floor pipe with seep ring

is provided, pack the annular space with polyethylene foam filler and fill the ends of the

penetration with 2 inches of elastomeric sealant on both sides of the structure.

3.02 Installation in Existing Concrete Walls and Slabs

Core drill holes 1 to 2 inches larger in diameter than the outside diameter of the wall flange or

collar. Install wall pipe and collar assembly axially aligned with the piping to which it will be

connected or will contain. Pack the void space between the sleeve and concrete with grout. See

Section 03300 for grouting specification.

3.03 Installation in New Concrete Walls and Slabs

Install wall pipes and sleeves in walls before placing concrete. Do not allow any portion of the

pipe or sleeve to touch any of the reinforcing steel. Install wall pipe or sleeve and collar assembly

axially aligned with the piping to which it will be attached or will contain. Provide supports to

prevent the pipe or sleeve from displacing or deforming while the concrete is being poured and is

curing.

3.04 Installation in Dry Floors and Slabs

Install pipe sleeves and spools in concrete floors and slabs which do not have water over them

such that the sleeve or pipe extends from the bottom of the floor or slab to 2 inches above the

floor or slab unless shown otherwise in the drawings.

3.05 Installation of Wall Pipes Having Flanged End Connections

A. Check alignment before grouting in place or pouring concrete. Realign if the sleeve is not

properly aligned.

B. Install flanged end wall sleeves or penetrations with bolt holes of the end flanges straddling

the horizontal and vertical centerlines of the sleeve.

3.06 Qualifications of Welders

Welder qualifications shall be in accordance with AWS D1.1.

Page 13: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 04/2010 15062-6 Wall Pipes, Seep Rings, And Penetrations

AECOM 60096414

3.07 Installation of Rubber Annular Hydrostatic Sealing Devices

Install in accordance with the manufacturer's instructions.

3.08 Field Testing

Check each wall penetration for leakage at the time the hydraulic structure is tested for leakage;

see Section 03300. Penetrations shall show zero leakage.

END OF SECTION

Page 14: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-1 Pipe Hangers And Supports

AECOM REBID

SECTION 15064

PIPE HANGERS AND SUPPORTS

PART 1 - GENERAL

1.01 Description

This section includes materials and installation of pipe hangers and supports including accessory

items, such as anchor bolts and screws, neoprene isolation pads.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Fusion-Bonded Epoxy Linings and Coatings: 09961.

C. Wall Pipes, Seep Rings, and Penetrations: 15062.

D. Flexible Pipe Couplings and Expansion Joints: 15122.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Provide line drawings of each piping system to the scale shown in the drawings, locating

each support or hanger. Identify each type of hanger or support by the manufacturer's

catalog number or figure.

C. Provide installation drawings and manufacturer's catalog information on each type of

hanger and support used. Clearly indicate the actual pipe outside diameter (not just

nominal pipe size) that is used for the hangers and supports.

PART 2 - MATERIALS

2.01 Design Criteria

A. Not all pipe supports or hangers required are shown in the drawings. Provide pipe supports

for every piping system installed. Support piping by pipe support where it connects to

pumps or other mechanical equipment.

B. Pipe support and hanger components shall withstand the dead loads imposed by the weight

of the pipes, fittings, and valves (all filled with water), plus valve actuators and any

insulation, and shall have a minimum safety factor of five based on material ultimate

strength.

Page 15: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-2 Pipe Hangers And Supports

AECOM REBID

2.02 Hanger and Support Systems

A. Pipe hangers and supports shall be as manufactured by Anvil, Unistrut, B-Line, Superstrut,

or equivalent.

B. Pipe hangers and supports shall comply with MSS SP-58 for the standard types referenced

in the drawings. Construct special hangers and supports if detailed in the drawings. Type

numbers for standard hangers and supports shall be in accordance with MSS SP-58 as

listed below:

Type

Number Description

Manufacturer and Model

(or Equal)

1 Adjustable steel clevis Anvil Fig. 590 or 260, B-Line B3100

or B3102

3 Steel double-bolt pipe clamp Anvil Fig. 295A or 295H, B-Line

B3144 or B3144A

4 Steel pipe clamp (pipes smaller than 3

inches)

Anvil Fig. 212, B-Line B3140

4 Steel pipe clamp (pipes 3 inches and

larger)

Anvil Fig. 216, B-Line 3142

5 Pipe hanger B-Line B6690

6 Adjustable swivel pipe ring Anvil Superstrut 714, Anvil Fig. 104

7 Adjustable steel band hanger B-Line B3172

8 Extension pipe or riser clamp Anvil Fig. 261, B-Line B5573

9 Adjustable band hanger Anvil Fig. 97

10 Adjustable swivel ring band hanger Anvil Fig. 70, B-Line B3170 NF

11 Split pipe ring with adjustable

turnbuckle

Anvil Fig. 108, B-Line B3173

13 Steel turnbuckle Anvil Fig. 230, B-Line B3202

14 Steel clevis Anvil Fig. 299, B-Line B3201

15 Swivel turnbuckle Anvil Fig. 114, B-Line B3224

16 Malleable iron socket Anvil Fig. 110R, B-Line B3222

17 Steel weldless eye nut B-Line B3200

18 Steel or malleable iron concrete insert Anvil Fig. 281, Superstrut 452

19 Top beam C-clamp Anvil Fig. 92, B-Line B3033

20 Side I-beam or channel clamp Anvil Fig. 14 or 217

21 Center I-beam clamp Anvil Figure 134

22 Welded attachment type Anvil Fig. 66 B-Line B3083

23 C-clamp Anvil Fig. 86, B-Line B3036L

24 U-bolt Anvil Fig. 137, B-Line B3188

26 Clip Anvil Fig. 262, B-Line B3180

28 Steel I-beam clamp with eye nut Anvil Fig. 228

Page 16: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-3 Pipe Hangers And Supports

AECOM REBID

Type

Number Description

Manufacturer and Model

(or Equal)

29 Steel wide flange Anvil Fig. 228 clamp with eye nut

30 Malleable iron beam clamp with

extension piece

Superstrut CM-754, B-Line B3054

31 Light welded steel bracket Anvil Fig. 194, B-Line B3063

32 Medium welded steel bracket Anvil Fig. 195, B-Line B3066

33 Heavy welded steel bracket Anvil Fig. 199, B-Line B3067

34 Side beam bracket Anvil Fig. 202, B-Line B3062

36 Pipe saddle support Anvil Fig. 258, B-Line B3095

37 Pipe stanchion saddle Anvil Fig. 259, B-Line B3090

38 Adjustable pipe saddle support Anvil Fig. 264, B-Line B3089

39 Steel pipe covering Anvil Fig. 160, 161, 162, 163, 164, or

165; Superstrut A 789; B-Line

B3160/B3165

40 Insulation protection shield Anvil Fig. 167, B-Line B3151

41 Single pipe roll Anvil Fig. 171, B-Line B3114

43 Adjustable roller hanger with swivel Anvil Fig. 181, B-Line B3110

44 Pipe roll, complete Anvil Fig. 271, B-Line B3117SL

C. Pipe hangers and supports shall be plain carbon steel (ASTM A36, A575, or A576). Bases,

rollers, and anchors shall be steel as described above or may be cast iron (ASTM A48).

Pipe clamps shall be steel as described above or may be malleable iron (ASTM A47).

2.03 Offset Pipe Clamp

Anvil Figure 103 or equivalent. Material shall be carbon steel.

2.04 Miscellaneous Pipe Supports and Hangers

A. Pipe Anchor Chair: Anvil Figure 198 or equivalent.

B. One Hole Clamp: Anvil Figure 126 or equivalent.

C. Roller Chair: Anvil Figure 175 or equivalent.

2.05 Steel Channel Framing System

A. Steel channel frames shall be 1 5/8 inches wide by 1 5/8 or 3 1/4 inches high by 12-gauge

metal thickness, unless otherwise shown in the drawings. Material shall conform to ASTM

A36, A570 (Grade 33 minimum), or A653. One side of the channel shall have a continuous

open slot with inturned clamping ridges. Maximum allowable stress under any

combination of applied uniformly distributed loads and concentrated loads shall not exceed

those recommended in the AISC or AISI. Deflection shall not exceed 1/240 of span. Use

multiple back-to-back channels to achieve these criteria if single channels are not

Page 17: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-4 Pipe Hangers And Supports

AECOM REBID

sufficient. Products: Unistrut P1000 or P5000 Series, B-Line B11 or B22 Series, or

equivalent.

B. Select galvanized, plain, PVC, or fusion-bonded epoxy coating option in paragraph E.2.

C. Steel channels shall be coated with fusion-bonded epoxy per Section 09961.

D. Nuts shall be machined and case hardened. Provide rectangular nuts with the ends shaped

to permit a quarter turn crosswise in the framing channel. Provide two serrated grooves in

the nut to engage the inturned edges of the channel.

E. Pipe clamps (including attachment screws and nuts) shall be Unistrut P1100 or P2000

Series, B-Line B2000 Series, or equivalent. Material shall be Type 304 stainless steel.

F. Hanger rods for trapezes shall be carbon steel (ASTM A36, A575, or A576).

G. Accessory fittings and brackets shall be the same material as the channel or trapeze.

Provide coating on carbon steel fittings and brackets as specified for the channels and

frames.

1. Flat Plate Fittings: Unistrut P1065, P1066, P1925; Superstrut AB-206, AB-207; or

equivalent.

2. Post Bases: Unistrut P2072A, Superstrut AP-232, or equivalent.

3. 90-Degree Brackets: Unistrut P1326, P1346; Superstrut AB-203; or equivalent.

4. Rounded-End Flat Plate Fittings: Unistrut P2325, Superstrut X-240, or equivalent.

H. Parallel pipe clamps shall be Unistrut P1563 through P1573, Superstrut AB-719, or

equivalent. Material shall be carbon steel, coated as specified for channels and frames.

2.06 FRP Channel Framing System

A. FRP pipe hangers and supports shall be Aickinstrut, Inc., or equivalent.

B. Material properties shall be as follows:

Longitudinal Direction

Ultimate Tensile (psi) 35,000 minimum

Ultimate Compressive (psi) 35,000 minimum

Ultimate Flexural (psi) 35,000 minimum

Tensile Modulus (psi) 3.0 x 106 minimum

Flexural Modulus (psi) 2.0 x 106 minimum

Ultimate Shear Strength (psi) 6,000 minimum

Izod Impact (ASTM D256) ft-lb/inch notch 30 minimum

Page 18: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-5 Pipe Hangers And Supports

AECOM REBID

Transverse Direction

Ultimate Tensile (psi) 10,000 minimum

Ultimate Compressive (psi) 20,000 minimum

Ultimate Flexural (psi) 14,000 minimum

Tensile Modulus (psi) 1.0 x 106 minimum

Compressive Modulus (psi) 1.4 x 106 minimum

Flexural Modulus (psi) 1.0 x 106 minimum

Ultimate Shear Strength (psi) 5,500 minimum

Ultimate Bearing Stress (psi) 35,000 minimum

Izod Impact, ft-lb notch 5 minimum

Hardness

Barcol Test 50 minimum

C. Glass fiber reinforced composites and plastic products shall have a flame spread rating of

25 or less when tested per ASTM E84.

D. Channel framing shall be 1 5/8 inches deep by 1 5/8 inches wide and shall be made using

vinylester resin equivalent to Derakane 411, Ashland Hetron 922, or Reichhold Dion 9800.

It shall have a nexus polyester surfacing veil over 100% of the surface which, along with a

filler system, will protect against degradation from ultraviolet light. Channel shall be

supplied with integral notches 1 inch on center. Notches shall be located on the interior

flange to prevent slippage of pipe clamps and fittings after installation. In place of notched

channel, unnotched channel may be used if the vertical channel sections supporting the

horizontal piping are provided with stop lock hardware at each pipe clamp to prevent

slippage. Channel framing shall be Aickinstrut G.R.P. Type V 200 series or equivalent.

E. Channel framing connections shall be made with vinylester glass fiber composite nuts,

bolts, all threaded rods, channel fittings, bases, and hanger assemblies. Nuts, bolts, and

rods shall be Aickinstrut 4200 series, Strut Tech PVCG, or equivalent. Channel fittings

shall be Aickinstrut 2800 style or equivalent.

F. Load-bearing pipe clamps and nonload-bearing pipe straps shall be nonmetallic and

nonconductive and shall be made by the injection molding process using polyurethane base

resin. Pipe clamps and straps shall be Aickinstrut 3100 series or equivalent.

G. Clevis hangers shall be made with vinylester glass fiber and be Aickinstrut 1500 series or

equivalent.

H. Hanger rods for trapezes shall be carbon steel (ASTM A36, A575, or A576).

2.07 Waffle Isolation Pads

Mason Type "W"; Machinery Installation Systems "Unisorb" Type S, SB, F, or FB; or equivalent.

Provide minimum 1/4-inch thickness.

Page 19: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-6 Pipe Hangers And Supports

AECOM REBID

2.08 Anchor Bolts and Screws

Anchor bolts and screws for attaching pipe supports and hangers to walls, floors, ceilings, and

roof beams shall be hot-dipped galvanized steel, ASTM A307. Nuts shall be galvanized steel,

ASTM A563.

PART 3 - EXECUTION

3.01 Pipe Hanger and Wall Support Spacing

Install pipe hangers and wall supports on horizontal and vertical runs at the spacing shown or

detailed in the drawings. Provide hanger rods (for horizontal runs) and wall supports of the sizes

shown or detailed in the drawings. If no spacing or rod sizes are given in the drawings or in the

specifications for a particular piping system, use the following:

A. Pipe Hanger and Wall Support Spacing for Steel and Ductile-Iron Pipe (Sections 15230,

15240, 15253):

Pipe Size

(inches)

Maximum Support or

Hanger Spacing

(feet)

Minimum Rod Size

(inches)

3/8 and smaller 4 3/8

1/2 through 1 6 3/8

1 1/4 through 2 8 3/8

2 1/2 and 3 10 1/2

3 1/2 and 4 10 5/8

6 12 3/4

8 12 7/8

10 and 12 14 7/8

14 and 16 16 1

18 15 1

20 through 24 9 1

30 6 1

B. Pipe Hanger or Wall Support Spacing for PVC and CPVC Pipe (Sections 15290, and

15294):

Page 20: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-7 Pipe Hangers And Supports

AECOM REBID

Pipe Size

(inches)

Maximum Support or Hanger

Spacing

(feet)

Minimum Rod Size

(inches)

3/4 4 3/8

1 4 3/8

1 1/2 5 3/8

2 5 3/8

2 1/2 5 1/2

3 6 1/2

C. Pipe Hanger or Wall Support Spacing for Copper Tubing and Pipe (Section 15220):

Pipe Size

(inches)

Maximum Support or

Hanger Spacing

(feet)

Minimum Rod Size

(feet)

1 and smaller 4 3/8

1 1/4 through 2 6 3/8

2 1/2 through 3 8 1/2

3.02 Pipe Support Spacing for Supports on Top of Slabs or Grade

Install pipe supports on horizontal runs at the spacing shown or detailed in the drawings. Provide

supports of the type shown or detailed in the drawings. If no spacings are given in the drawings or

in the specifications for a particular piping system, use the following:

A. Pipe Support Spacing for Steel and Ductile-Iron Pipe (Sections 15230, and 15240):

Pipe Size

(inches)

Maximum Support Spacing

(feet)

3/8 and smaller 4

1/2 through 1 6

1 1/4 through 2 8

2 1/2 and 3 10

3 1/2 and 4 10

6 12

8 12

10 and 12 14

14 and 16 16

18 16

20 through 24 18

30 18

Page 21: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15064-8 Pipe Hangers And Supports

AECOM REBID

B. Pipe support spacing for other pipe materials shall be the same as described above in

paragraph entitled “Pipe Hanger and Wall Support Spacing.”

3.03 Installing Pipe Hangers and Supports

A. Provide separate hangers or supports at each valve. Provide one hanger or support around

each end of the valve body or on the adjacent connecting pipe within one pipe diameter of

the valve end. Provide additional hangers or supports to relieve eccentric loadings imposed

by offset valve actuators.

B. Provide separate hangers or supports at each pipe elbow, tee, or fitting. Provide separate

hangers or supports on both sides of each nonrigid joint or flexible pipe coupling.

C. Adjust pipe hangers per MSS SP-89, paragraph 10.6.

D. Install leveling bolts beneath support baseplates. Provide 3/4-inch thick grout pad beneath

each base.

E. Install piping without springing, forcing, or stressing the pipe or any connecting valves,

pumps, and other equipment to which the pipe is connected.

3.04 Installing Steel and FRP Channel Frames

A. Use 1-5/8-inch-high channel frames unless 3-1/4-inch is needed to provide clearance from

walls. Use multiple back-to-back channels if additional clearance is needed.

B. Seal the ends of cut FRP channel frames with the channel manufacturer’s sealant or resin.

3.05 Installing Neoprene Isolating Sleeves

Install a sleeve around each metal pipe 6 inches and smaller at the point of bearing or contact with

the pipe hanger or support.

3.06 Painting and Coating

A. Grind welds of fabricated steel pipe supports smooth, prepare surface by sandblasting, and

apply coating system.

B. Paint exposed pipe hangers and supports to match the color of the adjacent wall using

System No. 10 per Section 09900. If the adjacent wall is not painted, paint the hangers and

supports to match color code of the largest pipe on the support.

C. Coat submerged pipe hangers and supports per Section 09900, System No. 7 or 1.

END OF SECTION

Page 22: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-1 Equipment, Piping, & Valve Identification

AECOM REBID

SECTION 15075

EQUIPMENT, PIPING, AND VALVE IDENTIFICATION

PART 1 - GENERAL

1.01 Description

This section includes materials and installation of markers, labels, and signs for pipes, ducts, and

valves; for mechanical equipment; for hazardous materials warnings; and for miscellaneous plant

services.

1.02 Related Work Specified Elsewhere

Painting and Coating: 09900.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit manufacturer's catalog data and descriptive literature describing materials, colors,

letter size, and size of labels.

PART 2 - MATERIALS

2.01 Labels for Exposed Piping

A. Labels for piping shall bear the full piping system name as shown in the Piping Schedule

and/or in the drawings. Provide separate flow directional arrows next to each label. Color,

size, and labeling shall conform to ANSI A13.1 and Z535.1. Labels for piping inside

buildings shall be vinyl cloth: W. H. Brady Co. B-500 vinyl cloth, Seton Name Plate

Corporation Pipe Markers, or equivalent. Labels for piping located outdoors shall be

weather- and UV-resistant acrylic plastic and shall be W. H. Brady Co. B-946, Seton Name

Plate Corporation Pipe Markers, or equivalent.

B. Alternatively, provide preprinted, semirigid, snap-on, color-coded pipe markers. Color,

size, and labeling shall conform to ANSI A13.1 and Z535.1. Label shall cover 360 degrees

(minimum). Labels shall be fabricated of weather- and UV-resistant acrylic plastic. Labels

shall be Seton Nameplate Corporation SetMark pipe marks or equivalent.

2.02 Labels for Exposed Valves

Provide each valve of size 3 inches and larger with an identification tag. Tag shall be 2-inch-

square or circular aluminum or 1/16-inch-thick fiberglass: W. H. Brady B-60, Seton Name Plate

Corp. Series SVT, or equivalent. Aluminum tags shall have black-filled letters. Tag shall show

the valve tag number and/or name or designation as given in the drawings.

Page 23: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-2 Equipment, Piping, & Valve Identification

AECOM REBID

2.03 Hose Bibb Signs--Unsafe Water

Provide a rigid sign labeled "DANGER--UNSAFE WATER" for each hose bibb. Size and

lettering shall conform to OSHA requirements. Signs shall be Seton Nameplate Company 20-

gauge baked enamel, minimum size 7 inches by 3 inches; Brady B-120 Fiber-Shield fiberglass,

minimum size 7 inches by 3 inches, 1/8 inch thick; or equivalent.

2.04 Labels for Mechanical Equipment

Provide a label for each pump, blower, compressor, tank, feeder, flocculator, flash mixer, clarifier

mechanism, or other piece of mechanical equipment. Label shall show the equipment name and

tag number as shown in the drawings. Labels shall be 1 1/2 inches (minimum) by 4 inches

(minimum) brass, aluminum, or 1/8-inch-thick fiberglass tags: Brady B-120 Fiber-Shield, Seton

Style 2065, or equivalent.

2.05 Labels for Exposed Tanks

Signs shall be weather and UV-resistant. Labels shall be Brady B-946, Seton Name Plate

Corporation PSPL, or equivalent. Minimum size shall be 7 inches by 10 inches. Provide a sign on

each tank bearing the tank tag number and the name of the liquid stored.

2.06 Labels for Automatic Start/Stop Equipment

Provide a sign reading "CAUTION--EQUIPMENT STARTS AND STOPS

AUTOMATICALLY" on each piece of equipment listed below. Signs shall be pressure-sensitive

vinyl with adhesive for application to equipment. Signs mounted on adjacent walls are also

acceptable. Size shall be 10 inches by 7 inches minimum. Products: Seton, Brady, or equivalent.

