District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB...
Transcript of District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB...
![Page 1: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/1.jpg)
District Energy SystemProgram Options Report
August 16th 2018
![Page 2: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/2.jpg)
DES Project Summary� FVB responded to, and was hired after a Request for
Proposal (RFP) issuance in 2017
� FVB prepared a comprehensive evaluation report for Metro to summarize the in-depth assessment of the economic viability of the DES
� Options/recommendations are provided for the future of the system
� Four scenarios are developed and compared
![Page 3: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/3.jpg)
DES Project Scenarios� FVB developed and analyzed four primary DES scenarios:
� No Growth (Business as Usual (BaU)) scenario� Based on existing operations with little or no growth
� Growth scenario� Based on expanding the system capabilities and customer base� Two different and not mutually exclusive expansion options explored
� Internal management and operations option� Metro retains ownership and internally manages and operates DES
� Business Exit case� Valuations if Metro exits the business
![Page 4: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/4.jpg)
DES Project Scenarios Overview� FVB evaluated options for the future of the DES, but
no specific option is favored or recommendation explicitly given
![Page 5: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/5.jpg)
DES Project Key Takeaways� Regardless of the ownership of DES, an active management
structure that takes ownership, has accountability, and encourages growth will need to be put in place
� It will be necessary to incorporate an effective marketing scheme into the management structure to successfully capture growth opportunities
� New customers should sign contracts that do not tie debt service to customer revenues, and existing customer contracts need to be revisited and restructured to allow additional capital to flow to the DES to allow for system growth, Energy Generation Facility (EGF) maintenance and improvements, and additional capital expenditure (CAPEX) needs
![Page 6: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/6.jpg)
Scenario Overview� DES currently receives a yearly subsidy from Metro in
the form of the Metro Funding Amount (MFA) – Fiscal
Year (FY) 2019 MFA is $1,640,300
� The MFA will go down over time in any scenario, but at
different rates
� NPV (Net Present Value) is the difference between the
present value of the benefits of a project and its costs.
![Page 7: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/7.jpg)
BaU Scenario:Takeaways
� NPV of future MFAs discounted at 4.33%:� $4.9 MM without additional CAPEX� $10.4 MM with additional CAPEX
� Sales value will decrease over time:� Energy Generation Facility (EGF) equipment will age
and require additional CAPEX� Contracts will move towards expiration� Potential additional growth opportunities will be missed
![Page 8: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/8.jpg)
BaU Scenario:CAPEX Requirements
$3,292,300
$687,500 $577,500
$2,142,800
$495,000
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
2019 2020 2021 2022 2023
CA
PEX
Req
uire
men
ts
Fiscal Year
CAPEX requirements are estimated and subject to revision. $495,000/year is assumed after starting in 2023.
![Page 9: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/9.jpg)
BaU Scenario:The Metro Funding Amount (MFA) Over Time
-
500
1,000
1,500
2,000
2,500
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
USD
(in 0
00's)
Year
MFA MFA with CAPEX
A 10% reduction in System Operator (SO) costs beginning in Fiscal Year 2019 is assumed.
![Page 10: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/10.jpg)
Growth Scenario:Energy Generation Facility (EGF) Expansion
� Expand the existing EGF to its maximum site capacity by serving additional customers in the growing SoBro area
![Page 11: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/11.jpg)
Growth Scenario:Thermal Energy Storage (TES) Tank
� Construct a TES to serve additional customers in the downtown area
![Page 12: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/12.jpg)
Growth Scenario:Takeaways
� Promising option� Will require substantial upfront capital investment
� Energy Generation Facility (EGF) Expansion� Present day capital cost: $52.7 MM� Investment has a positive return but negative cash flows would
need to be funded for the first eight years� Thermal Energy Storage (TES) Expansion
� Present day capital cost: $38.5 MM� Investment has a positive return but negative cash flows would
need to be funded for the first five years
![Page 13: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/13.jpg)
Growth Scenario:The MFA Over Time
� The Growth scenario generates a sustained cash surplus starting in 2031, consequently:� Contributes to the value of the DES in the long run and
demonstrates promise to a potential acquirer.� Does not contribute to a more rapid decline of the MFA.
![Page 14: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/14.jpg)
Internal Management and Operations Option:Takeaways
� Possible cost savings and operational efficiencies to be gained could yield a 19% reduction in annual operations & maintenance (O&M) costs enabling the MFA to be eliminated faster
� A well-defined transition plan, management structure, and capital plan are needed
![Page 15: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/15.jpg)
Internal Management and Operations Option:The MFA Over Time
-
500
1,000
1,500
2,000
2,500
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
USD
(in 0
00's)
Year
MFA MFA with CAPEX
![Page 16: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/16.jpg)
Business Exit Case:Takeaways
� Sale of the DES is likely to repay all existing debt obligations
� The MFA will no longer be required
![Page 17: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/17.jpg)
Business Exit Case:Valuation Metrics
� Potential growth� CAPEX requirements (based on the age and condition
of the system)� Customer contracts (structure and term)� Commodity risk (mitigated by pass-through contract
provisions)
![Page 18: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/18.jpg)
Business Exit Case:DES Market Valuation Range with Reduced System Operator Costs
and System Growth
Valuation* Valuation Net of Debt*
$46.7 MM -$4.9 MM
$56.1 MM $4.5 MM
$65.4 MM $13.8 MM
*DES net debt as of the end of FY 2017 is $51.6 MM.
An active market for DE assets and strong market participants suggest that the higher valuation range may be achieved.
![Page 19: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/19.jpg)
DES Project Summary� FVB developed and analyzed four primary DES scenarios:
� No Growth (Business as Usual (BaU)) scenario� Based on existing operations with little or no growth
� Growth scenario� Based on expanding the system capabilities and customer base
� Internal management and operations option� Metro retains ownership and internally manages and operates DES
� Business Exit case� Valuations if Metro exits the business
![Page 20: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/20.jpg)
Summary of ScenariosBaU Scenario
• CAPEX funding not adequate• Sales value will decrease over time• Will continue to require
subsidization through FY 2021
Growth Scenario• Two promising and not mutually
exclusive growth options• Will require substantial upfront
capital investment
Internal Management and Operations Option
• Possible cost savings and operational efficiencies to be gained could yield a 19% reduction in annual operations & maintenance (O&M) costs
• A well-defined transition plan, management structure, and capital plan are needed
Business Exit Case• Sale of the DES is likely to repay all
existing debt obligations• The MFA will no longer be required
![Page 21: District Energy System Program Options Report August 16th 2018 · DES Project Scenarios FVB developed and analyzed four primary DES scenarios: No Growth(Business as Usual (BaU)) scenario](https://reader033.fdocuments.in/reader033/viewer/2022041621/5e3f5bd82b429e70da3b9cc6/html5/thumbnails/21.jpg)
Questions?