Differences between the Civil and Common Law:...

17
Differences between the Civil and Common Law: Part 2: Delay Damages and Taking-Over Cremona Cotovelea Nina Tsaturova Jeremy Glover

Transcript of Differences between the Civil and Common Law:...

Page 1: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Differences between the Civil

and Common Law: Part 2: Delay

Damages and Taking-Over

Cremona Cotovelea

Nina Tsaturova

Jeremy Glover

Page 2: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Sub-Clause 10.1: Taking Over

“The Engineer shall, within 28 days after receiving the Contractor’s Notice either:

(i) issue the Taking-Over Certificate to the Contractor, stating the date on which the Works or Section were completed in accordance with the Contract, except for any minor outstanding work and defects (as listed in the Taking-Over Certificate) which will not substantially affect the safe use of the Works or Section for their intended purpose (either until or whilst this work is completed and these defects are remedied);”

Page 3: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Common Law Approach

• Practical completion means the completion of all the work that has been done

under the contract.

• It is possible for the works to be practically complete even though there may be

latent (i.e. hidden) defects in the works.

• The works will not be complete if there are patent defects (i.e. visible defects). If

there are patent defects in the works, practical completion should not be certified.

• It is possible to certify practical completion where there is minor (often called de

minimis) work still to be carried out.

Page 4: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Sub-Clause 10.1: Taking Over

Common law approach:

“For all practical purposes, that is to say for purposes of allowing the Employer

to take possession of the works and use them as intended, but not ‘complete’

down to the last detail, however trivial and unimportant.”

Jarvis v Westminster

[1981] CA 1 WLR 448

Page 5: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Civil Law Approach

There is no unitary legal regulation

Usually:• It could be mandatory, therefore applicable to both: private and public projects.

• Contractual Taking Over procedure could add to the legal procedure or be replaced by it.

Implications:• Acceptance of the Works

• DNP regime under applicable law

• Legal warranty

Page 6: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Civil Law Approach

When mandatory, it could request the verification of the:

Works:• the completion of all the works stipulated in the contract

• the works have been completed in accordance with the contract, of thedesign documentation, of the execution documentation, and of thespecific regulations, in compliance with the fundamental requirements,according to the law

• compliance with the provisions of the building permit as well as thepermits / agreements and the conditions of execution imposed by thecompetent authorities

Documents (i.e. as-built records) required by law/contract were submitted

Page 7: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Georgian Law Approach

• Contractor shall deliver the works to the Employer and the Employer shall accept the works when the works are completed in accordance with the contract.

• Article 652 of the Civil Code: “If the employer is aware of a defect in an object and still accepts it without asserting a claim, then the employer may not assert any claims with regards to defect.”

Page 8: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Georgian Law Approach

• Article 649 of the Civil Code: “The works shall be deemed to be accepted, if the Employer delays the acceptance within the time stipulated by the Contractor.”

• Article 633(1) of the Civil Code: “The contractor may claim loss if the employer does not accept the work performed. The employer shall also pay damages if he/she does not perform actions necessary for performance of the work.”

Page 9: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Taking Over: Georgian Law Approach

• FIDIC Red Book Sub-Clause 11.9: “Only the Performance Certificate shall be deemed to constitute the acceptance of the Works.”

• What about Taking Over under Sub-Clause 10.1?

Page 10: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Sub-Clause 8.8: Delay Damages

“If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Employer shall be entitled subject to Sub-Clause 20.2 [Claims For Payment and/or EOT] to payment of Delay Damages by the Contractor for this default. Delay Damages shall be the amount stated in the Contract Data, which shall be paid for every day which shall elapse between the relevant Time for Completion and the relevant Date of Completion of the Works or Section. The total amount due under this Sub-Clause shall not exceed the maximum amount of Delay Damages (if any) stated in the Contract Data.”

Page 11: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Common Law Approach

• The new test for whether a clause is a penalty is, as set out by Lord

Neuberger:

"whether the impugned provision is a secondary obligation which imposes a detriment

on the contract-breaker out of all proportion to any legitimate interest of the innocent

party in the enforcement of the primary obligation."

Cavendish Square Holding BV v Talal El Makdessi

[2015] UKSC 67

• But what does that mean?

Page 12: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Common Law Approach

• A Tribunal will now consider the wider commercial context of a transaction.

• A clause will not necessarily be penal, and therefore unenforceable, simply

because it is aimed at deterrence rather than compensation, e.g. delay

damages might be set by government bodies which do not necessarily suffer

financial losses in the same way as commercial parties.

Page 13: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Common Law Approach

• Even if the amount required by a clause bears no relationship to the loss

actually attributable to the breach, it will not necessarily be a penalty if it can

be shown that there is a legitimate reason why compensation for the actual

loss suffered would not be sufficient.

• Successful challenges to delay damages clauses historically have been rare

and that positon will remain, especially where the parties have negotiated a

contract and with the assistance of professional advisors.

Page 14: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Civil Law Approach

Damages: • Could have a double nature: compensatory and punitive

• Both acceptable depending on the national legislation and the evolution of the concept

• Could be compensatory or moratory*

*moratory damages (mora from Latin- delay) meaning, as the contract shows, that they are damages recoverable for loss resulting from the Contractor's delay in performing the Works.

Page 15: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Civil Law Approach

Both categories are usually acceptable:

• Compensatory damages OR the execution of contract (fulfilment of the principal

obligation)

• Moratory* damages AND the execution of contract

*moratory damages (mora from Latin- delay) meaning, as the contract shows, that they are damages recoverable for loss resulting from the Contractor's delay in performing the Works.

Page 16: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Civil Law Approach

Penal Clause – Penalty Clause – (Stipulatio poenae)

A penalty is a clause by which a person, in order to ensure performance of anagreement, binds himself to something in case of non-performance.

A penalty clause is a compensation for the damages which the creditor suffersfrom the non-performance of the principal obligation (art 1226, 1229 FrenchCivil Code 2016)

Contractual penalties can often be reduced by judges if they are unreasonablyhigh or not drafted in strict accordance with the governing law.

Page 17: Differences between the Civil and Common Law: …fidic.org/sites/default/files/2.16.Glover_Cotovelea...Taking Over: Common Law Approach • Practical completion means the completion

Delay Damages: Georgian Law Approach

• “For breaking a promise” to secure the performance of primary obligation(Article 417 of the Civil Code)

• Amount of penalty may exceed the actual loss (Article 418(1) of the CivilCode)

• Not an exhaustive remedy for delay (unless otherwise agreed by the parties)– loss caused by delay may always be claimed (Article 419(2) of the CivilCode)

• Parties may agree on exclusion of liability other than that caused byintentional/deliberate breach of obligation (Article 395(2) of the CivilCode)