Dist Overview _ Vivek Jha
Transcript of Dist Overview _ Vivek Jha
-
7/31/2019 Dist Overview _ Vivek Jha
1/93
1
WELCOME
to a presentation onPOWER DISTRIBUTION SECTOR
and
NTPC IN POWER DISTRIBUTION
VIVEK JHA
-
7/31/2019 Dist Overview _ Vivek Jha
2/93
2
Presentation overview:
Introduction and Power Scenario In The Country
The Distribution sector :
Status and need for reforms Key issues and challenges
What is being Done : Reform Initiatives in Distribution
NTPCs foray in Distribution sector (NESCL)
-
7/31/2019 Dist Overview _ Vivek Jha
3/93
3
Introduction
and
Indian Power Sector
-
7/31/2019 Dist Overview _ Vivek Jha
4/93
4
There is no substitute for energy.
The whole edifice of modern life is built upon it.
Although energy can be bought and soldlike any other commodity,
it is not just another commodity
but the precondition of all other commodities,
a basic factor likeAir, Water and Earth.
- E. F. SCHUMACHER(British Economist)
Introduction
-
7/31/2019 Dist Overview _ Vivek Jha
5/93
5
Electrical energy : Backbone of economy
8 % growth in GDP => At least 10 % growth inElectricity industry
There has been tremendous improvement andaugmentation in Generation, Transmission andDistribution since independence. However, we still have
significant shortage of power supply. Distrubution is the key area in power sector
Introduction
-
7/31/2019 Dist Overview _ Vivek Jha
6/93
6
Historical Overview
First electricity generating station in India a small hydrostation in Darjeeling in 1896
Total installed capacity in 1947 : 1362 MW.
Pre-1948, all generation privately-owned. (Licensed ®ulated by Govt. under Indian Electricity Act, 1910) Retaildistribution only around generating stations. No transmission.
PostIndependence, Electricity( Supply) Act, 1948, aimed toincrease access to electricity. creation of SEBs. Govt.becomes owner and operator in addition to being regulator
Central sector entry in 1975 Privatization and reforms after 1991 Electricity Act 2003
-
7/31/2019 Dist Overview _ Vivek Jha
7/93
7
GENERATION CAPACITY
1362 17004600
13,000
28,000
63,636
98,184
146,753
0
20000
40000
60000
80000
100000
120000
140000
160000
1947 1950 1960 1970 1980 1990 2000 2008 (As On
31 Oct)
YEAR
MW
-
7/31/2019 Dist Overview _ Vivek Jha
8/93
8
INDIA Vs CHINA
63,63698,184
138,000
65869
126638
299090
623561
28,000
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
1980 1990 2000 2007
INDIA CHINA
Installed Capacity :
-
7/31/2019 Dist Overview _ Vivek Jha
9/93
9
M a r - 0 7 2 0 1 2 2 0 2 2 2 0 3 2
Source: Integrated Energy Policy GOI
132 GW
220 GW
425 GW
778 GW
Demand Projectionconsidering 8% GDP growth
-
7/31/2019 Dist Overview _ Vivek Jha
10/93
-
7/31/2019 Dist Overview _ Vivek Jha
11/93
11
8.8
7.17.3
8.4
9.69.9
12.2
11.211.7
12.3
13.
16
0
2
4
6
8
10
12
14
16
18
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
P EAK DEMAND SHORTAGE %
ENERGY SHORT AGE %
source : MoP
ENERGY AND PEAK DEMAND SHORTAGES
-
7/31/2019 Dist Overview _ Vivek Jha
12/93
12
PER CAPITA CONSUMPTION OF ELECTRICITY
YEAR PER CAPITA CONSUMPTION
KWh / per year
1950 15
2007 612
2008 704
2012 - Target 1000
-
7/31/2019 Dist Overview _ Vivek Jha
13/93
13
Electricity Distribution Sector
-
7/31/2019 Dist Overview _ Vivek Jha
14/93
14
Electricity supply Chain
