Discussion Paper: Damage Prevention Framework for Federally Regulated Power Lines · 2019-01-23 ·...
Transcript of Discussion Paper: Damage Prevention Framework for Federally Regulated Power Lines · 2019-01-23 ·...
Discussion Paper: DAMAGE PREVENTION FRAMEWORK FOR FEDERALLY REGULATED POWER LINES
1
Discussion Paper:
Damage Prevention Framework for Federally Regulated Power Lines
Introduction
Bill C-69, which creates the proposed Canadian Energy Regulator Act (CER Act)1, updates the
regulatory framework for safely conducting activities near federally regulated power lines.
The purpose of this document is to seek feedback on related regulations. The document
contains nine (9) questions for your consideration and comment. Appendix A found at the
end of this document provides a glossary of terms used in this document.
Context
Federally regulated power lines
Power lines in Canada that cross international borders are federally regulated. The federal
legislation that applies is the National Energy Board Act (NEB Act), in particular Part III.1,
which requires a person to obtain either a certificate or permit from the National Energy
Board (NEB or Board) to build and operate the power line.
Power lines that cross provincial borders may also be federally regulated under the NEB Act,
through a Governor-in-Council (federal Cabinet) designation process. At this time, there are
no designated interprovincial power lines and all interprovincial connections are regulated by
provinces.
For power lines that cross the international border with the United States (U.S.), federally
regulated certificate and permit holders (holders) must follow the NEB Act, the orders made
under the authority of the NEB Act and its regulations, and any applicable laws of a province.
Today there are 85 federally regulated international power lines of varying lengths. They are
located in the provinces of British Columbia, Alberta, Saskatchewan, Manitoba, Ontario,
Quebec, and New Brunswick, and have a total combined length of approximately 1,430
kilometers.
Current regulatory framework
The process for safely conducting activities near federally regulated power lines is provided
in the Power Line Crossing Regulations2 made by the NEB in 1995 under the NEB Act. Under
1 The proposed CER Act was introduced in February 2018 through Bill C-69, An Act to enact the Impact Assessment
Act and the Canadian Energy Regulator Act, to amend the Navigation Protection Act and to make consequential
amendments to other Acts. When Bill C-69 receives royal assent, the CER Act would come into force, replace the
NEB Act, and introduce the Canadian Energy Regulator (the Regulator), with an adjudicative Commission, which
would continue oversight of federally regulated power lines. 2 The text of the current Power Line Crossing Regulations is provided in Appendix B.
2
the Power Line Crossing Regulations, ‘Leave of the Board’ (permission) is not required to
conduct specified activities provided certain safety conditions are met.
This process exists for the safety of people conducting activities near these power lines and
to prevent damage to power lines while the activity is being conducted.
Key safety considerations for conducting activities near power lines include contact with the
power line, power outages, damage to the power line or related infrastructure, and
maintaining the reliability of the electrical grid. Some examples of activities that may pose
safety risks or damage to the power line are:
Operating vehicles or equipment under overhead power lines (e.g. operating a
boom-truck under a power line);
• Construction activities occurring around power lines (e.g. work on roads, pipelines,
and communication lines); and
• Digging/ Excavation around buried power lines, or overhead power line
infrastructure (e.g. pylons, towers).
Proposed updated regulatory framework
As a result of the proposed CER Act3, the Power Line Crossing Regulations will need to be
changed. Below is a summary of the current and proposed regulatory framework for power
lines.
Current regulatory framework under
the NEB Act4
Proposed regulatory framework under
the CER Act
1. Construction of a facility or conducting activities near a power line
No person shall construct a facility
across, on, along or under a federally
regulated power line or to excavate
using power-operated equipment or
explosives within 30 metres of a power
line unless leave (permission) is first
obtained from the Board. (section
58.31)
No facility can be constructed across, on,
along or under a federally regulated power
line unless the construction is authorized
by an order or in regulations. (section
273(1))
No activity causing a ground disturbance
can occur in a ‘prescribed area’ near the
power line, unless the activity is authorized
by an order or in regulations. (section
273(1))
The term ‘excavation using power
equipment or explosives’ is removed and
3 The proposed CER Act text appears in Appendix C. 4 NEB Act, Sections 58.28, 58.31, 58.33; and the Power Line Crossing Regulations.
