Dist Overview _ Vivek Jha

download Dist Overview _ Vivek Jha

of 93

Transcript of Dist Overview _ Vivek Jha

  • 7/31/2019 Dist Overview _ Vivek Jha

    1/93

    1

    WELCOME

    to a presentation onPOWER DISTRIBUTION SECTOR

    and

    NTPC IN POWER DISTRIBUTION

    VIVEK JHA

  • 7/31/2019 Dist Overview _ Vivek Jha

    2/93

    2

    Presentation overview:

    Introduction and Power Scenario In The Country

    The Distribution sector :

    Status and need for reforms Key issues and challenges

    What is being Done : Reform Initiatives in Distribution

    NTPCs foray in Distribution sector (NESCL)

  • 7/31/2019 Dist Overview _ Vivek Jha

    3/93

    3

    Introduction

    and

    Indian Power Sector

  • 7/31/2019 Dist Overview _ Vivek Jha

    4/93

    4

    There is no substitute for energy.

    The whole edifice of modern life is built upon it.

    Although energy can be bought and soldlike any other commodity,

    it is not just another commodity

    but the precondition of all other commodities,

    a basic factor likeAir, Water and Earth.

    - E. F. SCHUMACHER(British Economist)

    Introduction

  • 7/31/2019 Dist Overview _ Vivek Jha

    5/93

    5

    Electrical energy : Backbone of economy

    8 % growth in GDP => At least 10 % growth inElectricity industry

    There has been tremendous improvement andaugmentation in Generation, Transmission andDistribution since independence. However, we still have

    significant shortage of power supply. Distrubution is the key area in power sector

    Introduction

  • 7/31/2019 Dist Overview _ Vivek Jha

    6/93

    6

    Historical Overview

    First electricity generating station in India a small hydrostation in Darjeeling in 1896

    Total installed capacity in 1947 : 1362 MW.

    Pre-1948, all generation privately-owned. (Licensed &regulated by Govt. under Indian Electricity Act, 1910) Retaildistribution only around generating stations. No transmission.

    PostIndependence, Electricity( Supply) Act, 1948, aimed toincrease access to electricity. creation of SEBs. Govt.becomes owner and operator in addition to being regulator

    Central sector entry in 1975 Privatization and reforms after 1991 Electricity Act 2003

  • 7/31/2019 Dist Overview _ Vivek Jha

    7/93

    7

    GENERATION CAPACITY

    1362 17004600

    13,000

    28,000

    63,636

    98,184

    146,753

    0

    20000

    40000

    60000

    80000

    100000

    120000

    140000

    160000

    1947 1950 1960 1970 1980 1990 2000 2008 (As On

    31 Oct)

    YEAR

    MW

  • 7/31/2019 Dist Overview _ Vivek Jha

    8/93

    8

    INDIA Vs CHINA

    63,63698,184

    138,000

    65869

    126638

    299090

    623561

    28,000

    0

    100,000

    200,000

    300,000

    400,000

    500,000

    600,000

    700,000

    1980 1990 2000 2007

    INDIA CHINA

    Installed Capacity :

  • 7/31/2019 Dist Overview _ Vivek Jha

    9/93

    9

    M a r - 0 7 2 0 1 2 2 0 2 2 2 0 3 2

    Source: Integrated Energy Policy GOI

    132 GW

    220 GW

    425 GW

    778 GW

    Demand Projectionconsidering 8% GDP growth

  • 7/31/2019 Dist Overview _ Vivek Jha

    10/93

  • 7/31/2019 Dist Overview _ Vivek Jha

    11/93

    11

    8.8

    7.17.3

    8.4

    9.69.9

    12.2

    11.211.7

    12.3

    13.

    16

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    2002-03 2003-04 2004-05 2005-06 2006-07 2007-08

