DISPROPORTIONATE COSTS IN PRACTICE
description
Transcript of DISPROPORTIONATE COSTS IN PRACTICE
DISPROPORTIONATE COSTS DISPROPORTIONATE COSTS IN PRACTICEIN PRACTICE
Case study considering a potential derogation
Inspired froma real case study in the Rhin-Meuse district (F)
Some elements were picked from "Economic assessment of groundwater protection. Groundwater restoration in the potash mining fields of Alsace,
France",BRGM 2003
http://agire.brgm.fr/eco_EU.htm
Derogation
Need to assess the disproportion of costs of required
measures
Formal definitions in the directiveart. 4.4: deadline extension for two 6 years periods
art. 4.5: less stringent objective to be reviewed every 6 years
Derogation may apply only in limited caseswhen it is impossible to achieve GES by 2015 for justified technical, environmental or economic reasons
and provided that no further deterioration occurs
and when the derogation is justified on a transparent basis
WHAT DEROGATIONS UNDER WFD?
2/10
Derogation
FLOW CHART OF THE PROCEDURE FOR THE JUSTIFICATION OF
DEROGATIONIdentification of key pressures
causing the potential gap in 2015 and design of potential
supplementary measures
Cost-benefit analysis of potential supplementary
measures
Is the cost of the supplementary measures
disproportionate?
no
Reach the goal in 2015
yes
Does it remain disproportionate if
the implementation of
measures is phased out?
The goal can be reached in 2021 or
2027
The goal can't be reached by 2027
no
yes
A lower objective may be defined according to art. 4.5Redefine the programme of
measures
Main steps
Economic analysisGoal
3/10
Derogation
DEROGATION IN PRACTICE
Sourc
e:
Min
istr
y o
f th
e e
nvir
onm
ent,
Québ
ec,
Canad
a
4/10
Derogation
DESCRIPTION OF THE SITUATION
10-15% of the salt
withdrawn every
yearProspectivemodel shows that the impact of the
measures is not sufficient to reach the goal by 2015 (after 2027)
supplementary measures are needed
salt <250mg/l
in all the
aquifer
5/10
polluted zone
salt tips
limit of the aquifer
Description of the site aquifer intensely polluted by mining
activity: huge waste deposits of salt efficient measures already implemented:
geo-membrane on some dumps, artificial dissolution of waste with high concentration of salt ...
Aquifer
Source: BRGM & Agence de l'eau Rhin-Meuse
Derogation
SUPPLEMENTARY MEASURES AND THEIR EFFECTIVENESS
Measure 1 Measure 2 Measure 3
Complete removal ofsalt tips
Construction of lines ofpumping wellsdownstream the highlypolluted areas
Construction of lines ofpumping wellsi-downstream the
highly polluted areasii-in the centre of the
pollution plume
Effectiveness
?
Restoredsurface
(ha)
Surfaceremaining torestore (ha)
Effectiveness(% )
Businessas usual
2 600 2 200 54
Measure 1 2 800 2 000 58
Measure 2 4 520 280 94
Measure 3 4 779 21 99,5
in
2015
Ineffectiv
e
Maybe
further
investigated
if necessary
6/10
Derogation
COST-BENEFIT ANALYSIS
Define scale of assessment
Who will be affected? To what extent? Directly or not?...
Identify types of costs and benefits
Quantitative, qualitative or monetary? Present and/or future? Which appear significant?...
Choose methodologyIs it necessary to apply different methods? What resources are available for original research?...
Collect data Do we need first hand data? Can we rely on other resources?...
Assess costs and benefits
Are impacts important and properly weighted? How can different types of impacts can be presented in a way that facilitates decision-making?...
7/10
Derogation
COST-BENEFIT ANALYSISIDENTIFICATION OF COSTS AND
BENEFITS Types of costs
Agriculture - corrosion damages to irrigation equipment- potential impact on quality of soil investments, operating and maintenance costs damages
Public watersupply
- mitigation of water salinity: dilution, treatments, alternative resources… investments, operating and maintenance costs
Agriculture - avoided damages. E.g. renewal of corroded pipes and pumps- more valuable crops possible. E.g. tobacco potential future benefit
Public watersupply
- no need for more mitigation measures- pure water potentially available in the future potential future benefit
Industry - pure water available for specific activity (electronics…) potential future benefit
Types of benefits
TD OD
8/10
Derogation
COST BENEFIT ANALYSISEstimated costs (M€)
Construction of the wells 9
Operation of the wells 8,9
Connection of wells (11km) 2,5
Doubling of the canal for salmons 3
Damages to wetlands not assessed
Total estimated costs (M€) 23,4
Estimated benefits (M€)
For direct users
Agriculture : avoided damages to equipment, soiland crops due to salinisation
3,1
Public water supply : no further treatment needed,no need to investigate for alternative resources
13,9
For potential future uses
The aquifer is free of nitrates and pesticides: it maygenerate benefits in the future once desalinated
6,6
Total estimated benefits (M€) 23,6
NET COST (M€) -0,2Estimated
potential benefits
equal costs
A9/10
Derogation
TARGET:
reach the goal
in 2015
COST BENEFIT ANALYSIS
Estimated costs (M€) Measure 3
Construction of the wells 16,8
Operation of the wells 13,1
Connection of wells (11km) 2,5
Doubling of the canal for salmons 3
Damages to wetlands not assessed
Total estimated costs (M€) 35,4
Estimated benefits (M€)
For direct users
Agriculture : avoided damages to equipment,soil and crops due to salinisation
3,1
Public water supply : no further treatment, nomore investigation for alternative resources
13,9
For potential future uses
Aquifer free of nitrates and pesticides: it maygenerate future benefits once desalinated
6,6
Total estimated benefits (M€) 23,6
NET COST (M€) 11,8
B9/12
Derogation
Simulation for
2021
COST BENEFIT ANALYSIS