3
Current regulatory framework under
the NEB Act4
Proposed regulatory framework under
the CER Act
Anyone who wishes to conduct these
activities must comply with the Power
Line Crossing Regulations:
Design and execute these
activities in accordance with the
Canadian Standards Association
(CSA) safety standards for
overhead and underground
electrical systems;
Obtain written permission from
the holder to conduct these
activities; and
Follow a written procedure and
schedule for the work that is
agreed to by the holder.
If this permission cannot be obtained, a
person can apply to the Board for leave
to conduct the activity (i.e. through an
order, which can have safety conditions
and other conditions attached to it).
replaced with the broader term ‘ground
disturbance’.
The prescribed area can be specified
through an order or in regulations.
(sections 275(1) and 275(2))
Measures to be met for safely conducting
activities and receive authorization to
conduct a ground disturbance within the
prescribed area, or to build a facility across,
on, along or under a federally regulated
power line, may be identified in an order or
in regulations. (section 275(2)) In the
regulations, the Regulator 5 , may also
authorize the holder of a permit or
certificate to give an authorization for
these activities on any conditions the
holder considers appropriate. (section 275
(3)(b)).
If this authorization cannot be obtained, a
person can apply to the Commission for
authorization to conduct the activity (i.e.
through an order, which can have safety
conditions and other conditions attached
to it). (section 275(1))
2. Operating a vehicle or mobile equipment across a federally regulated power line
Anyone who wishes to operate a
vehicle or mobile equipment across the
federally regulated power line in an
area other than a highway or a public
road, must first obtain leave
Authorization to operate a vehicle or
mobile equipment across the federally
regulated power line in an area other than
the travelled portion of a highway or public
road must be obtained through an order
5 Section 275(3)(b) of the CER Act provides the Regulator with the authority to make regulations, with the approval of the Governor in Council, pertaining to safety measures for construction and ground disturbance activities.
4
Current regulatory framework under
the NEB Act4
Proposed regulatory framework under
the CER Act
(permission) from the holder. (section
58.31)
If this permission cannot be obtained
from the holder, a person can apply to
the Board for leave to cross the power
line (i.e. through an order, which can
have safety conditions and other
conditions attached to it).
from the Commission or be authorized in
regulations. (section 273(2))
Measures to be met for safely crossing
under or over a federally regulated power
line by a vehicle or mobile equipment may
be identified through an order or in
regulations. (sections 275(2) and 275(3)(b))
In the proposed regulations, the
Regulator6, may also authorize the holder
to give an authorization for these activities
on any conditions the holder considers
appropriate. (section 275 (3)(b))
3. Construction of federally regulated power lines near facilities
No federally regulated power line that
passes on, over, along, or under a
facility can be constructed unless a
permit or certificate has been issued by
the Board. (section 58.28)
The permit or certificate must contain a
term or condition relating to that
facility. Otherwise the applicant must
be granted leave by order from the
Board. The federally regulated power
line must be constructed in the
circumstances specified in an order or
in regulations. (section 58.28)
No federally regulated power line that
passes on, over, along, or under a facility
can be constructed unless a permit or
certificate has been issued by the
Commission. (section 272(1))
The permit or certificate must contain a
condition related to that facility. Otherwise
the applicant must obtain authorization for
construction by order from the
Commission and the power line must be
constructed in the circumstances specified
in an order or in regulations. (section
272(1))
6Section 275(3)(b) of the CER Act provides the Regulator with the authority to make regulations, with the approval of the Governor in Council, pertaining to safety measures for vehicle crossings.