http://images.google.co.in/imgres?imgurl=http://www.geokem.com/images/scans/Indonesian_coal_mine.jpg&imgrefurl=http://www.geokem.com/global-element-dist1.html&h=826&w=1220&sz=194&hl=en&start=12&tbnid=p6o2eDKcI0OBDM:&tbnh=102&tbnw=150&prev=/images%3Fq%3Dcoal%26gbv%3D2%26hl%3Den%26sa%3DGhttp://images.google.co.in/imgres?imgurl=http://tuxgraphics.org/electronics/powersockets/power_socket_uk.jpg&imgrefurl=http://tuxgraphics.org/electronics/powersockets/&h=281&w=300&sz=17&hl=en&start=3&tbnid=1DyBw9biKk2oUM:&tbnh=109&tbnw=116&prev=/images%3Fq%3Dpower%2Bsocket%26gbv%3D2%26hl%3Den%26sa%3DGhttp://images.google.co.in/imgres?imgurl=http://www.menard.com/gifs/power-dist-system.gif&imgrefurl=http://www.menard.com/mec_power_system.html&h=452&w=518&sz=28&hl=en&start=7&tbnid=y-CI7SHxL-xMEM:&tbnh=114&tbnw=131&prev=/images%3Fq%3Dpower%2BDistribution%26gbv%3D2%26hl%3Denhttp://images.google.co.in/imgres?imgurl=http://www.mccullagh.org/db9/950-22/moss-landing-power-plant.jpg&imgrefurl=http://www.mccullagh.org/image/950-22/moss-landing-power-plant.html&h=576&w=768&sz=97&hl=en&start=10&tbnid=EDh8S7aGeSyi2M:&tbnh=107&tbnw=142&prev=/images%3Fq%3Dpower%2Bplant%26gbv%3D2%26hl%3Denhttp://images.google.co.in/imgres?imgurl=http://lifeboat.com/images/electric.grid.jpg&imgrefurl=http://lifeboat.com/ex/energy.2020&h=354&w=560&sz=217&hl=en&start=4&tbnid=SVp1tjPa9j_4CM:&tbnh=84&tbnw=133&prev=/images%3Fq%3Delectricity%2Bgeneration%26gbv%3D2%26hl%3Den -
7/31/2019 Dist Overview _ Vivek Jha
15/93
15
Power Distribution : Analogy with Goods Distribution
Generation DistributionTransmission Consumer
Production DistributionTransport Consumer
-
7/31/2019 Dist Overview _ Vivek Jha
16/93
16
Retailing Electricity : a different commodity
can not be seen, counted in numbers, or measured in kg, litres or
metres,
can not be put in a container with a forwarding address, on a
particular truck taking a particular route, but flows as per laws of
physics,
can not be stored, and whose availability and cost keep changing
widely intermingles with all other supplies in an inevitable pool, and can
not have an owners name tag ?
There is another peculiarity: the buyer has no control over what theseller supplies, and the seller has no control over what the buyerdraws from the pool, and the two may not match !
-
7/31/2019 Dist Overview _ Vivek Jha
17/93
17
Typical Electric Power Supply System.
-
7/31/2019 Dist Overview _ Vivek Jha
18/93
18
Typical Electric Power Supply System.
Generating units that produce electricity;
High voltage transmission lines that transportelectricity over long distances;
Low voltage distribution lines that deliverelectricity to consumers
Substations,
Energy control centres to coordinate
-
7/31/2019 Dist Overview _ Vivek Jha
19/93
19
Installation Cost
of Generating
Station
Rs.40,000/kW
T&D
Network Cost
Rs.40,000/kW
OH & Tech
Losses Rs.
20,000/kW
Total Cost
Rs.1.0Lac/kW
Result = 1 kW
load connection
to user
Cost of Delivering Power to Customer
-
7/31/2019 Dist Overview _ Vivek Jha
20/93
20
MANUFACTURER WHOLESALER
RETAILERCUSTOMER
Price X
PriceX+
X
Price X+ X+ Y
Payment
Payment
Pay
men
t BUSINESS EXPANSION
PROFITS
( X)
Y)
Value Addition In Manufactured Goods
GSS:P
-
7/31/2019 Dist Overview _ Vivek Jha
21/93
21
Raw Material
(Pre-Paid)
Power
Generated
(P)
Transmission
DistributionConsumer
P-
t=95
u
P-t-d=84uP-t-d-tf=64
Overpriced
Subsidized
Loss (3-
5%)
Loss(7-1
1%)
d
Theft(10-20%)
tf
Average realization = 30 -40 %
Last Mile Power Distribution
t
-
7/31/2019 Dist Overview _ Vivek Jha
22/93
22
SYSTEM ELEMENT POWER LOSS (%)
Minimum Maximum
Step Up transformers & EHVtransmission system
0.5 1.0
Transformation to intermediate voltagelevel, transmission system & step downto sub transmission voltage level
1.5 3.0
Sub transmission system & step down todistribution voltage level
2.0 4.5
Distribution lines & service connections 3.0 7.0
Total losses 7.0 15.5
Some Facts: EPRI LOSS TABLE
-
7/31/2019 Dist Overview _ Vivek Jha
23/93
23
Country T&D Losses(%) Country T&D Losses(%)
Japan 4 Switzerland 6
Denmark 4 Sweden 6.4
Germany 4 USA 7
Singapore 4 UK 7
Ghana 4 Taiwan 7
Macau 4.8 Italy 7.4
Korea 5.5 London 8.3
France 6 Malaysia 10
Australia 6 Thailand 10.3
Canada 6 Indonesia 12
China 6 Mexico 14South Africa 6 Hong Kong 15
Worldwide T&D Losses
INDIA 32
-
7/31/2019 Dist Overview _ Vivek Jha
24/93
24
The Dream
Power For All
The Reality
The Crisis..!