Estimated costs (M€) Measure 2 Measure 3
Construction of the wells 8,4 16,8
Operation of the wells 9,2 15,1
Connection of wells (11km) 2,5 2,5
Doubling of the canal for salmons 3 3
Damages to wetlands not assessed not assessed
Total estimated costs (M€) 23,1 37,4
Estimated benefits (M€)
For direct users
Agriculture : avoided damages to equipment,soil and crops due to salinisation
1,5 1,5
Public water supply : no further treatment, nomore investigation for alternative resources
7 7
For potential future uses
Aquifer free of nitrates and pesticides: it maygenerate future benefits once desalinated
3,3 3,3
Total estimated benefits (M€) 11,8 11,8
NET COST (M€) 11,3 25,6
B11/12
Derogation
TARGET
reach the goal
in 2015
COST BENEFIT ANALYSIS
Estimated costs (M€) Measure 3
Construction of the wells 16,8
Operation of the wells 12,1
Connection of wells (11km) 3,5
Doubling of the canal for salmons 4
Damages to wetlands 1,1
Total estimated costs (M€) 37,5
Estimated benefits (M€)
For direct users
Agriculture : avoided damages to equipment, soiland crops due to salinisation
3,1
Public water supply : no further treatment needed,no need to investigate for alternative resources
13,9
For potential future uses
The aquifer is free of nitrates and pesticides: it maygenerate benefits in the future once desalinated
6,6
Total estimated benefits (M€) 23,6
NET COST (M€) 13,9
C9/12
Derogation
Simulation
s
2021-2027
COST BENEFIT ANALYSIS
Measure 2 Measure 3Estimated costs (M€)
2021 2027 2021 2027
Construction of the wells 11,4 11,4 16,8 16,8
Operation of the wells 9,6 12 15,1 18,9
Connection of wells (11km) 3,5 3,5 3,5 3,5
Doubling of the canal for salmons 4 4 4 4
Damages to wetlands 1,1 1,1 1,1 1,1
Total estimated costs (M€) 29,6 32 40,5 44,3
Estimated benefits (M€)
For direct users
Agriculture : avoided damages toequipment, soil and crops due to salinisation
1,5 0,9 1,5 0,9
Public water supply : no further treatment, nomore investigation for alternative resources
7 5,4 7 5,4
For potential future uses
Aquifer free of nitrates and pesticides: it maygenerate future benefits once desalinated
3,3 3,3 3,3 3,3
Total estimated benefits (M€) 11,8 9,6 11,8 9,6
NET COST (M€) 17,8 22,4 28,7 34,7
C11/12
Derogation
GO FURTHER
Article 4.4 - Time derogation Article 4.5 - Less stringent objective Effectiveness of the potential alternative
measures aimed at reducing aquifer pollution
Derogation
Derogation
DEROGATIONS IN WFDEXTENSION OF DEADLINE - Art. 4.4
The deadlines (…) may be extended for the purposes of phased achievement of the objectives for bodies of water, provided that no further deterioration occurs in the status of the affected body of water when all of the following conditions are met:
(a)Member States determine that all necessary improvements in the status of bodies of water cannot reasonably be achieved within the timescales (…) for at least one of the following reasons:
(i) the scale of improvements required can only be achieved in phases exceeding the timescale, for reasons of technical feasibility;
(ii) completing the improvements within the timescale would be disproportionately expensive;
(iii) natural conditions do not allow timely improvement in the status of the body of water.
(b)Extension of the deadline, and the reasons for it, are specifically set out and explained in the river basin management plan (…).
(c)Extensions shall be limited to a maximum of two further updates of the river basin management plan except in cases where the natural conditions are such that the objectives cannot be achieved within this period.
(d)A summary of the measures (…) which are envisaged as necessary to bring the bodies of water progressively to the required status by the extended deadline, the reasons for any significant delay in making these measures operational, and the expected timetable for their implementation are set out in the river basin management plan. A review of the implementation of these measures and a summary of any additional measures shall be included in updates of the river basin management plan.
Derogation
Derogation
DEROGATIONS IN WFDLESS STRINGENT OBJECTIVE - Art. 4.5
Member States may aim to achieve less stringent environmental objectives than those required (…) for specific bodies of water when they are so affected by human activity, as determined in accordance with Article 5(1), or their natural condition is such that the achievement of these objectives would be infeasible or disproportionately expensive, and all the following conditions are met:
(a)the environmental and socio-economic needs served by such human activity cannot be achieved by other means, which are a significantly better environmental option not entailing disproportionate costs;
(b)Member States ensure, - for surface water, the highest ecological and chemical status
possible is achieved, given impacts that could not reasonably have been avoided due to the nature of the human activity or pollution,
- for groundwater, the least possible changes to good groundwater status, given impacts that could not reasonably have been avoided due to the nature of the human activity or pollution;
(c)no further deterioration occurs in the status of the affected body of water;
(d)the establishment of less stringent environmental objectives, and the reasons for it, are specifically mentioned in the river basin management plan (…) and those objectives are reviewed every six years.Derogatio
n
Derogation
EFFECTIVENESS OF THE MEASURES
0
5
10
15
20
25
2015 2021 2027
Quantity of salt remainingvs. initial stock (%)
0
5
10
15
20
25
2015 2021 2027
Surface with more than 250mg/l salt (km²)
Measure 1Measure 2Measure 3
17/10
Derogation
Source: BRGM & Agence de l'eau Rhin-Meuse