5
Current regulatory framework under
the NEB Act4
Proposed regulatory framework under
the CER Act
4. Damage Prevention Program
All holders must develop, implement, and
maintain a damage prevention program
that contains public awareness elements
and process requirements to manage
authorization and locate requests.
Description of proposed regulations
As new regulations will be required under the proposed CER Act; below is a description of the
proposed approach.
1. Construction of a facility or conducting activities near a power line
The approach would be to continue the safety requirements from the current Power Line
Crossing Regulations in the new regulations. These requirements would apply to anyone
planning to conduct an activity causing a ground disturbance within the prescribed area, or
to construct a facility across, on, along or under a federally regulated power line.
The proposed regulations would maintain the following safety measures:
Thirty metres as the distance from the power line within which an authorization is
required. This would be the “prescribed area”.
The requirement to design and conduct work in accordance with the CSA safety
standards for overhead and underground electrical systems7.
The requirement to obtain a written authorization from the holder including any
conditions identified by the holder.
The requirement that a written procedure and schedule for the work have been agreed
to by the holder, and the person conducting the activity.
The proposed regulations would add new safety measures:
The person conducting the planned activity would be required to make a locate request
to a one-call centre at least three working days before the start of the activity, or
request a locate from the holder if there is no one-call centre in the geographical area
where the activity will be conducted.
7 The standards address design measures such as maintaining electrical clearances, preventing mechanical contact,
preventing undermining of exposed buried facilities or structure foundations, and preventing electrostatic,
inductive, and conductive coupling between facilities.
6
The person conducting the activity would be required to inform, before the start of the
activity, all persons working on their behalf including employees, contractors, and
subcontractors of their obligations under the regulations (i.e. the safety measures, the
written procedures and schedule agreed to by the holder, etc.).
Examples of activities causing a ground disturbance include: digging, boring, trenching,
excavating, grading, plowing, drilling, tree planting, blasting or any other activity that breaks
the ground. In addition to the risks associated with contact with a power line, activities
causing a ground disturbance near the base of overhead structures (e.g. towers, pylons) or
appurtenances8 could potentially undermine these structures resulting in structural
damage, or damage to the power line and its appurtenances.
1.a) Obtaining written authorization – ground disturbance
The process would require that anyone planning to conduct an activity causing a ground
disturbance within the prescribed area, or to construct a facility across, on, along or under a
federally regulated power line, contact the holder to apply for and obtain a written
authorization. When planning the work, the safety requirements in the regulations must be
followed, as well as any conditions required by the holder.
1.b) Notification requirements
For safety considerations and to maintain communication between the person conducting
the activity and the holder, the following notifications would be required:
If, during the planned and authorized activity, contact is made with the power line,
to immediately notify the holder.
Before backfilling over underground infrastructure related to a power line, the
holder must be notified at least 24 hours in advance.
Question 1: Is a prescribed area of 30 metres on either side of the federally regulated
power line adequate to maintain safety and prevent damage to the power line?
Question 2: Are the proposed safety measures adequate to maintain safety and prevent
damage to the power line?
1.c) Responding to requests for authorization
Through the proposed regulations, the holder would be required to respond to a person’s
request for an authorization to conduct an activity near a power line. The holder must
inform the person making the request whether the authorization has been granted or
refused, and if refused, why.
8 See Appendix A for definitions.
7
If an authorization is not granted by the holder, the person requesting the authorization
may file an application with the Commission to request review for authorization. The
person would also need to provide a copy of the application to the holder.
Question 3: What other considerations, if any, need to be taken into account when a holder
responds to a request for authorizations?
1.d) Making a locate request
A person planning to conduct an activity that will cause a ground disturbance within the
prescribed area must contact a one-call centre where one exists in the geographical location
of the planned activity. One-call centres currently operate in British Columbia, Alberta,
Saskatchewan, Manitoba, Ontario, Québec and portions of the Atlantic Provinces. Where
there is no one-call centre, the person must contact the holder directly.
