Director’s Review Feb 3-4, 2005
1
Installation and Technical+Physics Commissioning
ofDØ RunIIb Silicon & Trigger Upgrades
Schedule & CostsR.P. Smith for
the DØ Collaboration
![Page 2: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/2.jpg)
Director’s Review Feb 3-4, 2005
2
Action Items from July 2004 Review
Understand Clearances for Layer Zero (in 2004 Shutdown) Incorporate Physics Commissioning in Installation Plans and
Schedule Review Manpower Estimates, articulate needs for extra-DØ
help Provide analysis of Installation Risks
+ Incorporate new information from L0 and Trigger hardware development teams, 2004 Shutdown experience
![Page 3: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/3.jpg)
Director’s Review Feb 3-4, 2005
3
2004 Shutdown Activities Related to Installation
Upgrade Installation “Infrastructure” tasks accomplished during 2004 Shutdown (in CH or MCH)
L1 Cal – None scheduled L1 CalTrack – begin mods of Muon PDT and Scintillator
FEB’s, terminate L1CTT transition and MTCxx cables L1CTT - install parallel “slice”: crate, controller, few DFEA’s,
cables for CTOC, CTT L2 Beta – None scheduled L2 STT – None scheduled L0 Silicon – L0 clearance survey, adapter card and 4-Hybrid
SVX4 string, N&S mini fuse panels, new Wiener PS, Interlock chassis
Online – Move Online (DAQ, Oracle, NFS) to new host cluster
![Page 4: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/4.jpg)
Director’s Review Feb 3-4, 2005
4
Beam-Off Time Paced by Silicon
Present Installation Schedule shows Tevatron Shutdown Time driven by Layer Zero Silicon Installation
Detector Not Removed From Collision Hall 2004 Shutdown experiences verifying silicon clearance are
leading to reconsiderations of installation plans => Revising existing schedule!
Consideration of each installation step, appropriate (repeated) repositioning of End Calorimeter(s) and installation of precision fixturing, indicates L0 Installation requires 12 weeks.
Resume Tevatron operations in week 13 with opportunity to re-enter CH during L0 technical commissioning.
14th week required to close detector and make final survey Workweeks are standard 40 hours, five days Silicon installation dominates CH access time. Trigger
Elements require lesser amounts of CH access in time “shadow” of L0.
![Page 5: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/5.jpg)
Director’s Review Feb 3-4, 2005
5
Silicon Installation Milestone Overview
ID WBS TASK NAMESTART-DATE
FINISH-DATE
DURATION
4 1.5.3 Hardware Ready for Installation 8/16/05 8/16/05 0 w
5 1.5.4Tevatron Shutdown for Installation Begins
8/16/05 8/16/05 0 w
54 1.5.5.9 H-Disks Removed 8/23/05 8/23/05 0 w
591.5.5.11
RunIIa Be Beampipe Removed 9/09/05 9/09/05 0 w
821.5.5.19
L0 Installed and Connected to Readout 10/10/05 10/10/05 0 w
921.5.5.23
RunIIb Be Beampipe Installed in SMT 10/21/05 10/21/05 0 w
961.5.5.25
Inner H-disks Reinstalled 10/26/05 10/26/05 0 w
105
1.5.5.29
RunIIb Beam Pipe Closed 11/7/05 11/7/05 0 w
107
1.5.5.31
Silicon Ready for Technical Commissioning
11/8/05 11/8/05 0 w
119
1.5.5.34
Detector Closed for Tevatron Resumption 11/23/05 11/23/05 0 w
Current schedules for hardware elements forecast
“T0”. Forecasts lack
schedule contingency.
Tevatron Downtime
~ 14 weeks elapsed
![Page 6: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/6.jpg)
Director’s Review Feb 3-4, 2005
6
L1 Cal Installation Task
L1Cal Ready for Technical Commissioning
~ 2 weeks before beam Resumes
ID WBS TASK NAME START-DATE
FINISH-DATE
DURATION
5 1.5.4 Tevatron Shutdown for Installation Begins
8/16/05 8/16/05 0 w
154
1.5.7.3.2.5 Decable BLS cables from Trigger Crates 8/16/05 8/22/05 1 w
155
1.5.7.3.2.6 Remove Rack Infrastructure from Sidewalk Racks
8/16/05 8/22/05 1 w
156
1.5.7.3.2.7 Depopulate & Remove Run I Trigger Crates
8/23/05 9/6/05 2 w
157
1.5.7.3.2.8 Install Rack Infrastructure in Active (ADF) racks
9/7/05 9/27/05 3 w
158
1.5.7.3.2.9 Install Patch Panels in Passive Racks, Reconnect BLS cables
9/28/05 10/04/05 1 w
159
1.5.7.3.2.10
Install ADF Crates 10/5/05 10/11/05 1 w
160
1.5.7.3.2.11
Connect Pleated Foil Cables 10/12/05 10/18/05 1 w
161
1.5.7.3.2.12
Connect ADF – TAB/GAB & TFW Cables 10/19/05 10/20/05 2 d
Current schedules for hardware elements forecast
“T0”. Forecasts lack
schedule contingency.
