DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S- 3228 applies R&M Engineering 08/16/11 Page 1 DTM 11-003 R&M Engineering Implementation Strategy Andrew Monje Deputy Assistant Secretary of Defense, Systems Engineering Office of the Under Secretary of Defense (Acquisition, Technology and Logistics) 16 Aug 2011

Transcript of DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies...

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 appliesR&M Engineering08/16/11 Page 1

DTM 11-003R&M Engineering

Implementation StrategyAndrew Monje

Deputy Assistant Secretary of Defense, Systems Engineering Office of the Under Secretary of Defense (Acquisition, Technology and Logistics)

16 Aug 2011

R&M Engineering08/16/11 Page 2

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

PURPOSE• Provide overview of the R&M Implementation

Strategy upon approval of DTM 11-003

AGENDA• DTM Overview• Policy Implementation - DTM 11-003• Process - Guidance & Standards/DIDs• People - Human Capital• Summary• Open Discussion

Purpose / Agenda

R&M Engineering08/16/11 Page 3

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

• Engineering activities (AS to describe tasks and processes to be stated in the RFP)– R&M Allocations, block diagrams and predictions– Failure definitions and scoring criteria– Failure Mode, Effects and Criticality Analysis (FMECA)– Built-in test and maintainability demonstrations– Reliability Growth testing at system/subsystem level– Failure Reporting, Analysis and Corrective Action System (FRACAS)

• Preliminary RAM-C Report in support of MS A and updated for MS B & C– Provides early (Pre-MS A) reliability, availability, maintainability and ownership cost

feasibility assessments of alternative concepts− Includes early formulation of maintenance & support concepts

– Provides an audit trail that documents and supports JCIDS thresholds– Ensures correct balance between the sustainment metrics (Availability-KPP, Materiel

Reliability-KSA, and Ownership Cost-KSA)– Provides early risk reduction by ensuring requirements are realistic and correct

• AS and SEP to specify how the JCIDS sustainment thresholds have been translated into R&M design requirements for use in contract specifications

DTM 11-003 Overview

R&M Engineering08/16/11 Page 4

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

DTM 11-003 Overview

• Reliability Growth Strategy– Documents system-level reliability growth curves in the SEP beginning at

MS A and updated in the TEMP beginning at MS B– Establishes intermediate goals for reliability growth curves that will be

tracked through fully integrated system-level test and evaluation events until the threshold is achieved

– Requires MS C PMs and Operational Test Agencies to assess reliability growth required to achieve the reliability threshold during Initial Operational Test and Evaluation

• Tracking and Monitoring– Requires PMs to report status of reliability objectives and/or thresholds as

part of the formal system engineering review process– Incorporates Reliability Growth Curves into the Defense Acquisition

Executive System (DAES) review process

R&M Engineering08/16/11 Page 5

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

DoDI 5000.02Encl(6) Test

DAES

Quad Chart

Policy Implementation DTM 11-003

• Incorporating DTM in DoD 5000 and affected Governance Documents– DoDI 5000.02 & enclosure 12 (SE)

revision – Complete & sent to DPAP– Enclosure 13 (Logistics) – Comments

provided to L&MR– Systems Engineering Plan Outline –

Approved– Acquisition Strategy Outline – Approved– Preliminary Design Review Report

Guideline – Completed– TEMP outline – Currently in review– LCSP outline – In work– DAES RVW Growth Quad chart – In

work

SystemsEngineeringPlan (SEP)

Test & Evaluation

Master Plan

(TEMP)

TechnologyDevelopment

Strategy/Acquisition

Strategy

PreliminaryDesign ReviewReport

DTM11-0033/21/11

Life-Cycle Sustainment

Plan

Encl(12)System

Engineering

In review/In-work

Approved

Status:

DTM to Policy and Acquisition Document Relationships

DoDI 5000.02Encl(13)

Lifecycle Logistics

R&M Engineering08/16/11 Page 6

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 appliesv.01

Annotated Outlines for TDS/AS, SEP Released as “Expected Business Practice”

TDS/AS and SEP outlines signed

April 20, 2011

Technology Development Strategy [or] Acquisition Strategy

Annotated Outline

Systems Engineering PlanAnnotated Outline

April 20, 2011

http://www.acq.osd.mil/se/docs/PDUSD-ATLMemo-Expected-Bus-Practice-TDS_AS_SEP-20Apr11.pdf

R&M Engineering08/16/11 Page 7

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 appliesv.01

• Identify the engineering activities to be stated in the RFP and required of the contractor to demonstrate the achievement of the reliability and maintainability design requirements.

• Provide a table (see example below) to specify how the sustainment key performance parameter thresholds have been translated into reliability and maintainability design and contract specifications … The reliability threshold is often expressed as Mean Time Between Failure (MTBF). Use the appropriate life units (e.g., hours, cycles, etc.). “MTTR” is “mean time to repair;” “N/A” may be entered if an item is not applicable.

