Director’s Review Feb 3-4, 2005

1

Installation and Technical+Physics Commissioning

ofDØ RunIIb Silicon & Trigger Upgrades

Schedule & CostsR.P. Smith for

the DØ Collaboration

Page 2: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

2

Action Items from July 2004 Review

Understand Clearances for Layer Zero (in 2004 Shutdown) Incorporate Physics Commissioning in Installation Plans and

Schedule Review Manpower Estimates, articulate needs for extra-DØ

help Provide analysis of Installation Risks

+ Incorporate new information from L0 and Trigger hardware development teams, 2004 Shutdown experience

Page 3: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

3

2004 Shutdown Activities Related to Installation

Upgrade Installation “Infrastructure” tasks accomplished during 2004 Shutdown (in CH or MCH)

L1 Cal – None scheduled L1 CalTrack – begin mods of Muon PDT and Scintillator

FEB’s, terminate L1CTT transition and MTCxx cables L1CTT - install parallel “slice”: crate, controller, few DFEA’s,

cables for CTOC, CTT L2 Beta – None scheduled L2 STT – None scheduled L0 Silicon – L0 clearance survey, adapter card and 4-Hybrid

SVX4 string, N&S mini fuse panels, new Wiener PS, Interlock chassis

Online – Move Online (DAQ, Oracle, NFS) to new host cluster

Page 4: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

4

Beam-Off Time Paced by Silicon

Present Installation Schedule shows Tevatron Shutdown Time driven by Layer Zero Silicon Installation

Detector Not Removed From Collision Hall 2004 Shutdown experiences verifying silicon clearance are

leading to reconsiderations of installation plans => Revising existing schedule!

Consideration of each installation step, appropriate (repeated) repositioning of End Calorimeter(s) and installation of precision fixturing, indicates L0 Installation requires 12 weeks.

Resume Tevatron operations in week 13 with opportunity to re-enter CH during L0 technical commissioning.

14th week required to close detector and make final survey Workweeks are standard 40 hours, five days Silicon installation dominates CH access time. Trigger

Elements require lesser amounts of CH access in time “shadow” of L0.

Page 5: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

5

Silicon Installation Milestone Overview

ID WBS TASK NAMESTART-DATE

FINISH-DATE

DURATION

4 1.5.3 Hardware Ready for Installation 8/16/05 8/16/05 0 w

5 1.5.4Tevatron Shutdown for Installation Begins

8/16/05 8/16/05 0 w

54 1.5.5.9 H-Disks Removed 8/23/05 8/23/05 0 w

591.5.5.11

RunIIa Be Beampipe Removed 9/09/05 9/09/05 0 w

821.5.5.19

L0 Installed and Connected to Readout 10/10/05 10/10/05 0 w

921.5.5.23

RunIIb Be Beampipe Installed in SMT 10/21/05 10/21/05 0 w

961.5.5.25

Inner H-disks Reinstalled 10/26/05 10/26/05 0 w

105

1.5.5.29

RunIIb Beam Pipe Closed 11/7/05 11/7/05 0 w

107

1.5.5.31

Silicon Ready for Technical Commissioning

11/8/05 11/8/05 0 w

119

1.5.5.34

Detector Closed for Tevatron Resumption 11/23/05 11/23/05 0 w

Current schedules for hardware elements forecast

“T0”. Forecasts lack

schedule contingency.

Tevatron Downtime

~ 14 weeks elapsed

Page 6: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

6

L1 Cal Installation Task

L1Cal Ready for Technical Commissioning

~ 2 weeks before beam Resumes

ID WBS TASK NAME START-DATE

FINISH-DATE

DURATION

5 1.5.4 Tevatron Shutdown for Installation Begins

8/16/05 8/16/05 0 w

154

1.5.7.3.2.5 Decable BLS cables from Trigger Crates 8/16/05 8/22/05 1 w

155

1.5.7.3.2.6 Remove Rack Infrastructure from Sidewalk Racks

8/16/05 8/22/05 1 w

156

1.5.7.3.2.7 Depopulate & Remove Run I Trigger Crates

8/23/05 9/6/05 2 w

157

1.5.7.3.2.8 Install Rack Infrastructure in Active (ADF) racks

9/7/05 9/27/05 3 w

158

1.5.7.3.2.9 Install Patch Panels in Passive Racks, Reconnect BLS cables

9/28/05 10/04/05 1 w

159

1.5.7.3.2.10

Install ADF Crates 10/5/05 10/11/05 1 w

160

1.5.7.3.2.11

Connect Pleated Foil Cables 10/12/05 10/18/05 1 w

161

1.5.7.3.2.12

Connect ADF – TAB/GAB & TFW Cables 10/19/05 10/20/05 2 d

Current schedules for hardware elements forecast

“T0”. Forecasts lack

schedule contingency.