http://www.blogger.com/rearrange?blogID=7878970162782960467&widgetType=Image&widgetId=Image1&action=editWidget -
7/31/2019 Dist Overview _ Vivek Jha
25/93
25
1. Highly Capital Intensive
2. Inputs totally pre-paid
3. Instantly delivered
4. Reluctantly paid for, if at all
5. No accounting and accountability
Power Characteristics
GSS:P
A Sure way from Brightness to Darkness
-
7/31/2019 Dist Overview _ Vivek Jha
26/93
26
FINANCIAL PERFORMANCE OF SEBs
0
5000
10000
15000
20000
25000
30000
35000
97-98 98-99 99-2K 2K-01 2K1-02
Year
Losses(Rs.Cr
Commercial Losses(with subsidy) Commercial Losses(without subsidy)
24,837
33,177
-
7/31/2019 Dist Overview _ Vivek Jha
27/93
27
Inaccurate energy accounting
Only 45 % power is metered
Metered power is only 60 % accurate
Whatever is billed-approx 80-85 % is collected
Boards are collecting only 1/3
rd
of the revenue for powersupplied
-
7/31/2019 Dist Overview _ Vivek Jha
28/93
28
Gap between cost of supply & tariff increasing
due to differential & skewed tariff
Gap B etween Cost of Supply and Av
0
50
1 0 0
1 5 0
2 0 0
2 5 0
3 0 0
3 5 0
4 0 0
9 5 -9 6 9 6 -9 7 9 7 -9 8 9 8 -9 9 9 9 -0 0 00 -0 1 2 0 0 1 -0 2
Year
Paise
Cos t of S upply Av. Ta rif
CostofSupply
AverageTa
riff
Gap : 110 Paise
-
7/31/2019 Dist Overview _ Vivek Jha
29/93
29
AT&C LOS
-120
-100
-8 0
-6 0
-4 0
-2 0
0
AT&CLoss(%)
2000-01 2001-02 2002-03
H.P Goa T.N Maharastra U.P Karnataka W.B Rajasthan Punjab Haryana A.P Kerala Gujarat Assam
-
7/31/2019 Dist Overview _ Vivek Jha
30/93
30
AT&C Loss
DISTRIBUTION SECTOR : NEGLECTED ( and
-
7/31/2019 Dist Overview _ Vivek Jha
31/93
31
DISTRIBUTION SECTOR : NEGLECTED ( and
therefore, SPOILED CHILD OF POWER SECTOR
GEN
3.5 CR
TRAN
1 CR2.5 CR
DIS
LAST 25 YEARS WE HAVE ADDED APPROX 60,000 MW FOR AN
INVESTMENT OF RS. 1.2 LAC CR
TRANSMISSION 40,000 CR CLOSE
DISTRIBUTION 80,000 CR 30,000 CR ONLY
-
7/31/2019 Dist Overview _ Vivek Jha
32/93
32
0
0 . 2
0 . 4
0 . 6
0 . 8
1
1 . 2
1 . 4
1 s t
P L A N
2 n d
P L A N
3 r d
P L A N
T h r e e
A n n
4 t h
P L A N
5 t h
P L A N
A n n u a l
P la n
6 t h
P L A N
7 t h
P L A N
A n n u a l
P la n
A n n u la
P la n
8 t h
P L A N
9 t h
P L A N
T & D + R E
IN V E S T M E N T /E X P E N D IT U R E O
IN V E S T M E N T /E X P E N D IT U R E O
One of the main reason for increase in losses in the sector is low
investment in the t&d in comparison to the generation.
Investment in generation and T&D including RE should be 1:1
-
7/31/2019 Dist Overview _ Vivek Jha
33/93
33
Some Major Concerns in Distribution
Dilapidated Network, Lack of modern technology Metering Billing
Collection Power Theft Consumer care Regulatory compliance
-
7/31/2019 Dist Overview _ Vivek Jha
34/93
34
Metering
No Meters !