Equipment Type Location Tag Number

Grit Classifier Headworks 02-GC-2

Bar Screen Headworks 02-S-1

2.07 Hazardous Materials Warning and Danger Signs

A. Provide hazardous materials warning diamond signs complying with NFPA 704. Size shall

be 10 inches square. Wall signs shall be 1/8-inch-thick fiberglass: Brady B-120 Fiber-

Shield or equivalent. Signs attached to tanks, cabinets, or pieces of equipment shall be self-

adhesive vinyl cloth: Brady B-946 or equivalent. Provide signs at the following locations:

Page 24: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-3 Equipment, Piping, & Valve Identification

AECOM REBID

Tank or Equipment

Room No. Tag Number Location Chemical

Hypochlorite

Building

Tank 1 Hypochlorite Building Sodium Hypochlorite

Hypochlorite

Building

Tank 2 Hypochlorite Building Sodium Hypochlorite

B. Provide signs reading "DANGER" followed by the name of the chemical, gas, or hazard.

Size shall be 10 inches by 14 inches. Signs shall be 1/8-inch-thick fiberglass: Brady B-120

or equivalent. Provide signs at the following locations:

Room No. Sign Location Name of Hazardous Material

Hypochlorite

Building

By metering pumps Sodium Hypochlorite

2.08 Underground Plastic Warning Tape for Metallic Pipe

Provide permanent, bright-colored, continuous-printed plastic tape, intended for direct burial

service, not less than 6 inches wide by 3.5 mils thick. Provide tape with printing which most

accurately indicates type of service of buried pipe. Provide the following colored tape for the

various piping services:

Service Color

Cable TV Orange

Chemical Yellow

Electric Red

Fuel Oil, Gasoline Yellow

Gas Yellow

Reclaimed Water Violet

Sewer Green

Telephone Orange

Water Blue

Page 25: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-4 Equipment, Piping, & Valve Identification

AECOM REBID

2.09 Underground Detectable Metallic Pipe Warning Tape for Nonmetallic Pipe

Provide permanent, bright-colored, continuous-printed tape consisting of an aluminum or steel

foil sheathed in a plastic laminate, not less than 2 inches wide by 3 mils thick. Provide tape with

printing which most accurately indicates type of buried service. Provide the following colored

tape for the various piping services:

Service Color

Cable TV Orange

Chemical Yellow

Electric Red

Fuel Oil, Gasoline Yellow

Gas Yellow

Reclaimed Water Violet

Sewer Green

Telephone Orange

Water Blue

2.10 Marker Posts for Underground Utilities

A. Marker posts shall be single-piece, continuous glass fiber reinforced thermosetting

material, flat “T”-shaped with reinforcing ribs at the sides. Markers shall be suitable for an

operating temperature range of -40ºF to 140ºF. The bottom end shall be pointed for ease of

ground penetration. The marker post shall incorporate a line across the bottom to indicate

proper burial depth. The marker post shall be 3.5 to 4 inches wide, with a minimum

thickness of 0.125 inch. Provide 3-inch-wide reflector on the face of the post.

B. The marker post shall have a uniform color throughout. Provide UV inhibitors into the

material. Color coding shall be as follows:

Service Color

Cable TV Orange

Chemical Yellow

Electric Red

Fuel Oil, Gasoline Yellow

Gas Yellow

Reclaimed Water Violet

Sewer Green

Telephone Orange

Water Blue

C. Mechanical properties of the post material shall be as follows:

Page 26: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-5 Equipment, Piping, & Valve Identification

AECOM REBID

Property or Parameter

ASTM Test

Method

Minimum

Value

Ultimate tensile strength D638 50,000 psi

Ultimate compressive strength D638 45,000 psi

Glass content by weight D2584 50% to 60%

Barcol hardness D2583 45

D. Construct post so that it has a minimum burial depth of 18 inches and a height above the

roadway or ground surface of 36 inches.

E. Products: Carsonite CUM-375 or equivalent.

PART 3 - EXECUTION

3.01 Installing Pipe Labels

A. Provide label and flow arrow at each connection to pumps or other mechanical equipment,

at wall boundaries, at tees and crosses, and at 20-foot centers on straight runs of piping.

B. On piping having external diameters less than 6 inches (including insulation, if any),

provide full-band pipe markers, extending 360 degrees around pipe at each location.

C. On piping having external diameters of 6 inches and larger (including insulation, if any),

provide either full-band or strip-type pipe markers but not narrower than three times letter

height (and of required length), fastened by one of the following methods:

1. Laminated or bonded application of pipe marker to pipe or insulation.

2. Strapped-to-pipe or insulation application of semirigid type with Type 304 or 305

stainless steel bands.

3.02 Installing Valve and Equipment Labels

A. Attach labels to the valve or piece of equipment with Type 304 or 316 stainless steel chains

or wires.

B. Attach valve labels to the valve handwheels. If the valve has no handwheel, attach the label

to the valve by tying the tag wire or chain around the operating shaft or nut.

3.03 Installing Miscellaneous Signs

Attach per sign manufacturer's recommendations and per OSHA requirements.

3.04 Installing Wall and Door Signs

Attach to walls and doors using epoxy adhesive.

Page 27: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15075-6 Equipment, Piping, & Valve Identification

AECOM REBID

3.05 Installing Labels for Automatic Start/Stop Equipment and Hazardous Materials Warning Signs

for Equipment

A. Attach signs for exposed equipment directly to the equipment.

B. Attach signs for grinder or sump pumps on the adjacent wall.

3.06 Installing Underground Plastic Warning Tape for Metal Pipe

During backfilling of each exterior underground piping system, install continuous underground-

type plastic line marker, located directly over buried line at 6 to 8 inches above the top of the

pipe. Where multiple small lines are buried in common trench and do not exceed overall width of

16 inches, install single line marker.

3.07 Installing Underground Detectable Metallic Pipe Warning Tape

Install tape 4 to 6 inches below finished ground surface, located directly over buried pipelines.

Where multiple small pipelines are buried in a common trench and do not exceed an overall width

of 16 inches, install a single marker tape.

END OF SECTION

Page 28: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-1 Manual, Check, And Process Valves

AECOM REBID

SECTION 15100

MANUAL, CHECK, AND PROCESS VALVES

PART 1 - GENERAL

1.01 Description

This section includes materials, testing, and installation of manually operated valves, check

valves, and process valves including gate, , butterfly, ball, hose bibbs, eccentric plug, check,

pinch, solenoid, pet cocks, mud valves, vacuum breakers, flap valves, gauge valves, instrument

valve manifolds, and telescoping valves.

1.02 Related Work Specified Elsewhere

A. Connections to Existing Buried Pipelines: 02282.

B. Painting and Coating: 09900.

C. Polyethylene Sheet Encasement (AWWA C105): 09954.

D. Fusion-Bonded Epoxy Linings and Coatings: 09961.

E. Fire Hydrants: 15109.

F. Backflow Preventers: 15112.

G. Piping Schedule and General Piping Requirements: 1550A.

H. Pressure Testing of Piping: 15144.

I. Air-Release and Vacuum-Relief Valves: 15108.

J. Spring-Actuated Control Valves: 15111.

K. Equipment, Piping, Duct, and Valve Identification: 15075.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit manufacturer's catalog data and detail construction sheets showing all valve parts.

Describe each part by material of construction, specification (such as AISI, ASTM, SAE,

or CDA), and grade or type. Identify each valve by tag number to which the catalog data

and detail sheets pertain.

C. Show valve dimensions including laying lengths. Show port sizes. Show dimensions and

orientation of valve actuators, as installed on the valves. Show location of internal stops for

gear actuators. State differential pressure and fluid velocity used to size actuators. For

Page 29: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-2 Manual, Check, And Process Valves

AECOM REBID

worm-gear actuators, state the radius of the gear sector in contact with the worm and state

the handwheel diameter.

D. Show valve linings and coatings. Submit manufacturer's catalog data and descriptive

literature.

E. Submit six copies of a report verifying that the valve interior linings and exterior coatings

have been tested for holidays and lining thickness. Describe test results and repair

procedures for each valve. Do not ship valves to project site until the reports have been

returned by the Owner's Representative and marked "Resubmittal not required."

F. For butterfly and eccentric plug valves, show the clear diameter or size of the port. Show

the actual area of the port as a percentage of the area as calculated for the nominal valve

size.

1.04 Proof of Design Test for Eccentric Plug Valves (Types 500, 510, and 520)

A. Require the valve manufacturer to furnish six certified copies of reports covering the

design tests for the eccentric plug valves as described in AWWA C517 and the following.

One prototype valve of each size and class of a manufacturer's design shall be tested for

leakage at the specified design pressure and hydrostatically tested with twice the specified

design pressure. The hydrostatic test shall be performed with the plug in the open position.

The leakage test shall be performed with the plug in the closed position. The duration of

each test shall be 10 minutes minimum. During the leakage test, there shall be no

indication of leakage past the valve plug. Valves specified to have bi-directional seats shall

be leak tight in both directions. In the case of flanged valves, the valve body shall be bolted

to a flanged test head.

B. No part of the valve or plug shall be permanently deformed by the hydrostatic test. During

the hydrostatic test, there shall be no leakage through the metal, the end joints, or the shaft

seal.

C. It is the intent that the valve manufacturer provide evidence of the adequacy of each type

offered to perform under design pressures within the applicable rating for a sufficient

number of test cycles simulating a full service life. The adequacy is to be proven by tests,

made on one or more valves selected to represent each basic type of seat design of a size

within each applicable group, in a pressure class or classes equal to or greater than that

specified. The required number of test cycles appears in the following table:

TEST CYCLES REQUIRED

Size Group

(inches)

No. of

Cycles

Minimum Differential

Pressure

(psig)

3 to 20 10,000 150

24 to 42 5,000 150

Every test cycle shall consist of applying the specified differential pressure to the plug in

the closed position, then opening the plug (which will relieve the pressure) to the wide-

open position and then closing the plug.

Page 30: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-3 Manual, Check, And Process Valves

AECOM REBID

D. The valve shall be leak tight under the specified pressure differential upon completion of

the cycle test without having to stop during the test to repair the valve, modify or reinforce

the seat, or install shims or wedges around the seat.

E. The plug shall not be rotated past the center position to jam the plug onto the seat during

the hydrostatic test, the leakage test, or the cycle test.

PART 2 - MATERIALS

2.01 General

A. Valves are identified in the drawings by size and type number. For example, a callout in

the drawings of 2" V-310 refers to Type 310 valve in these specifications, which is a PVC

ball valve.

B. In addition, valves are further described by a suffix letter on the type number:

Suffix Letter Description

L Limit switches at the fully open and fully closed positions

M Motorized actuator per Section 15119

C. Install valves complete with operating handwheels or levers, chainwheels, extension stems,

floor stands, gear actuators, operating nuts, chains, and wrenches required for operation.

D. Valves shall have the name of the manufacturer and the size of the valve cast or molded

onto the valve body or bonnet or shown on a permanently attached plate.

E. For buried locations, valves with mechanical joint ends may be substituted for the flanged

ends specified provided the mechanical joint ends are compatible with the pipe ends.

2.02 Valve Actuators

A. Provide lever or wrench actuators for exposed valves 8 inches and smaller. For larger

valves, provide handwheels.

B. Where manually operated valves (size 4 inches and larger) are installed with their

centerlines more than 6 feet 9 inches above the floor, provide chainwheel and guide

actuators.

C. Provide 2-inch AWWA operating nuts for buried and submerged valves.

D. Provide enclosed gear actuators on butterfly, ball, and plug valves 8 inches and larger,

unless electric motorized valve actuators are shown in the drawings or the tag list. Gear

actuators for valves 8 through 20 inches shall be of the worm and gear, or of the traveling

nut type. Gear actuators for valves 24 inches and larger shall be of the worm and gear

types.

Gear actuators for motorized valves shall be of the worm and gear type, regardless of size.

Page 31: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-4 Manual, Check, And Process Valves

AECOM REBID

E. Provide gear actuators on gate valves 14 inches and larger, unless electric motorized valve

actuators are shown in the drawings. Gear actuators shall be of the bevel or spur gear type.

Provide grease case. Gearing shall comply with AWWA C500.

F. Design gear actuators assuming that the differential pressure across the plug, gate, or disc

is equal to the test pressure of the connecting piping and assuming a fluid velocity of 16

fps for valves in liquid service and 80 fps for valves in air or gas service and a line fluid

temperature range of 33°F to 125°F unless otherwise required in the detailed valve

specifications. Size actuators using a minimum safety factor of 1.5 for valves in open/close

service and 2.0 in modulating service.

G. Gear actuators shall be enclosed, oil lubricated, with seals provided on shafts to prevent

entry of dirt and water into the actuator. Gear actuators for valves located above ground or

in vaults and structures shall have handwheels. The actuators for valves in exposed service

shall contain a dial indicating the position of the valve disc or plug. Gear actuators for

buried or submerged valves shall have 2-inch-square AWWA operating nuts.

H. For buried or submerged service, provide watertight shaft seals and watertight valve and

actuator cover gaskets. Provide totally enclosed actuators designed for buried or

submerged service.

I. Traveling nut and worm and gear actuators shall be of the totally enclosed design so

proportioned as to permit operation of the valve under full differential pressure rating of

the valve with a maximum pull of 80 pounds on the handwheel or crank. Provide stop

limiting devices in the actuators in the open and closed positions. Actuators shall be of the

self-locking type to prevent the disc or plug from creeping. Design actuator components

between the input and the stop-limiting devices to withstand without damage a pull of 200

pounds for handwheel or chainwheel actuators and an input torque of 300 foot-pounds for

operating nuts when operating against the stops.

J. Handwheel diameters for traveling nut actuators shall not exceed 8 inches for valves 12

inches and smaller and shall not exceed 12 inches for valves 20 inches and smaller.

K. Self-locking worm gear shall be a one-piece design of gear bronze material (ASTM B427;

or ASTM B84, Alloy C86200), accurately machine cut. Actuators for eccentric and

lubricated plug valves may use ductile-iron gears provided the gearing is totally enclosed

with spring-loaded rubber lip seals on the shafts. The worm shall be hardened alloy steel

(ASTM A322, Grade G41500 or G41400; or ASTM A148, Grade 105-85), with thread

ground and polished. Support worm-gear shaft at each end by ball or tapered roller

bearings. The reduction gearing shall run in a proper lubricant. The handwheel diameter

shall be no more than twice the radius of the gear sector in contact with the worm. Worm-

gear actuators shall be Limitorque Model HBC, EIM Series W, or equivalent.

L. Design actuators on buried valves to produce the required torque on the operating nut with

a maximum input of 150 foot-pounds.

M. Valve actuators, handwheels, or levers shall open by turning counterclockwise.

Page 32: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-5 Manual, Check, And Process Valves

AECOM REBID

2.03 Cast-Iron Valve Boxes for Buried Valves

A. Valve boxes shall be two-piece sliding type, cast iron, with extension shafts. Units shall be

as manufactured by Tyler Pipe, Geneco, Star Pipe Products, or equivalent. Extension pipes

shall be as shown in the drawings.

B. Coat buried cast-iron pieces per Section 09900, System No. 21 or with fusion-bonded

epoxy per Section 09961.

2.04 Extension Stems for Buried and Submerged Valve Actuators

A. Where the depth of the valve is such that its centerline is more than 4 feet below grade,

provide operating extension stems to bring the operating nut to a point 6 inches below the

surface of the ground and/or box cover. Where the valve is submerged, provide operating

extension stems to bring the operating nut to 6 inches above the water surface. Extension

stems shall be steel, solid core, and shall be complete with 2-inch-square operating nut.

The connections of the extension stems to the operating nuts and to the valves shall

withstand without damage a pull of 300 foot-pounds.

B. Extension stem diameters shall be as tabulated below:

Valve Size

(inches)

Minimum Extension

Stem Diameter

(inches)

2 3/4

3, 4 7/8

6 1

8 1 1/8

10, 12 1 1/4

14 1 3/8

16, 18 1 1/2

20, 24, 30, 36 1 3/4

42, 48, 54 2

2.05 Floor Stands, Extension Stems, and Extension Stem Support Brackets

A. When required by the installations, provide floor stands and extension stems for operation

of valves. Floor stands shall be of the nonrising stem, indicating type, complete with steel

extension stems, couplings, handwheels, stem guide brackets, and special yoke attachments

as required by the valves and recommended and supplied by the stand manufacturer. Floor

stands shall be cast-iron base type: Clow, Figure F-5515; Bingham and Taylor; Stockham;

or equivalent. Handwheels shall turn counterclockwise to open the valves.

B. Provide Type 316 stainless steel anchor bolts.

C. Provide steel extension stems for valves in exposed service. Provide Type 316 stainless

steel extension stems for valves/stems exposed to hydrogen sulfide (like the Influent Pump

Station). Provide Type 316 stainless steel stems for valves in submerged service.

Page 33: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-6 Manual, Check, And Process Valves

AECOM REBID

D. Provide adjustable stem guide brackets for extension stems. The bracket shall allow valve

stems to be set over a range of 2 to 36 inches from walls. Provide bushings drilled to accept

up to 2-inch-diameter stems. Base, arm, and clamp shall be ductile iron. Coat ductile iron

components with fusion-bonded epoxy per Section 09961. Bushing shall be bronze (ASTM

B584, Alloy C86400 or C83600). Bolts, nuts, screws, and washers (including wall anchor

bolts) shall be Type 316 stainless steel. Provide slots in the bracket to accept 3/4-inch bolts

for mounting the bracket to the wall. Products: Trumbull Industries, Inc., Adjustable Stem

Guide or equivalent.

2.06 Chainwheels and Guides

Chainwheels and guides shall be Clow Figure F-5680, DeZurik Series W or LWG, Stockham, or

equivalent. Chainwheels and guides shall be aluminum. Chains shall extend to within 4 feet of the

operating floor. Chains shall be galvanized steel.

2.07 Valve Tagging and Identification

Provide identifying valve tags per Section 15075.

2.08 Bolts and Nuts for Flanged Valves

Bolts and nuts for flanged valves shall be as described in Section 15050A.

2.09 Gaskets for Flanges

Gaskets for flanged end valves shall be as described in Section 15050A.

2.10 Limit Switches for Check Valves

See Division 16.

2.11 Painting and Coating

A. Coat metal valves located above ground or in vaults and structures the same as the adjacent

piping. If the adjacent piping is not coated, then coat valves per Section 09900, System No.

10. Apply the specified prime coat at the place of manufacture. Apply intermediate and

finish coats in field. Finish coat shall match the color of the adjacent piping. Coat

handwheels the same as the valves.

B. Coat buried metal valves at the place of manufacture per Section 09900, System No. 21.

C. Coat submerged metal valves, stem guides, extension stems, and bonnets at the place of

manufacture per Section 09900, System No. 7.

D. Line the interior metal parts of metal valves 4 inches and larger, excluding seating areas

and bronze and stainless steel pieces, per Section 09900, System No. 7. Apply lining at the

place of manufacture.

E. Alternatively, line and coat valves with fusion-bonded epoxy per Section 09961 unless the

valve is in contact with raw sewage, sludge, RAS, WAS, or MLSS.

F. Coat floor stands per Section 09900, System No. 10.

Page 34: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-7 Manual, Check, And Process Valves

AECOM REBID

G. Test the valve interior linings and exterior coatings at the factory with a low-voltage (22.5

to 80 volts, with approximately 80,000-ohm resistance) holiday detector, using a sponge

saturated with a 0.5% sodium chloride solution. The lining shall be holiday free.

H. Measure the thickness of the valve interior linings per Section 09900. Repair areas having

insufficient film thickness per Section 09900.

2.12 Packing, O-Rings, and Gaskets

Unless otherwise stated in the detailed valve specifications, packing, O-rings, and gaskets shall be

one of the following nonasbestos materials:

A. Teflon.

B. Kevlar aramid fiber.

C. Acrylic or aramid fiber bound by nitrile. Products: Garlock "Bluegard," Klinger "Klingersil

C4400," or equivalent.

D. Buna-N (nitrile).

2.13 Rubber Seats

Rubber seats shall be made of a rubber compound that is resistant to free chlorine and

monochloramine concentrations up to 10 mg/L in the fluid conveyed.

2.14 Valves

A. Gate Valves:

1. Type 100--Aboveground Bronze Gate Valves 3 Inches and Smaller:

Aboveground threaded end gate valves, 1/4 through 3 inches, for water and air

service shall be rising stem, screwed or union bonnet, solid wedge disc type, Class

125 or 150, having a minimum working pressure of 200 or 300 WOG psi

respectively at a temperature of 150°F. Ends shall be female threaded, ASME

B1.20.1. Materials of construction shall be as follows:

Component Material Specification

Body and bonnet Bronze ASTM B61 or B62

Disc Bronze ASTM B61, B62, or B584

(Alloy C97600)

Stem Bronze or copper

silicon

B99 (Alloy 651), B584

(Alloy C87600), B371 (Alloy

C69400)

Seat rings (Classes 200

and 300 only)

Stainless steel AISI Type 410

Page 35: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-8 Manual, Check, And Process Valves

AECOM REBID

Handwheels shall be aluminum, brass, or malleable iron. Packing shall be Teflon or

Kevlar aramid fiber. Valves shall be Crane 428 or 431, Stockham B-100 or B-120,

or equivalent.

2. Type 120--2- and 3-Inch Cast-Iron Buried Gate Valves:

Buried gate valves of sizes 2 through 3 inches for water service shall be iron body,

bronze mounted, nonrising stem type, double disc, parallel seat, and shall have a

working pressure of at least 200 psi. Valves shall have flanged, PVC, or threaded

ends to match the pipe ends. Valves shall have a 2-inch AWWA operating nut.

Materials of construction shall be as follows:

Component Material Specification

Body, bonnet, operating

nut, and stuffing box

Cast iron ASTM A126, Class B or C

Bonnet bolts and

stuffing box bolts

Stainless steel ASTM A193, Grade B8M

Discs, disc nut, disc

ring, and seat ring

Bronze ASTM B62

O-ring Synthetic rubber

Stem Copper silicon or

manganese bronze

ASTM B584, Alloy C87600,

C86200, C86300, C86400,

C87500

Valves shall be Kennedy Figure 597X or 561X, Mueller Gate Valves, Clow F-5070

or F-5085, or equivalent.

