Discussion Discussion Topics Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Transcript of Discussion Topics Construction Contract Administration Other Construction Issues Questions? /...

Page 1: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Discussion TopicsDiscussion Topics

Construction Contract Administration

Other Construction Issues

Questions? / Comments (Anytime)

Page 2: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Non-conforming MaterialsNon-conforming MaterialsSubsections 105.3 and 105.7(1) of Std Specs

105.3.2.1 Engineer-Accepted Nonconforming Work

(1) If the work does not conform to the contract, the engineer will determine the circumstances under which that nonconforming work may be accepted and allowed to remain in place…

105.7 Authority and Duties of Project Engineer

(1) The engineer authorizes the project engineer to reject defective material and to suspend all work being improperly performed…

CMM 2.18.1 Authority of the Engineer

Page 3: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Non-conforming MaterialsNon-conforming Materials

As a general rule – Do not allow non-conforming materials to be incorporated into the work.

The engineer has the authority to reject nonconforming materials – the contractor does not have the right to incorporate nonconforming materials into the work at a reduced price.

Page 4: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Non-conforming MaterialsNon-conforming Materials

Price reductions are assessed in situations where nonconforming materials are inadvertently incorporated into the work.

If it is decided to allow nonconforming materials to be incorporated – agree on adjusted price prior to utilizing materials in work. If a price adjustment cannot be agreed upon – reject the material.

Page 5: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Nonconforming MaterialsNonconforming Materials CMM 8-10.5 and 8-10.6 Guidance

When proposing a significant or controversial price reduction for non-testing or nonconforming materials – BTS and BPD needs to know. Contact Regional Oversight Engineer.

Regional Oversight Engineer will advise whether BTS and BPD involvement is necessary.

Page 6: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Issues / ClaimsIssues / Claims If the contractor and department mutually agree, the

department will get a third party advisory opinion. Recommendation is not binding.

Subsection 104.3.6 (3) “If the contractor does not agree with the project engineer’s decision…if the contractor and department mutually agree… the department will get a third party advisory opinion…”

Contact Regional Construction Oversight Engineer

Page 7: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Issue Issue Claim Subsection105.13 Claim Subsection105.13

If the contractor does not agree with the engineer’s decision on a contract change, the contractor may pursue a claim as specified in 105.13.

Prime contractor must certify all claims. Not good enough to have subcontractor certify the claim.

Department expects that prime is satisfied with the validity of their subcontractor’s claim.

Page 8: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Issues / ClaimsIssues / ClaimsFeds request claim information on a regular scheduled basis.

Complete Claim Submittal Form (pantry software)

Construction Oversight Engineer.

Page 9: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Contract ModificationContract Modification

Does the change affect the controlling item?

Does this change affect contract time?

If no, say so in the Contract Modification.

If yes, provide info as to how new contract time was or will be determined.

Always address contract time.

Page 10: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Force AccountForce Account Per subsection 109.4.5, the contractor is required to

submit a force account proposal.

Avoid conflicts/misunderstanding later.

Require contractor to submit a force account proposal prior to beginning force account work. Proposal should include: when work will be performed, whether work will be done utilizing OT, classifications of workers, equipment needed or on standby, materials to be used, subsistence, estimated time to complete work, time extensions, etc.

Page 11: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Force AccountForce Account

Common for contractors to add 1% to force account total.

Provisions do not provide for a separate markup for the contract bond and should not be paid.

Page 12: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Force AccountForce AccountEquipment on standbyEquipment on standby

If equipment is on site for FA work, but not in operation, do not pay in-operation rate – pay standby. If a truck is idle, it is not in-operation and should only be paid as standby.

If equipment is idle it is not consuming fuel, oil, grease or experiencing wear and tear. Standby is intended to pay for a portion of ownership costs only not operating costs that are being incurred.

Page 13: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Force AccountForce Account

Work by subcontractors– Prime contractor allowed markup on work performed by

subcontractor Markup 10% on first $10,000 Markup 2% on work in excess of $10,000

– Markup does not apply for first tier subs or lower tier subcontractors – only the prime receives the prescribed markup.

These specific markups only apply to Force Account work. Negotiated prices for contract revisions includes “a reasonable allowance for profit and applicable overhead”.