Contacting the one-call centre is necessary to determine whether there is underground
infrastructure related to the power line, and to request a locate prior to starting an activity
causing a ground disturbance. The proposed regulations would provide the process for
making the locate request, including:
The request must be made by the person (or designate) planning to conduct the
activity at least three working days before the day on which the construction or
activity is to start.
During the three day notice period the holder will review and respond to the locate
request, and will mark the location of any underground infrastructure related to the
federally regulated power line.
The holder must explain to the requestor the meaning and significance of the locate
markings used.
The requester must follow the regulations and the safety practices required by the
holder.
Question 4: What other considerations, if any, need to be taken into account when making
a locate request prior to conducting work near a federally regulated power line?
1.e) One-call centre membership
For the locate request process, the proposed regulations would require that all holders
become members of a one-call centre, if there is one in the area where their power lines
are located. Many holders across Canada are already members of one-call centres.
Question 5: Do you have any comments on the proposed requirement for a holder to be a
member of a One-Call Centre?
8
2. Operating a vehicle or mobile equipment across a federally regulated power line
Currently, operating a vehicle or mobile equipment across a federally regulated power line
(in an area other than a highway or public road) is not allowed unless the holder has
provided leave (permission). This approach would be continued in the proposed regulations
by requiring any person planning to operate a vehicle or mobile equipment across such a
power line to obtain authorization from the holder. The authorization issued by the holder
may contain any conditions the holder considers appropriate.
2.a) Obtaining written authorization – crossings
The process would require that anyone planning to operate a vehicle or mobile equipment
across a federally regulated power line, contact the holder to apply for and obtain a written
authorization. Any conditions required by the holder must be followed.
3. Construction of federally regulated power lines near facilities
Currently, no federally regulated power line that passes on, over, along, or under a facility
(e.g. highway, irrigation ditch, drainage systems, sewer line, underground communication
lines) can be constructed unless a permit or certificate for the power line has been issued
from the Board that contains a condition related to that facility. A person may also be
granted leave for construction through an order. The power line must be constructed in the
circumstances specified in the order or in the Power Line Crossing Regulations. In the
updated regulatory framework, this requirement would be maintained.
The proposed regulations would maintain requirements:
That the power line is designed and constructed in accordance with the CSA safety
standards for overhead and underground electrical systems.
That the holder obtain written permission from the owner of the facility.
That a written procedure and schedule for the work have been agreed to by the holder,
and the owner of the facility.
Question 6: Do you have any other comments on the requirements for construction of
federally regulated power lines near facilities?
4. Damage prevention program
For consistency across all federally regulated power lines, the proposed regulations would
require that all present and future holders develop, implement and maintain a damage
prevention program that meets the public awareness and process requirements outlined
below.
9
4.a) Public awareness elements in damage prevention program
The damage prevention program would be required to have the following public awareness
elements to inform the public about:
the location of the power line
how to work safely near the power line
how to report an unexpected situation related to a power line that could endanger life
or cause substantial property damage
how to report any contact with or damage to a federally regulated power line
services offered by a one-call centre if one exists in the geographical area of the
underground federally regulated power line
the necessity of applying for a written authorization from the holder when constructing
a facility across, on, along or under a power line, engaging in an activity causing a
ground disturbance within the prescribed area, or operating vehicles or mobile
equipment across a federally regulated power line
what information must be provided in a request for an authorization for any of these
activities
the requirement to make a locate request, and how to do so in the relevant
geographical area for the federally-regulated power line.
4.b) Processes for managing authorization requests
As part of the damage prevention program, processes would need to be developed by the
holder for the management of requests for authorizations for planned and locate requests,
and for timely responses to locate requests.
Question 7: What other considerations, if any, need to be taken into account for a holder
to have a damage prevention program for power lines?