3. Type 135--Cast-Iron Tapping Gate Valves 3 Through 24 Inches:

Valves shall conform to AWWA C500 and the following. Valves shall be iron

bodied, bolted bonnet, nonrising stem, solid bronze internal working parts, parallel

faced, bottom wedging double-discs, and O-ring seals. Discs for valves 12 inches

and smaller shall be solid bronze; discs for valves larger than 12 inches shall either

be solid bronze or shall be cast iron with bronze facings. Bronze for internal working

parts, including stems, shall not contain more than 2% aluminum or more than 7%

zinc. Bronze shall conform to ASTM B62 or ASTM B584 (Alloy C83600), except

that stem bronze shall have a minimum tensile strength of 60,000 psi, a minimum

yield strength of 30,000 psi, and a minimum of 10% elongation in 2 inches (ASTM

B584, Alloy C87600). Body bolts shall be Type 316 stainless steel, ASTM A276.

Ends shall be flanged, Class 125, ASME B16.1. One end shall have slotted bolt

holes to fit tapping machines. Seat rings shall be oversized to permit the use of full

size cutter. Valves shall be Clow, American Flow Control, or equivalent. Type 137

valves may be substituted for Type 135 valves.

4. Type 137--Ductile-Iron Resilient Wedge Tapping Gate Valves 4 Through 16 Inches

(AWWA C515):

Valves shall comply with AWWA C515 and the following. Valves shall be of the

bolted bonnet type with nonrising stems. Valve stems shall be Type 304 or 316

Page 36: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-9 Manual, Check, And Process Valves

AECOM REBID

stainless steel or cast, forged, or rolled bronze. Stem nuts shall be made of solid

bronze. Bronze for internal working parts, including stems, shall not contain more

than 2% aluminum or more than 7% zinc. Bronze shall conform to ASTM B62 or

ASTM B584 (Alloy C83600), except the stem bronze shall have a minimum tensile

strength of 60,000 psi, a minimum yield strength of 30,000 psi, and a minimum of

10% elongation in 2 inches (ASTM B584 or B763, Alloy C87600 or C99500). Body

bolts shall be Type 316 stainless steel. Ends shall be flanged, Class 125, ASME

B16.1. One end shall have slotted bolt holes per AWWA C515, paragraph 4.4.1.3.4

to fit tapping machines.

Provide reduction thrust bearings above the stem collar. Stuffing boxes shall be O-

ring seal type with two rings located in stem above thrust collar. Each valve shall

have a smooth unobstructed waterway free from any sediment pockets.

Valves shall be lined and coated at the place of manufacture with either fusion-

bonded epoxy or heat-cured liquid epoxy. Minimum epoxy thickness shall be 8 mils.

Manufacturers: Clow, AVK, American Flow Control, Mueller, Waterous, Kennedy,

or equivalent.

5. Type 150--Stainless Steel Gate Valves:

Stainless steel gate valves, 1/2 through 2 inches, shall be of the single wedge type

with rising stem and handwheel. Minimum working pressure shall be 200 psig.

Bonnet shall be of the screwed type. Ends shall be threaded, ASME B1.20.1.

Materials of construction shall be as follows:

Component Material Specification

Body, bonnet, plug, disc, and

follower

Stainless steel ASTM A351, Grade CF8M

Packing gland, nut, retainer

ring, and stem

Stainless steel ASTM A276, Type 316

Handwheel Malleable iron ASTM A47, A197

Stuffing box packing Teflon --

Valves shall be Powell Figure 1832, Crane/Alloyco Figure 90, or equivalent.

6. Type 180—Cast-Iron Resilient Wedge Gate Valves 3 Through 20 Inches (AWWA

C509):

Valves shall comply with AWWA C509 and the following. Valves shall be of the

bolted-bonnet type with nonrising stems. Valve stems shall be Type 304 or 316

stainless steel or cast, forged, or rolled bronze. Provide operating nut for buried

valves. Provide handwheel for exposed valves. Stem nuts shall be made of solid

bronze. Bronze for internal working parts, including stems, shall not contain more

than 2% aluminum or more than 7% zinc. Bronze shall conform to ASTM B62 or

ASTM B584 (Alloy C83600), except the stem bronze shall have a minimum tensile

strength of 60,000 psi, a minimum yield strength of 30,000 psi, and a minimum of

10% elongation in 2 inches (ASTM B584 or B763, Alloy C87600 or C99500). Body

Page 37: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-10 Manual, Check, And Process Valves

AECOM REBID

bolts shall be Type 316 stainless steel. End connections for exposed valves shall be

flanged. End connections for buried valves shall be mechanical joint or push-on type

that can be restrained.

Provide reduction thrust bearings above the stem collar. Stuffing boxes shall be O-

ring seal type with two rings located in stem above thrust collar. Each valve shall

have a smooth unobstructed waterway free from any sediment pockets.

Valves shall be lined and coated at the place of manufacture with either fusion-

bonded epoxy or heat-cured liquid epoxy. Minimum epoxy thickness shall be 8 mils.

Manufacturers: Clow R/W, AVK, American Flow Control CRS-80, Waterous Series

500, Kennedy Ken-Seal, or equivalent.

Type 185 valves may be substituted for Type 180 valves.

7. Type 185—Ductile-Iron Resilient Wedge Gate Valves 4 Through 36 Inches

(AWWA C515):

Valves shall comply with AWWA C515 and the following. Valves shall be of the

bolted-bonnet type with nonrising stems. Valve stems shall be Type 304 or 316

stainless steel or cast, forged, or rolled bronze. Provide operating nut for buried

valves. Provide handwheel for exposed valves. Stem nuts shall be made of solid

bronze. Bronze for internal working parts, including stems, shall not contain more

than 2% aluminum or more than 7% zinc. Bronze shall conform to ASTM B62 or

ASTM B584 (Alloy C83600), except the stem bronze shall have a minimum tensile

strength of 60,000 psi, a minimum yield strength of 30,000 psi, and a minimum of

10% elongation in 2 inches (ASTM B584 or B763, Alloy C87600 or C99500). Body

bolts shall be Type 316 stainless steel. End connections for exposed valves shall be

flanged. End connections for buried valves shall be mechanical joint or push-on type

that can be restrained.

Provide reduction thrust bearings above the stem collar. Stuffing boxes shall be O-

ring seal type with two rings located in stem above thrust collar. Each valve shall

have a smooth unobstructed waterway free from any sediment pockets.

Valves shall be lined and coated at the place of manufacture with either fusion-

bonded epoxy or heat-cured liquid epoxy. Minimum epoxy thickness shall be 8 mils.

Manufacturers: Clow, AVK, American Flow Control, Waterous, Kennedy, or

equivalent.

B. Butterfly Valves:

1. Thrust Bearings for Butterfly Valves (Types 200, 240, and 260):

Provide thrust bearings to hold the valve disc in the center of the valve seat. No

bearings shall be mounted inside the valve body within the waterway. Do not use

thrust bearings in which a metal bearing surface on the disc rubs in contact with an

opposing metal surface on the inside of the body.

Page 38: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-11 Manual, Check, And Process Valves

AECOM REBID

2. Bronze Components in Butterfly Valves (Types 200, 210, and 240):

Bronze components in contact with water shall comply with the following

requirements:

Constituent Content

Zinc 7% maximum

Aluminum 2% maximum

Lead 8% maximum

Copper + Nickel + Silicon 83% minimum

3. Port Sizes for Butterfly Valves (Types 200):

For valves 24 inches and smaller, the actual port diameter shall be at least 93% of

the nominal valve size. For valves larger than 24 inches, the port diameter shall not

be more than 1.25 inches smaller than the nominal valve size. The dimension of the

port diameter shall be the clear waterway diameter plus the thickness of the rubber

seat.

4. Corrosion-Resistant Materials in Butterfly Valves (Types 200):

Where AWWA C504 requires “corrosion resistant” material, such material shall be

one of the following:

(1) Bronze as described above.

(2) Type 304 or 316 stainless steel.

(3) Monel (UNS N04400).

(4) Synthetic nonmetallic material.

5. Seating Surfaces in Butterfly Valves (Types 200):

Seating surfaces in valves having motorized actuators shall be stainless steel or

nickel-copper per AWWA C504 or nickel-chromium alloy containing a minimum of

72% nickel and a minimum of 14% chromium.

6. Factory Leakage Testing (Types 200):

Perform factory leakage tests per AWWA C504 on both sides of the seat.

7. Type 200--Flanged, Rubber-Seated Butterfly Valves 4 Through 72 Inches, Class

150B:

Butterfly valves shall be short body, flanged type for exposed valves and valves in

vaults or structures, and either flanged or mechanical joint for buried valves. Valve

shall conform to AWWA C504, Class 150B. Minimum working differential pressure

across the valve disc shall be 150 psi. Flanged ends shall be Class 125, ASME

Page 39: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-12 Manual, Check, And Process Valves

AECOM REBID

B16.1. Valve shafts shall be stub shaft or one-piece units extending completely

through the valve disc. Materials of construction shall be as follows:

Component Material Specification

Body Cast iron or ductile

iron

AWWA C504

Exposed body cap

screws and bolts and

nuts

Stainless steel ASTM A276, Type 304

Discs Cast iron, ductile iron,

or Ni-Resist

AWWA C504

Shafts, disc fasteners,

seat retention segments,

and seat fastening

devices

Stainless steel ASTM A276, Type 304

Seat material EPDM --

Where the rubber seat is applied to the disc, it shall be bonded to a stainless steel

seat retaining ring which is clamped to the disc by Type 304 or 316 stainless steel

screw fasteners or secured to a stainless steel seat by a combination of cap screws, a

serrated disc retaining ring, and molded shoulders in the seat mating with machined

registers in the disc. Where the rubber valve seat shall be secured to or retained in

the valve body. Valves shall be Pratt, DeZurik Series BAW, M&H, Val-Matic, or

equivalent.

C. Ball Valves:

1. Type 300—Full Port Threaded Bronze Ball Valves 2 Inches and Smaller:

Ball valves, 2 inches and smaller, for air or water service shall have a pressure rating

of at least 600 psi WOG at a temperature of 100°F. Provide full port ball and body

design. Valves shall comply with MSS SP-110. Provide bronze (ASTM B62 or

ASTM B584, Alloy C83600 or C84400) body and plug ball retainer. Ball and stem

shall be Type 316 stainless steel. Valves shall have threaded ends (ASME B1.20.1),

nonblowout stems, reinforced Teflon seats, and have plastic-coated lever actuators.

Provide locking lever handle. Valves shall be Stockham T-285 Series, Apollo 77C-

140 Series, or equivalent.

2. Type 310--Double Union PVC Ball Valves 3 Inches and Smaller:

Thermoplastic ball valves, 3 inches and smaller, for water and chemical (do not use

for sodium hypochlorite server) service shall be rated at a pressure of 150 psi at a

temperature of 105°F. Body, ball, and stem shall be PVC conforming to ASTM

D1784, Type 1, Grade 1. Seats shall be Teflon. O-ring seals shall be Viton. Valve

ends shall be of the double-union design. Ends shall be socket welded except where

threaded or flanged-end valves are specifically shown in the drawings. Valves shall

have handle for manual operation. Valves shall be as manufactured by Chemtrol,

Hayward, R & G Sloan, Spears Manufacturing Company, Plast-O-Matic, IPEX

Series VK or VKD, or equivalent.

Page 40: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-13 Manual, Check, And Process Valves

AECOM REBID

3. Type 316--Double Union CPVC Ball Valves 3 Inches and Smaller with Vented Ball:

Vented CPVC ball valves, 3 inches and smaller, for chemical service shall be rated

at a pressure of 150 psi at a temperature of 105°F and rated at a pressure of 85 psi at

a temperature of 140°F. Provide machined vent hole, deburred, in the ball to allow

gases to vent. Body, ball, and stem shall be CPVC conforming to ASTM D1784,

Type 4, Grade 1. Seats shall be Teflon. O-ring seals shall be EPDM. Valve ends

shall be of the double-union design. Ends shall be socket welded except where

threaded or flanged-end valves are specifically shown in the drawings. Valves shall

have handle for manual operation. Valves shall be Plast-O-Matic “Z-MBV-Vent,”

Asahi/America Type 21, or equivalent.

4. Type 320--Regular Port Threaded Stainless Steel Ball Valves 2 Inches and Smaller:

Stainless steel ball valves, 2 inches and smaller, for water service shall be rated at a

minimum pressure of 1,500 psi WOG at a temperature of 100°F. Valve body, ball,

and stem shall be Type 316 stainless steel, ASTM A276 or A351. Seat and seals

shall be reinforced Teflon. Valves shall have lever actuators, plastic coated. Provide

locking lever handle. Valves shall have threaded ends (ASME B1.20.1) and

nonblowout stems. Valves shall be McCanna Figure M402, Worcester Series 48,

Stockham Figure SD 2120-SSMO-R-T, Apollo 76-100 Series, or equivalent.

5. Type 325--Flanged Stainless Steel Ball Valves 4 inches and smaller, Class 150:

Stainless steel ball valves 1/2 through 4 inches shall have flanged ends, ASME

B16.5, Class 150. Pressure rating shall be at least 250 psi at a temperature of 100°F.

Bodies shall be Type 316 stainless steel (ASTM A351, Type CF8M). Ball, stem, and

compression ring shall be Type 316 stainless steel. Bonnet bolting shall be ASTM

A193, Grade B8M. Seats and seals shall be Teflon. Valves shall be Neles-Jamesbury

Type 5150 or 7150, McCanna Series F151-S6, Apollo Series 87, or equivalent.

D. Angle Valves, Hose Valves, Hose Bibbs, and Fire Hydrants:

1. Type 410--Bronze Angle Hose Valves:

Angle-type hose valves of sizes 1 1/2 and 2 1/2 inches shall be brass or bronze

(ASTM B62 or ASTM B584, Alloy C83600) body with rising or nonrising stem,

composition disc, and bronze or malleable iron handwheel. Stem shall be bronze,

ASTM B62, ASTM B584 (Alloy C83600), or ASTM B198 (Alloy C87600). Valves

shall have a cold-water service pressure rating of at least 150 psi. Provide cap and

chain with valve. Threads on the valve outlet shall be American National Standard

fire hose coupling screw thread. Valves shall be Nibco T-301-HC, Powell Figure

151 with Figure 527 nipple adapter, Crane 17TF with hose nipple adapter, or

equivalent.

2. Type 420--Bronze Hose Bibbs:

Hose bibbs of size 1/2 inch, 3/4 inch, and 1 inch shall be all bronze (ASTM B62 or

ASTM B584, Alloy C83600) with rising or nonrising stem, composition disc,

bronze or malleable iron handwheel, and bronze stem (ASTM B99, Alloy C65100;

ASTM B371, Alloy C69400; or ASTM B584, Alloy C87600). Packing shall be

Page 41: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-14 Manual, Check, And Process Valves

AECOM REBID

Teflon or graphite. Valves shall have a pressure rating of at least 125 psi for cold-

water service. Threads on valve outlet shall be American National Standard fire hose

coupling screw thread (ASME B1.20.7). Provide atmospheric vacuum breaker

conforming to ASSE Standard 1011 and IAPMO code and approved by the Collier

County Health Department. Valves shall be Jenkins Figure 112, 113, or 372, Nibco

Figure T-113-HC, Powell Figure 503H, or equivalent.

3. Type 492--Dry Barrel Fire Hydrants (AWWA C502):

See Section 15109.

E. Plug Valves:

1. Plug and Seating Design for Eccentric Plug Valves (Types 500, 510, 515, 520, and

525):

Eccentric plug valves shall comply with AWWA C517 and the following. Provide a

rectangular or circular plug design, with an associated rectangular or round seat.

Provide bidirectional seating design. The valve shall seat with the rated pressure

both upstream and downstream of the closed plug. Provide geared actuators sized for

bidirectional operation.

2. For Types 500, 510, 515, 520, and 525 eccentric plug valves, the metallic portion of

the plug shall be one-piece design and shall be without external reinforcing ribs

which result in there being a space between the rib and the main body of the plug

through which water can pass. Nowhere in the valve or actuators shall the valve

shaft be exposed to iron on iron contact. Sleeve bearings shall be stainless steel in

valve sizes 20 inches and smaller and bronze or stainless steel in valve sizes 24

inches and larger. Provide enclosed worm-gear actuators for valves 6 inches and

larger.

3. Rubber compounds shall have less than 2% volume increase when tested in

accordance with ASTM D471 after being immersed in distilled water at a

temperature of 73.4°F ±2°F for 70 hours.

4. Type 510--Eccentric Plug Valves 4 Through 12 Inches:

Eccentric plug valves, 4 through 12 inches, shall be nonlubricated type. Minimum

pressure rating shall be 175 psi. Bodies shall be cast iron per ASTM A126, Class B.

Ends shall be flanged, Class 125 per ASME B16.1. Plugs shall be cast iron (ASTM

A126, Class B), or ductile iron (ASTM A536, Grade 65-45-12) with Buna-N or

neoprene facing. Design plugs to seat over a pressure range of 25 psi to the valve

design pressure rating. Valve body seats shall be Type 304 or 316 stainless steel or

have a raised welded-in overlay at least 1/8-inch thick of not less than 90% nickel.

Body cap screws and bolts and nuts shall be Type 316 stainless steel. Packing shall

be butadiene-filled Teflon. Alternatively, U-cup seals may be provided. Valves shall

be DeZurik Figure 118 PEC or PEF, Clow F-5412, Val-Matic “Cam-Centric,”

Milliken “Millcentric,” Pratt “Ballcentric,” or equivalent.

Page 42: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-15 Manual, Check, And Process Valves

AECOM REBID

5. Type 520--Eccentric Plug Valves 14 through 24 Inches:

Eccentric plug valves, 14 inches and larger, shall be nonlubricated type. Minimum

pressure rating shall be 150 psi. Bodies shall be cast iron per ASTM A126, Class B.

Ends shall be flanged, Class 125 per ASME B16.1. Plugs shall be cast iron (ASTM

A126, Class B), or ductile iron (ASTM A536, Grade 65-45-12) with Buna-N or

neoprene facing. Design plugs to seat over a pressure range of 25 psi to the valve

design pressure rating. Valve body seats shall be Type 304 or 316 stainless steel or

have a raised welded-in overlay at least 1/8-inch thick of not less than 90% nickel.

Plug shall be of the one-piece design. Body cap screws and bolts and nuts shall be

Type 316 stainless steel. Packing shall be butadiene-filled Teflon. Alternatively, U-

cup seals may be provided. Valves shall be DeZurik Figure 118 PEC or PEF, Clow

F-5412, Val-Matic “Cam-Centric,” Milliken "Millcentric," Pratt “Ballcentric,” or

equivalent.

F. Diaphragm Valves:

1. Type 625--PVC Diaphragm Valves 1/2 Through 4 Inches in Sodium Hypochlorite

Service:

Diaphragm valves, sizes 1/2 through 4 inches, shall be of the weir type with PVC

bodies and PVC or polypropylene bonnets. PVC shall comply with ASTM D1784,

Cell Classification 12454. Polypropylene shall comply with ASTM D4101. Body

wall thickness shall conform to Schedule 80 per ASTM D1785. Valve diaphragms

shall be PTFE coated. Provide Buna-N elastomer backing for diaphragms. O-rings

shall be Viton. Body-bonnet bolting shall be Hastelloy C (ASTM F468, Grade

N10276). Provide polypropylene manual handwheel actuator with rising indicator

stem. Minimum pressure rating shall be 150 psi at a temperature of 73°F and 135 psi

at a temperature of 110°F. Ends shall be true union with socket weld connections.

Ends for valves larger than 3 inches shall be flanged, Class 125, ASME B16.1.

Products: Spears Manufacturing Company, ITT Dia-Flo, or equivalent.

2. Type 635--CPVC Diaphragm Valves 1/2 Through 4 Inches in Sodium Hypochlorite

Service:

Diaphragm valves, sizes 1/2 through 4 inches, shall be of the weir type with PVC

bodies and PVC or polypropylene bonnets. PVC shall comply with ASTM D1784,

Cell Classification 12454. Polypropylene shall comply with ASTM D4101. Body

wall thickness shall conform to Schedule 80 per ASTM D1785. Valve diaphragms

shall be PTFE coated. Provide Buna-N elastomer backing for PTFE diaphragms. O-

rings shall be Viton. Body-bonnet bolting shall be Hastelloy C (ASTM F468, Grade

N10276). Provide polypropylene manual handwheel actuator with rising indicator

stem. Minimum pressure rating shall be 150 psi at a temperature of 73°F and 135 psi

at a temperature of 110°F. Ends shall be true union with socket weld connections.

Ends for valves larger than 3 inches shall be flanged, Class 125, ASME B16.1.

Products: Spears Manufacturing Company, ITT Dia-Flo, or equivalent.

G. Check Valves:

1. Type 700--Bronze Check Valves 3 Inches and Smaller:

Page 43: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-16 Manual, Check, And Process Valves

AECOM REBID

Check valves 3 inches and smaller shall be Class 125, wye pattern, bronze, ASTM

B61, B62, or B584 (Alloy C83600). Ends shall be female threaded, ASME B1.20.1.

Disc shall be bronze, swing type. Minimum working pressure shall be 200 psi WOG

at a temperature of 150°F. Valves shall be Crane No. 37, Nibco T-413-B, Stockham

B-319, or equivalent.

2. Type 720--Cast-Iron Swing Check Valves 3 Inches and Larger, Class 125:

Swing check valves, 3 inches and larger, shall be iron body, bronze mounted

complying with AWWA C508 with the following materials of construction:

Description Material Specification

Disc or clapper seat

ring and valve body

seat ring

Bronze or brass ASTM B62 or B584 (Alloy

C84400 or C87600)

Body and cap (bonnet) Cast iron ASTM A126, Class B

Disc and hinge or arm

(valves 4 inches and

smaller)

Bronze ASTM B62 or ASTM B584

(Alloy C84400)

Disc and hinge or arm

(valves larger than 4

inches)

Cast iron or bronze ASTM A126, Class B; ASTM

B62.

