Disputes/Claims 2009 Overview
Division of Construction Management
2
2009 Claims Summary
• Approximately 50 disputes were reported to Central Office in 2009• 25 escalated to Step 3• Remainder resolved at District Level (Step 2)
• Additionally, an unknown number were resolved at Project Level or prior to a formal Step 2 Hearing
2010 Conaway Conference
2009 Claims Summary
•25 Step 3 Claims (PN109)– 17 decided by the Director’s Claims Board– 1 was arbitrated– 2 were mediated– 5 were dropped or settled prior to hearing
8 DCB Hearings conducted (Some hearings considered multiple claims)
2010 Conaway Conference 3
2009 Claims Summary•Of the 17 claims decided by the
DCB–4 awarded 100% of claimed amount–7 awarded 0% of claimed amount–6 awarded from 1% to 97% of claimed amount
2010 Conaway Conference 4
2009 Claims Summary
• Of the 17 claims decided by the DCBTotal Demanded: $
12,580,738.49Total Awarded: $
1,996,864.25
Average: 16% of demand was awarded
2010 Conaway Conference 5
2009 Claims Summary
1 claim was arbitratedDemand: $68,778.36Award: $0
2010 Conaway Conference 6
2009 Claims Summary2 claims were Mediated• 1 was settled • 1 did not settle
– ODOT executed change order for amount it believed it owed
– Case filed in Court of Claims
Total demanded: $ 1,689,367.54Total paid: $ 497,388.49
Average 29 % of Demand was Paid
2010 Conaway Conference 7
2009 Claims Summary
Currently 8 active Dispute Review Boards(PN108)
• 4 Claims were heard by Dispute Review Boards
• DRBs rarely decide on damages but rather provide guidance to the parties for resolution and cost negotiation
2010 Conaway Conference 8
2009 Claims Summary
• Of the 4 claims considered by DRBs– 2 with recommendations to deny the
claim– 2 with recommendations of sufficient
entitlement to resolve and negotiate
2010 Conaway Conference 9
2009 Claims Summary
• Decisions will be within the “four corners of the contract”
• Decisions will be based on “what does the contract say?” (plain reading)
• Decisions will be based on the reading of the Contract as a whole
2010 Conaway Conference 10
2009 Claims SummaryLessons Learned:• ODOT is responsible for interest on tardy
payments • ODOT personnel must proactively pursue final
quantity agreement with Contractor • Change orders must be processed timely for
what is known to be owed (even if quantities are not completely agreed upon)
• DOCUMENT DOCUMENT DOCUMENT!
2010 Conaway Conference 11
2009 Claims SummaryLessons Learned:• Contractor is responsible for Borrow material.
– If sampling and testing is required, contractor is responsible for requesting samples as material changes
– Material must be able to serve the purpose intended and must be acceptable when incorporated into the work
– Contractor is responsible for material failure even if reason for failure is not identified
2010 Conaway Conference 12
2009 Claims SummaryLessons Learned:• DCB will not find entitlement when
notice of dispute has not been given• ODOT personnel – BEWARE of
“constructive notice” – even if nothing in writing in 2 days – “knew or should have known” is a consideration– be PROACTIVE -ASK-DOCUMENT-MITIGATE COSTS!!
2010 Conaway Conference 13
2009 Claims SummaryLessons Learned:• ODOT has discretion (“may”) accept
defective Work based on engineering judgment BUT if the DCE “determines the Work is not in reasonably close conformity with Contract Documents” the Contractor must “remove, replace or otherwise correct the Work at no expense to the Department.” (C&MS 105.03)
2010 Conaway Conference 14
2009 Claims Summary
Lessons Learned:• Contractor must continue with all
Work including disputed work. ODOT must continue to pay for Work.
2010 Conaway Conference 15
2008 and 2009 Claim Comparison
2008• 23 Claims to Step
3• 7 dropped or
settled• 14 DCB
Decisions• 2 Arbitrations
2009• 25 Claims to Step
3• 5 dropped or
settled• 17 DCB Decisions• 1 Arbitration• 2 Mediations
2010 Conaway Conference 16
2008 and 2009 Claim Comparison
200814 DCB Decisions:1 paid 100%
demand7 paid 0 %
demand6 paid range from
6% to 44%
200917 DCB Decisions:
4 paid 100% demand
7 paid 0% demand6 paid range from
1% to 97%
2010 Conaway Conference 17
2008 and 2009 Claim Comparison
2008• Total
Demanded:$ 8,430,308.73
• Total Awarded:$ 2,228,903.21
26%
2009• Total
Demanded:$14,663,041.87
• Total Awarded:$ 2,628,127.10
18%2010 Conaway Conference 18
Claim Processing Time
2008• Ave. # Days Between
NOI and Decision Issued
314 days• Ave. # Days Between
Hearing and Decision Issued
107 days
2009• Ave. # Days Between
NOI and Decision Issued
198 days• Ave. # Days Between
Hearing and Decision Issued
49 days
2010 Conaway Conference 19
Questions?