Page 14: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Force AccountForce Account

Read CMM 2.46 Force Account Work– Provides good info for documenting and tracking costs.– Provides example of contractor’s itemized statement of

actual costs. – Provides an example of cost breakdown for CCO’s.

READ Std Spec 109.4.5 Force Account

Page 15: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Cost Reduction Incentives Cost Reduction Incentives (CRI’s)(CRI’s)

FHWA has asked Department to track CRI’s– Types– Acceptance (Approved or Denied)– Costs

Send copy of ALL CRI’s to Construction Oversight Engineer. Include (cc) in response.

Some CRI’s are NOT true CRI’s (little or no info being provided in contractor concept and/or proposal to evaluate). Also, if conditions are different than those anticipated when developing the plans which leads to changes – not a CRI. Please contact the Regional Oversight Engineer concerning significant CRIs.

Page 16: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Buy AmericaBuy America

In addition to item specific BA certification required, an umbrella (Blanket) certification is now required upon completion of project.

“ Upon completion of the project certify to the engineer, in writing using department form WS4567, that all steel, iron, and coating processes for steel or iron incorporated into the contract work conform to these "Buy America" provisions...”

Page 17: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

ASP 4 – Prompt PaymentASP 4 – Prompt Payment 10 days per tier to pay subcontractors.

“Just Cause” required within10-day window if contractor intends to withhold payment. Department no longer needs to provide approval.

Prime contractor to certify that all subcontractors have been paid in full (includes release of retainage) prior to submittal of final estimate.

“Within 30 calendar days of receiving the semi-final estimate from the department, submit written certification that subcontractors at all tiers are paid in full for acceptably completed work and that no routine retainage is being withheld.”

Page 18: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Maintenance and Repair of Maintenance and Repair of Haul RoadsHaul Roads

We always pay the item. Contractor may incur costs when employing mitigating measures to limit damage to haul road instead of making physical repairs.

Page 19: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Finals Process Finals Process for Let Project Closeout for Let Project Closeout

Developed to provide step-by-step guidance for staff involved in the Final Process for Let Project Closeout.

Goal - increase the number of regional and local program projects that closeout within six months.

Page 20: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Finals Process Finals Process for Let Project Closeout for Let Project Closeout

PROCESS DEFINITION

The Finals Process includes the process steps required to close out a construction contract within 6 months, beginning when the department determines that work under the contract is Substantially Complete and ending on the date the department approves the Final Estimate for payment.

Page 21: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Finals Process Finals Process for Let Project Closeout for Let Project Closeout

Assigns roles and responsibilities.

Provides standard definitions for terms utilized in the finals process.

Assigns timeframe to complete distinct process steps in the finals process.

Flow chart – Responsible parties, tasks, and process steps.

Includes tracking system.

Page 22: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Finals Process Finals Process for Let Project Closeout for Let Project Closeout

Snapshot at end of June (fiscal year)

Goal – 45% of projects finaled within 6 months of substantial completion.

Page 23: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Progress SchedulesProgress Schedules

CMM 1.65.2.2 Acceptance of Progress Schedules– Answers to questions must be YES to accept

contractor’s schedule.

CMM 1.65.2.3 Progress Payments– No progress payments (except materials) until

schedule is accepted.

Updates– Important to administration of contract– Important in claims

Page 24: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

CMM 1.65.2.2CMM 1.65.2.2

Page 25: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Timely Decision MakingTimely Decision Making

Line of Communication

Designated Materials Person

3-Week Look-ahead Schedule

Request for Information (RFI)

Evaluations

Page 26: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Timely Decision MakingTimely Decision Making

Expectation is that projects will employ the tools incorporated into the Timely Decision Making Guidelines.

Guidelines can be found at:

http://roadwaystandards.dot.wi.gov/standards/admin/index.htm

Page 27: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Start Notice / Notice to ProceedStart Notice / Notice to Proceed

Subsection 108.3 states, “The department will issue a written notification to begin or resume work for all … contracts. Do not begin or resume work before receiving the engineer’s notification.”

Page 28: Discussion Topics Construction Contract Administration Other Construction Issues Questions? / Comments (Anytime)

Conditional Start NoticeConditional Start NoticeFDM 19-10-30.3 Factors Influencing Contract Time

Exclusions from Contract Time Charges include, but are not limited to:

Construction Staking, initial layout before grading work begins.

Move-in of equipment by the contractor.

Delivery, installation and removal of temporary traffic control devices.