Hinge pin Stainless steel Type 303, 304, or 410 stainless

Cover bolts and nuts Stainless steel ASTM A193, Grade B8M;

ASTM A194, Grade 8M

Internal fasteners and

accessories

Bronze or Type 304

or 316 stainless steel

Bronze or brass components in contact with water shall comply with the following

requirements:

Constituent Content

Zinc 7% maximum

Aluminum 2% maximum

Lead 8% maximum

Copper + Nickel + Silicon 83% minimum

Ends shall be flanged, Class 125, ASME B16.1. Minimum valve working pressure

shall be 150 psi. Provide check valves with outside lever and weight.

The shop drawing submittal shall include a detail showing how the hinge pin

extends through the valve body. Show packing gland, hinge pin gland, cap, and

other pieces utilized.

Valves shall be M&H Style 159-02, Clow 106LW or 159-02, or equivalent.

Page 44: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-17 Manual, Check, And Process Valves

AECOM REBID

3. Type 750--Rubber Flapper Swing Check Valves:

Valves shall consist of body, flapper, and bolted cover. Operating pressure shall be

at least 175 psi at a temperature of 212°F. Valve seat shall be set at an angle of 35 to

45 degrees to the centerline of the pipe. Ends shall be flanged, ASME B16.1, Class

125. Body and cover shall be cast iron (ASTM A48, Class 30, or ASTM A126,

Class B). Flapper shall consist of a steel disk insert and a steel bar hinge covered

with EPDM bonded to the metal pieces. Provide O-ring seal bonded onto the disk.

Provide 1/8-inch-thick EPDM lining in valve body. Lining shall have a hardness of

50 to 60 durometer, Shore A. Cover bolts shall be Type 316 stainless steel. Products:

APCO Series 100R, Val-Matic Series 500, or equivalent.

H. Solenoid Valves:

1. Design and construct solenoid valves such that they can be used in both horizontal

and vertical piping.

2. Type 900--Metallic Solenoid Valves 1 1/2 Inches and Smaller:

Solenoid valves of sizes 1/4 through 1 1/2 inches for water and air service shall have

forged brass (Alloy C23000) or bronze (ASTM B62) bodies with Teflon main seats.

Internal plunger, core tube, plunger spring, and cage assembly shall be stainless steel

(Types 302, 304, or 305). Solenoid enclosures shall be NEMA 4, except where

explosion-proof is noted in the drawings. Valve actuators shall be 120-volt a-c. Seals

shall be Teflon. Valves shall have a maximum operating pressure and a maximum

differential pressure of 125 psi. Solenoid valves shall be energized to open, unless

otherwise noted on the drawings. Valves shall be ASCO "Redhat" Model 8210 and

8211, Parker Hannifin “Skinner” Models 2R2, 2LC or 2LB or equivalent.

I. Pet Cocks and Drain Cocks:

1. Type 1000--Pet Cocks 1/2 Inch and Smaller:

Pet cocks shall be all bronze (ASTM B62) or brass (ASTM B16), rated at 125 psi.

Provide lever or tee handle operator. Pet cocks shall be Crane Figure 724,

Lunkenheimer Figure 478 or 479, or equivalent.

J. Mud Valves:

Type 1020--Mud Valves 4 Through 24 Inches:

Mud valves shall be rising stem with flanged end, unless otherwise shown in the drawings.

Materials of construction shall be as follows:

Component Material Specification

Body Cast iron ASTM A48 or A126

Stem, nut, disc ring, and

seat ring

Bronze ASTM B62 or B584, Alloy

C83600

Extension stem Stainless steel AISI Type 316

Page 45: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-18 Manual, Check, And Process Valves

AECOM REBID

Provide extension stem, stem guides, and AWWA operating nut. Mud valves shall be Clow

Figure F-3088, Waterman Industries, or equivalent.

K. Vacuum Breakers:

Type 1030--PVC Vacuum Breaker Valves, 1 Inch and Smaller:

Vacuum breaker valves shall have PVC body and Viton diaphragm and seals. The

diaphragm shall unseat at 2-inch Hg vacuum and allow air to enter the system at 80 scfm.

End shall be socket welded. Vacuum breaker valve shall be Plast-O-Matic Series VBM,

Ryan Herco, Harrington Industrial Plastics, or equivalent.

L. Flap Valves:

Type 1060--Flap Valves:

Flap valves shall have cast-iron body (ASTM A48 or A126) with bronze (ASTM B62)

hinge pin, flap ring, and seat. Ends shall be flanged, spigot end, or hub to match the

connecting pipe. Products: Clow F-3012, F-3014, F-3016; Waterous Flap Valves;

Waterman Industries; or equivalent.

M. Gauge Valves, and Valve Manifolds:

Type 1080--Gauge Valve:

Gauge valves shall be a combination isolation and vent valve with a minimum pressure

rating of 3,000 psi at 200°F. Isolation valve shall have interchangeable hard or soft seat.

Body, bonnet, and stem shall be Type 316 stainless steel. Packing shall be Buna-N. Valves

shall have screwed ends and nonblowout stems. Valves shall be AGCO M9 gauge valve or

equivalent.

N. Telescoping Valves:

Type 1090--Telescoping Valves 12 Inches and Smaller:

Fabricate plain telescoping valve tube from Type 304 stainless steel with a minimum wall

thickness of 1/8 inch. Provide Type 304 stainless steel lifting strap, companion flange,

stem, fasteners, and hardware. Provide Buna-N gasket for watertight seal around the

sliding tube. Valve travel shall be as shown in the drawings. Provide rising stem upright or

offset handwheel actuator as shown on the drawings/ coordinated with the tank

manufacturer. Acutators shall be provided with clear vented plastic stem cover and

position indicator calibrated in 1/4-inch increments. Provide Type 304 or 316 stainless

steel anchor bolts for actuator pedestal. Manufacturers: Waterman Industries, Inc.,

Coldwell-Wilcox Company, or equivalent.

Page 46: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-19 Manual, Check, And Process Valves

AECOM REBID

PART 3 - EXECUTION

3.01 Valve Shipment and Storage

A. Provide flanged openings with metal closures at least 3/16-inch thick, with elastomer

gaskets and at least four full-diameter bolts. Install closures at the place of valve

manufacture prior to shipping. For studded openings, use all the nuts needed for the

intended service to secure closures. Alternatively, ship flanged valves 3 inches and smaller

in separate sealed cartons or boxes.

B. Provide threaded openings with steel caps or solid-shank steel plugs. Do not use

nonmetallic (such as plastic) plugs or caps. Install caps or plugs at the place of valve

manufacture prior to shipping. Alternatively, ship valves having threaded openings or end

connections in separate sealed cartons or boxes.

C. Inspect valves on receipt for damage in shipment and conformance with quantity and

description on the shipping notice and order. Unload valves carefully to the ground without

dropping. Use forklifts or slings under skids. Do not lift valves with slings or chain around

operating shaft, actuator, or through waterway. Lift valves with eyebolts or rods through

flange holes or chain hooks at ends of valve parts.

D. Protect the valve and actuators from weather and the accumulation of dirt, rocks, and

debris. Do not expose rubber seats to sunlight or ozone for more than 30 days. Also, see

the manufacturer’s specific storage instructions.

E. Make sure flange faces, joint sealing surfaces, body seats, and disc seats are clean. Check

the bolting attaching the actuator to the valve for loosening in transit and handling. If loose,

tighten firmly. Open and close valves having manual or power actuators to make sure the

valve operates properly and that stops or limit switches are correctly set so that the valve

seats fully. Close valve before installing.

3.02 Factory Pressure Testing

A. Hydrostatically test the valve pressure-containing parts at the factory per the valve

specification or per the referenced standard. If no testing requirement is otherwise specified

or described in the referenced standards, then test with water for 30 minutes minimum at a

pressure of 1.5 times the rated pressure but not less than 20 psig. Test shall show zero

leakage. If leaks are observed, repair the valve and retest. If dismantling is necessary to

correct valve deficiencies, then provide an additional operational test and verify that the

valve components function.

B. The chloride content of liquids used to test austenitic stainless steel materials shall not

exceed 50 ppm. To prevent deposition of chlorides as a result of evaporative drying,

remove residual liquid from tested parts at the conclusion of the test.

3.03 Installing Valves--General

A. Remove covers over flanged openings and plugs from threaded openings, after valves have

been placed at the point to which the valves will be connected to the adjacent piping. Do

not remove valves from storage cartons or boxes until they are ready to be installed.

Page 47: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-20 Manual, Check, And Process Valves

AECOM REBID

B. Handle valves carefully when positioning, avoiding contact or impact with other

equipment, vault or building walls, or trench walls.

C. Clean valve interiors and adjacent piping of foreign material prior to making up valve to

pipe joint connection. Prepare pipe ends and install valves in accordance with the pipe

manufacturer’s instructions for the joint used. Do not deflect pipe-valve joint. Do not use a

valve as a jack to pull pipe into alignment. The installation procedure shall not result in

bending of the valve/pipe connection with pipe loading.

D. Make sure valve ends and seats are clean. Check exposed bolting for loosening in transit

and handling and tighten to manufacturer’s recommendations. Open and close the valve to

make sure it operates properly and that stops or limit switches are correctly set so that the

vane, ball, gate, needle, diaphragm, disc, plug, or other seating element seats fully. Close

the valve before installing. Check coatings for damage and repair. Handle valves carefully

when positioning, avoiding contact or impact with other equipment or structures.

E. Prior to assembly, coat threaded portions of stainless steel bolts and nuts with lubricant.

3.04 Installing Exposed Valves

A. Unless otherwise indicated in the drawings, install valves in horizontal runs of pipe having

centerline elevations 4 feet 6 inches or less above the floor with their operating stems

vertical. Install valves in horizontal runs of pipe having centerline elevations between 4

feet 6 inches and 6 feet 9 inches above the floor with their operating stems horizontal.

B. Install valves on vertical runs of pipe that are next to walls with their stems horizontal,

away from the wall. Valves on vertical runs of pipe that are not located next to walls shall

be installed with their stems horizontal, oriented to facilitate valve operation.

3.05 Installing Buried Valves

A. Connect the valve, coat the flanges, apply tape wrapping or polyethylene encasement, and

place and compact the backfill to the height of the valve stem.

B. Place block pads under the extension pipe to maintain the valve box vertical during

backfilling and repaving and to prevent the extension pipe from contacting the valve

bonnet.

C. Mount the upper slip pipe of the extension in midposition and secure with backfill around

the extension pipe. Pour the concrete ring allowing a depression so the valve box cap will

be flush with the pavement surface.

D. In streets without concrete curbs and in open areas, install the valve box as for a paved area

with concrete curb except include a marker post. Cut the marker post from 4-inch by 4-inch

dense structural grade Southern Pine No. 2 surfaced on four sides to a length of 5 feet.

Chamfer the top. Set the post in concrete, 2 feet into the ground, away from traffic, and to

the side of the pipeline. Coat with a seal and finish coat of white alkyd exterior paint. On

the side facing the valve, letter in black the word "VALVE" and the distance in feet from

the marker post to the valve box cap.

Page 48: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-21 Manual, Check, And Process Valves

AECOM REBID

3.06 Field Coating Buried Valves

A. Coat flanges of buried valves and the flanges of the adjacent piping, and the bolts and nuts

of flanges and mechanical joints, per Section 09900, System No. 24.

B. Wrap buried metal valves 6 inches and larger with polyethylene sheet per Section 09954

3.07 Installing Eccentric Plug Valves

A. Unload, store, and install in accordance with AWWA C517, Appendix A and the

following. Unload valves carefully to the ground without dropping. On valves larger than

12 inches, use forklifts or slings under skids. On smaller valves, do not lift valves with

slings or chain around actuator or through waterway. Lift these valves with eyebolts or

rods through flange holes or chain hooks at the ends of valve parts. If it is not practical to

store the valve indoors, protect the valve and actuators from weather and the accumulation

of dirt, rocks, and debris.

B. Install such that the rotation of the plug is about a horizontal axis. Install such that the plug

stores in the top when the valve is open.

C. Orient the valve such that the seat is opposite the high-pressure side.

3.08 Assembling Joints

A. Bolt holes of flanged valves shall straddle the horizontal and vertical centerlines of the pipe

run to which the valves are attached. Clean flanges by wire brushing before installing

flanged valves. Clean flange bolts and nuts by wire brushing, lubricate threads with oil and

graphite, and tighten nuts uniformly and progressively. If flanges leak under pressure

testing, loosen or remove the nuts and bolts, reseat or replace the gasket, reinstall or

retighten the bolts and nuts, and retest the joints. Joints shall be watertight.

B. Install lug-type valves with separate hex head machine bolts at each bolt hole and each

flange (two bolts per valve bolt hole).

3.09 Installing Extension Stem Guide Brackets

Install at 6- to 8-foot centers. Provide at least two support brackets for stems longer than 10 feet,

with one support near the bottom of the stem and one near the top.

3.10 Mounting Gear Actuators

The valve manufacturer shall select and mount the gear actuator and accessories on each valve

and stroke the valve from fully open to fully closed prior to shipment.

3.11 Field Installation of Gear Actuator

Provide the actuator manufacturer's recommended lubricating oil in each actuator before

commencing the field testing.

Page 49: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15100-22 Manual, Check, And Process Valves

AECOM REBID

3.12 Valve Field Testing

A. Test valves for leakage at the same time that the connecting pipelines are hydrostatically

tested. See Section 15144 for pressure testing requirements. Protect or isolate any parts of

valves, actuators, or control and instrumentation systems whose pressure rating is less than

the pressure test. Valves shall show zero leakage. Repair or replace any leaking valves and

retest.

B. Operate manual valves through three full cycles of opening and closing. Valves shall

operate from full open to full close without sticking or binding. Do not backfill buried

valves until after verifying that valves operate from full open to full closed. If valves stick

or bind, or do not operate from full open to full closed, repair or replace the valve and

repeat the tests.

C. Gear actuators shall operate valves from full open to full close through three cycles without

binding or sticking. The pull required to operate handwheel- or chainwheel-operated valves

shall not exceed 80 pounds. The torque required to operate valves having 2-inch AWWA

nuts shall not exceed 150 ft-lbs. If actuators stick or bind or if pulling forces and torques

exceed the values stated previously, repair or replace the actuators and repeat the tests.

Operators shall be lubricated in accordance with the manufacturer's recommendations prior

to operating.

END OF SECTION

Page 50: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15108-1 Air-Release And Vacuum-Relief Valves

AECOM REBID

SECTION 15108

AIR-RELEASE AND VACUUM-RELIEF VALVES

PART 1 - GENERAL

1.01 Description

This section includes materials and installation of air-release valves for sewage service.

1.02 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following.

B. Submit manufacturer's catalog data and detail drawings showing valve parts and describe

by material of construction, specification (such as AISI, ASTM, SAE, or CDA), and grade

or type. Show linings and coatings.

PART 2 - MATERIALS

2.01 Type C: Valve Design and Operation

A. The air-release and vacuum relief valve shall be of a single chamber design with solid

cylindrical polyproyl control floats housed in a reinforced nylon body. The valve shall

have an integral orifice mechanism which shall operate automatically to limit transient

pressure rise or shock induced by closure to 2 x valve rated working pressure.

B. Air-release valve shall be of the rolling seal mechanism type (patented by A.R.I.) and shall

incorporate a two-piece body, polypropyl floats with a brass drainage outlet valve.

C. The intake orifice area shall be equal to the nominal size of the valve. The large orifice

sealing shall be affected by the flat face of the control float seating against a nitrile rubber

O-ring housed in dovetail groove circumferentially surrounding the orifice. Discharge of

pressurized air shall be controlled by the seating and unseating of a small orifice nozzle on

a natural rubber seal affixed into the control float. The nozzle shall have a flat seating land

surrounding the orifice.

D. Provide a brass ASTM A124 bleed cock with fiber seal.

E. Prior to the ingress of liquid into the valve chamber, as when the pipeline is being filled,

valves shall vent through the large orifice. At higher water approach velocities, the valve

shall automatically discharge air through the orifice mechanism and reduce water approach

velocity.

Page 51: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15108-2 Air-Release And Vacuum-Relief Valves

AECOM REBID

F. Valve shall not exhibit leaks or weeping of liquid past the large orifice seal at operating

pressures of 3 psi to twice rated working pressure. Working pressure shall be assumed to

be 75 psi.

G. Valves shall respond to the presence of air by discharging it through the small orifice at

any pressures within the specified design range and shall remain leak tight in the absence

of air.

H. Valves shall react immediately to pipeline drainage or water column separation by the full

opening of the large orifice so as to allow unobstructed air intake at the lowest possible

negative internal pipeline pressure.

2.02 Type C: Materials of Construction

A. Materials of construction for air release, air and vacuum, and combination air valves for

water service shall be as follows:

Item Material Specification

Body, base, clamping stem and seal

plug assembly

Reinforced Nylon --

Stem clamp, spring washer, crown nut,

fasteners, other internal metal parts

Stainless steel AISI Type 316

O-ring BUNA-N --

Floats Foamed

polypropyl

--

Stopper Acetal --

B. Rubber seats shall be made of a rubber compound that is resistant to sewage.

2.03 Seating

Valves shall seat driptight at a pressure of 3 psi.

2.04 Valve End Connections

A. Valves 2 inches and smaller shall have threaded ends.

B. Threaded ends shall comply with ANSI B1.20.1.

2.05 Valves

Sewage Air-Release Valves, 2 Inch: Valves shall have an operating pressure of 150 psi. Valves

shall be A.R.I. Model D-025 reinforced nylon, Val-Matic Model VM-801A, or equivalent.

Page 52: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15108-3 Air-Release And Vacuum-Relief Valves

AECOM REBID

PART 3 - EXECUTION

3.01 Installation

Clean threaded joints by wire brushing or swabbing. Apply Teflon joint compound or Teflon tape

to pipe threads before installing threaded valves. Joints shall be watertight.

3.02 Valve Pressure Testing

Test valves at the same time that the connecting pipelines are pressure tested. See Section 15144

for pressure testing requirements. Protect or isolate any parts of valves, operators, or control and

instrumentation systems whose pressure rating is less than the test pressure.

END OF SECTION

Page 53: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15109-1 Fire Hydrants

AECOM REBID

SECTION 15109

FIRE HYDRANTS

PART 1 - GENERAL

1.01 Description

This section includes materials, testing, and installation of dry barrel fire hydrants.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Trenching, Backfilling, and Compacting: 02223.

C. Manual, Check, and Process Valves: 15100.

D. Ductile-Iron Pipe: 15240.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit certificate of compliance with AWWA C502.

C. Submit manufacturer's catalog data and descriptive literature. Show materials of

construction. Submit dimensional drawings. Show coatings.

PART 2 - MATERIALS

2.01 Fire Hydrant Selection

Provide fire hydrants of the dry barrel design, compression type conforming to AWWA C502

“Standard for Dry-Barrel Fire Hydrants” and additional requirements as set forth herein.

2.02 Dry Barrel Fire Hydrant Design

A. Hydrants shall have breakaway upper sections capable of ready replacement without loss in

the event of traffic damage. Each hydrant shall have a 6” bottom inlet connection and valve

opening at least 5-1/4 inches in diameter. Hydrants shall have a national standard pentagon

1.5 inch, point to flat operation nut and turn to the left (counter-clockwise) to open. Each

hydrant shall be fitted with one 4-1/2 inch pumper connection and two 2-1/2 inch hose

connections, both having threads that conform to the Fire Division Standard for the area.

Hose caps shall be chained to the hydrant barrel and fitted with nuts the same size as the

hydrant operation nuts.

Page 54: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15109-2 Fire Hydrants

AECOM REBID

B. Each hydrant shall have a barrel of sufficient length to bring the bottom of the 6” pipe

connection 3 feet below the surface of the finished ground. Each hydrant shall have

breakaway flanges and be made in at least two sections bolted together. Interior working

parts of the hydrant shall be removable from the top of the hydrant to allow repairs without

removing the hydrant barrel after it has been installed. Hydrants shall have renewable O-

ring stem seals. Hydrant barrels shall be painted AWWA Safety Yellow or as specified by

the appropriate fire district. They shall be designed for a working pressure of 150 lbs.

C. Hydrant shall have no drain parts. If parts exist, they shall be plugged with a threaded plug.

D. Operating stem shall be equipped with anti-friction thrust bearing to reduce operating

torque and assure easy opening. Provide stops to limit stem travel. Enclose stem threads in

a permanently sealed lubricant reservoir with O-ring seals.

E. Hydrants shall be designed for 150 psi working pressure and shop tested to 300 psi

pressure with main valve both open and closed. Under test the valve shall not leak, the

automatic drain shall function and there shall be no leakage into the bonnet.

F. Hydrants shall be of the current year’s manufacture when construction commenced.

G. Hydrants shall be AVK Model 2780 (or Owner Approved Equivalent) per IWSD

standards.

2.03 Bronze Components in Contact with Water

Bronze shall have the following chemical characteristics:

Constituent Content

Zinc 7% maximum

Aluminum 2% maximum

Lead 8% maximum

Copper + Nickel + Silicon 83% minimum

2.04 Wrenches

Provide one wrench to operate the hydrant for every three hydrants in the project.

PART 3 - EXECUTION

3.01 Painting and Coating

A. Coat hydrant top section and the exposed portion of the bury section per Section 09900,

System No. 10. Apply prime coat at factory. Color of finish coat shall be AWWA Safety

Yellow per Collier County standards, unless directed otherwise by the Owner. Apply finish

coat in field.

B. Coat buried ductile iron per Section 15240.

Page 55: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15109-3 Fire Hydrants

AECOM REBID

C. If cement-mortar coated bury sections are used, hold back the mortar coating so it does not

extend more than 2 inches above grade.

3.02 Factory Testing

Test per AWWA C502, Section 5.