    P EAK DEMAND SHORTAGE %

    ENERGY SHORT AGE %

    source : MoP

    ENERGY AND PEAK DEMAND SHORTAGES

  • 7/31/2019 Dist Overview _ Vivek Jha

    12/93

    12

    PER CAPITA CONSUMPTION OF ELECTRICITY

    YEAR PER CAPITA CONSUMPTION

    KWh / per year

    1950 15

    2007 612

    2008 704

    2012 - Target 1000

  • 7/31/2019 Dist Overview _ Vivek Jha

    13/93

    13

    Electricity Distribution Sector

  • 7/31/2019 Dist Overview _ Vivek Jha

    14/93

    14

    Electricity supply Chain

    http://images.google.co.in/imgres?imgurl=http://www.geokem.com/images/scans/Indonesian_coal_mine.jpg&imgrefurl=http://www.geokem.com/global-element-dist1.html&h=826&w=1220&sz=194&hl=en&start=12&tbnid=p6o2eDKcI0OBDM:&tbnh=102&tbnw=150&prev=/images%3Fq%3Dcoal%26gbv%3D2%26hl%3Den%26sa%3DGhttp://images.google.co.in/imgres?imgurl=http://tuxgraphics.org/electronics/powersockets/power_socket_uk.jpg&imgrefurl=http://tuxgraphics.org/electronics/powersockets/&h=281&w=300&sz=17&hl=en&start=3&tbnid=1DyBw9biKk2oUM:&tbnh=109&tbnw=116&prev=/images%3Fq%3Dpower%2Bsocket%26gbv%3D2%26hl%3Den%26sa%3DGhttp://images.google.co.in/imgres?imgurl=http://www.menard.com/gifs/power-dist-system.gif&imgrefurl=http://www.menard.com/mec_power_system.html&h=452&w=518&sz=28&hl=en&start=7&tbnid=y-CI7SHxL-xMEM:&tbnh=114&tbnw=131&prev=/images%3Fq%3Dpower%2BDistribution%26gbv%3D2%26hl%3Denhttp://images.google.co.in/imgres?imgurl=http://www.mccullagh.org/db9/950-22/moss-landing-power-plant.jpg&imgrefurl=http://www.mccullagh.org/image/950-22/moss-landing-power-plant.html&h=576&w=768&sz=97&hl=en&start=10&tbnid=EDh8S7aGeSyi2M:&tbnh=107&tbnw=142&prev=/images%3Fq%3Dpower%2Bplant%26gbv%3D2%26hl%3Denhttp://images.google.co.in/imgres?imgurl=http://lifeboat.com/images/electric.grid.jpg&imgrefurl=http://lifeboat.com/ex/energy.2020&h=354&w=560&sz=217&hl=en&start=4&tbnid=SVp1tjPa9j_4CM:&tbnh=84&tbnw=133&prev=/images%3Fq%3Delectricity%2Bgeneration%26gbv%3D2%26hl%3Den
  • 7/31/2019 Dist Overview _ Vivek Jha

    15/93

    15

    Power Distribution : Analogy with Goods Distribution

    Generation DistributionTransmission Consumer

    Production DistributionTransport Consumer

  • 7/31/2019 Dist Overview _ Vivek Jha

    16/93

    16

    Retailing Electricity : a different commodity

    can not be seen, counted in numbers, or measured in kg, litres or

    metres,

    can not be put in a container with a forwarding address, on a

    particular truck taking a particular route, but flows as per laws of

    physics,

    can not be stored, and whose availability and cost keep changing

    widely intermingles with all other supplies in an inevitable pool, and can

    not have an owners name tag ?

    There is another peculiarity: the buyer has no control over what theseller supplies, and the seller has no control over what the buyerdraws from the pool, and the two may not match !

  • 7/31/2019 Dist Overview _ Vivek Jha

    17/93

    17

    Typical Electric Power Supply System.

  • 7/31/2019 Dist Overview _ Vivek Jha

    18/93

    18

    Typical Electric Power Supply System.

    Generating units that produce electricity;

    High voltage transmission lines that transportelectricity over long distances;

    Low voltage distribution lines that deliverelectricity to consumers

    Substations,

    Energy control centres to coordinate

  • 7/31/2019 Dist Overview _ Vivek Jha

    19/93

    19

    Installation Cost

    of Generating

    Station

    Rs.40,000/kW

    T&D

    Network Cost

    Rs.40,000/kW

    OH & Tech

    Losses Rs.

    20,000/kW

    Total Cost

    Rs.1.0Lac/kW

    Result = 1 kW

    load connection

    to user

    Cost of Delivering Power to Customer

  • 7/31/2019 Dist Overview _ Vivek Jha

    20/93

    20

    MANUFACTURER WHOLESALER

    RETAILERCUSTOMER

    Price X

    PriceX+

    X

    Price X+ X+ Y

    Payment

    Payment

    Pay

    men

    t BUSINESS EXPANSION

    PROFITS

    ( X)

    Y)

    Value Addition In Manufactured Goods

    GSS:P

  • 7/31/2019 Dist Overview _ Vivek Jha

    21/93

    21

    Raw Material

    (Pre-Paid)

    Power

    Generated

    (P)

    Transmission

    DistributionConsumer

    P-

    t=95

    u

    P-t-d=84uP-t-d-tf=64

    Overpriced

    Subsidized

    Loss (3-

    5%)

    Loss(7-1

    1%)

    d

    Theft(10-20%)

    tf

    Average realization = 30 -40 %

    Last Mile Power Distribution

    t

  • 7/31/2019 Dist Overview _ Vivek Jha

    22/93

    22

    SYSTEM ELEMENT POWER LOSS (%)

    Minimum Maximum

    Step Up transformers & EHVtransmission system

    0.5 1.0

    Transformation to intermediate voltagelevel, transmission system & step downto sub transmission voltage level

    1.5 3.0

    Sub transmission system & step down todistribution voltage level

    2.0 4.5

    Distribution lines & service connections 3.0 7.0

    Total losses 7.0 15.5

    Some Facts: EPRI LOSS TABLE

  • 7/31/2019 Dist Overview _ Vivek Jha

    23/93

    23

    Country T&D Losses(%) Country T&D Losses(%)