R&M in the TDS/AS

Reliability and Maintainability Requirements

Parameter ThresholdContract Specification

Requirement

Reliability (e.g., MTBF)

Maintainability (e.g., MTTR)

R&M Engineering08/16/11 Page 8

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

New Reliability Reporting

Document the Reliability Growth Curve beginning at MS A, updated at each successive milestone, …

and report planning to generate R&M artifacts.

Implementation of New Reliability Policy

R&M Engineering08/16/11 Page 9

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 appliesv.01

• Update to DAG Chapter 4 R&M Sec 4.4.15– Include overview of R&M Eng Activities by phase– Apply R&M Eng activities based on program position in

Life Cycle– Also based on acquisition strategy and equipment type

− Provides guidance on Reliability Growth Program– Includes R&M contract guidance with associated DIDs

• Collaborate with DAG Editors (i.e., to ensure R&M guidance is properly integrated

• Develop R&M Engineering Guidance with task descriptions per phase

– Describes R&M engineering activities across typical program areas

• Forming R&M Standards working group– Priority given to standards that directly relate to the R&M

engineering activities required by the DTM– R&M Eng Mgt STDs 1st (i.e. 785, 470, & 2165)– Design & Reliability Growth STDs (i.e. 1629, 1635)

Process - Guidance & Standards/DIDs

DAG LM&R

Chapter 5Updates

DAG SE Chapter 4 Updates

Key R&MEngineeringStandards &

DIDs DAG DDT&EChapter 9Updates

Defense AcquisitionGuidebook

R&M Engineering Guidebook

R&M Engineering08/16/11 Page 10

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 appliesv.01

Materiel Solution Analysis Phase

MS A

MDD

DOD 5000.02

LIFECYCLE ENTRY

ICD TES

TDS

SEP

GOV TASK ASSIGNMENT

PR & RFP FOR MSA

INPUT TO TDS

PR/RFP TECH DEV

PHASE

PROPOSAL EVAL

CRITERIA

PROCUREMENT (SECT. VIII)

INPUT TO TES

TEST AND EVALUATION (SECT.

VII)

MAINT. ANALYSIS

LIFE CYCLE SUSTAINMENT

PLAN

R&M RQMTS.

ANALYSES

TRADEOFF STUDIES

R&M ANALYSIS REPORTS

SYSTEM ENGINEERING (SECT. V)

CONFIG MGMT.

TECH DEV SYSTEM

SPEC

CONFIGURATION MANAGEMENT (SECT.

IV)

R&M DATA RQMTS UPDATE

DATA CONTROL (SECT. III)

RAM-C REPORT

SUMMARY

INPUT TO SEP

PM PLAN

PROGRAM REVIEW

PROJECT CONTROL (SECT. II)

MS-A PHASE FUNCTIONS

R&M PLANS TECHNOLOGY

DEV PHASE

REJECT

ACCEPTA

R&M PLANS

MSAICD

1

4 5 6

12 15 19

8

7

2 1 23

10

9 11

17

16

18

13

20 14 22

2

R&M DATA

RQMTS

3

REVIEW CONTRACT

ITR ASR

FUNCTIONAL BASELINE

AOA

Draft CDD

LOGISTICS PLANNING (SECT. VI)

R&M Engineering08/16/11 Page 11

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

PeopleHuman Capital

• Objective: Increase PM demand for R&M Engineering and enhance R&M Engineering professional capabilities to successfully implement a R&M program.

• Approach– Define R&M Engineering tasks– Develop R&M Engineering

competencies for PM and R&M Engineers

– Submit R&M competencies to DAU for curriculum development via SE FIPT chair

– DAU develops training architecture, curriculums, training content and delivers training.

R&M Engineering E&T Strategy

Capture/Define R&M Engineering Tasks and Associated Roles

Define R&M Engineering Competencies For Associated Roles (incl. KSAs)

Define R&M Engineering Learning Architecture (e.g. CLMs, SPRDE/SE Courses & R&M Competencies

Integration, Dedicated R&M Courses)

Develop and Deliver Training

R&M Engineering08/16/11 Page 12

DISTRIBUTION STATEMENT A: Cleared for Public Release by OSR on 8/04/11; SR Case # 11-S-3228 applies

Summary

• Actively engaged on all Focus Areas to improve “Technical Health” of R&M Engineering

• Institutionalizing the process across the Services• Collaborating with other functionals (e.g., test, logistics …)• DTM implementation will:

– Not burden the programs with unreasonable expectations– Not drive a “One Size Fit All Solution” on programs

– Smartly apply engineering activities based on acquisition strategy & life cycle position