Defective Meters
Meters not read
Errors in manual record keeping Customer data updating neglected
-
7/31/2019 Dist Overview _ Vivek Jha
35/93
35
Billing
1. Non-billing
2. Imperfect bills
3. Faulty bill distribution4. Prolonged disputes
5. Lack of consumer friendly policies
6. Software mistakes
7. Connivance
8. Poor consumer data updating
9. No surveillance
P Th ft
-
7/31/2019 Dist Overview _ Vivek Jha
36/93
36
Power Theftby Direct Tapping
-
7/31/2019 Dist Overview _ Vivek Jha
37/93
37
Dilapidated Network
Almost 100% of the networks are overloaded which makes
the system quite vulnerable to weather conditions.
Inadequate reactive compensation leading to poor quality ofpower supply.Inadequacy of load management leading to peaks and
valleys which are beyond manageable limits.Poor reliability of supply.
-
7/31/2019 Dist Overview _ Vivek Jha
38/93
38
Problems Galore
Non-remunerative Tariff Structure andSubsidies
Political and Bureaucratic interference Working Culture and Employees morale
-
7/31/2019 Dist Overview _ Vivek Jha
39/93
39
What is being Done ?
-
7/31/2019 Dist Overview _ Vivek Jha
40/93
40
What is being Done ?
Restructuring of SEBs
Generate More power, corresponding strengthening
of T&D Reduce Losses and improve MBC
Professional Management Practices
Use of IT
Customer orientation
-
7/31/2019 Dist Overview _ Vivek Jha
41/93
41
Restructuring SEBs: What led to Reforms
Cost of supply not realized by SEBs Lack of commercial focus SEBs set up with social objectives! Statueprovided a sustainable framework
SEBs not recovering statutory ROR System inefficiencies
Unaccounted Electricity.Metering High T&D losses (~30% approx.)
Technical, Commercial (Theft) No serious attempts to address issue! Quality of supplyintermittent & poor ( 5-8 hours)
Some farmers may be willing to pay for regular & good quality power Tariff making process
Driven by political motives! Lack of commercial focus !
-
7/31/2019 Dist Overview _ Vivek Jha
42/93
42
Restructuring SEBs: What led to Reforms .
Agricultural consumption Tariff subsidized Irrigation pumps not meteredWasteful consumption,Inefficient pumps & Illegal
connections Industrial consumers bearing the burden of cross subsidy
SEBs virtual monopoly
No competition or choice Consumers & service obligations ignored Lack corporate governance & accountability No independent body regulating operationsImpact Limited improvement in service quality.no incentive or motive! Ability to invest in new projects hampered
Need of the hour Need for Private sector participation for bridging demand-supply gap Need for bringing in accountability in functioning & operations Need for creating a market choice !
SEB R t t i
-
7/31/2019 Dist Overview _ Vivek Jha
43/93
43
SEBRestructuring.
Generation
Transmission
Distribution
CustomerCustomer
SEB
ES Act
1948
BY VIRTUE OF BEING
INTEGRATED
NO SPECIFIC FOCUSON
DISTRIBUTION
NO SYTEM OF ACCOUNTING SEGGREGATION !
WHERE DOES THE PROBLEM LIE?
-
7/31/2019 Dist Overview _ Vivek Jha
44/93
44
Unbundling Accountability!
Unbundling forces profitability raising costsUnbundling forces profitability raising costs
Generation
Transmission
Distribution
CustomerCustomer
FUNCTIONAL
SEGGREGATION
ENABLES FOCUSON
EACH SEGEMENT
ACCOUNTING SEGGREGATION !
IDENTIFES WHERE THE PROBLEM LIES?
Retail Tariff - ERC
Bulk Tariff- ERC
PPA Tariff ERC
LOSSES
IDENTIFIED
-
7/31/2019 Dist Overview _ Vivek Jha
45/93
45
Restructuring of power sector set up
Current set up: Single Buyer Model
Gen Co Gen Co Gen Co IPPs
Transmission Co.
Dis Co Dis Co Dis Co Dis Co
Customer Customer Customer Customer
-
7/31/2019 Dist Overview _ Vivek Jha
46/93
46
TRANSMISSION OPEN ACCESS
Restructuring
Transmission Open Access
Eligible CustomerEligible Customer
Generator GeneratorGenerator
Distribution Distribution Distribution
Trader
Trader
Non -Eligible
Customer
Non -Eligible
Customer
Non -EligibleCustomer
Future set up: Multi Buyer Model
Non Eligible
Customer
GeneratorGeneratorGenerator
Transmission Open access
Non Eligible
Customer
Non Eligible
Customer
DistributorDistributor Distributor
Eligible Customer Eligible Customer
Trader
Trader
-
7/31/2019 Dist Overview _ Vivek Jha
47/93
47
Some steps that can be taken by the utilities to meet these
challenges
- improving metering efficiency;
- proper energy accounting and auditing;
- improved billing and collection efficiency;
- fixing of accountability of the personnel/feeder managers which mayhelp considerably in reduction of AT&C loss;
- providing better quality power in terms of voltage fluctuations and
reliability by reducing power cuts;
- better maintenance, renovation and modernization;
- instituting a customer complaint redressal mechanism, which is more
responsive and proactive;- adopting better management practices
- application of Information Technology.