    Japan 4 Switzerland 6

    Denmark 4 Sweden 6.4

    Germany 4 USA 7

    Singapore 4 UK 7

    Ghana 4 Taiwan 7

    Macau 4.8 Italy 7.4

    Korea 5.5 London 8.3

    France 6 Malaysia 10

    Australia 6 Thailand 10.3

    Canada 6 Indonesia 12

    China 6 Mexico 14South Africa 6 Hong Kong 15

    Worldwide T&D Losses

    INDIA 32

  • 7/31/2019 Dist Overview _ Vivek Jha

    24/93

    24

    The Dream

    Power For All

    The Reality

    The Crisis..!

    http://www.blogger.com/rearrange?blogID=7878970162782960467&widgetType=Image&widgetId=Image1&action=editWidget
  • 7/31/2019 Dist Overview _ Vivek Jha

    25/93

    25

    1. Highly Capital Intensive

    2. Inputs totally pre-paid

    3. Instantly delivered

    4. Reluctantly paid for, if at all

    5. No accounting and accountability

    Power Characteristics

    GSS:P

    A Sure way from Brightness to Darkness

  • 7/31/2019 Dist Overview _ Vivek Jha

    26/93

    26

    FINANCIAL PERFORMANCE OF SEBs

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    97-98 98-99 99-2K 2K-01 2K1-02

    Year

    Losses(Rs.Cr

    Commercial Losses(with subsidy) Commercial Losses(without subsidy)

    24,837

    33,177

  • 7/31/2019 Dist Overview _ Vivek Jha

    27/93

    27

    Inaccurate energy accounting

    Only 45 % power is metered

    Metered power is only 60 % accurate

    Whatever is billed-approx 80-85 % is collected

    Boards are collecting only 1/3

    rd

    of the revenue for powersupplied

  • 7/31/2019 Dist Overview _ Vivek Jha

    28/93

    28

    Gap between cost of supply & tariff increasing

    due to differential & skewed tariff

    Gap B etween Cost of Supply and Av

    0

    50

    1 0 0

    1 5 0

    2 0 0

    2 5 0

    3 0 0

    3 5 0

    4 0 0

    9 5 -9 6 9 6 -9 7 9 7 -9 8 9 8 -9 9 9 9 -0 0 00 -0 1 2 0 0 1 -0 2

    Year

    Paise

    Cos t of S upply Av. Ta rif

    CostofSupply

    AverageTa

    riff

    Gap : 110 Paise

  • 7/31/2019 Dist Overview _ Vivek Jha

    29/93

    29

    AT&C LOS

    -120

    -100

    -8 0

    -6 0

    -4 0

    -2 0

    0

    AT&CLoss(%)

    2000-01 2001-02 2002-03

    H.P Goa T.N Maharastra U.P Karnataka W.B Rajasthan Punjab Haryana A.P Kerala Gujarat Assam

  • 7/31/2019 Dist Overview _ Vivek Jha

    30/93

    30

    AT&C Loss

    DISTRIBUTION SECTOR : NEGLECTED ( and

  • 7/31/2019 Dist Overview _ Vivek Jha

    31/93

    31

    DISTRIBUTION SECTOR : NEGLECTED ( and

    therefore, SPOILED CHILD OF POWER SECTOR

    GEN

    3.5 CR

    TRAN

    1 CR2.5 CR

    DIS

    LAST 25 YEARS WE HAVE ADDED APPROX 60,000 MW FOR AN

    INVESTMENT OF RS. 1.2 LAC CR

    TRANSMISSION 40,000 CR CLOSE

    DISTRIBUTION 80,000 CR 30,000 CR ONLY

  • 7/31/2019 Dist Overview _ Vivek Jha

    32/93

    32

    0

    0 . 2

    0 . 4

    0 . 6

    0 . 8

    1

    1 . 2

    1 . 4

    1 s t

    P L A N

    2 n d

    P L A N

    3 r d

    P L A N

    T h r e e

    A n n

    4 t h

    P L A N

    5 t h

    P L A N

    A n n u a l

    P la n

    6 t h

    P L A N

    7 t h

    P L A N

    A n n u a l

    P la n

    A n n u la

    P la n

    8 t h

    P L A N

    9 t h

    P L A N

    T & D + R E

    IN V E S T M E N T /E X P E N D IT U R E O

    IN V E S T M E N T /E X P E N D IT U R E O

    One of the main reason for increase in losses in the sector is low

    investment in the t&d in comparison to the generation.

    Investment in generation and T&D including RE should be 1:1

  • 7/31/2019 Dist Overview _ Vivek Jha

    33/93

    33

    Some Major Concerns in Distribution

    Dilapidated Network, Lack of modern technology Metering Billing

    Collection Power Theft Consumer care Regulatory compliance

  • 7/31/2019 Dist Overview _ Vivek Jha

    34/93

    34

    Metering

    No Meters !