3.03 Installation

A. Install with the face of the bottom flange of the barrel 4 to 6 inches above the adjacent

ground or paving.

B. Install hydrants so that the distance from the curb face to a hydrant outlet is no less than 2

feet and no greater than 6 feet.

C. Provide thrust block on buried elbow as detailed in the drawings.

END OF SECTION

Page 56: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15111-1 Spring-Actuated Control Valves

AECOM REBID

SECTION 15111

SPRING-ACTUATED CONTROL VALVES

PART 1 - GENERAL

1.01 Description

This section includes requirements for materials and installation of spring-loaded, direct-actuated

control valves acting as pressure-reducing, pressure-relief, backpressure, and regulating valves

for water.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Pressure Testing of Piping: 15144.

C. Manual, Check, and Process Valves: 15100.

D. Equipment, Piping, Duct, and Valve Identification: 15075.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions Section, 01300 and the

following:.

B. Submit dimensional drawings for each size and type of valve provided.

C. Submit manufacturer’s catalog data and detail drawings showing valve parts and describe

by material of construction, specification (such as AISI, ASTM, SAE, or CDA), and grade

or type. Show manufacturer's recommended maximum operating pressure and maximum

recommended flow. Show linings and coatings. Identify each valve by tag number to

which the catalog data and detail sheets pertain.

PART 2 - MATERIALS

2.01 Valve Identification

Valves are identified in the drawings by size and type number. For example, a callout in the

drawings of 1" V-1401 refers to a Type 1401 valve in these specifications which is a spring-

actuated pressure regulator.

2.02 Valve End Connections

A. Unless otherwise specified, valves 2 inches and smaller shall have threaded ends. Valves

larger than 2 inches shall have flanged ends.

Page 57: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15111-2 Spring-Actuated Control Valves

AECOM REBID

B. Cast-iron flanges shall comply with ASME B16.1, Class 125. Carbon steel and stainless

steel flanges shall comply with ASME B16.5, Class 150. Flanges shall be flat face.

C. Threaded ends shall comply with ASME B1.20.1.

2.03 Coating for Metallic Valves

Coat metal (other than stainless steel and bronze or brass) valves the same as the adjacent piping.

If the adjacent piping is not coated, then coat valves per Section 09900, System No. 10.Apply the

specified prime coats at the place of manufacture. Apply intermediate and finish coats in the field.

Finish coat shall match the color of the connecting piping. Do not coat aluminum or stainless

steel valves.

2.04 Bronze

Bronze in contact with water shall have the following chemical constituents:

Constituent Content

Zinc 7% maximum

Aluminum 2% maximum

Lead 8% maximum

Copper + Nickel + Silicon 83% minimum

2.05 Valves

A. Type 1401 – Spring-Actuated Pressure Regulators for Water Service:

1. Spring-actuated regulators 2 inches and smaller shall automatically convert high,

varying inlet water pressure to a lower, constant outlet pressure. Provide a valve

design consisting of a spring in a chamber acting on a diaphragm that transmits

motion to the valve. Outlet pressure shall be adjustable by turning an adjusting

screw to vary spring tension. Body shall be bronze. Diaphragm shall be nitrile.

Maximum inlet pressure shall be at least 200 psi.

2. Outlet pressure shall be field adjustable over a range of 25 to 75 psi. Valves shall be

Watts Series 223, Fisher Type 75A, or equivalent.

B. Type 1402 – Spring-Actuated Pressure-Reducing Valves for Air and Water Service:

1. Valves shall be of the spring-loaded, direct-operated type for air and water service.

The valves shall automatically convert high, varying inlet pressure to a lower,

constant outlet pressure. Provide a valve design consisting of a spring in a chamber,

acting on a diaphragm that transmits motion to the valve. Outlet pressure shall be

adjustable by turning an adjusting handwheel to vary spring tension. Provide

pressure gauge integral with the valve, indicating outlet pressure. Body shall be

bronze or brass. Diaphragm shall be nitrile or rubber.

2 Outlet pressure shall be field adjustable over a range of 5 to 95 psi. Valves shall be

Leslie Class AWRG, Fisher Series 67, or equivalent.

Page 58: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15111-3 Spring-Actuated Control Valves

AECOM REBID

C. Type 1430 – PVC Pressure-Relief or Backpressure Valves for Chemical Service:

Relief and backpressure valves shall be of the spring-actuated type, with an adjusting

screw to change the relief or backpressure pressure setting. Pressure setting shall be field

adjustable over a range of 5 to 100 psi. Bodies shall be PVC conforming to ASTM A1784,

Type I, Grade 1. Shafts shall be Teflon. Seals shall be Viton. Valves shall be Plast-O-Matic

Type RVT, Harrington, or equivalent.

2.06 Valve Tagging and Identification

Provide identifying valve tags per Section 15075.

PART 3 - EXECUTION

3.01 Valve Installation

Clean threaded joints by wire brushing or swabbing. Apply Teflon joint compound or Teflon tape

to pipe threads before installing threaded valves. Joints shall be leaktight.

3.02 Field Testing

A. Test valves at the same time that the connecting pipelines are pressure tested. See Section

15144 for pressure testing requirements. Protect or isolate any parts of valves, operators, or

control and instrumentation systems whose pressure rating is less than the test pressure.

Valve bodies and joints shall have zero leakage.

B. Run water through liquid service valves and air through air or gas service valves and assure

that valves regulate or sustain pressure to the specified setting. Duration of this test shall be

at least 10 minutes.

END OF SECTION

Page 59: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15112-1 Backflow Preventers

AECOM REBID

SECTION 15112

BACKFLOW PREVENTERS

PART 1 - GENERAL

1.01 Description

This section includes materials and installation of reduced pressure backflow preventers.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Pressure Testing of Piping: 15144.

C. Manual, Check, and Process Valves: 15100.

D. Equipment, Piping, Duct, and Valve Identification: 15075.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit manufacturer's certificate of compliance with AWWA C511 for backflow

preventers. Submit manufacturer's certificate of compliance with NSF 61.

C. Provide manufacturer's certification that materials are lead free.

D. Submit dimensional drawings for each size and type of backflow preventer.

E. Submit manufacturer’s catalog data and detail drawings showing backflow preventer parts

and describe by material of construction, specification (such as AISI, ASTM, SAE, or

CDA), and grade or type. Show manufacturer’s recommended maximum operating

pressure and maximum recommended flow. Show linings and coatings. Identify each

backflow preventer by tag number to which the catalog data and detail sheets pertain.

F. Submit certificate of approval of backflow preventer device by Collier County.

G. Submit certificate of backflow preventer installation by a certified installer. Installer shall

be certified by Collier County.

PART 2 - MATERIALS

2.01 Backflow Preventers

A. Backflow preventers shall be of the reduced pressure type, complying with AWWA C511.

Provide two independently operating check valves, two shutoff valves, an automatic

Page 60: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15112-2 Backflow Preventers

AECOM REBID

pressure differential relief valve, and test cocks so that a test of each check valve can be

made. Design backflow preventers for cold-water service.

B. Backflow preventers of sizes 2 inches and smaller shall have bronze (ASTM B61 or B62)

check valves. Check valves shall be of the poppet type and have replaceable seats.

C. Backflow preventers 2 inches and larger shall have check valves of either the poppet or the

toggle lever type. Check valves larger than 2 inches shall have cast-iron (ASTM A126,

Class B) body and cover.

D. Differential relief valve shall be bronze (ASTM B61 or B62) with Type 304 or 316

stainless steel trim.

E. Isolation valves shall be Type V-100 gate or Type V-300 ball per Section 15100 for

backflow preventers smaller than 3 inches and Type V-130, V-180, or V-185 gate valve

per Section 15100 for backflow preventers 3 inches and larger.

F. Backflow preventers shall be Clayton Model RP, Mueller Model FRP-II or 6CM, or

equivalent.

2.02 Bronze Components

Bronze in contact with water shall have the following chemical constituents:

Constituent Content

Zinc 7% maximum

Aluminum 2% maximum

Lead 8% maximum

Copper + Nickel + Silicon 83% minimum

PART 3 - EXECUTION

3.01 Painting and Coating

A. Coat backflow preventers including isolation valves the same as the adjacent piping. If the

adjacent piping is not coated, then coat per Section 09900, System No. 10. Apply the

specified prime coat at the place of manufacture. Apply intermediate and finish coats in

field. Do not coat bronze or stainless steel items. Finish coat shall match the color of the

adjacent piping.

B. Line backflow preventers 4 inches and larger (including isolation valves) on the interior

metal parts, excluding seating areas and bronze and stainless steel pieces per Section

09900, System No. 7.

C. Shipment and Storage

D. Identify the equipment with item and serial numbers and project equipment tag numbers.

Material shipped separately shall be identified with securely affixed, corrosion-resistant

metal tags indicating the item and serial number and project equipment tag numbers of the

Page 61: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15112-3 Backflow Preventers

AECOM REBID

equipment for which it is intended. In addition, ship crated equipment with duplicate

packing lists, one inside and one on the outside of the shipping container.

E. Pack and ship one copy of the manufacturer’s standard installation instructions with the

equipment. Provide the instructions necessary to preserve the integrity of the storage

preparation after the equipment arrives at the jobsite and before start-up.

F. Provide flanged openings with metal closures at least 3/16-inch thick, with elastomer

gaskets and at least four full-diameter bolts. Provide closures at the place of pump

manufacture prior to shipping. For studded openings, use all the nuts needed for the

intended service to secure closures.

G. Provide threaded openings with steel caps or solid-shank steel plugs. Do not use

nonmetallic (such as plastic) plugs or caps. Provide caps or plugs at the place of pump

manufacture prior to shipping.

H. Clearly identify lifting points and lifting lugs on the equipment or equipment package.

Identify the recommended lifting arrangement on boxed equipment.

3.02 Installation of Backflow Preventers

A. Installation shall be done by an installer certified in Collier County.

B. Do not use duct tape and plastic for covering the ends of pipe flanges. Use a solid metal

cover with rubber gasket to cover flange openings during installation. These metal covers

shall remain in place until the piping is connected to the equipment.

C. Do not spring flanges of connecting piping into position. Separately work inlet and outlet

piping systems into position to bring the piping flanges into alignment with the matching

equipment flanges. Do not move equipment to achieve piping alignment. Do not use

electrical heating stress relieving to achieve piping alignment.

D. Line up pipe flange bolt holes with machinery nozzle bolt holes within 1/16 inch maximum

offset from the center of the bolt hole to permit insertion of bolts without applying any

external force to the piping.

E. Flange face separation shall be within the gasket spacing ±1/16 inch. Use only one gasket

per flanged connection.

3.03 Field Testing

Pressure test the backflow preventers along with the connecting piping per Section 15144. There

shall be no visible leaks in the backflow preventer assembly, valves, or joints of the

interconnecting piping.

END OF SECTION

Page 62: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-1 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

SECTION 15122

FLEXIBLE PIPE COUPLINGS AND EXPANSION JOINTS

PART 1 - GENERAL

1.01 Description

This section includes materials and installation of flexible gasketed sleeve-type compression pipe

couplings for steel and ductile-iron pipe; flexible expansion joints; and couplings for connecting

different pipe materials.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Polyethylene Sheet Encasement (AWWA C105): 09954.

C. Fusion-Bonded Epoxy Linings and Coatings: 09961.

D. Cathodic Protection and Joint Bonding: 264213.

E. Piping Schedule and General Piping Requirements: 15050A.

F. Pressure Testing of Piping: 15144.

G. Wall Pipes, Seep Rings, and Penetrations: 15062.

H. Pipe Hangers and Supports: 15064.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit manufacturer's catalog data on flexible pipe couplings, and expansion joints. Show

manufacturer's model or figure number for each type of coupling or joint for each type of

pipe material for which couplings and joints are used. Show coatings.

C. Submit manufacturer's recommended torques to which the coupling bolts shall be tightened

for the flexible gasketed sleeve-type compression pipe couplings.

D. Show materials of construction by ASTM reference and grade. Show dimensions.

E. Show number, size, and material of construction of tie rods and lugs for each thrust harness

on the project.

Page 63: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-2 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

PART 2 - MATERIALS

2.01 Coupling System Design and Component Unit Responsibility

The coupling manufacturer shall furnish the gaskets, bolts, nuts, glands, end rings, and hardware

for pipe couplings of all types and shall design these components as an integral system. Design

the gaskets for the coupling and appropriately size to provide a watertight seal at the design

pressure and temperature. Ship gaskets, bolts, nuts, glands, end rings, and hardware for pipe

couplings with the pipe coupling and clearly label indicating the origin of the material, including

place and date of manufacture. Package the manufacturer's printed installation instructions with

each pipe coupling.

2.02 Carbon Steel Flexible Pipe Couplings and Flanged Coupling Adapters

A. Steel couplings shall have center sleeves and end rings made of carbon steel conforming to

AWWA C219, Section 4. Minimum center sleeve length shall be 5 inches for pipe sizes

3/4 inch through 4 1/2 inches, 7 inches for pipe sizes 5 inches through 24 inches, and 10

inches for pipe sizes larger than 24 inches.

B. Sleeve bolts in exposed service shall be carbon steel per AWWA C219, Section 4. Sleeve

bolts in buried or submerged service shall be Type 304 stainless steel per AWWA C219,

Section 4.

C. End rings shall be cast, forged, or hot rolled in one piece. Do not use rings fabricated from

two or more shapes.

D. Wall thickness of sleeve shall be at least that specified for the size of pipe in which the

coupling is to be used.

2.03 Ductile-Iron Flexible Pipe Couplings

A. Couplings shall have center sleeves and end rings made of ductile iron conforming to

AWWA C219, Section 4.

B. Sleeve bolts in exposed service shall be carbon steel per AWWA C219, Section 4. Sleeve

bolts in buried or submerged service shall be Type 304 stainless steel per AWWA C219,

Section 4.

2.04 Joint Harnesses

A. Tie bolts or studs shall be as shown in the following table. Bolt or stud material shall

conform to ASTM A193, Grade B7. Nuts shall conform to ASTM A194, Grade 2H. Lug

material shall conform to ASTM A36, ASTM A283, Grade B, C, or D, or ASTM A285,

Grade C. Lug dimensions for steel pipe shall be as shown in AWWA Manual M11 (2004

edition), Figure 13-20, using the number and size of lugs as tabulated below.

B. Lugs for steel pipe shall be Type P for pipes 6 through 10 inches and Type RR for pipes 12

inches and larger. Lug or ear dimensions for ductile-iron pipe shall be as shown in the

drawings.

Page 64: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-3 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

TIE BOLTS OR STUD REQUIREMENTS FOR FLEXIBLE PIPE COUPLINGS

FOR STEEL PIPE

Tie Bolt or Stud Minimum Requirements

150 psi 300 psi

Nominal

Pipe Size

(inches)

No. Bolts or

Studs and

Size

(inches)

Minimum

Pipe Wall

Thickness

(inches)

No. Bolts or

Studs and

Size

(inches)

Minimum

Pipe Wall

Thickness

(inches)

6 2 x 5/8 0.193 2 x 5/8 0.282

8 2 x 5/8 0.239 2 x 5/8 0.354

10 2 x 5/8 0.312 2 x 3/4 0.466

12 2 x 3/4 0.188 4 x 7/8 0.250

14 2 x 7/8 0.188 4 x 1 0.250

16 2 x 1 0.250 4 x 1 1/8 0.250

18 2 x 1 1/8 0.250 4 x 1 1/8 0.250

20 2 x 1 1/4 0.250 4 x 1 1/8 0.250

24 4 x 7/8 0.250 4 x 1 1/8 0.250

30 4 x 1 1/8 0.250 4 x 1 3/8 0.375

36 4 x 1 3/8 0.313 6 x 1 3/8 0.375

42 6 x 1 1/4 0.375 6 x 1 5/8 0.375

48 6 x 1 3/8 0.375 6 x 1 3/4 0.500

54 6 x 1 1/2 0.375 8 x 1 3/4 0.625

60 6 x 1 5/8 0.375 12 x 1 3/4 0.625

66 8 x 1 5/8 0.469 14 x 1 3/4 0.688

72 8 x 1 3/4 0.500 14 x 1 7/8 0.750

Page 65: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-4 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

TIE BOLTS OR STUD REQUIREMENTS FOR FLEXIBLE PIPE COUPLINGS FOR

DUCTILE IRON PIPE

Tie Bolt or Stud Minimum Requirements

150 psi(1)

300 psi(2)

Pipe

Nominal Pipe

Size

(inches)

No. Bolts or

Studs

Size

(inch)

Ear(3)

Type

No. Bolts or

Studs

Size

(inch)

Ear(3)

Type

4 2 5/8 A 2 5/8 A

6 2 5/8 A 2 5/8 A

8 2 5/8 A 2 5/8 A

10 2 5/8 A 4 5/8 A

12 2 5/8 A 4 5/8 A

14 4 5/8 A 5 3/4 A

16 4 5/8 A 5 3/4 B

18 4 3/4 B 8 3/4 B

20 4 3/4 B 8 3/4 B

24 5 7/8 B 8 7/8 B

30 4 1 1/8 B 14 7/8 B

36 8 1 B 16 1 B

42 9 1 B -- -- --

48 14 1 B -- -- --

54 16 1 B -- -- --

(1) Use ASME B16.1 Class 125 flanges.

(2) Use ASME B16.1 Class 250 flanges.

(3) Ear type as shown in the detail on the last page of Section 15122.

C. Select number and size of bolts based on the test pressure shown in the Piping Schedule in

the drawings and/or Section 15144. Stagger bolts equally around pipe circumference.

Where odd number is tabulated, place odd bolt at top. For test pressures less than or equal

to 150 psi, use the 150-psi design in the table above. For test pressures between 150 and

300 psi, use the 300-psi design in the table above.

D. Provide washer for each nut. Washer material shall be the same as the nuts. Minimum

washer thickness shall be 1/8 inch.

2.05 Flexible Pipe Couplings for Plain-End Steel Pipe

Couplings shall be stainless steel, Dresser Style 38, Smith-Blair Type 411, Baker Series 200, or

equivalent.

2.06 Flexible Pipe Couplings for Plain-End Ductile-Iron Pipe

A. Couplings for pipe 12 inches and smaller shall be cast iron, Dresser Style 253 or 253 long

sleeve, Smith-Blair Type 441, Baker Series 228, or equivalent.

Page 66: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-5 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

B. Couplings for pipe larger than 12 inches shall be cast iron or steel, Dresser Style 38 or 253,

Smith-Blair Style 411, Baker Series 228, or equivalent.

2.07 Transition Couplings

Couplings for connecting different pipes having different outside diameters shall be steel: Dresser

Style 62 or 162, Smith-Blair Series 413, Baker Series 212 or 220, or equivalent. Couplings shall

have an internal full circumference ring pipe stop at the midpoint of the coupling. Inside diameter

of coupling pipe stop shall equal inside diameter of smaller diameter pipe.

2.08 Flanged Coupling Adapters for Steel Pipe

Adapters for steel pipe shall be steel: Dresser Style 128, Smith-Blair Type 913, or equivalent.

Flange ends shall match the flange of the connecting pipe; see detail piping specifications.

2.09 Flanged Coupling Adapters for Cast- and Ductile-Iron Pipe

A. Adapters for cast- and ductile-iron pipe 12 inches and smaller shall be cast iron: Dresser

Style 127, Smith-Blair Series 912, or equivalent.

B. Adapters for cast- and ductile-iron pipe larger than 12 inches shall be steel: Dresser Style

128, Smith-Blair Type 913, or equivalent.

C. Flange ends shall match the flange of the connecting pipe; see detail piping specifications.

2.10 Type 1 Expansion Joints: For Copper Pipe

Expansion joints for copper pipe shall be all bronze: Metraflex Model HPMF expansion

compensator, Hyspan Model 8509 or 8510 expansion compensator, or equivalent. Expansion

compensators shall have antitorque devices to protect the bellows. Minimum working pressure

shall be 175 psig.

2.11 Type 4 Expansion Joints: Spherical Expansion Joints

A. Spherical design expansion joints shall be chlorobutyl with polyester fiber reinforcing and

be provided with steel retaining rings and Type 304 stainless steel gusset plates and control

rods. Expansion joints shall have flat-face flanges integral with the body to match 125/150-

pound flanges. Expansion joints for hot water service shall be rated at a minimum of 150

psig at 212°F.

Joint Size

Flange-to-Flange Length

(inches)

Minimum Pressure Rating

(150°F)

(psi)

4 to 8 6 225

10 to 12 8 225

14 to 20 10 to 12 125

B. Expansion joints shall be manufactured by Metraflex Metrasphere, Proco Series 240, or

equivalent.

Page 67: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-6 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

2.12 Type 5 Expansion Joints: Single Arch Rubber Type (24 Inches and Smaller)

A. Expansion joints shall be rubber, single arch type, with integral flat-face ANSI Class

125/150 flanges.

1. Cover Elastomer: shall be suitable for exposure to sunlight but shall be limited to

Butyl, Neoprene, or Chlorobutyl.

2. Tube Elastomer: shall be suitable for the service intended, but shall be limited to

Butyl, Neoprene, Chlorobutyl, Hypalon®, or Nitrile.

3. Arch Type: Open .

4. Fluid: Raw sewage.

5. Fluid Temperature Range: 40°F to 105°F.

6. Ambient Temperature Range: 30°F to 120°F.

B. Minimum working pressure shall be 150 psi for joints 12 inches and smaller, 120 psi for

14- and 16-inch joints, 110 psi for 18- and 20-inch joints, and 100 psi for 24-inch joints.

Provide steel thrust plates, retaining rings, and control rods. Products: Proco Style 220,

General Rubber Style 1075, or equivalent.