![Page 7: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/7.jpg)
Director’s Review Feb 3-4, 2005
7
Overall Schedule
Dotted Portions: <50% special runs for item
![Page 8: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/8.jpg)
Director’s Review Feb 3-4, 2005
8
Installation Effort
Workweek = Standard 5 days/40 hrs per week
Run IIb Technician Effort
0
2
4
6
8
10
12
14
16
18
20
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Calendar Weeks
Wee
kly
FT
E P
eak
Tev Suspended
Includespersonnel not presently in D0
Group
![Page 9: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/9.jpg)
Director’s Review Feb 3-4, 2005
9
Installation Effort
Workweek = Standard 5 days/40 hrs per week
Run IIb Engineer Effort
0
2
4
6
8
10
12
14
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Calendar Weeks
Wee
kly
FT
E P
eak
CompSP
EngU
ElecEngF
MechEngF
Tev Suspended Includespersonnel not presently in D0
Group
For assumed T0
this is week of 12/25
![Page 10: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/10.jpg)
Director’s Review Feb 3-4, 2005
10
Installation Effort
Run IIb Physicist Effort
0
5
10
15
20
25
30
35
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Calendar Weeks
Wee
kly
FT
E P
eak
PhysU
PhysF
Tev Suspended
For assumed T0 this is week of 12/25
![Page 11: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/11.jpg)
Director’s Review Feb 3-4, 2005
11
Detector Gap Occupancy
Per Gap Limit: 2
Run IIb Gap Occupancy
0
1
1
2
2
3
3
4
4
5
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29
Calendar Weeks
Wee
kly
FT
E P
eak
Tev Suspended
For assumed T0 Tev on-week
is obscured
![Page 12: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/12.jpg)
Director’s Review Feb 3-4, 2005
12
Identified Additional Manpower Needs
L0 Installation Expert Engineer: Youri Orlov L0 Installation Expert Instrumentalist: Mike Roman L0 Installation Expert Technicians: Dave Butler, Dennis Graham CTT Expert: Jamieson Olson Two Computer Science Professionals L1 Cal University Engineers: Dan Edmunds, Phillipe Laurens Four Electrical Techs for two weeks for PDT mods
Costed in schedule, important to have the named individuals
![Page 13: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/13.jpg)
Director’s Review Feb 3-4, 2005
13
Installation Costs
Burdened FY05/FY06 Installation Costs
Base FY05
Base FY06
Contingency
Total
Effort 909K 296K 603K 1808K
M&S 178K 52K 115K 345K
Total 1087K 348K 718K 2153K
![Page 14: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/14.jpg)
Director’s Review Feb 3-4, 2005
14
Installation Risk Analysis
Schedule Risks from Unanticipated Difficulties Encountered during L0 Installation: substantially ameliorated by
2004 shutdown clearance survey Experience with survey instruments in gaps Handling of EC’s and beampipe open-up/reclosing
Careful design of and practice with Installation Tooling beforehand Involve personnel with previous DØ SMT experience where possible No second shift or overtime work currently scheduled MSProject Installation Management Tool
Risk from Accidental Handling Damage to L0 during Installation: substantially ameliorated by
RunIIa Experience Will develop detailed step-by-step plans for every aspect of the
work Involve personnel with previous DØ SMT experience where possible No second shift or overtime work currently scheduled
See W. Cooper’s Talk
![Page 15: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/15.jpg)
Director’s Review Feb 3-4, 2005
15
Installation Risk Analysis
Schedule Risk from prolonged Commissioning of L1Cal: substantially ameliorated by
Careful “non-invasive” handling of fragile BLS cable installation (1280 coax cables under MCH1 floor, >15 years old)
Preparation of BLS/ADF “patch panels” to facilitate reconnection to new ADF’s
Test Site on DAB “Sidewalk” – full system to be operated using collider data input prior to shutdown
Test data at L2 and L3 thoroughly verified Operating software to be exercised
![Page 16: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/16.jpg)
Director’s Review Feb 3-4, 2005
16
Installation Risk Analysis
Schedule Risk from prolonged commissioning of L1CTT: substantially ameliorated by
“Parallel Chain Slice Test” installed in 2004 Shutdown to enable system level operation of real hardware (crate, crate controller, DFEA2’s)
Full test of system software (download, monitor, diagnose) Test that new hardware loaded with present doublet equations
gives identical results to current trigger Test/optimize (effic. vs rate) algorithms with real data
Schedule Risk from prolonged commissioning of L1CTM: substantially ameliorated by
“Single Button” running in global runs with real production CalTrack boards prior to shutdown
![Page 17: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.](https://reader036.fdocuments.in/reader036/viewer/2022082518/5697bfd31a28abf838cac0da/html5/thumbnails/17.jpg)
Director’s Review Feb 3-4, 2005
17
Conclusions
Installation Management Team in place SC-IPC up and running to monitor physics commissioning
planning and manpower scheduling Evolution of Schedule Continues
Tasks detailed to sixth sublevel Resources (Effort, M&S) loaded WBS Dictionary and BOE in place Timeline assumptions depend on availability of identified
personnel Schedule refinements underway as planning evolves
DØ prefers Tevatron shutdown that begins after all upgrade components are ready (to minimize integrated luminosity cost)