    Defective Meters

    Meters not read

    Errors in manual record keeping Customer data updating neglected

  • 7/31/2019 Dist Overview _ Vivek Jha

    35/93

    35

    Billing

    1. Non-billing

    2. Imperfect bills

    3. Faulty bill distribution4. Prolonged disputes

    5. Lack of consumer friendly policies

    6. Software mistakes

    7. Connivance

    8. Poor consumer data updating

    9. No surveillance

    P Th ft

  • 7/31/2019 Dist Overview _ Vivek Jha

    36/93

    36

    Power Theftby Direct Tapping

  • 7/31/2019 Dist Overview _ Vivek Jha

    37/93

    37

    Dilapidated Network

    Almost 100% of the networks are overloaded which makes

    the system quite vulnerable to weather conditions.

    Inadequate reactive compensation leading to poor quality ofpower supply.Inadequacy of load management leading to peaks and

    valleys which are beyond manageable limits.Poor reliability of supply.

  • 7/31/2019 Dist Overview _ Vivek Jha

    38/93

    38

    Problems Galore

    Non-remunerative Tariff Structure andSubsidies

    Political and Bureaucratic interference Working Culture and Employees morale

  • 7/31/2019 Dist Overview _ Vivek Jha

    39/93

    39

    What is being Done ?

  • 7/31/2019 Dist Overview _ Vivek Jha

    40/93

    40

    What is being Done ?

    Restructuring of SEBs

    Generate More power, corresponding strengthening

    of T&D Reduce Losses and improve MBC

    Professional Management Practices

    Use of IT

    Customer orientation

  • 7/31/2019 Dist Overview _ Vivek Jha

    41/93

    41

    Restructuring SEBs: What led to Reforms

    Cost of supply not realized by SEBs Lack of commercial focus SEBs set up with social objectives! Statueprovided a sustainable framework

    SEBs not recovering statutory ROR System inefficiencies

    Unaccounted Electricity.Metering High T&D losses (~30% approx.)

    Technical, Commercial (Theft) No serious attempts to address issue! Quality of supplyintermittent & poor ( 5-8 hours)

    Some farmers may be willing to pay for regular & good quality power Tariff making process

    Driven by political motives! Lack of commercial focus !

  • 7/31/2019 Dist Overview _ Vivek Jha

    42/93

    42

    Restructuring SEBs: What led to Reforms .

    Agricultural consumption Tariff subsidized Irrigation pumps not meteredWasteful consumption,Inefficient pumps & Illegal

    connections Industrial consumers bearing the burden of cross subsidy

    SEBs virtual monopoly

    No competition or choice Consumers & service obligations ignored Lack corporate governance & accountability No independent body regulating operationsImpact Limited improvement in service quality.no incentive or motive! Ability to invest in new projects hampered

    Need of the hour Need for Private sector participation for bridging demand-supply gap Need for bringing in accountability in functioning & operations Need for creating a market choice !

    SEB R t t i

  • 7/31/2019 Dist Overview _ Vivek Jha

    43/93

    43

    SEBRestructuring.

    Generation

    Transmission

    Distribution

    CustomerCustomer

    SEB

    ES Act

    1948

    BY VIRTUE OF BEING

    INTEGRATED

    NO SPECIFIC FOCUSON

    DISTRIBUTION

    NO SYTEM OF ACCOUNTING SEGGREGATION !

    WHERE DOES THE PROBLEM LIE?

  • 7/31/2019 Dist Overview _ Vivek Jha

    44/93

    44

    Unbundling Accountability!

    Unbundling forces profitability raising costsUnbundling forces profitability raising costs

    Generation

    Transmission

    Distribution

    CustomerCustomer

    FUNCTIONAL

    SEGGREGATION

    ENABLES FOCUSON

    EACH SEGEMENT

    ACCOUNTING SEGGREGATION !

    IDENTIFES WHERE THE PROBLEM LIES?

    Retail Tariff - ERC

    Bulk Tariff- ERC

    PPA Tariff ERC

    LOSSES

    IDENTIFIED

  • 7/31/2019 Dist Overview _ Vivek Jha

    45/93

    45

    Restructuring of power sector set up

    Current set up: Single Buyer Model

    Gen Co Gen Co Gen Co IPPs

    Transmission Co.

    Dis Co Dis Co Dis Co Dis Co

    Customer Customer Customer Customer

  • 7/31/2019 Dist Overview _ Vivek Jha

    46/93

    46

    TRANSMISSION OPEN ACCESS

    Restructuring

    Transmission Open Access

    Eligible CustomerEligible Customer

    Generator GeneratorGenerator

    Distribution Distribution Distribution

    Trader

    Trader

    Non -Eligible

    Customer

    Non -Eligible

    Customer

    Non -EligibleCustomer

    Future set up: Multi Buyer Model

    Non Eligible

    Customer

    GeneratorGeneratorGenerator

    Transmission Open access

    Non Eligible

    Customer

    Non Eligible

    Customer

    DistributorDistributor Distributor

    Eligible Customer Eligible Customer

    Trader

    Trader

  • 7/31/2019 Dist Overview _ Vivek Jha

    47/93

    47

    Some steps that can be taken by the utilities to meet these

    challenges

    - improving metering efficiency;

    - proper energy accounting and auditing;

    - improved billing and collection efficiency;

    - fixing of accountability of the personnel/feeder managers which mayhelp considerably in reduction of AT&C loss;

    - providing better quality power in terms of voltage fluctuations and

    reliability by reducing power cuts;

    - better maintenance, renovation and modernization;

    - instituting a customer complaint redressal mechanism, which is more

    responsive and proactive;- adopting better management practices

    - application of Information Technology.