-
7/31/2019 Dist Overview _ Vivek Jha
48/93
48
Improving Customer Satisfaction
Fully networked Consumer Care Centres
Providing ample bill payment avenues
Providing better quality power in terms ofvoltage fluctuations and reliability by reducing
power cuts.
customer complaint redressal mechanism
-
7/31/2019 Dist Overview _ Vivek Jha
49/93
49
NewConnection
Meters
Reading
Power
Reliability
Quality
Fault
Management
Consumer
Relationshi
p
OwnershipChange/
Addition/
Reductionof
Load
Redressal
Management
Billing
Payments
Convenience
Consumer priorities
-
7/31/2019 Dist Overview _ Vivek Jha
50/93
50
Electricity Distribution Industry Performance Indices
SAIFI: System Average Interruption Frequency Index
Measures the average frequency of Sustained (>5mts) interruptions per customer
Total no. of Customer
interruptionsSAIFI =
Total no. of Customers Served
SAIDI: System Average Interruption Duration Index
The average time that all customers are interrupted
Sum of Customer Interruption DurationsSAIDI =
Total no. of Customers
-
7/31/2019 Dist Overview _ Vivek Jha
51/93
51
Total no. of Customer Interruptions
CAIFI :Total no. of Customers affected
CAIDI: Customer Average interruptions Duration IndexRepresents the average time required to restore service, to the averagecustomer per sustained outage
Sum of Customer Interruption Durations
CAIDI =Total no. of Customer Interruptions
-
7/31/2019 Dist Overview _ Vivek Jha
52/93
52
Reliability Standards
-
7/31/2019 Dist Overview _ Vivek Jha
53/93
53
Some Recent Initiatives
APDRP
RGGVY
DRUM
Urban / Rural Franchisee in Distribution
Power Trading and power Exchange
INITIATIVES TAKEN
-
7/31/2019 Dist Overview _ Vivek Jha
54/93
54
Obligation of the State Government
Setting up of SERC & Rationalisation of Tariffs
Reorganisation of State Electricity Boards
Metering of 11 kV feeders & of all consumers
Energy Audit at all level
Support from Government of India
Supply of additional power wherever feasible
Assistance for distribution system: APDRP, DRUM
Funding for 100% rural electrification: RGGVY
Strengthening & improvement of transmission network by POWERGRID:
Concessional financing by PFC
INITIATIVES TAKEN ..
-
7/31/2019 Dist Overview _ Vivek Jha
55/93
55
APDRP
Objectives of APDRP : Improving financial viability of State Power Utilities
Reduction of AT & C losses
Improving customer satisfaction Increasing reliability &quality of power supply
Components Incentive component
Investment component
-
7/31/2019 Dist Overview _ Vivek Jha
56/93
56
-
7/31/2019 Dist Overview _ Vivek Jha
57/93
57
Funds Utilizedunder APDRP
INVESTMENTCOMPONENT
-
7/31/2019 Dist Overview _ Vivek Jha
58/93
58
FUNDS UTILIZED (Rs Crores)
587
2418
3009
2621
2176
1090
0
500
1000
1500
2000
2500
3000
3500
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
Funds Utilizedunder APDRP
INVESTMENT COMPONENT
Funds Released under APDRP
-
7/31/2019 Dist Overview _ Vivek Jha
59/93
59
Funds Released under APDRP
INCENTIVECOMPONENT
Source: MoP
Ranking of SEBs
-
7/31/2019 Dist Overview _ Vivek Jha
60/93
60
g
-
7/31/2019 Dist Overview _ Vivek Jha
61/93
61
RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJANA
RGGVY was launched in April-05 Under the programme 90% grant is provided by Govt. of India and 10% as
loan by REC (the nodal agency) to the State Governments.
Objectives: Electrifying all villages and habitations as pernew definition Providing access to electricity to all rural households Providing electricity Connection to BPL families free of charge
Infrastructure under RGGVY: Rural Electricity Distribution Backbone (REDB) with 33/11 KV (or 66/11 KV)
sub-station of adequate capacity in blocks where these do not exist. Village Electrification Infrastructure (VEI) with provision of distribution
transformer of appropriate capacity in villages/habitations. Decentralized Distributed Generation (DDG) Systems based on
conventional & non conventional energy sources where grid supply is not
feasible or cost-effective.