Question 8: Is a period of three months from the coming into force of the proposed
regulations to develop and implement a damage prevention program sufficient?
Question 9: Are there any other comments related to the proposed regulations that you
would like to provide?
Next Steps
If you have feedback or comments on any of the nine (9) questions posed in this Discussion
Paper, please submit them by email, fax, or mail to the address listed below. The deadline for
providing comments is November 28, 2018.
After the close of the comment period, written comments will be posted on the NRCan Public
Consultations Opportunities: A new Canadian Energy Regulator web page, at
https://www.rncanengagenrcan.ca/en/collections/new-canadian-energy-regulator. Comments
10
received by the deadline will be reviewed and considered for use in the development of the
damage prevention regulations for federally regulated power lines. The proposed regulations
will then be pre-published in the Canada Gazette, Part I for a 30 day comment period.
Information concerning the Canada Gazette, Part I comment period will be provided at a later
date. Notice of this opportunity will be posted on this site.
Please visit https://www.nrcan.gc.ca/21385 for information and updates on the proposed regulations. You may also sign up there to be included in an email distribution list for receiving updates as the regulations are developed, including information on public engagement opportunities.
Contact Information
Power Line Damage Prevention Project Team
National Energy Board
Suite 210, 517 Tenth Avenue SW
Calgary, Alberta T2R 0A8
Telephone: 403-292-4800 (or toll free at: 1-800-899-1265)
Fax: 403-292-5503 (or toll free at: 1-877-288-8803)
TTY (teletype): 1-800-632-1663
Email:
Departmental Contacts:
National Energy Board
Chantal Briand, Regulatory Drafting Specialist
Phone: (403) 292-4192
Rebecca Vanderspiegel, Regulatory Development Specialist
Phone: (403) 472-2254
11
Appendix A.
Glossary of Terms
Proposed CER Act Definitions
Ground disturbance: means a ground disturbance other than one that
(a) is caused by any activity that is specified in the orders or regulations made in respect of
pipelines under section 335 or made in respect of international or interprovincial power
lines under section 275;
(b) is, in relation to a pipeline, caused by cultivation to a depth of less than 45 cm below the
surface of the ground; or
(c) is, in relation to a pipeline, caused by any other activity to a depth of less than 30 cm
and that does not result in a reduction of the earth cover over the pipeline to a depth
that is less than the cover provided when the pipeline was constructed. (CER Act,
section 2)
Holder: the holder of a certificate or permit issued under Part III.1 of the NEB Act, and, in the
future, under Part 2 and Part 4 of the CER Act in respect of a regulated facility. (CER Act, section
93, definition of holder)
International power line: means facilities that are constructed or operated for the purpose of
transmitting electricity from a place in Canada to a place outside Canada or from a place
outside Canada to a place in Canada. It does not however include an offshore power line.
(section 2)
Interprovincial power line: means facilities that are constructed or operated for the purpose of
transmitting electricity from a place in a province to a place in another province. (section 2)
Regulator means the corporation established under subsection 10(1) (section 2)
Other terms as used in this document
Appurtenance: Anything attached to a piece of land or building such that it becomes part of
that property, and is passed onto a new owner when the property is sold. It may be something
tangible like a garage, septic system, water tank or something abstract such as an easement or
right of way9.
CSA means Canadian Standards Association (CSA)
CSA C22.3 NO 1, Overhead Systems: a standard developed by the Canadian Standards
Association pertaining to the design of overhead crossings.
9 Source: The Business Dictionary. http://www.businessdictionary.com/definition/appurtenance.html
12
CSA C22.3 NO 7, Underground Systems: a standard developed by the Canadian Standards
Association pertaining to the design of underground crossings.