  • 7/31/2019 Dist Overview _ Vivek Jha

    48/93

    48

    Improving Customer Satisfaction

    Fully networked Consumer Care Centres

    Providing ample bill payment avenues

    Providing better quality power in terms ofvoltage fluctuations and reliability by reducing

    power cuts.

    customer complaint redressal mechanism

  • 7/31/2019 Dist Overview _ Vivek Jha

    49/93

    49

    NewConnection

    Meters

    Reading

    Power

    Reliability

    Quality

    Fault

    Management

    Consumer

    Relationshi

    p

    OwnershipChange/

    Addition/

    Reductionof

    Load

    Redressal

    Management

    Billing

    Payments

    Convenience

    Consumer priorities

  • 7/31/2019 Dist Overview _ Vivek Jha

    50/93

    50

    Electricity Distribution Industry Performance Indices

    SAIFI: System Average Interruption Frequency Index

    Measures the average frequency of Sustained (>5mts) interruptions per customer

    Total no. of Customer

    interruptionsSAIFI =

    Total no. of Customers Served

    SAIDI: System Average Interruption Duration Index

    The average time that all customers are interrupted

    Sum of Customer Interruption DurationsSAIDI =

    Total no. of Customers

  • 7/31/2019 Dist Overview _ Vivek Jha

    51/93

    51

    Total no. of Customer Interruptions

    CAIFI :Total no. of Customers affected

    CAIDI: Customer Average interruptions Duration IndexRepresents the average time required to restore service, to the averagecustomer per sustained outage

    Sum of Customer Interruption Durations

    CAIDI =Total no. of Customer Interruptions

  • 7/31/2019 Dist Overview _ Vivek Jha

    52/93

    52

    Reliability Standards

  • 7/31/2019 Dist Overview _ Vivek Jha

    53/93

    53

    Some Recent Initiatives

    APDRP

    RGGVY

    DRUM

    Urban / Rural Franchisee in Distribution

    Power Trading and power Exchange

    INITIATIVES TAKEN

  • 7/31/2019 Dist Overview _ Vivek Jha

    54/93

    54

    Obligation of the State Government

    Setting up of SERC & Rationalisation of Tariffs

    Reorganisation of State Electricity Boards

    Metering of 11 kV feeders & of all consumers

    Energy Audit at all level

    Support from Government of India

    Supply of additional power wherever feasible

    Assistance for distribution system: APDRP, DRUM

    Funding for 100% rural electrification: RGGVY

    Strengthening & improvement of transmission network by POWERGRID:

    Concessional financing by PFC

    INITIATIVES TAKEN ..

  • 7/31/2019 Dist Overview _ Vivek Jha

    55/93

    55

    APDRP

    Objectives of APDRP : Improving financial viability of State Power Utilities

    Reduction of AT & C losses

    Improving customer satisfaction Increasing reliability &quality of power supply

    Components Incentive component

    Investment component

  • 7/31/2019 Dist Overview _ Vivek Jha

    56/93

    56

  • 7/31/2019 Dist Overview _ Vivek Jha

    57/93

    57

    Funds Utilizedunder APDRP

    INVESTMENTCOMPONENT

  • 7/31/2019 Dist Overview _ Vivek Jha

    58/93

    58

    FUNDS UTILIZED (Rs Crores)

    587

    2418

    3009

    2621

    2176

    1090

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    2002-03 2003-04 2004-05 2005-06 2006-07 2007-08

    Funds Utilizedunder APDRP

    INVESTMENT COMPONENT

    Funds Released under APDRP

  • 7/31/2019 Dist Overview _ Vivek Jha

    59/93

    59

    Funds Released under APDRP

    INCENTIVECOMPONENT

    Source: MoP

    Ranking of SEBs

  • 7/31/2019 Dist Overview _ Vivek Jha

    60/93

    60

    g

  • 7/31/2019 Dist Overview _ Vivek Jha

    61/93

    61

    RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJANA

    RGGVY was launched in April-05 Under the programme 90% grant is provided by Govt. of India and 10% as

    loan by REC (the nodal agency) to the State Governments.

    Objectives: Electrifying all villages and habitations as pernew definition Providing access to electricity to all rural households Providing electricity Connection to BPL families free of charge

    Infrastructure under RGGVY: Rural Electricity Distribution Backbone (REDB) with 33/11 KV (or 66/11 KV)

    sub-station of adequate capacity in blocks where these do not exist. Village Electrification Infrastructure (VEI) with provision of distribution

    transformer of appropriate capacity in villages/habitations. Decentralized Distributed Generation (DDG) Systems based on

    conventional & non conventional energy sources where grid supply is not

    feasible or cost-effective.

