Differences BetweenNTTF 2.3 Seismic & USI A-46

Richard Starck, MPRCaroline Schlaseman, MPRCaroline Schlaseman, MPRRobert Kassawara, EPRI

W biWebinar on:June 25, 2012

Teleconference Etiquette

• Many participants on teleconference• Place your phone on mute to avoid background noise• Mute your phone by:

Hitting *6 or– Hitting 6, or– Hitting the “Mute” button on your phone

• When you wish to be heard:When you wish to be heard:– Hit *6 again, or– Hit the “Un-Mute” button on your phone

• Please DO NOT place your call on HOLD during webinar– Some phone systems play background music

2© 2012 Electric Power Research Institute, Inc. All rights reserved.

– Simply mute phone instead

SQUG Web Site

• NTTF 2.3 Seismic related documents are posted to the SQUG web site Link to documents on home page:SQUG web site. Link to documents on home page:http://squgweb.mpr.com

• Documents on this site include:Documents on this site include:– NTTF 2.3 Seismic Walkdown Guidance (on EPRI web site)

– Word versions of:• Seismic Walkdown Checklist (SWC)• Area Walk-By Checklist (AWC• Peer Review Checklist for SWEL

– How NTTF 2.3 Seismic Differs From USI A-46C f thi t ti

3© 2012 Electric Power Research Institute, Inc. All rights reserved.

– Copy of this presentation

Objectives

• Understand NTTF 2.3 seismic program

• Know the major differences between Guidance and GIP• Know the major differences between Guidance and GIP

• Have your questions answered on implementingHave your questions answered on implementing NTTF 2.3 seismic program

4© 2012 Electric Power Research Institute, Inc. All rights reserved.

Background

5© 2012 Electric Power Research Institute, Inc. All rights reserved.

6© 2012 Electric Power Research Institute, Inc. All rights reserved.

7© 2012 Electric Power Research Institute, Inc. All rights reserved.

8© 2012 Electric Power Research Institute, Inc. All rights reserved.

Near-Term Task Force (NTTF)

9© 2012 Electric Power Research Institute, Inc. All rights reserved.

Lead Organizations

NRCNRCNEINEI

EPRIEPRIMPRMPR

10© 2012 Electric Power Research Institute, Inc. All rights reserved.

EPRI Report 1025286

11© 2012 Electric Power Research Institute, Inc. All rights reserved.

EPRI Report 1025286

USI A-46 vs. NTTF 2.3 Seismic

Topic GIP NTTF 2.3 SeismicConcern Equipment not qualified Degraded nonconformingConcern Equipment not qualified

to IEEE Std. 344-1975Degraded, nonconforming,

unanalyzed conditionsApproach Implement alternative

qualification methodVerify that plant meets seismic

licensing basisqualification method licensing basisScope of

EquipmentReactor safe shutdown

functionsReactor safe shutdown

functionsContainment functionSpent fuel integrity

Scope of Walkdown

Detailed Limited scopeArea Walk-By of nearby

equipmentSeismic Engineer

Qualifications5 years experienceSQUG 5-day trainingP E required

Nuclear experienceEPRI 2-day trainingP E not required

12© 2012 Electric Power Research Institute, Inc. All rights reserved.

P.E. required P.E. not required

USI A-46 vs. NTTF 2.3 Seismic (Cont’d)

Topic GIP NTTF 2.3 SeismicEquipment Caveats Not requiredEquipment

capacity vs. demand

CaveatsInternal load pathCapacity vs. demand calc

Not required

Anchorage Visual inspection Visual inspection onlyAnchorage Visual inspectionTorque testingCapacity vs. demand calc

Visual inspection only

Seismic Interaction Spatial Spatialp pFlooding/sprayFire

Relay Review Required Not requiredTanks & HXs Full scope Visual check of anchorageCable/conduit

racewaysFull scope Visual check for unusual

conditions

13© 2012 Electric Power Research Institute, Inc. All rights reserved.

USI A-46 vs. NTTF 2.3 Seismic (Cont’d)

Topic GIP NTTF 2.3 SeismicIdentified Issue “Outlier” “Adverse Seismic Condition”Identified Issue Outlier Adverse Seismic ConditionChecklists Yes YesPeer Review Limited Extensive using Peer Review

“T ”“Team”

14© 2012 Electric Power Research Institute, Inc. All rights reserved.

Questions and Answers

Enter your questions in WebEx comment window

15© 2012 Electric Power Research Institute, Inc. All rights reserved.

Contact Information

Richard StarckMPR Associates Inc

Caroline SchlasemanMPR Associates IncMPR Associates, Inc.

320 King StreetAlexandria, VA 22314

MPR Associates, Inc.320 King StreetAlexandria, VA 22314

(703) [email protected]

(703) [email protected]

Robert P. KassawaraEPRI3420 Hillview AvenuePalo Alto, CA 94304(650) 855-2302rkassawa@epri com