One–Call Centre: an organization that, for the purpose of protecting underground
infrastructure of its members from damage and ensuring public safety, receives locate requests
from members of the public and notifies its members who may be affected by the proposed
activity. (Source: National Energy Board Pipeline Damage Prevention Regulations – Obligations
of Pipeline Companies s.2(2); National Energy Board Pipeline Damage Prevention Regulations –
Authorizations s.3(4))
Working days: means any day that is not a Saturday or a Sunday or other holiday (Source:
National Energy Board Pipeline Damage Prevention Regulations – Authorizations s.1; National
Energy Board Pipeline Damage Prevention Regulations – Obligations of Pipeline Companies s. 2).
13
Appendix B.
Power Line Crossing Regulations SOR/95-500 (currently in effect)
Regulations Respecting Crossings of International Power Lines or Interprovincial Power Lines Constructed Without Leave of the National Energy Board (These regulations were made in 1995, under the National Energy Board Act.) Short Title 1 These Regulations may be cited as the Power Line Crossing Regulations. Interpretation 2 In these Regulations, Act means the National Energy Board Act; (Loi) CSA means the Canadian Standards Association; (CSA) holder means the holder of a permit or certificate issued in respect of a power line; (titulaire) Crossings 3 Leave of the Board to construct a facility across, on, along or under a power line or to excavate using power-operated equipment within 30 m of a power line, pursuant to subsection 58.31(1) or subsection 112(1) of the Act, is not necessary where
(a) these activities are designed and executed in accordance with CAN/CSA-C22.3 No. 1-M87, Overhead Systems, as amended from time to time, in respect of overhead crossings; (b) these activities are designed and executed in accordance with CAN3-C22.3 No. 7-M86, Underground Systems, as amended from time to time, in respect of underground crossings; (c) written permission has been obtained by the owner of the facility or the owner’s sub-contractor from the holder; and (d) a written procedure and schedule for the work have been agreed to by the holder and the owner of the facility or the owner’s sub-contractor.
4 For the purposes of paragraph 58.28(1)(c) of the Act, the circumstances in which a person may construct an international or interprovincial power line that passes on, over, along or under a facility are as follows:
(a) the power line is designed and constructed in accordance with CAN/CSA-C22.3 No. 1-M87, Overhead Systems, as amended from time to time, in respect of overhead crossings; (b) the power line is designed and constructed in accordance with CAN3-C22.3 No. 7-M86, Underground Systems, as amended from time to time, in respect of underground crossings; (c) written permission has been obtained by the holder or the holder’s sub-contractor from the owner of the facility;
14
(d) a written construction procedure and schedule have been agreed to by the holder or the holder’s sub-contractor and the owner of the facility; and (e) the length of the power line will not be extended beyond all termini of that power line.
15
Appendix C.
Proposed Canadian Energy Regulator Act, Part 2 and Part 4 (Bill C-69, Part 2 as
passed by the House of Commons on June 20, 2018)
The following are excerpted relevant sections from Parts 2 and 4 of the proposed Canadian Energy Regulator Act. Please refer to Bill C-69, An Act to enact the Impact Assessment Act and the Canadian Energy Regulator Act, to amend the Navigation Protection Act and to make consequential amendments to other Acts10 for the full text and further details.
Part 2: Safety, Security, and Protection of Persons, Property, and Environment
Reasonable Care 94 The holder must take all reasonable care to ensure the safety and security of persons, the safety and security of regulated facilities and abandoned facilities and the protection of property and the environment.
Regulations
96 The Regulator may, with the approval of the Governor in Council, make regulations
(a) respecting the design, construction and operation of pipelines, international power lines and interprovincial power lines designated by an order made under section 261;
(b) respecting the abandonment of pipelines;
(c) respecting surveillance or monitoring measures that, in relation to the activities referred to in paragraphs (a) and (b), are for the safety and security of persons and for the protection of property and the environment;
(d) respecting abandoned facilities;
(e) requiring holders to have management systems in place and to comply with them; and
(f) providing for the elements to be included in those management systems — including human or organizational factors — and respecting any criteria to be met by those management systems.