  • 7/31/2019 Dist Overview _ Vivek Jha

    62/93

    62

  • 7/31/2019 Dist Overview _ Vivek Jha

    63/93

    63

    DRUM(Distribution Reform, Upgrades and Management)

    Objective:to demonstrate best commercial and technological practicesthat improve the quality and reliability of last mile power distribution in

    selected urban and rural distribution circles

    Components: DRUM Technical Advisory

    Rural Electrification Program being done jointly by the USA's Rural UtilityService (RUS) and the Rural Electrification Corporation (REC) of India

    DRUM Training

    Water & Energy Nexus Activity, dealing with the water-energy nexus.A separate consortium is providing this contract, which deals with rural

    water-energy issues.

  • 7/31/2019 Dist Overview _ Vivek Jha

    64/93

    64

    Urban / Rural Franchisee in Distribution

    A franchisee may be an entity empowered by the State todistribute electricity within an identified area for a prescribedduration and collect revenues directly from rural consumers

    Who can be a franchisee ? Non govt. organisation (NGO)

    Users Association ( UA)

    Cooperative

    Entrepreneur, Panchayat

    Self help groups fulfilling the criteria laid out

    for this purpose

  • 7/31/2019 Dist Overview _ Vivek Jha

    65/93

    65

    Power Trading:

    Emerging Option for Distribution Companies

    POWER TRADING VOLUME

    1617

    4178

    1102911847

    1418815022

    20964

    0

    5000

    10000

    15000

    20000

    25000

    1 2 3 4 5 6 7

    YEAR

    MILLIONUNITS

    2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08

    Source: CERC

  • 7/31/2019 Dist Overview _ Vivek Jha

    66/93

    66

    NTPCs Foray intoDistribution

  • 7/31/2019 Dist Overview _ Vivek Jha

    67/93

    67

    NESCL

    A new wholly owned subsidiary called

    NTPC ELECTRIC SUPPLY CO. LTD.

    was incorporated on 21st aug., 2002

    to establish its presence in distribution

    MAIN OBJECTIVES

  • 7/31/2019 Dist Overview _ Vivek Jha

    68/93

    68

    MAIN OBJECTIVES

    To acquire, establish & operate electrical systemsfor retaildistribution

    To undertake works on behalf of others To act as Engineers & consultants

    VISION

  • 7/31/2019 Dist Overview _ Vivek Jha

    69/93

    69

    VISION

    To deliver quality power to the Nation by

    creating models of excellence andbenchmarks in electricity distribution

    thereby achieving customer delight.

  • 7/31/2019 Dist Overview _ Vivek Jha

    70/93

    70

    MISSION

    To create a role model in the electricity distribution business by settingnew benchmarks.

    To speedily plan and implement distribution networks using state-of-the-art technologies.

    To provide transparent, ethical and prompt services for enhancing

    customer delight.To adopt creative and innovative techniques for demand-side managementand financial viability of the distribution businesses.

    To provide reliable, uninterrupted and quality power at appropriate tariffs.

    To achieve effective energy accounting by ensuring accurate metering,timely billing and collection of revenues.

    To create competent and committed human resource by nurturingtechnological & commercial competence for organisational growth andexcellence.

    NESCLs Core Competency

  • 7/31/2019 Dist Overview _ Vivek Jha

    71/93

    71

    p y

    Resource bank of experienced and committed man power Proven Project Management expertise of NTPC. Time tested system & procedures in the field of contracting/

    procurement, Quality Assurance & Inspection Core engineering group backed by 25 years of experience in design

    & engineering of electrical systems and IT based applications Ability to infuse new and emerging technology Consolidated expertise in the industry derived from the APDRP

    assignments. Exhaustive data bank of cost estimates, reliable & reputed

    manufacturers and contractors, including their sub-vendors. Proven capability in Renovation and Modernization . IT capabilities including IT-enabled systems & procedures

  • 7/31/2019 Dist Overview _ Vivek Jha

    72/93

    72

    OVERVIEW OF INITIATIVES

    of

    NTPC ELECTRIC SUPPLY COMPANY

  • 7/31/2019 Dist Overview _ Vivek Jha

    73/93

    73

    DIRECT

    Acquisition of distribution circle

    Create a model distribution circle

    Competence in retail distribution Take efficiency improvement measures through

    introduction of new & innovative technology and IT enabled

    solutions & services

    INDIRECT

  • 7/31/2019 Dist Overview _ Vivek Jha

    74/93

    74

    INDIRECT

    Supplement the initiatives being taken by state utilities, byrendering support in the areas of:

    Formulation of DPR and processing the sanction ofscheme/ loan

    Assist SEBs in carrying out Energy Audit Design & Engineering Project execution

    Quality Assurance & Inspection IT enabled applications APDRP consultancyRGGVY

  • 7/31/2019 Dist Overview _ Vivek Jha

    75/93

    75

    NESCL: WHERE DO WE STAND

    TODAY??