-
7/31/2019 Dist Overview _ Vivek Jha
62/93
62
-
7/31/2019 Dist Overview _ Vivek Jha
63/93
63
DRUM(Distribution Reform, Upgrades and Management)
Objective:to demonstrate best commercial and technological practicesthat improve the quality and reliability of last mile power distribution in
selected urban and rural distribution circles
Components: DRUM Technical Advisory
Rural Electrification Program being done jointly by the USA's Rural UtilityService (RUS) and the Rural Electrification Corporation (REC) of India
DRUM Training
Water & Energy Nexus Activity, dealing with the water-energy nexus.A separate consortium is providing this contract, which deals with rural
water-energy issues.
-
7/31/2019 Dist Overview _ Vivek Jha
64/93
64
Urban / Rural Franchisee in Distribution
A franchisee may be an entity empowered by the State todistribute electricity within an identified area for a prescribedduration and collect revenues directly from rural consumers
Who can be a franchisee ? Non govt. organisation (NGO)
Users Association ( UA)
Cooperative
Entrepreneur, Panchayat
Self help groups fulfilling the criteria laid out
for this purpose
-
7/31/2019 Dist Overview _ Vivek Jha
65/93
65
Power Trading:
Emerging Option for Distribution Companies
POWER TRADING VOLUME
1617
4178
1102911847
1418815022
20964
0
5000
10000
15000
20000
25000
1 2 3 4 5 6 7
YEAR
MILLIONUNITS
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
Source: CERC
-
7/31/2019 Dist Overview _ Vivek Jha
66/93
66
NTPCs Foray intoDistribution
-
7/31/2019 Dist Overview _ Vivek Jha
67/93
67
NESCL
A new wholly owned subsidiary called
NTPC ELECTRIC SUPPLY CO. LTD.
was incorporated on 21st aug., 2002
to establish its presence in distribution
MAIN OBJECTIVES
-
7/31/2019 Dist Overview _ Vivek Jha
68/93
68
MAIN OBJECTIVES
To acquire, establish & operate electrical systemsfor retaildistribution
To undertake works on behalf of others To act as Engineers & consultants
VISION
-
7/31/2019 Dist Overview _ Vivek Jha
69/93
69
VISION
To deliver quality power to the Nation by
creating models of excellence andbenchmarks in electricity distribution
thereby achieving customer delight.
-
7/31/2019 Dist Overview _ Vivek Jha
70/93
70
MISSION
To create a role model in the electricity distribution business by settingnew benchmarks.
To speedily plan and implement distribution networks using state-of-the-art technologies.
To provide transparent, ethical and prompt services for enhancing
customer delight.To adopt creative and innovative techniques for demand-side managementand financial viability of the distribution businesses.
To provide reliable, uninterrupted and quality power at appropriate tariffs.
To achieve effective energy accounting by ensuring accurate metering,timely billing and collection of revenues.
To create competent and committed human resource by nurturingtechnological & commercial competence for organisational growth andexcellence.
NESCLs Core Competency
-
7/31/2019 Dist Overview _ Vivek Jha
71/93
71
p y
Resource bank of experienced and committed man power Proven Project Management expertise of NTPC. Time tested system & procedures in the field of contracting/
procurement, Quality Assurance & Inspection Core engineering group backed by 25 years of experience in design
& engineering of electrical systems and IT based applications Ability to infuse new and emerging technology Consolidated expertise in the industry derived from the APDRP
assignments. Exhaustive data bank of cost estimates, reliable & reputed
manufacturers and contractors, including their sub-vendors. Proven capability in Renovation and Modernization . IT capabilities including IT-enabled systems & procedures
-
7/31/2019 Dist Overview _ Vivek Jha
72/93
72
OVERVIEW OF INITIATIVES
of
NTPC ELECTRIC SUPPLY COMPANY
-
7/31/2019 Dist Overview _ Vivek Jha
73/93
73
DIRECT
Acquisition of distribution circle
Create a model distribution circle
Competence in retail distribution Take efficiency improvement measures through
introduction of new & innovative technology and IT enabled
solutions & services
INDIRECT
-
7/31/2019 Dist Overview _ Vivek Jha
74/93
74
INDIRECT
Supplement the initiatives being taken by state utilities, byrendering support in the areas of:
Formulation of DPR and processing the sanction ofscheme/ loan
Assist SEBs in carrying out Energy Audit Design & Engineering Project execution
Quality Assurance & Inspection IT enabled applications APDRP consultancyRGGVY
-
7/31/2019 Dist Overview _ Vivek Jha
75/93
75
NESCL: WHERE DO WE STAND
TODAY??