Page 7: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

7

Overall Schedule

Dotted Portions: <50% special runs for item

Page 8: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

8

Installation Effort

Workweek = Standard 5 days/40 hrs per week

Run IIb Technician Effort

0

2

4

6

8

10

12

14

16

18

20

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29

Calendar Weeks

Wee

kly

FT

E P

eak

Tev Suspended

Includespersonnel not presently in D0

Group

Page 9: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

9

Installation Effort

Workweek = Standard 5 days/40 hrs per week

Run IIb Engineer Effort

0

2

4

6

8

10

12

14

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29

Calendar Weeks

Wee

kly

FT

E P

eak

CompSP

EngU

ElecEngF

MechEngF

Tev Suspended Includespersonnel not presently in D0

Group

For assumed T0

this is week of 12/25

Page 10: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

10

Installation Effort

Run IIb Physicist Effort

0

5

10

15

20

25

30

35

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29

Calendar Weeks

Wee

kly

FT

E P

eak

PhysU

PhysF

Tev Suspended

For assumed T0 this is week of 12/25

Page 11: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

11

Detector Gap Occupancy

Per Gap Limit: 2

Run IIb Gap Occupancy

0

1

1

2

2

3

3

4

4

5

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29

Calendar Weeks

Wee

kly

FT

E P

eak

Tev Suspended

For assumed T0 Tev on-week

is obscured

Page 12: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

12

Identified Additional Manpower Needs

L0 Installation Expert Engineer: Youri Orlov L0 Installation Expert Instrumentalist: Mike Roman L0 Installation Expert Technicians: Dave Butler, Dennis Graham CTT Expert: Jamieson Olson Two Computer Science Professionals L1 Cal University Engineers: Dan Edmunds, Phillipe Laurens Four Electrical Techs for two weeks for PDT mods

Costed in schedule, important to have the named individuals

Page 13: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

13

Installation Costs

Burdened FY05/FY06 Installation Costs

Base FY05

Base FY06

Contingency

Total

Effort 909K 296K 603K 1808K

M&S 178K 52K 115K 345K

Total 1087K 348K 718K 2153K

Page 14: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

14

Installation Risk Analysis

Schedule Risks from Unanticipated Difficulties Encountered during L0 Installation: substantially ameliorated by

2004 shutdown clearance survey Experience with survey instruments in gaps Handling of EC’s and beampipe open-up/reclosing

Careful design of and practice with Installation Tooling beforehand Involve personnel with previous DØ SMT experience where possible No second shift or overtime work currently scheduled MSProject Installation Management Tool

Risk from Accidental Handling Damage to L0 during Installation: substantially ameliorated by

RunIIa Experience Will develop detailed step-by-step plans for every aspect of the

work Involve personnel with previous DØ SMT experience where possible No second shift or overtime work currently scheduled

See W. Cooper’s Talk

Page 15: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

15

Installation Risk Analysis

Schedule Risk from prolonged Commissioning of L1Cal: substantially ameliorated by

Careful “non-invasive” handling of fragile BLS cable installation (1280 coax cables under MCH1 floor, >15 years old)

Preparation of BLS/ADF “patch panels” to facilitate reconnection to new ADF’s

Test Site on DAB “Sidewalk” – full system to be operated using collider data input prior to shutdown

Test data at L2 and L3 thoroughly verified Operating software to be exercised

Page 16: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

16

Installation Risk Analysis

Schedule Risk from prolonged commissioning of L1CTT: substantially ameliorated by

“Parallel Chain Slice Test” installed in 2004 Shutdown to enable system level operation of real hardware (crate, crate controller, DFEA2’s)

Full test of system software (download, monitor, diagnose) Test that new hardware loaded with present doublet equations

gives identical results to current trigger Test/optimize (effic. vs rate) algorithms with real data

Schedule Risk from prolonged commissioning of L1CTM: substantially ameliorated by

“Single Button” running in global runs with real production CalTrack boards prior to shutdown

Page 17: Director’s Review Feb 3-4, 2005 1 Installation and Technical+Physics Commissioning of DØ RunIIb Silicon & Trigger Upgrades Schedule & Costs R.P. Smith.

Director’s Review Feb 3-4, 2005

17

Conclusions

Installation Management Team in place SC-IPC up and running to monitor physics commissioning

planning and manpower scheduling Evolution of Schedule Continues

Tasks detailed to sixth sublevel Resources (Effort, M&S) loaded WBS Dictionary and BOE in place Timeline assumptions depend on availability of identified

personnel Schedule refinements underway as planning evolves

DØ prefers Tevatron shutdown that begins after all upgrade components are ready (to minimize integrated luminosity cost)