    DIRECT ASSOCIATION

  • 7/31/2019 Dist Overview _ Vivek Jha

    76/93

    76

    DIRECT ASSOCIATION

    Initial efforts to acquire KESCO/ MESCOM Technical due diligence for KESCO carried out in-house Public Relationship (PR) blue print prepared and finalised Feedback from employees Negotiations with representatives of employee unions

    All information related to HR, Finance, Commercial, Technicaland Contracts has been obtained.

    SBI caps appointed for carrying out the due diligence ofMESCOM (Mangalore)

    Obtained all necessary clearances from the localadministration

    MOU signed with KESCO (GoUP) Draft agreement sent to Govt. of Karnataka & GoUP for their

    acceptance

    DIRECT ASSOCIATION

  • 7/31/2019 Dist Overview _ Vivek Jha

    77/93

    77

    CHATTISGARH

    Parallel licensing in district KORBA

    Due Diligence is under process

    M.P. Parallel licensing in district SIDHI

    Due Diligence is under process

    GUJARAT Areas of distribution being identified by a committee

    constituted by MOP

    DIRECT ASSOCIATION

    DIRECT ASSOCIATION

  • 7/31/2019 Dist Overview _ Vivek Jha

    78/93

    78

    KINFRA

    JV with KINFRA for retail distribution of power

    Areas of distribution Industrial parks/ SEZs under

    KINFRA

    Agreement signed with State Govt. and JV formed.

    CESU

    To be appointed as managers on behalf of OERC

    Operation in a phased manner

    Final decision of OERC pending

    DIRECT ASSOCIATION

    INDIRECT ASSOCIATION

  • 7/31/2019 Dist Overview _ Vivek Jha

    79/93

    79

    INDIRECT ASSOCIATION

    ADVISOR TO APDRP PROGRAM LEAD Advisor cum consultant (AcC ) TO MOP INVOLVEMENT IN 12 STATES 5 STATES DIRECTLY

    (MP,CHHATISGARH,MAHARASHTRA,HARYANA&PUNJAB)

    To review and suggest action plan for improvement in systemreliability

    To monitor and facilitate the progress of schemes under APDRP in

    states on behalf of MOP, GOI To impart training to different level of executives of SEB/Utilities in

    the area of Distribution business for their Capacity building

  • 7/31/2019 Dist Overview _ Vivek Jha

    80/93

    80

    INDIRECT ASSOCIATION

    Project Execution on behalf of a client

    Rendering consultancy services in areas of

    Design & Engineering Procurement & Contracting

    Project Management

    QA&I

    ALL IN THE DISTRIBUTION SECTORALL IN THE DISTRIBUTION SECTOR

    ASSIGNMENTS SUCCESSFULLY EXECUTED

  • 7/31/2019 Dist Overview _ Vivek Jha

    81/93

    81

    Providing project management support to MPSEB, WZ, Indore in thearea of Project Management and QA& I.

    Providing project management support to MPSEB, CZ, Bhopal/Gwalior in the area of Project Management and QA&I.

    Design, Engineering, procurement, erection, testing and

    commissioning of 66KV/ 11KV,2x20MVA sub station at UTChandigarh.

    Augmentation of transformation capacity at existing 66KV,1x20MVAsub-station, at Indl. Area II, UT Chandigarh

    Conversion of 66KV Overhead Transmission line to underground by

    laying 66KV Single Core XLPE 400 Sq. mm cable. Design engineering, procurement, erection, testing and

    commissioning of Rural Electrification in the state of West Bengal

    ASSIGNMENTS SUCCESSFULLY EXECUTED

  • 7/31/2019 Dist Overview _ Vivek Jha

    82/93

    82

    CURRENT ASSIGNMENTS

    Turnkey execution of 3x10 MVA, 33/11 KV sub-stationwith control room at Hotwar, Ranchi.

    Planning & Monitoring of RE Project in the state ofMP, Uttaranchal, Karnataka.

    Design engineering, procurement, erection, testingand commissioning of Rural Electrification in the stateof Chhattisgarh, Madhya Pradesh, Orissa, Kerala,Jharkhand and UT-Lakshadweep.

    Turnkey execution of projects under APDRP schemein the districts of Ashoknagar & Shivpuri (MP) Third Party Inspection of Stock Material for UPCL,

    MPPoKVVCL

  • 7/31/2019 Dist Overview _ Vivek Jha

    83/93

    83

    CURRENT ASSIGNMENTS

    In 11th plan RGGVY programme NESCL has been

    entrusted with 22 more projects( in addition of 8 in 10th

    Plan in West Bengal & M.P.) covering 22 districts forthe implementation of rural electrification on turnkey

    basis in 4 States i. e Chhattisgarh, Jharkhand, Orissa

    and West Bengal covering approx 40,000 Villages in

    30 districts with a sanctioned cost of Rs 2514 crore.