DIRECT ASSOCIATION
-
7/31/2019 Dist Overview _ Vivek Jha
76/93
76
DIRECT ASSOCIATION
Initial efforts to acquire KESCO/ MESCOM Technical due diligence for KESCO carried out in-house Public Relationship (PR) blue print prepared and finalised Feedback from employees Negotiations with representatives of employee unions
All information related to HR, Finance, Commercial, Technicaland Contracts has been obtained.
SBI caps appointed for carrying out the due diligence ofMESCOM (Mangalore)
Obtained all necessary clearances from the localadministration
MOU signed with KESCO (GoUP) Draft agreement sent to Govt. of Karnataka & GoUP for their
acceptance
DIRECT ASSOCIATION
-
7/31/2019 Dist Overview _ Vivek Jha
77/93
77
CHATTISGARH
Parallel licensing in district KORBA
Due Diligence is under process
M.P. Parallel licensing in district SIDHI
Due Diligence is under process
GUJARAT Areas of distribution being identified by a committee
constituted by MOP
DIRECT ASSOCIATION
DIRECT ASSOCIATION
-
7/31/2019 Dist Overview _ Vivek Jha
78/93
78
KINFRA
JV with KINFRA for retail distribution of power
Areas of distribution Industrial parks/ SEZs under
KINFRA
Agreement signed with State Govt. and JV formed.
CESU
To be appointed as managers on behalf of OERC
Operation in a phased manner
Final decision of OERC pending
DIRECT ASSOCIATION
INDIRECT ASSOCIATION
-
7/31/2019 Dist Overview _ Vivek Jha
79/93
79
INDIRECT ASSOCIATION
ADVISOR TO APDRP PROGRAM LEAD Advisor cum consultant (AcC ) TO MOP INVOLVEMENT IN 12 STATES 5 STATES DIRECTLY
(MP,CHHATISGARH,MAHARASHTRA,HARYANA&PUNJAB)
To review and suggest action plan for improvement in systemreliability
To monitor and facilitate the progress of schemes under APDRP in
states on behalf of MOP, GOI To impart training to different level of executives of SEB/Utilities in
the area of Distribution business for their Capacity building
-
7/31/2019 Dist Overview _ Vivek Jha
80/93
80
INDIRECT ASSOCIATION
Project Execution on behalf of a client
Rendering consultancy services in areas of
Design & Engineering Procurement & Contracting
Project Management
QA&I
ALL IN THE DISTRIBUTION SECTORALL IN THE DISTRIBUTION SECTOR
ASSIGNMENTS SUCCESSFULLY EXECUTED
-
7/31/2019 Dist Overview _ Vivek Jha
81/93
81
Providing project management support to MPSEB, WZ, Indore in thearea of Project Management and QA& I.
Providing project management support to MPSEB, CZ, Bhopal/Gwalior in the area of Project Management and QA&I.
Design, Engineering, procurement, erection, testing and
commissioning of 66KV/ 11KV,2x20MVA sub station at UTChandigarh.
Augmentation of transformation capacity at existing 66KV,1x20MVAsub-station, at Indl. Area II, UT Chandigarh
Conversion of 66KV Overhead Transmission line to underground by
laying 66KV Single Core XLPE 400 Sq. mm cable. Design engineering, procurement, erection, testing and
commissioning of Rural Electrification in the state of West Bengal
ASSIGNMENTS SUCCESSFULLY EXECUTED
-
7/31/2019 Dist Overview _ Vivek Jha
82/93
82
CURRENT ASSIGNMENTS
Turnkey execution of 3x10 MVA, 33/11 KV sub-stationwith control room at Hotwar, Ranchi.
Planning & Monitoring of RE Project in the state ofMP, Uttaranchal, Karnataka.
Design engineering, procurement, erection, testingand commissioning of Rural Electrification in the stateof Chhattisgarh, Madhya Pradesh, Orissa, Kerala,Jharkhand and UT-Lakshadweep.
Turnkey execution of projects under APDRP schemein the districts of Ashoknagar & Shivpuri (MP) Third Party Inspection of Stock Material for UPCL,
MPPoKVVCL
-
7/31/2019 Dist Overview _ Vivek Jha
83/93
83
CURRENT ASSIGNMENTS
In 11th plan RGGVY programme NESCL has been
entrusted with 22 more projects( in addition of 8 in 10th
Plan in West Bengal & M.P.) covering 22 districts forthe implementation of rural electrification on turnkey
basis in 4 States i. e Chhattisgarh, Jharkhand, Orissa
and West Bengal covering approx 40,000 Villages in
30 districts with a sanctioned cost of Rs 2514 crore.