2.13 Type 7: Elastomeric Coupling

Provide elastomeric couplings suitable for the pipe types and sizes to be connected. Elastomeric

coupling shall consist of an elastomeric plastic sleeve and Type 304 or 305 stainless steel pipe

clamps. Provide a minimum of two clamps for pipes up to 15 inches in outer diameter. Provide a

minimum of four clamps on a sleeve 10 inches long for pipes larger in diameter than 15 inches.

2.14 Type 8 Couplings: For Connecting Vitrified Clay Pipe to Plastic or Ductile-Iron Pipe

Couplings shall consist of a styrene butadiene (SBR) or neoprene rubber body with stainless steel

bands, housings, and clamps. The clamping device for couplings 10 inches and larger shall be

cold-rolled steel or stainless steel. Products: Calder Couplings for pipes 3 through 8 inches and

Ceramicweld Coupling for pipes 10 through 42 inches.

2.15 Bolts and Nuts for Flanges

See Section 15050A.

PART 3 - EXECUTION

3.01 Shipment and Storage of Flexible Pipe Couplings, and Expansion Joints

A. Inspect on receipt for damage in shipment and conformance with quantity and description

on the shipping notice and order. Unload carefully to the ground without dropping. Do not

load or unload by inserting forklift tines or lifting chains inside the waterway. Use

nonmetallic slings, padded chains, or padded forklift tines to lift items. Lift with eyebolts

or rods through flange holes or chain hooks at ends.

Page 68: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-7 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

B. Protect from weather and the accumulation of dirt, rocks, and debris. Do not expose rubber

seats to sunlight or ozone for more than 30 days. Also, see the manufacturer’s specific

storage instructions.

C. Make sure flange faces, joint sealing surfaces, body seats, and disc seats are clean.

3.02 Installation of Flexible Pipe Couplings, and Expansion Joints

A. Clean oil, scale, rust, and dirt from pipe ends. Clean gaskets in flexible pipe couplings

before installing.

B. Install expansion joints per manufacturer's recommendations, so that 50% of total travel is

available for expansion and 50% is available for contraction.

C. Do not spring flanges or ends of connecting piping into position. Separately work

connecting piping system into position to bring the piping flanges or ends into alignment

with the matching coupling flanges or joints. Do not move couplings to achieve piping

alignment.

D. The intent of this requirement is to ensure that flange bolts can be easily installed without

the application of external force.

E. Line up pipe flange bolt holes with coupling or joint flange bolt holes within 1/16 inch

maximum offset from the center of the bolt hole to permit insertion of bolts without

applying any external force to the piping.

F. Flange face separation shall be within the gasket spacing ±1/16 inch. Use only one gasket

per flanged connection.

G. Lubricate bolt threads with graphite and oil prior to installation.

H. The following text on assembling nuts for the bolts or studs used in harnessed flexible pipe

coupling is adapted from AWWA Manual M11, Chapter 13, section on “Joint Harnesses.”

I. Thoroughly clean contact surfaces of gaskets and pipe ends of flexible pipe couplings just

prior to assembly for a distance equal to center-sleeve length plus 2 inches. Install flexible

pipe couplings such that the center sleeves are centered over the gap between the ends of

the pipes being joined. Install centerline gaps per AWWA C219, Table 5 unless otherwise

indicated. Install harnessed flexible pipe couplings in straight-run piping such that 50% of

the total travel of the center sleeve or permissible centerline gap is available for expansion

and 50% of the travel is available for contraction. In assembling the bolted or studded

harnesses of flexible pipe couplings, tighten the nuts gradually and equally at diametrically

opposite sides until snug. Do not misalign the harness bolts or studs. Tighten such that

bolts or studs carry equal loads. Do not use wrenches or power fastening tools to tighten

the nuts.

3.03 Painting and Coating

A. Coat buried flexible pipe couplings (including joint harness assemblies), transition

couplings, and flanged coupling adapters per Section 09900, System No. 21. Coat buried

Page 69: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-8 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

bolt threads, tie bolt threads, and nuts per Section 09900, System No. 24. Then wrap the

couplings with polyethylene wrap per Section 09954.

B. Coat flexible pipe couplings (including joint harness assemblies), transition couplings, and

flanged coupling adapters located indoors, in vaults and structures, and above ground with

the same coating system as specified for the adjacent pipe. If the adjacent pipe is not

coated, coat couplings per Section 09900, System No. 10. Apply prime coat at factory.

C. Line carbon steel and iron flexible pipe couplings per Section 09900, System No. 7.

D. Alternatively, line and coat carbon steel and iron flexible pipe couplings and segmented

sleeve couplings with fusion-bonded epoxy per Section 09961.

E. Delete paragraph 5 if you are not using Types 7 and 8 couplings in your project. Note that

Types 7 and 8 couplings are only used in buried service.

F. Wrap Types 7 and 8 buried couplings with polyethylene per Section 09954.

G. Coat expansion joints, located above ground or in vaults and structures with the same

coating system as specified for the adjacent pipe. If the adjacent pipe is not coated, coat

couplings per Section 09900, System No. 10. Color shall match the color of the connecting

pipe.

3.04 Hydrostatic Testing

Hydrostatically test flexible pipe couplings, expansion joints, segmented sleeve couplings, and

expansion compensators in place with the pipe being tested. Test in accordance with Section

15144.

3.05 Pipe Hangers and Supports for Expansion Joints (Types 1)

A. At each expansion compensator or bellows-type expansion joint located on horizontal

piping runs, provide a pipe alignment guide within four pipe diameters of each end of the

expansion joint or compensator. Provide a second pipe alignment guide within 14 pipe

diameters of each end of the expansion joint or compensator.

B. Mount pipe alignment guides on wall brackets or steel channels as manufactured by Anvil

International, B-Line, or equal.

Page 70: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15122-9 Flexible Pipe Couplings And Expansion Joints

AECOM REBID

END OF SECTION

Page 71: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15123-1 Corporation Stops And Service Saddles

AECOM REBID

SECTION 15123

CORPORATION STOPS AND SERVICE SADDLES

PART 1 - GENERAL

1.01 Description

This section includes labor, materials and installation of service saddles and corporation stops.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Pressure Testing of Piping: 15144.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300, and the

following:

B. Submit manufacturer's catalog data and descriptive literature showing dimensions and

materials of construction by ASTM reference and grade. Show coatings.

PART 2 - MATERIALS

2.01 Corporation Stops

Corporation stops shall comply with AWWA C800 with inlets and outlets as tabulated below:

Type Inlet Connection Outlet Connection Manufacturer and Model

1 Outside I.P. Inside I.P. Less than 1 1/2 inches: Jones J-50,

Mueller H-10046 For sizes 1 1/2 and 2

inches: Jones J-1931, Ford FB-1700

2 Outside Corp.

Stop (AWWA

taper thread)

Inside I.P. Less than 1 1/2 inches: Jones J-51,

Mueller H-10045 For sizes 1 1/2 and 2

inches: Jones J-1932, Ford FB-1600

3 Outside Corp.

Stop (AWWA

taper thread)

Outside Coupling

Thread

Mueller H-9971, Ford F-200

4 Outside I.P. Outside I.P. Less than 1 1/2 inches: Jones J-41,

Mueller H-10013 For sizes 1 1/2 and 2

inches: Jones J-1943, Ford FB-500

Page 72: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15123-2 Corporation Stops And Service Saddles

AECOM REBID

Type Inlet Connection Outlet Connection Manufacturer and Model

5 Outside I.P. Copper Tubing Less than 1 1/2 inches: Jones J-1505,

Mueller H-15025 For sizes 1 1/2 and 2

inches: Jones J-1929, Ford FB-700

6 Outside Corp.

Stop (AWWA

taper thread)

Copper Tubing Less than 1 1/2 inches: Jones J-1500,

Mueller H-15050 For sizes 1 1/2 and 2

inches: Jones J-1930, Ford FB-600

2.02 Service Saddles for Ductile-Iron, Steel, and PVC (AWWA C900) Pipe

A. Type 1 service saddles shall be of the double-strap type. Bodies shall be malleable iron

(ASTM A47 or A197). Straps shall be forged steel (ASTM A105, A181, or A182). Tap

sizes on the outlet shall be 3/4 inch through 2 inches to accommodate the connecting

piping or corporation stops. Service saddles shall be Dresser Style 91, Smith-Blair Type

313, or equivalent.

B. Type 2 service saddles shall be of the double-strap type. Straps and bodies shall be bronze

or silicon bronze. Tap sizes on the outlet shall be 3/4 inch through 2 inches to

accommodate the connecting piping or corporation stops. Service saddles shall be James

Jones J-979 (for ductile-iron and steel pipe), James Jones J-996 (for PVC pipe), Mueller, or

equivalent.

C. Use Type 1 saddles unless plans direct otherwise.

2.03 Service Saddles for Schedule 40 and 80 PVC Pipe

Service saddles shall be malleable iron (ASTM A47 or A197) or bronze (ASTM B61 or B62),

using interlocking lugs and a single bolt to hold the saddle in place. Tap sizes on the outlet shall

be 3/4 inch or 1 inch to accommodate the connecting piping or corporation stops. Service saddles

shall be Dresser Style 194, Smith-Blair Models 395 or 397, or equivalent.

PART 3 - EXECUTION

3.01 Installation of Service Saddles

Install service saddles with the gaskets seated on the pipe so that zero leakage is obtained.

Tighten bolts to the torque recommended by the manufacturer.

3.02 Installation of Corporation Stops

A. Use a smooth-jawed adjustable wrench that fully and evenly engages the stop wrenching

flats. Place the wrench only on the stop body wrench flats. Do not use the rounded areas of

the stop body for tightening into the main or saddle. When connecting the outlet service

line, use two wrenches to make the connection. Use one wrench to support the corporation

stop and/or curb stop and the other wrench to tighten the service connection.

B. Backfill and compact soil around the corporation stop, curb stop, and service line to

prevent ground settling and damage to the valve or service line.

Page 73: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15123-3 Corporation Stops And Service Saddles

AECOM REBID

3.03 Field Pressure Testing of Corporation Stops and Service Saddles

A. Perform service line pressure testing prior to backfilling of buried service saddles and

corporation stops.

B. External leakage through the corporation stop body is not allowed. During testing of

ground key stops, the outlet may be capped to eliminate leakage through the stop’s closed

port opening. Test pressures shall not exceed 150% of the maximum working pressure

specified in AWWA C800. Cap stop outlets and test in the open position. When testing a

water main, if capping the corporation stop is impractical, test to the curb stop with the

corporation stop in the open position.

C. Test pressures on service saddles for attachment to plastic pipe should be limited to 150%

of the lower-rated component.

3.04 Painting and Coating of Service Saddles

A. Coat buried service saddles per Section 09900, System No. 21.

B. Coat submerged service saddles the same as the piping to which they are attached.

C. Coat service saddles located above ground or in vaults and structures per Section 09900,

System No. 10. Apply prime coat at factory. Color of finish coat shall match the color of

the pipe to which the service saddle is connected.

END OF SECTION

Page 74: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15141-1 Disinfection Of Piping

AECOM REBID

SECTION 15141

DISINFECTION OF PIPING

PART 1 - GENERAL

1.01 Description

This section includes materials and procedures for disinfection of water mains by the continuous

feed method and by the slug method. Disinfect piping in accordance with AWWA C651, except

as modified below.

1.02 Related Work Described Elsewhere

Pressure Testing of Piping: 15144.

1.03 Job Conditions

A. Discharge of chlorinated water into watercourses or surface waters is regulated by the

National Pollutant Discharge Elimination System (NPDES). Provide for the disposal of the

chlorinated disinfection water and the flushing water.

B. Schedule the rate of flow and locations of discharges in advance to permit review and

coordination with Owner and cognizant regulatory authorities: Collier County. The

allowable locations of discharges are to the retention or effluent basins and are shown in

the drawings:

C. Use potable water for chlorination.

D. Submit request for use of water from waterlines of Owner 48 hours in advance.

PART 2 - MATERIALS

2.01 Liquid Chlorine

Inject with a solution feed chlorinator and a water booster pump. Follow the instructions of the

chlorinator manufacturer.

2.01 Calcium Hypochlorite (Dry)

Dissolve in water to a known concentration in a drum and pump into the pipeline at a metered

rate.

2.03 Sodium Hypochlorite (Solution)

Further dilute in water to desired concentration and pump into the pipeline at a metered rate.

Page 75: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15141-2 Disinfection Of Piping

AECOM REBID

2.04 Chlorine Residual Test Kit

For measuring chlorine concentration, supply and use a medium range, drop count, DPD drop

dilution method kit per AWWA C651, Appendix A.1. Maintain kits in good working order

available for immediate test of residuals at point of sampling.

PART 3 - EXECUTION

3.01 Continuous Feed Method for Pipelines

Introduce potable water into the pipeline at a constant measured rate. Feed the chlorine solution

into the same water at a measured rate. Proportion the two rates so that the chlorine concentration

in the pipeline is maintained at a minimum concentration of 50 mg/L. Check the concentration at

points downstream during the filling to ascertain that sufficient chlorine is being added.

3.02 Slug Method for Pipelines

Introduce the water in the pipeline at a constant measured rate. At the start of the test section, feed

the chlorine solution into the pipeline at a measured rate so that the chlorine concentration created

in the pipeline is 100 mg/L. Feed the chlorine for a sufficient period to develop a solid column or

"slug" of chlorinated water that will, as it passes along the line, expose all interior surfaces to a

concentration of at least 100 mg/L for at least three hours.

3.03 Disinfection of Valves, Blind Flanges, and Appurtenances

During the period that the chlorine solution or slug is in the section of pipeline, open and close

valves to obtain a chlorine residual at hydrants and other pipeline appurtenances. Swab exposed

faces of valves and blind flanges prior to bolting flanges in place with a 1% sodium hypochlorite

solution.

3.04 Disinfection of Connections to Existing Pipelines

Disinfect isolation valves, pipe, and appurtenances per AWWA C651, Section 4.7. Flush with

potable water until discolored water, mud, and debris are eliminated. Swab interior of pipe and

fittings with a 1% sodium hypochlorite solution. After disinfection, flush with potable water

again until water is free of chlorine odor.

3.05 Disinfection of Tapping Sleeves

Flush exterior of pipe with potable water after removal of existing coating. Swab exterior of pipe

with a 1% sodium hypochlorite solution. Disinfect per AWWA C651, Section 4.8. After

completion of tapping, swab interior of pipe, valves, and faces of flanges to be connected to

bypass piping with a 1% sodium hypochlorite solution.

3.06 Confirmation of Residual in Piping

A. After the chlorine solution applied by the continuous feed method has been retained in the

pipeline for 24 hours, confirm that a chlorine residual of 10 mg/L minimum exists along

the pipeline by sampling at air valves and other points of access, such as tapping valves.

Page 76: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15141-3 Disinfection Of Piping

AECOM REBID

B. With the slug method, confirm by sampling as the slug passes each access point and as it

leaves the pipeline that the chlorine concentration in the slug is at least 50 mg/L.

3.07 Pipeline Flushing

After confirming the chlorine residual, flush the excess chlorine solution from the pipeline until

the chlorine concentration in the water leaving the pipe is within 0.5 mg/L of the replacement

water .

3.08 Sampling and Bacteriologic Testing

A. There shall be no water in trenches up to the connection for sampling. The sampling piping

shall be clean, disinfected, and flushed prior to sampling.

B. Collect two sets of samples per AWWA C651, Section 5.1, deliver to a certified laboratory

within six hours of obtaining the samples, and obtain a bacteriologic quality test to

demonstrate the absence of coliform organisms in each separate section of the pipeline

after chlorination and refilling. Collect at least one set of samples from every 1,200 feet of

the new water main, plus one set from the end of the pipeline and at least one set from each

branch. At each connection to an existing pipeline, take two additional samples. Use

pipeline blowoffs or dedicated sampling ports for obtaining samples.

3.09 Piping Test Facility Removal

After satisfactory disinfection, disinfect and replace air valves, restore the pipe coating, and

complete the pipeline where temporary disinfection or test facilities were installed.

3.10 Piping to be Disinfected

A. Disinfect piping as indicated on the Piping Schedule in the drawings except:

1. Sewers, reclaimed water, and drainage piping.

2. Storm drain piping.

3. Reinforced concrete and vitrified clay pipe.

3.11 Repetition of Procedure

If the initial chlorination fails to produce required residuals and bacteriologic tests, repeat the

chlorination and retesting until satisfactory results are obtained.

END OF SECTION

Page 77: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15144-1 Pressure Testing Of Piping

AECOM REBID

SECTION 15144

PRESSURE TESTING OF PIPING

PART 1 - GENERAL

1.01 Description

This section specifies the cleaning and hydrostatic and leakage testing of pressure piping for

wastewater treatment plants.

1.02 Related Work Specified Elsewhere

A. Leakage and Infiltration Testing: 02530.

B. Disinfection of Piping: 15141.

C. Manual, Check, and Process Valves: 15100.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions Section 01300 and the

following:

B. Submit test bulkhead locations and design calculations, pipe attachment details, and

methods to prevent excessive pipe wall stresses.

C. Submit six copies of the test records to the Owner's Representative upon completion of the

testing.

1.04 Test Pressures

Test pressures for the various services and types of piping are shown in the Piping Schedule in

the drawings or in the subsection on “Test Pressure and Test Fluids” in Part 3.

1.05 Testing Records

Provide records of each piping installation during the testing. These records shall include:

A. Date and times of test.

B. Identification of process, pipeline, or pipeline section tested or retested.

C. Identification of which piping was tested per the requirements of the Florida Plumbing

Code.

D. Identification of pipeline material.

E. Identification of pipe specification.

Page 78: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15144-2 Pressure Testing Of Piping

AECOM REBID

F. Test fluid.

G. Test pressure at low point in process, or pipeline section.

H. Remarks: Leaks identified (type and location), types of repairs, or corrections made.

I. Provide certification that the leakage rate measured conformed to the specifications.

PART 2 - MATERIALS

2.01 Vents and Drains for Aboveground Piping

Install vents on the high points of aboveground piping, whether shown in the drawings or not.

Install drains on low points of aboveground piping, whether shown in the drawings or not.

Provide a valve at each vent or drain point. Valves shall be 3/4 inch for piping 3 inches and larger

and 1/2 inch for piping smaller than 3 inches. Valves shall be as specified in Section 15100, Type

100 or 300, unless otherwise shown in the drawings.

2.02 Manual Air-Release Valves for Buried Piping

Provide temporary manual air-release valves for pipeline test. Construct the pipe outlet in the

same manner as for a permanent air valve and after use, seal with a blind flange, pipe cap, or plug

and coat the same as the adjacent pipe.

2.03 Test Bulkheads

Design and fabricate test bulkheads per Section VIII of the ASME Boiler and Pressure Vessel

Code. Materials shall comply with Part UCS of said code. Design pressure shall be at least 2.0

times the specified test pressure for the section of pipe containing the bulkhead. Limit stresses to

70% of yield strength of the bulkhead material at the bulkhead design pressure. Include air-

release and water drainage connections.

2.04 Testing Fluid

A. Testing fluid shall be water unless a pneumatic test is indicated on the Piping Schedule or

shown in the following subsections.

B. For potable water pipelines, obtain and use only potable water for hydrostatic testing.

C. Submit request for use of water from waterlines of Owner 48 hours in advance.

D. Water for testing may be obtained from the Owner at the Owner's rate of charges.

2.05 Testing Equipment

Provide calibrated pressure gauges, pipes, bulkheads, pumps, chart recorder, and meters to

perform the hydrostatic testing.

Page 79: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15144-3 Pressure Testing Of Piping

AECOM REBID

PART 3 - EXECUTION

3.01 Testing Preparation

A. Pipes shall be in place, backfilled, and anchored before commencing pressure testing.

B. Conduct pressure tests on exposed and aboveground piping after the piping has been

installed and attached to the pipe supports, hangers, anchors, expansion joints, valves, and

meters.

C. For buried piping, the pipe may be partially backfilled and the joints left exposed for

inspection during an initial leakage test. Perform the final pressure test after completely

backfilling and compacting the trench.

D. Provide any temporary piping needed to carry the test fluid to the piping that is to be

tested. After the test has been completed and demonstrated to comply with the

specifications, disconnect and remove temporary piping. Do not remove exposed vent and

drain valves at the high and low points in the tested piping; remove any temporary buried

valves and cap the associated outlets. Plug taps or connections to the existing piping from

which the test fluid was obtained.

E. Provide temporary drain lines needed to carry testing fluid away from the pipe being

tested. Remove such temporary drain lines after completing the pressure testing. Drain the

pipes after they have been tested, unless the Owner or his representative indicates

otherwise.

F. Notify the Owner's Representative one hour prior to starting the test.

3.02 Cleaning

A. Before conducting hydrostatic tests, flush pipes with water to remove dirt and debris.

Maintain a flushing velocity of at least 3 fps for water testing. Flush pipes for time period

as given by the formula

T = 2L

3

in which:

T = flushing time (seconds)

L = pipe length (feet)

B. For pipelines 24 inches or larger in diameter, acceptable alternatives to flushing are use of

high-pressure water jet, sweeping, or scrubbing. Water, sediment, dirt, and foreign material

accumulated during this cleaning operation shall be discharged, vacuumed, or otherwise

removed from the pipe.

3.03 Testing and Disinfection Sequence for Potable Water Piping

A. Perform required disinfection after hydrostatic testing, except when pipeline being tested is

connected to a potable waterline.

Page 80: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15144-4 Pressure Testing Of Piping

AECOM REBID

B. Locate and install test bulkheads, valves, connections to existing pipelines, and other

appurtenances in a manner to provide an air gap separation between existing potable water

pipelines and the pipeline being tested. Disinfect water and pipeline being tested before

hydrostatic testing when connected to a potable waterline.

3.04 Initial Pipeline Filling for Hydrostatic Testing

Maximum rate of filling shall not cause water velocity in pipeline to exceed 1 fps. Filling may be

facilitated by removing automatic air valves and releasing air manually.