    FUTURE ASSIGNMENTS

  • 7/31/2019 Dist Overview _ Vivek Jha

    84/93

    84

    Design, Engineering, procurement, testing and commissioning of 2 Nos. 220KV GIS sub stations and associated cabling for Delhi Transco Limited

    GIS sub stations and associated cabling for NDMC

    Implementation of SCADA in the city of Chandigarh.

    Providing project management support to JVVNL, Jaipur in the area of

    Project Management, QA & I and Field Quality for Feeder Renovationprogramme

    Planning & Monitoring of RE work in the state of Himachal Pradesh, UT-Lakshadweep , Kerala

    Establishment of a central load despatch center for UHBVN for managementof load & UI and global accounting

    Consultancy services for supervision of T&D project under Durgapur ProjectLtd (DPL).

    Design, Engineering, procurement, testing and commissioning

  • 7/31/2019 Dist Overview _ Vivek Jha

    85/93

    85

    Services offered by NESCL

    Formulation of DPR

    Detailed Engineering including preparation ofTechnical Specifications.

    Contracts & Material Management Support Complete Project Management Support (Planning &

    Monitoring)

    Quality Assurance & Inspection Support

    Turnkey Execution of Projects

    IT application support

  • 7/31/2019 Dist Overview _ Vivek Jha

    86/93

    86

    Financial performance of NESCL.

    Revenue for 2007-08= Rs 41.892 crore (Rs 20.684crore)

    (PAT = Rs 12.665crore ( Rs 2.933 crore)

    Dividend =Rs 1.75crore

  • 7/31/2019 Dist Overview _ Vivek Jha

    87/93

    87

    Conclusion

  • 7/31/2019 Dist Overview _ Vivek Jha

    88/93

    88

    Distribution sectors challenges are diversifiedas technical, financial, historical and political

    Improvements needed in every area

    Central & state governments trying to make thesector commercially viable

    Private sector participation needed butprivatization is not the panacea

    Conclusion

  • 7/31/2019 Dist Overview _ Vivek Jha

    89/93

    89

    Thank YouANY QUESTIONS ?ANY QUESTIONS ?

  • 7/31/2019 Dist Overview _ Vivek Jha

    90/93

    90

    Cost of Power

    Source: CEA report : Oct 2008

    Details of the cash loss reduction and incentives released to variousstates under APDRP are as below:(As on 31 March 2008)

  • 7/31/2019 Dist Overview _ Vivek Jha

    91/93

    91

    Sl. No. State Claim Year Incentive AmountRecommendedforreleased to MoF

    Amount Released by MoF

    1. Andhra Pradesh 2002-03 265.11 265.11

    2. Gujarat 2001-02 236.38 236.382002-03 148.08 148.08

    2003-04 366.82 366.82

    2004-05 288.03 288.03

    3. Haryana 2001-02 105.49 105.49

    4. Kerala 2002-03 64.94 64.94

    2004-05 82.99 82.99

    5. Madhya Pradesh 2002-03 297.61 297.61

    6. Maharashtra 2001-02 137.89 137.89

    7. Rajasthan 2001-02 137.71 137.71

    8. West Bengal 2002-03 73.00 73.00

    2003-04 302.76 302.762004-05 5.88 5.88

    2005-06 115.10 115.10

    9. Punjab 2003-04 251.94 251.94

    Total 2879.63 2879.63

    f f f

    http://tempweb232.nic.in/rggvyportal/text_details.htmhttp://tempweb232.nic.in/rggvyportal/text_details.htm
  • 7/31/2019 Dist Overview _ Vivek Jha

    92/93

    92

    Definition of Electrified Village

    Prior to October 1997

    A Village should be classified as electrified if electricity is being used within its

    revenue area for any purpose whatsoever.

    After October 1997

    A village will be deemed to be electrified if the electricity is used in the inhabited

    locality, within the revenue boundary of the village for any purpose whatsoever.

    New definition of village electrification came into effect from the year 2004-05

    (Issued by MOP, vide their letter No. 42/1/2001-D(RE) dated 5th February 2004

    and its corrigendum vide letter no. 42/1/2001-D(RE) dated 17th February 2004.)

    As per the new definition, a village would be declared as electrified, if :

    1. Basic infrastructure such as Distribution Transformer and Distribution lines are

    provided in the inhabited locality as well as the Dalit Basti/ hamlet where it

    exists.

    2. Electricity is provided to public places like Schools, Panchayat Office, Health

    Centers, Dispensaries, Community centers etc.

    3. The number of households electrified should be at least 10% of the total

    number of households in the village.

    Power Cost Comparison

    http://tempweb232.nic.in/rggvyportal/text_details.htmhttp://tempweb232.nic.in/rggvyportal/text_details.htm
  • 7/31/2019 Dist Overview _ Vivek Jha

    93/93

    COUNTRY PRESENT COST FORECAST FOR 2007(In Cents/kWh) (In Cents/kWh)

    Canada 2 2

    Norway 1 1

    Sweden 2 2

    Thailand 4 5

    Egypt 3 3

    India 9 12