FUTURE ASSIGNMENTS
-
7/31/2019 Dist Overview _ Vivek Jha
84/93
84
Design, Engineering, procurement, testing and commissioning of 2 Nos. 220KV GIS sub stations and associated cabling for Delhi Transco Limited
GIS sub stations and associated cabling for NDMC
Implementation of SCADA in the city of Chandigarh.
Providing project management support to JVVNL, Jaipur in the area of
Project Management, QA & I and Field Quality for Feeder Renovationprogramme
Planning & Monitoring of RE work in the state of Himachal Pradesh, UT-Lakshadweep , Kerala
Establishment of a central load despatch center for UHBVN for managementof load & UI and global accounting
Consultancy services for supervision of T&D project under Durgapur ProjectLtd (DPL).
Design, Engineering, procurement, testing and commissioning
-
7/31/2019 Dist Overview _ Vivek Jha
85/93
85
Services offered by NESCL
Formulation of DPR
Detailed Engineering including preparation ofTechnical Specifications.
Contracts & Material Management Support Complete Project Management Support (Planning &
Monitoring)
Quality Assurance & Inspection Support
Turnkey Execution of Projects
IT application support
-
7/31/2019 Dist Overview _ Vivek Jha
86/93
86
Financial performance of NESCL.
Revenue for 2007-08= Rs 41.892 crore (Rs 20.684crore)
(PAT = Rs 12.665crore ( Rs 2.933 crore)
Dividend =Rs 1.75crore
-
7/31/2019 Dist Overview _ Vivek Jha
87/93
87
Conclusion
-
7/31/2019 Dist Overview _ Vivek Jha
88/93
88
Distribution sectors challenges are diversifiedas technical, financial, historical and political
Improvements needed in every area
Central & state governments trying to make thesector commercially viable
Private sector participation needed butprivatization is not the panacea
Conclusion
-
7/31/2019 Dist Overview _ Vivek Jha
89/93
89
Thank YouANY QUESTIONS ?ANY QUESTIONS ?
-
7/31/2019 Dist Overview _ Vivek Jha
90/93
90
Cost of Power
Source: CEA report : Oct 2008
Details of the cash loss reduction and incentives released to variousstates under APDRP are as below:(As on 31 March 2008)
-
7/31/2019 Dist Overview _ Vivek Jha
91/93
91
Sl. No. State Claim Year Incentive AmountRecommendedforreleased to MoF
Amount Released by MoF
1. Andhra Pradesh 2002-03 265.11 265.11
2. Gujarat 2001-02 236.38 236.382002-03 148.08 148.08
2003-04 366.82 366.82
2004-05 288.03 288.03
3. Haryana 2001-02 105.49 105.49
4. Kerala 2002-03 64.94 64.94
2004-05 82.99 82.99
5. Madhya Pradesh 2002-03 297.61 297.61
6. Maharashtra 2001-02 137.89 137.89
7. Rajasthan 2001-02 137.71 137.71
8. West Bengal 2002-03 73.00 73.00
2003-04 302.76 302.762004-05 5.88 5.88
2005-06 115.10 115.10
9. Punjab 2003-04 251.94 251.94
Total 2879.63 2879.63
f f f
http://tempweb232.nic.in/rggvyportal/text_details.htmhttp://tempweb232.nic.in/rggvyportal/text_details.htm -
7/31/2019 Dist Overview _ Vivek Jha
92/93
92
Definition of Electrified Village
Prior to October 1997
A Village should be classified as electrified if electricity is being used within its
revenue area for any purpose whatsoever.
After October 1997
A village will be deemed to be electrified if the electricity is used in the inhabited
locality, within the revenue boundary of the village for any purpose whatsoever.
New definition of village electrification came into effect from the year 2004-05
(Issued by MOP, vide their letter No. 42/1/2001-D(RE) dated 5th February 2004
and its corrigendum vide letter no. 42/1/2001-D(RE) dated 17th February 2004.)
As per the new definition, a village would be declared as electrified, if :
1. Basic infrastructure such as Distribution Transformer and Distribution lines are
provided in the inhabited locality as well as the Dalit Basti/ hamlet where it
exists.
2. Electricity is provided to public places like Schools, Panchayat Office, Health
Centers, Dispensaries, Community centers etc.
3. The number of households electrified should be at least 10% of the total
number of households in the village.
Power Cost Comparison
http://tempweb232.nic.in/rggvyportal/text_details.htmhttp://tempweb232.nic.in/rggvyportal/text_details.htm -
7/31/2019 Dist Overview _ Vivek Jha
93/93
COUNTRY PRESENT COST FORECAST FOR 2007(In Cents/kWh) (In Cents/kWh)
Canada 2 2
Norway 1 1
Sweden 2 2
Thailand 4 5
Egypt 3 3
India 9 12