3.05 Testing New Pipe Which Connects to Existing Pipe

Prior to testing new pipelines that are to be connected to existing pipelines, isolate the new line

from the existing line by means of test bulkheads, spectacle flanges, or blind flanges. After

successfully testing the new line, remove test bulkheads or flanges and connect to the existing

piping.

3.06 Hydrostatic Testing of Aboveground or Exposed Piping

A. Open vents at high points of the piping system to purge air while filling the pipe with

water. Venting during system filling may also be provided by temporarily loosening

flanges.

B. Subject the piping system to the test pressure indicated on the Piping Schedule in the

drawings. Maintain the test pressure for a minimum of four hours. Examine joints, fittings,

valves, and connections for leaks. The piping system shall show zero leakage or weeping.

Correct leaks and retest until zero leakage is obtained.

3.07 Hydrostatic Testing of Buried Piping

A. Where any section of the piping contains concrete thrust blocks or encasement, do not

perform the pressure test until at least 10 days after placing the concrete. When testing

mortar-lined or PVC piping, fill the pipe to be tested with water and allow it to soak for at

least 48 hours to absorb water before conducting the pressure test.

B. Apply and maintain the test pressure by means of a positive displacement hydraulic force

pump.

C. Maintain the test pressure for the following duration by restoring it whenever it falls an

amount of 5 psi:

Pipe Diameter

(inches)

Hours

18 and less 4

20 to 36 8

Greater than 36 24

D. After the test pressure is reached, use a meter to measure the additional water added to

maintain the pressure. This amount of water is the loss due to leakage in the piping system.

The allowable leakage volume is defined by the formula

Page 81: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15144-5 Pressure Testing Of Piping

AECOM REBID

L = HND(P)

1/2

C

in which:

L = allowable leakage (gallons)

H = specified test period (hours)

N = number of rubber-gasketed joints in the pipe tested

D = diameter of the pipe (inches)

P = specified test pressure (psig)

C = 7,400

E. The allowable leakage for buried piping having threaded, brazed, or welded (including

solvent welded) joints shall be zero.

F. Repair and retest any pipes showing leakage rates greater than that allowed in the above

criteria.

3.08 Repetition of Test

If the actual leakage exceeds the allowable, locate and correct the faulty work and repeat the test.

Restore the work and repair damage resulting from the leak and its repair. Eliminate visible

leakage.

3.09 Bulkhead and Test Facility Removal

After a satisfactory test, remove the testing fluid, remove test bulkheads and other test facilities,

and restore the pipe coatings.

END OF SECTION

Page 82: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15220-1 Copper Tubing

AECOM REBID

SECTION 15220

COPPER TUBING

PART 1 - GENERAL

1.01 Description

This section includes materials, installation, and testing of copper tubing and fittings for water

and air service.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Trenching, Backfilling, and Compacting: 02223.

C. Disinfection of Piping and Structures: 15141.

D. Piping Schedule and General Piping Requirements: 15050A

E. Pressure Testing of Piping: 15144.

F. Manual, Check, and Process Valves: 15100.

G. Wall Pipes, Seep Rings, and Penetrations: 15062.

H. Pipe Hangers and Supports: 15064.

I. Equipment, Piping, and Valve Identification: 15075.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit materials list showing material of tubing and fittings with ASTM reference and

grade.

C. Submit manufacturer's catalog data and descriptive literature for wye strainers, unions, and

coatings.

D. Submit manufacturer's catalog data and descriptive literature for solder.

Page 83: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15220-2 Copper Tubing

AECOM REBID

PART 2 - MATERIALS

2.01 Tubing

Copper tubing shall conform to ASTM B88. Tubing located above floors or suspended from

ceilings shall be Type L, hard drawn, except that tubing utilizing nut-and-ferrule fittings and

joints shall be soft annealed (Temper O). Buried tubing or tubing located beneath floor slabs shall

be Type K, annealed.

2.02 Pipe and Nipples

Short threaded nipples and pipe shall be brass conforming to ASTM B43 or copper conforming to

ASTM B42.Threads shall conform to ASME B1.20.1.

2.03 Solder Joint Fittings

A. Wrought copper solder joint seamless fittings shall be designed for use with copper water

tube and conform to ASTM B75 and ASME B16.22. Material shall be UNS C10200,

C12000, or C12200.

B. Cast copper solder joint pressure fitting shall be designed for use with copper water tube

and conform to ASME B16.18.

2.04 Threaded Fittings for Brass and Copper Pipe and Nipples

Cast bronze threaded fittings shall conform to ASME B16.15, Classes 125 and 250. Use Class

125 fittings for test pressures of 200 psi and less. Use Class 250 fittings for test pressures of

greater than 200 psi but less than 400 psi.

2.05 Flanges and Flanged Fittings

Cast bronze pipe flanges and flanged fittings shall conform to ASME B16.24, Classes 150 and

300. Use Class 150 flanged fittings for test pressures of 225 psi and less. Use Class 300 flanged

fittings for test pressures greater than 225 psi but less than 500 psi. Provide flat-faced flanges.

Use solder joint or threaded end companion flanges. Companion flanges with solder joint or

threaded end shall be limited to the pressure rating of the pipe connection and not the flanged

joint.

2.06 Nut and Ferrule Fittings

Fittings shall be brass and of the Swagelok type as manufactured by Crawford Fitting Company,

utilizing a nut and dual ferrule design to connect to tubing. End connections shall be of the union

type.

2.07 Solder

Solder shall be 95-5 (95% tin, 5% antimony) conforming to ASTM B32, Grade Sb5.

2.08 Soldering Flux

Soldering flux shall comply with ASTM B813.

Page 84: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15220-3 Copper Tubing

AECOM REBID

2.09 Bolts and Nuts for Flanges

See Section 15050A.

2.10 Gaskets for Flanges

See Section 15050A.

2.11 Wye Strainers

Wye strainers shall be bronze, ASTM B61 or B62, with 60-mesh Type 304 or 316 stainless steel

screens. Working pressure shall be at least 150 psi. Provide bronze plug on the tapped blowoff

outlet. Provide one spare screen for each strainer. Strainers shall be Walworth Figure 3699-1/2,

Muessco No. 351, or equivalent.

2.12 Unions

Unions shall be the same size as the pipe or tube, three part, with copper flare end connections.

Unions shall be bronze, ASTM B61 or B62. Unions shall be Mueller H-15400, Jones J-1528, or

equivalent.

PART 3 - EXECUTION

3.01 General

A. Piping and tubing penetrations through walls, slabs, and floors shall be as detailed in the

drawings and as specified in Section 15062.

B. Pipe and tube hangers and supports shall be as detailed in the drawings and as specified in

Section 15064.

C. Do not allow piping and tubing to come in contact with wood treated with ammonium

sulfate fire retardant. Provide hangers or supports.

3.02 Joint and Fitting Selection

A. Use soldered joints and fittings in exposed tubing service.

B. Use soldered joints and fittings in buried service.

C. Fittings and joints 3/8 inch and smaller in exposed service may be of the nut-and-ferrule

type with flared end connections or compression joint connections.

D. Use threaded joints and fittings in buried and exposed copper and brass piping.

3.02 Pressure Testing

Test copper tubing and piping for leakage in accordance with Section 15144. See Piping Schedule

in drawings and Section 15144 for test pressures.

Page 85: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15220-4 Copper Tubing

AECOM REBID

3.03 Installing Flange Bolts and Nuts

See Section 15050A.

3.04 Making Soldered Joints

A. Tube cutters shall always be sharp. Do not take too deep a cut with each turn of the cutter

or back and forth motion of a saw blade.

B. Cut tubing square and remove burrs. Clean both the inside and outside of fitting and pipe

ends with steel wool and muriatic acid before soldering. Prevent annealing of fittings and

tubing when making connections. Do not miter joints for elbows or notch straight runs of

pipe for tees.

C. Make soldered joints in accordance with ASTM B828. Solder shall penetrate to the full

depth of the cup in joints and fittings. Solderers shall comply with ASME B31.3, paragraph

333.

3.05 Installing Tubing and Pipe

A. Do not drag tubing out of tubing rack. Do not drag tubing across cement, asphalt, gravel, or

any other surface that could scratch it.

B. Bends in soft copper tubing shall be long sweep. Shape bends with shaping tools. Form

bends without flattening, buckling, or thinning the tubing wall at any point.

C. Install tube and pipe without springing, forcing, or stressing the pipe or any adjacent

connecting valves or equipment.

D. Clean threaded joints by wire brushing or swabbing. Apply Teflon joint compound or

Teflon tape to male pipe threads before installing threaded fitting. Joints shall be

watertight.

E. Install buried tubing in accordance with Section 02223.

F. Install aboveground or exposed tubing per Section 15050A.

3.06 Connecting Copper Tubing to Steel and Ductile-Iron Pipe

Provide an insulating union at the point of transition from copper tubing or piping to ferrous

piping.

3.07 Installing Unions

Provide unions on exposed piping and tubing 3 inches and smaller as follows:

A. At every change in direction (horizontal and vertical).

B. Downstream of valves, 6 to 12 inches.

C. Every 40 feet in straight tubing and piping runs.

Page 86: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15220-5 Copper Tubing

AECOM REBID

D. Where shown in the drawings.

3.08 Chlorination of Potable Waterlines

See Section 15141.

END OF SECTION

Page 87: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-1 Ductile-Iron Pipe

AECOM REBID

SECTION 15240

DUCTILE-IRON PIPE

PART 1 - GENERAL

1.01 Description

This section describes materials, testing, and installation of ductile-iron pipe and fittings 48

inches and smaller.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Polyethylene Sheet Encasement (AWWA C105): 09954.

C. Fusion-Bonded Epoxy Linings and Coatings: 09961.

D. Ceramic Epoxy Lining for Ductile-Iron Pipe: 09971.

E. Trenching, Backfilling, and Compacting: 02223.

F. Disinfection of Piping and Structures: 15141.

G. Piping Schedule and General Piping Requirements: 15050A.

H. Pressure Testing of Piping: 15144.

I. Wall Flanges, Seep Rings, and Penetrations: 400762.

J. Pipe Hangers and Supports: 15064.

K. Equipment, Piping, Duct, and Valve Identification: 15075.

L. Flexible Pipe Couplings and Expansion Joints: 15122.

M. Corporation Stops and Service Saddles: 15123.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Provide an affidavit of compliance with standards referenced in this specification, e.g.,

AWWA C151. Submit copy of report of pressure tests for qualifying the designs of all

sizes and types of AWWA C153 fittings that are being used in the project. The pressure

test shall demonstrate that the minimum safety factor described in AWWA C153, Section

5.5 is met.

Page 88: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-2 Ductile-Iron Pipe

AECOM REBID

C. Provide the following information:

1. Mortar lining thickness.

2. Wall thickness.

3. Show deflections at push-on and mechanical joints.

4. Submit joint and fitting details and manufacturer’s data sheets.

D. Submit calculations and test data proving that the proposed restrained joint arrangement

can transmit the required forces with a minimum safety factor of 1.5.

E. Submit certificate that cement for mortar lining complies with ASTM C150, designating

type.

F. Submit test report on physical properties of rubber compound used in the gaskets.

G. Submit drawing or manufacturer's data sheet showing flange facing, including design of

facing serrations.

H. Submit weld procedure specification, procedure qualification record, and welder's

qualifications prior to any welding to ductile-iron pipe.

PART 2 - MATERIALS

2.01 Pipe

Pipe shall be cast ductile (nodular) iron, conforming to AWWA C151.

2.02 Pipe Wall Thickness

A. Minimum wall thicknesses for pipe having grooved-end joints shall be as shown in the

following table:

Pipe and Fitting Sizes

(inches) Wall Thickness*

16 and smaller Special Class 53

18 Special Class 54

20 Special Class 55

24 to 36 Special Class 56

42 and larger Special Class 53 or Pressure Class

350

*Special Class and Pressure Class per AWWA C151.

B. Minimum wall thickness for pipe having push-on or mechanical joints, restrained joints,

plain ends, or cast flange ends shall be Special Class 52, unless otherwise shown in the

drawings.

Page 89: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-3 Ductile-Iron Pipe

AECOM REBID

C. Minimum wall thickness for pipe having threaded flanges shall be Special Class 53 or

Pressure Class 350.

D. Minimum pipe wall thickness required for corporation stops and tapped outlets shall be in

accordance with Table A.1 of AWWA C151 for three full threads for design pressures up

to 250 psi and four full threads for design pressures over 250 to 350 psi.

2.03 Fittings

A. Fittings 48 inches and smaller shall conform to AWWA C110 with a minimum pressure

rating of 250 psi. Material shall be ductile iron. Flanges shall be flat faced.

B. Mechanical joint fittings conforming to AWWA C153 may be used in lieu of AWWA

C110 fittings. Mechanical joint ductile-iron fittings 18 through 48 inches conforming to

AWWA C110 (except for laying length) with a minimum pressure rating of 250 psi may

also be used.

C. Grooved-end fittings shall conform to AWWA C110 with grooved ends conforming to

AWWA C606, radius cut rigid joints. Fitting material shall conform to ASTM A48, Class

30; ASTM A126, Class B; or ASTM A536, Grade 65-42-10. Wall thickness of ductile-iron

(ASTM A536) fittings shall conform to AWWA C110 or C153; Fittings and couplings

shall be furnished by the same manufacturer.

D. Material for fittings with welded-on bosses shall have a Charpy notch impact value of

minimum 10 ft-lbs under the conditions defined in AWWA C151. Test completed welds

by the liquid penetrant method per ASTM E165.

2.04 Flanges

A. Flanges shall be solid back, Class 125 per AWWA C115. Flanges on pipe shall be either

cast or threaded. Material shall be ductile iron.

B. Flanged pipe and fittings shall be shop fabricated, not field fabricated. Threaded flanges

shall comply with AWWA C115. Flanges shall be individually fitted and machine

tightened in the shop, then machined flat and perpendicular to the pipe barrel. Flanges shall

be backfaced parallel to the face of flange. Prior to assembly of the flange onto the pipe,

apply a thread compound to the threads to provide a leak-free connection. There shall be

zero leakage through the threads at a hydrostatic test pressure of 250 psi without the use of

the gasket.

2.05 Pipe Lining--Cement Mortar

A. Line pipe interior and fittings with cement-mortar per AWWA C104. Lining thickness

shall be the double thickness listed in AWWA C104, Section 4.7. Cement for lining

material shall conform to ASTM C150, Type II. Refer to the Piping Schedule on the

drawings and/or specifications for the pipe.

B. Line fittings per Section 09900, System No. 7. Refer to the Piping Schedule on the

drawings and/or specifications for the pipe.

Page 90: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-4 Ductile-Iron Pipe

AECOM REBID

C. Fittings may be lined and coated with fusion-bonded epoxy per Section 09961. Refer to the

Piping Schedule on the drawings and/or specifications for the pipe.

D. Line blind flanges per Section 09900, System No. 7 or Section 09961.

E. Cement-mortar for pointing interior joints shall consist of one part cement to one and one-

half parts of washed plaster sand conforming to ASTM C35, mixed with the minimum

amount of water which will permit placing the mortar.

F. Maintain a moist environment inside the lined pipe and fittings by sealing the ends with

polyethylene sheet.

G. Loose areas of cement-mortar lining are not acceptable. Remove and reconstruct lining in

areas where quality is defective, such as sand pockets, voids over sanded areas, blisters,

drummy areas, cracked areas, and thin spots. Longitudinal cracks in excess of 1/32 inch in

width or where crack extends to metal shall be repaired with epoxy. Repair all cracks larger

than 1/16 inch with epoxy.

2.06 Pipe Lining – Sewer Pipe

A. Line pipe designated for use in sewers per Section 09971 - Ceramic Epoxy Lining For

Ductile-Iron Pipe.

B. Line fittings designated for use in sewers per Section 09971 - Ceramic Epoxy Lining For

Ductile-Iron Pipe.

2.07 Grooved-End Couplings

A. Grooved-end pipe couplings shall be ductile iron, ASTM A536 (Grade 65-45-12). Gaskets

shall be Buna-N and shall conform to ASTM D2000.

B. Bolts in exposed service shall conform to ASTM A193, Grade B8, Class 2. Bolts in buried

or submerged service shall be ASTM A193, Grade B8, Class 2.

C. Couplings for pipe 24 inches and smaller shall conform to AWWA C606 for flexible

radius ductile-iron pipe, except where rigid radius couplings are required to connect to

fittings. Couplings for pipe sizes 30 and 36 inches shall be in accordance with the coupling

manufacturer's published literature for tolerances and dimensions for flexible and rigid

radius cut joints. Couplings shall be Victaulic Style 31, Gustin-Bacon No. 500, or equal.

D. Couplings for pipe larger than 36 inches shall conform to AWWA C606 for shouldered

end pipe. Couplings shall be Victaulic Style 44 or equal.

E. Grooved-end adapter flanges for piping 24 inches and smaller having an operating pressure

of 150 psi and less shall be Victaulic Style 341 or 342 or equal. Flange dimensions shall

conform to ASME B16.1, Class 125.

F. Grooved-end transition couplings for connecting ductile-iron pipe 12 inches and smaller to

steel pipe shall be Victaulic Style 307 or equal.

Page 91: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-5 Ductile-Iron Pipe

AECOM REBID

2.08 Gaskets for Flanges

See Section 15050A.

2.09 Gaskets for Mechanical, Push-On, and Restrained Joints

Synthetic rubber in accordance with AWWA C111.

2.10 Bolts and Nuts for Flanges

See Section 15050A.

2.11 Outlets and Nozzles

A. Provide outlets 2 inches and smaller by tapping the pipe and attaching a service clamp as

specified in Section 15123. Use Type 1 clamps for exposed piping. Use Type 2 clamps for

buried and submerged piping.

B. For outlets larger than 2 inches in exposed piping, use a tee with a flanged outlet.

C. For outlets larger than 2 inches in buried piping, use a tee with a restrained joint outlet.

2.12 Joints

A. Joints in aboveground or submerged piping or piping located in vaults and structures shall

be flanged, unless grooved couplings are specifically shown.

B. Joints in buried piping shall be of the restrained type per AWWA C111 except where

flanged joints are required to connect to valves, meters, and other equipment.

C. Restrained joints for piping 6 inches and larger shall be American Cast Iron Pipe "Lok-

Ring" or "Flex-Ring," U.S. Pipe "TR-Flex," or equivalent. Weldments for restrained joints

shall be tested by the liquid penetrant method per ASTM E165. Restrained joints for field

closures shall be “Megalug” by EBAA Iron.

D. Restrained joints in 4-inch-diameter buried piping shall be American Cast Iron Pipe

Company “Fast-Grip,” U.S. Pipe Field-lok gasket within Tyton joint pipe and fittings, or

equivalent. Joint restraint shall be certified to four times rated pressure of 200 psi by

Factory Mutual.

E. Where thrust restraint is called for in the drawings, provide pipe with restrained joints

capable of transmitting 1.5 times the thrust, as calculated by the following equation:

T = 1.5 * (0.785 * P * D2)

where:

P = Pressure class of pipe in psi.

D = Outside diameter of pipe in inches.

T = Thrust in pounds.

Page 92: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-6 Ductile-Iron Pipe

AECOM REBID

2.13 Mechanical Joint Restraint System Using Follower Ring and Wedges

The restraining mechanism shall consist of a follower gland having a seal gasket and individually

actuated wedges that increase their resistance to pullout as pressure or external forces increase.

The system manufacturer shall provide the components (follower ring, wedges, and gaskets) for

the restraining device. The device shall be capable of full mechanical joint deflection during

assembly, and the flexibility of the joint shall be maintained after burial. The joint restraint ring

and its wedging components shall be constructed of ductile iron conforming to ASTM A536,

Grade 60-42-10. The wedges shall be ductile iron, heat-treated to a minimum hardness of 370

BHN. Dimensions of the gland shall be such that it can be used with mechanical joint bells

conforming to AWWA C111 and AWWA C153. The design shall use torque limiting twist-off

nuts to provide actuation of the restraining wedges. The mechanical joint restraint shall be

available in the size range of 3 through 48 inches. Minimum rated pressure shall be 350 psi for

sizes 16 inches and smaller and 250 psi in sizes 18 inches and larger. Products: Megalug Series

1100 as manufactured by EBAA Iron, Inc., or equal.

2.14 Ductile-Iron Pipe Weldments

A. Welding to ductile-iron pipe, such as for bosses, joint restraint, and joint bond cables, shall

be done at the place of manufacture of the pipe. Perform welding by skilled welders

experienced in the method and materials to be used. Welders shall be qualified under the

standard qualification procedures of the ASME Boiler and Pressure Vessel Code, Section

IX, Welding Qualifications.

B. Welds shall be of uniform composition, neat, smooth, full strength, and ductile.

Completely grind out porosity and cracks, trapped welding flux, and other defects in the

welds in such a manner that will permit proper and complete repair by welding.

C. Completed welds shall be inspected at the place of manufacture by the liquid penetrant

method. Conform to the requirements specified in ASTM E165, Method A, Type I or Type

II. The materials used shall be water washable and nonflammable.

PART 3 - EXECUTION

3.01 Delivery, Unloading, and Temporary Storage of Pipe at Site

A. Use unloading and installation procedures that avoid cracking of the lining. Use plastic

sheet bulkheads to close pipe ends and keep cement-mortar lining moist.

B. Deliver the pipe alongside the pipelaying access road over which the pipe trailer-tractors

can travel under their own power. Place the pipe in the order in which it is to be installed

and secure it from rolling.

C. Do not move pipe by inserting any devices or pieces of equipment into the pipe barrel.

Field repair linings damaged by unloading or installation procedures.

3.02 Sanitation of Pipe Interior

A. During laying operations, do not place tools, clothing, or other materials in the pipe.

Page 93: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-7 Ductile-Iron Pipe

AECOM REBID

B. When pipelaying is not in progress, close the ends of the installed pipe by a child- and

vermin-proof plug.