10 Full text of Bill C-69 and proposed amendments can be obtained from the Parliament of Canada LEGISinfo website at the following link - http://www.parl.ca/LegisInfo/BillDetails.aspx?Language=E&billId=9630600. On the website you’ll note that there is a link to the text of the Bill on the upper right hand corner of the page. Click on the Latest Publication link to access the latest version of the Bill.
16
Part 4. International and Interprovincial Power Lines
Prohibition 247 A person must not construct or operate a section or part of an international power line except in accordance with a permit issued under section 248 or a certificate issued under section 262.
Construction — facility 272 (1) A person must not construct an international or interprovincial power line that passes on, over, along or under a facility unless a permit referred to in section 248, or a certificate, has been issued in respect of the power line and
(a) the permit or certificate contains a condition relating to that facility; (b) the person has been granted leave under subsection (2); or (c) the person is constructing the power line in circumstances specified in an order or regulation made under subsection (4).
Authority to grant leave 272 (2) On application, the Commission may, by order, grant a person leave to construct an international or interprovincial power line that passes on, over, along or under a facility. It may require from the applicant any plans, profiles and other information that it considers necessary to consider the application.
Conditions 272 (3) The leave may be granted in whole or in part and be subject to conditions.
Circumstances 272 (4) The Regulator may specify circumstances for the purposes of paragraph (1)(c) by regulation, and the Commission may do so by order.
Leave in emergency cases 272 (5) The Commission may grant leave under subsection(2) after construction of the work has commenced if it is satisfied that the work was urgently required and, before the commencement of construction, it was notified of the person’s intention to proceed with the work.
Prohibition — construction or ground disturbance 273 (1) It is prohibited for any person to construct a facility across, on, along or under an international or inter-provincial power line or engage in an activity that causes a ground disturbance within the prescribed area unless the construction or activity is authorized by the orders or regulations made under section 275 and done in accordance with them.
Prohibition — vehicles and mobile equipment 273 (2) It is prohibited for any person to operate a vehicle or mobile equipment across an international or interprovincial power line unless
(a) that operation is authorized by orders or regulations made under section 275 and done in accordance with them; or
17
(b) the vehicle or mobile equipment is operated within the travelled portion of a highway or public road.
Orders 275 (1) The Commission may, by order, give directions
(a) governing the design, construction, operation and abandonment of facilities constructed across, on, along or under an international or interprovincial power line; (b) prescribing the area for the purposes of subsection 273(1); (c) authorizing the construction of facilities across, on, along or under an international or interprovincial power line; (d) authorizing ground disturbances within the prescribed area; (e) governing the measures to be taken in relation to
(i) the construction of facilities across, on, along or under an international or interprovincial power line, (ii) the construction of an international or interprovincial power line across, on, along or under facilities, other than railways, and (iii) ground disturbances within the prescribed area;
(f) authorizing the operation of vehicles or mobile equipment across an international or interprovincial power line and governing the measures to be taken in relation to that operation; (g) governing the apportionment of costs directly incurred as a result of a construction or disturbance authorized under this subsection; (h) specifying activities for the purposes of paragraph (a) of the definition ground disturbance in section 2 in respect of international or interprovincial power lines; and (i) authorizing a holder of a permit or certificate to give an authorization referred to in paragraph (c), (d) or (f) on any conditions that the holder considers appropriate.
Regulations 275 (2) The Regulator may make regulations respecting any matter referred to in paragraphs (1)(a) to (f) and (h).
Regulations 275 (3) The Regulator may, with the approval of the Governor in Council, make regulations
(a) governing the apportionment of costs directly incurred as a result of a construction or disturbance authorized under this section; and (b) authorizing a holder of a certificate or permit issued under this Part to give an authorization referred to in paragraph (1)(c), (d) or (f) on any conditions that the holder considers appropriate.