3.03 Installing Flanged Pipe and Fittings

Install in accordance with Section 15050A. Cut the bore of the gaskets such that the gaskets do

not protrude into the pipe when the flange bolts are tightened.

3.04 Installing Grooved-End Pipe and Fittings

See Section 15050A.

3.05 Installing Buried Piping

A. Install in accordance with AWWA C600, Section 02223, and as follows.

B. When installing piping in trenches, do not deviate more than 1 inch from line or 1/4 inch

from grade. Measure for grade at the pipe invert.

C. Assemble restrained joints per manufacturer's instructions.

3.06 Joint Deflections for Buried Pipe

A. Do not exceed the following deflection angles for unrestrained buried pipe joints:

Pipe Size

(inches)

Maximum Deflection (degrees)

Push-On Joint Mechanical Joint

4 4 6 1/2

6 4 5 1/2

8 4 4

10 4 4

12 4 4

14 2 1/2 3

16 2 1/2 3

18 2 1/2 2 1/2

20 2 1/2 2 1/2

24 2 1/2 2

30 2 1/2 N/A

36 2 1/2 N/A

42 2 1/2 N/A

48 2 1/2 N/A

B. For restrained joints, do not exceed 80% of the manufacturer's recommended maximum

deflections.

Page 94: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-8 Ductile-Iron Pipe

AECOM REBID

C. Assemble joints in accordance with AWWA C600 and the manufacturer's

recommendations.

3.07 Installing Aboveground or Exposed Piping

See Section 15050A.

3.08 Painting and Coating

A. Coat pipe located above ground and in vaults and structures as shown in the Piping

Schedule in the drawings and/or per Section 09900, System No. 10. Apply prime coat in

the shop before transporting pipe to the jobsite. Apply intermediate and finish coats in the

field before installing the pipe, then touch up after installation.

B. Provide asphaltic coating on buried pipe per AWWA C151.

C. Coat buried flanges and buried mechanical and restrained joint bolts, nuts, and glands per

Section 09900, System No. 21.

D. Coat submerged pipe per Section 09900, System No. 1 or 7.

E. Line and coat exposed grooved-end couplings the same as the pipe exterior coating or with

fusion-bonded epoxy per Section 09961.

F. Line and coat submerged and buried grooved-end couplings with fusion-bonded epoxy per

Section 09961

3.09 Interior Joint Recesses for Buried Piping 30 Inches and Larger

A. Point interior joint recesses of 30-inch and larger nominal diameter pipes with cement-

mortar. Do not point interior joints until after backfilling the pipe section.

B. Working inside the pipe, remove foreign substances from joint recesses and pack with

cement-mortar. Finish the surface with a steel trowel to match adjoining pipe.

3.10 Cleaning Pipe

After interior joints have been pointed and mortar has hardened, sweep pipe clean of dirt and

debris. If hardened mud exists in the pipe, remove with the use of pressurized water hoses.

3.11 Field Hydrostatic Testing

Test pressures are shown in the Piping Schedule in the drawings and/or Section 15144. Test in

accordance with Section 15144.

3.12 Pipe Labeling

Label exposed pipe above grade or in buried vaults per Section 15075.

Page 95: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15240-9 Ductile-Iron Pipe

AECOM REBID

3.13 Buried Warning and Identification Tape

Provide detectable warning tape per Section 400775. Warning and identification shall read

“CAUTION BURIED WATER PIPING BELOW” or similar wording.

END OF SECTION

Page 96: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-1 PVC Pipe, 3 Inches And Smaller

AECOM REBID

SECTION 15290

PVC PIPE, 3 INCHES AND SMALLER

PART 1 - GENERAL

1.01 Description

This section includes materials, installation, and testing of PVC pipe and fittings of size 3 inches

and smaller for use in process piping having a maximum design pressure of 150 psi and having a

maximum design temperature of 105°F.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Trenching, Backfilling, and Compacting: 02223.

C. Piping Schedule and General Piping Requirements: 15050A.

D. Pressure Testing of Piping: 15144.

E. Manual, Check, and Process Valves: 15100.

F. Wall Pipes, Seep Rings, and Penetrations: 15062.

G. Pipe Hangers and Supports: 15064.

H. Equipment, Piping, and Valve Identification: 15075.

I. PVC Distribution Pipe (AWWA C900): 15292.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Submit materials list showing materials of pipe and fittings with ASTM reference and

grade. Submit manufacturer's certification of compliance with referenced standards, e.g.,

ASTM D1784, D1785, and D2467. Show wall thickness of pipe and fittings. Show fitting

dimensions.

C. Submit data sheets for solvent cement demonstrating compliance with ASTM D2564 and

F656.

Page 97: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-2 PVC Pipe, 3 Inches And Smaller

AECOM REBID

PART 2 - MATERIALS

2.01 Pipe

Pipe shall be Schedule 80, Type I, Grade 1 (Class 12454-B), conforming to ASTM D1784 and

D1785.

2.02 PVC Pipe Coloring and Marking for Reclaimed Water or Irrigation Service

PVC pipe shall be purple (Pantone 522) and shall be marked on both sides of the pipe with the

wording "CAUTION: IRRIGATION WATER--DO NOT DRINK." The lettering shall be

minimum 1 inch high, black, and shall be repeated at intervals not exceeding 60 inches. The

purple coloring shall be achieved by adding pigment to the PVC material as the pipe is being

manufactured.

2.03 Fittings

Fittings shall be Schedule 80 and shall conform to ASTM D2464 for threaded fittings and ASTM

D2467 for socket-type fittings.

2.04 Flanges

PVC flanges shall be of the one-piece solid socket design and shall be made of the same material

as the pipe. Pressure rating shall be at least 150 psi at a temperature of 73°F. Minimum burst

pressure shall be 500 psi. Flanges shall match the dimensions of ASME B16.5, Class 150, steel

flanges for outside diameter, bolt circle, and bolt holes. Do not use Van Stone flanges.

2.05 Unions

A. Unions shall have socket-type ends, Viton O-rings, and shall be Schedule 80. Material

shall be Type I, Grade 1 PVC, per ASTM D1784. Unions used on hypochlorite piping shall

have EPDM O-rings and shall be Schedule 80.

B. Union connections to other metal piping materials shall comply with MSS SP-107. The

fitting end for connection to PVC pipe shall be a female socket. Provide wrought or cast

copper tailpieces for connection to copper piping and tubing. Provide Type 316 stainless

steel tailpieces for connection to steel piping.

2.06 Joints

Pipe and fitting joints shall be socket welded except where threaded and flanged joints are

required to connect to valves and equipment.

2.07 Solvent Cement in Other Than Sodium Hypochlorite Service

Solvent cement for socket joints shall comply with ASTM D2564 and F656.

2.08 Solvent Cement in Sodium Hypochlorite Service

Solvent cement shall be free of silica. Products: IPS “Weld-On” PVC 724 or Oatey “Lo V.O.C.

PVC Heavy Duty Gray.”

Page 98: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-3 PVC Pipe, 3 Inches And Smaller

AECOM REBID

2.09 Gaskets for Flanges

See Section 15050A.

2.10 Bolts and Nuts for Flanges

See Section 15050A.

2.11 Lubricant for Stainless Steel Bolts and Nuts

See Section 15050A.

2.12 Wye Strainers

PVC wye strainers shall be manufactured of the same material as the pipe, with 30-mesh screens

and Viton seals. Connecting ends shall be the socket type, solvent welded. Provide one spare

screen for each strainer.

PART 3 - EXECUTION

3.01 General

A. Do not install PVC pipe when the temperature is below 40°F or above 90°F. Store loose

pipes on racks with a maximum support spacing of 3 feet. Provide shades for pipe stored

outdoors or installed outdoors until the pipe is filled with water.

B. Store fittings indoors in their original cartons.

C. Store solvent cement indoors or, if outdoors, shade from direct sunlight exposure. Do not

use solvent cements that have exceeded the shelf life marked on the storage container.

D. Before installation, check pipe and fittings for cuts, scratches, gouges, buckling, kinking,

or splitting on pipe ends. Remove any pipe section containing defects by cutting out the

damaged section of pipe.

E. Do not drag PVC pipe over the ground, drop it onto the ground, or drop objects on it.

3.02 Solvent-Welded Joints

A. Prior to solvent welding, remove fittings and couplings from their cartons and expose them

to the air at the same temperature conditions as the pipe for at least one hour.

B. Cut pipe ends square and remove burrs, chips, and filings before joining pipe or fittings.

Bevel solvent-welded pipe ends as recommended by the pipe manufacturer.

C. Wipe away loose dirt and moisture from the inside and outside of the pipe end and the

inside of the fitting before applying solvent cement. Clean the surfaces of both pipes and

fittings that are to be solvent welded with a clean cloth moistened with acetone or

methylethyl ketone. Do not apply solvent cement to wet surfaces.

Page 99: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-4 PVC Pipe, 3 Inches And Smaller

AECOM REBID

D. The pipe and fitting socket shall have an interference fit. Perform a dry fit test at each joint

before applying solvent cement. The pipe shall enter the fitting socket between one-third

and two-thirds of the full socket depth when assembled by hand.

E. Make up solvent-welded joints per ASTM D2855. Application of cement to both surfaces

to be joined and assembly of these surfaces shall produce a continuous bond between them

with visual evidence of cement at least flush with the outer end of the fitting bore around

the entire joint perimeter.

F. Allow at least eight hours of drying time before moving solvent-welded joints or subjecting

the joints to any internal or external loads or pressures.

G. Acceptance criteria for solvent-welded joints shall be as follows:

1. Unfilled Areas in Joint: None permitted.

2. Unbonded Areas in Joint: None permitted.

3. Protrusion of Material into Pipe Bore, Percent of Pipe Wall Thickness: Cement,

50%.

3.03 Flanged Joints

A. Lubricate carbon steel bolt threads with graphite and oil before installation.

B. Tighten bolts on PVC flanges by tightening the nuts diametrically opposite each other

using a torque wrench. Complete tightening shall be accomplished in stages and the final

torque values shall be as shown in the following table:

Pipe Size

(inches)

Final Torque

(foot-pounds)

1/2 to 1 1/2 10 to 15

2 to 3 20 to 30

3.04 Installation of Stainless Steel Bolts and Nuts

See Section 400500.

3.05 Assembling Threaded Joints

A. Cut threaded ends on PVC to the dimensions of ASTM F1498. Ends shall be square cut.

Follow the pipe manufacturer's recommendations regarding pipe hold-down methods, saw

cutting blade size, and saw cutting speed. Gauges, gauge tolerances, and gauging

procedures shall comply with ASTM F1498, Sections 7 and 8. Perform field gauging on

every field-cut threaded connection.

B. Pipe or tubing cutters shall be specifically designed for use on PVC pipe. Use cutters

manufactured by Reed Manufacturing Company, Ridge Tool Company, or equivalent.

Page 100: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-5 PVC Pipe, 3 Inches And Smaller

AECOM REBID

C. If a hold-down vise is used when the pipe is cut, insert a rubber sheet between the vise jaws

and the pipe to avoid scratching the pipe.

D. Thread cutting dies shall be clean and sharp and shall not be used to cut materials other

than plastic.

E. Apply Teflon® thread compound or Teflon® tape lubricant to threads before screwing on

the fitting.

F. Assemble threaded flanges and fittings per ASTM F1498, Sections 4, 7, and 8. Do not

tighten threaded connections more than two turns past finger tightness for both internal and

external threads.

3.06 Installing Unions

Provide unions on exposed piping 3 inches and smaller as follows:

A. At every change in direction (horizontal and vertical).

B. 6 to 12 inches downstream of valves.

C. Every 40 feet in straight pipe runs, unless otherwise noted on the drawings.

D. Where shown in the drawings.

3.07 Installing Buried Pipe

A. Install in accordance with Section 02223 and as follows.

B. Trench bottom shall be continuous, smooth, and free of rocks. See the details in the

drawings for trench dimensions, pipe bedding, and backfill.

C. After the pipe has been solvent-welded and the joints have set, snake the pipe in the trench

per the pipe manufacturer's recommendations in order to allow for thermal expansion and

contraction of the pipe.

D. Do not backfill the pipe trench until the solvent-welded joints have set. Support the pipe

uniformly and continuously over its entire length on firm, stable soil. Do not use blocking

to change pipe grade or to support pipe in the trench.

E. Install buried PVC pipe in accordance with ASTM D2774 and the pipe manufacturer's

recommendations. Backfill materials in the pipe zone shall be imported sand per Section

02223.

3.08 Installing Aboveground or Exposed Piping

A. See Section 15050A.

B. Fill empty piping with water and provide temporary shading or other means to keep the

surface temperature of the pipe below 100°F.

Page 101: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15290-6 PVC Pipe, 3 Inches And Smaller

AECOM REBID

3.09 Painting and Coating

Coat exposed piping per Section 09900, System No. 41. Color code per the Pipe Schedule on the

drawings.

3.10 Hydrostatic Testing

Perform hydrostatic testing for leakage in accordance with Section 15144.

END OF SECTION

Page 102: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15292-1 PVC Distribution Pipe (AWWA C900)

AECOM REBID

SECTION 15292

PVC DISTRIBUTION PIPE (AWWA C900)

PART 1 - GENERAL

1.01 Description

This section includes materials, installation, and testing of PVC distribution pipe conforming to

AWWA C900. Size range is 4 through 12 inches.

1.02 Related Work Specified Elsewhere

A. Painting and Coating: 09900.

B. Polyethylene Sheet Encasement (AWWA C105): 09954.

C. Fusion-Bonded Epoxy Linings and Coatings: 09961.

D. Trenching, Backfilling, and Compacting: 02223.

E. Piping Schedule and General Piping Requirements: 15050A.

F. Pressure Testing of Piping: 15144.

G. Flexible Pipe Couplings and Expansion Joints: 15122.

H. Corporation Stops and Service Saddles: 15123.

1.03 Submittals

A. Submit shop drawings in accordance with the General Conditions, Section 01300 and the

following:

B. Provide affidavit of compliance with AWWA C900.

C. Submit fully dimensioned cross-section of the bell and barrel of the pipe. Show the bell

maximum outside diameter in the pressurized area and its minimum wall thickness at the

same location.

D. Submit copies of the following manufacturer-required tests conducted on project pipe:

1. Quick-burst strength of pipe and couplings.

2. Flattening resistance of pipe.

3. Record of additional tests after test sample failure.

E. Submit manufacturer's literature of ductile-iron fittings including dimensions, thickness,

weight, coating, lining, and a statement of inspection and compliance with the acceptance

Page 103: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15292-2 PVC Distribution Pipe (AWWA C900)

AECOM REBID

tests of AWWA C110 or C153. Submit copy of report of pressure tests for qualifying the

designs of sizes and types of AWWA C153 fittings that are being used in the project. The

pressure test shall demonstrate that the minimum safety factor described in AWWA C153,

Section 53-15 is met.

F. Submit outline drawings and materials description of service connection saddles,

corporation stops, and pipe plugs.

G. Submit restrained joint system installation instructions. Include bolt torque limitations and

assembly tolerances.

PART 2 - MATERIALS

2.01 Pipe

AWWA C900, rubber-ring gasket bell end or plain end with elastomeric gasket coupling, DR 18,

cast iron equivalent outside diameter, material cell classification 12454-B per ASTM D1784.

2.02 PVC Pipe Coloring and Marking for Reclaimed Water or Irrigation Service

PVC pipe shall be purple (Pantone 522) and shall be marked on both sides of the pipe with the

wording "CAUTION: IRRIGATION WATER--DO NOT DRINK." The lettering shall be

minimum 1 inch high, black, and shall be repeated at intervals not exceeding 60 inches. The

purple coloring shall be achieved by adding pigment to the PVC material as the pipe is being

manufactured.

2.03 Fittings

A. Fittings shall conform to AWWA C110 with a minimum pressure rating of 250 psi. Size

bells specifically for outside diameter of cast-iron equivalent PVC pipe including rubber-

ring retaining groove.

B. Mechanical joint fittings conforming to AWWA C153 may be used in lieu of AWWA

C110 fittings.

2.04 Lining and Coating for Fittings

Water Pipe: Line and coat fittings with double cement lining.

Sewer Pipe: Line and coat fittings with ceramic epoxy per Section 09971.

2.05 Flanges

Flanges on outlets of fittings shall be Class 125 per ASME B16.1.

2.06 Gaskets for Flanges

See Section 15050A.

Page 104: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15292-3 PVC Distribution Pipe (AWWA C900)

AECOM REBID

2.07 Bolts and Nuts for Flanges

See Section 15050A.

2.08 Outlets and Nozzles

A. Provide outlets 2 inches and smaller by attaching a service clamp as specified in Section

15123. Use Type 2 clamps.

B. For outlets larger than 2 inches, use a tee with a flanged outlet.

2.09 Restrained Joints

Provide restrained joints where indicated in the drawings. Restrained joints shall be provided by

restraining systems that incorporate a series of machined serrations on the inside diameter of a

restraint ring to provide positive restraint. Restraining systems shall meet or exceed the

requirements of UNI-B-13-94 and ASTM F1674 and the following:

A. Restraint devices for bell-and-spigot joints shall consist of a split restraint ring installed on

the spigot, connected to a solid backup ring seated behind the bell.

B. Restraint devices for connection to ductile-iron mechanical joints shall consist of a split

restraint ring installed behind the ductile-iron fitting follower gland and gasket and shall

retain the full deflection capability of the joint.

C. The split restraint ring shall be machined to match the outside diameter of the pipe, provide

full 360-degree support around the barrel of the pipe, and shall incorporate a series of

machined serrations for gripping the outside surface of the pipe. The serrations shall be

uniform and extend the full circumference of the clamp. The ring shall also incorporate a

positive means of avoiding applying excessive clamping force to the pipe.

D. Materials used in the restraint device shall be ductile iron conforming to ASTM A536,

Grade 60-42-12 or 65-45-12.

E. T-bolts, studs, and connecting hardware shall be high-strength, low alloy material in

accordance with AWWA C111.

F. Design restraining devices to have a 2:1 safety factor based on the design strength of the

pipe.

G. Restraining devices shall be UNI-Flange Block Buster Series 1300 or 1500, EBAA Iron

Series 1600, or equivalent.

2.10 Flanged Coupling Adapters

See Section 15122.

Page 105: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15292-4 PVC Distribution Pipe (AWWA C900)

AECOM REBID

PART 3 - EXECUTION

3.01 Product Marking

Legibly mark pipe at 5-foot intervals and each coupling to identify the nominal diameter, the

outside diameter base, that is, cast-iron or steel pipe (IPS), the material code for pipe and

couplings, the dimension ratio number, AWWA C900, and the seal of the testing agency that

verified the suitability of the material for potable water service (NSF in the United States).

3.02 Delivery and Temporary Storage of Pipe

A. Ship, store, and place pipe at the installation site, supporting the pipe uniformly. Avoid

scratching the pipe surface. Do not stack higher than 4 feet or with weight on bells. Cover

to protect from sunlight.

B. Do not install pipe that is gouged or scratched forming a clear depression.

3.03 Pipe Layout for Curved Alignment

Pipe lengths may be bent for curved alignment but to no smaller radius curve than the following:

Pipe Diameter

(inches)

Minimum Curve Radius

(feet)

4 400

6 600

8 800

10 1,000

12 1,200

3.04 Handling Pipe

Hoist pipe with mechanical equipment using a cloth belt sling or a continuous fiber rope that

avoids scratching the pipe. Do not use a chain. Pipes up to 12 inches in diameter may be lowered

by rolling on two ropes controlled by snubbing. Pipes up to 6 inches in diameter may be lifted by

hand.

3.05 Installing Buried Piping

A. Install in accordance with AWWA C605, Section 02223, and as follows.

B. When installing pipe in trenches, do not deviate more than 1 inch from line or 1/4 inch

from grade. Measure for grade at the pipe invert.

C. Backfill materials in the pipe zone shall be imported sand per Section 02223. Do not add

successive layers unless the previous layer is compacted to 95% relative compaction per

ASTM D1557.

D. Compact material placed within 12 inches of the outer surface of the pipe by hand tamping

only.

Page 106: DIVISION 15 MECHANICAL - D.N. Higgins, Inc. - …dnhiggins.com/docs/Division 15.pdf · DIVISION 15 ... shall have "nominal" pipe size inside diameters not the inside diameters per

IWSD 01/2011 15292-5 PVC Distribution Pipe (AWWA C900)

AECOM REBID

E. Compact trench backfill to the specified relative compaction. Do not float pipe. Do not use

high-impact hammer-type equipment.

3.06 Assembly of Pipe Joint

A. The spigot and bell or bell coupling shall be dirt free and slide together without displacing

the rubber ring. Lay the pipe section with the bell coupling facing the direction of laying.

B. Insert the rubber ring into the groove in the bell in the trench just before joining the pipes.

First clean the groove. Observe the correct direction of the shaped ring. Feel that the ring is

completely seated.

C. Lubricate the spigot over the taper and up to the full insertion mark with the lubricant

supplied by the pipe manufacturer. If the lubricated pipe end touches dirt, clean the pipe

end and reapply lubricant.

D. Insert the spigot into the bell and force it slowly into position.

E. Check that the rubber ring has not left the groove during assembly by passing a feeler

gauge around the completed joint.

3.07 Wrapping Fittings and Restrained Joint Devices

Wrap buried cast-iron fittings and restrained joint devices with polyethylene per Section 09954.

3.08 Field Hydrostatic Testing

Test pressures are shown in the Piping Schedule in the drawings and/or Section 15144. Test in

accordance with Section 15144.

3.09 Disinfection

See Section 15141 for disinfection of potable water lines. Reclaimed or irrigation (nonpotable)

water are not required to be disinfected.

END OF SECTION