DG Inyorkern Weekly Project Summary 1/17/14

5
DG Inyorkern Weekly Project Summary 1/17/14

description

DG Inyorkern Weekly Project Summary 1/17/14. DG Inyokern 1/17/14: Percentage Overview. Install pipe for sewer ,water and phone Insulate walls and skin exterior walls Block up front wall and build dumpster Start curb and gutter Inspections on street work and phone Backfill ditches. - PowerPoint PPT Presentation

Transcript of DG Inyorkern Weekly Project Summary 1/17/14

Page 1: DG Inyorkern Weekly Project Summary 1/17/14

DG InyorkernWeekly Project Summary

1/17/14

Page 2: DG Inyorkern Weekly Project Summary 1/17/14

DG Inyokern 1/17/14: Percentage Overview• Demolition: • Pad Prep: 100% Finished and ceriified • Footing & Foundation: 100% finished• Underground Plumbing: 100% finished under slab• Underground Electric: 100% finished underslab• Underground Inspections:• Back fill: 100% • Slab Prep: 100%• Pour Slab: 100%• Framing:30%• Storefront Install:• Install Hoods:• Install Welded Duct:• Plumbing Rough:• Install Trench Drains:• Electrical Rough:• Fire Sprinkler Rough:NA• HVAC Rough:• Refrigeration Rough:• Alarm Rough:• Fire & Burg Alarm Rough:• Drywall:• Spackle & Tape:• FRP:• Install Walk-ins:• Quarry Tile Install:• Python Pull Coke/Beer:• Acoustical Ceiling:• Equipment Install:• Light Fixture Install:• Front of house Flooring & Wall Tile:• Running Trim:• Wall Covering:• Millwork Install:• Paint & Stain:• Décor Install:• Finish Plumbing:• Finish Electric:• Finish HVAC:• Finish Alarms:• Finish Refrigeration:• Bathroom partition Install:• Furniture Install:• Sign Install:• Awning Install:• Patio Furniture Install:• Landscape:• Final Inspections:

Install pipe for sewer ,water and phone

Insulate walls and skin exterior walls

Block up front wall and build dumpster

Start curb and gutter

Inspections on street work and phone

Backfill ditches

Progress this week

Stripped forms and graded around slab

Finished hauling out extra dirt

Started building installed all heavy steel

Completed bolt inspection

Dug out for Water , sewer and phone to street

Saw cut street for laterals ready to enter Monday

Block delivered ready to start Monday

Page 3: DG Inyorkern Weekly Project Summary 1/17/14

DG Inyokern 1/17/14: Weekly Project Summary

Page 4: DG Inyorkern Weekly Project Summary 1/17/14

DG Inyorkern 1/17/14 : WEEKLY PROJECT SUMMARYPERMIT(S) STATUS:

PROJECT START DATE: 12/13/13

___________________________

PROJECT PUNCH DATE: 3/15/14

IS THE PUNCH DATE OK? Yes

IF PUNCH DATE IS NOT ACHIEVABLE, WHAT DATE CAN PUNCH BE DONE? N/A

___________________________

BID COST VS. SITE CONDITIONS:

*None known at this time

___________________________

UNRESOLVED ARCHITECTURAL ISSUES THAT ARE CAUSING DELAYS: [INCLUDING MEP ISSUES]

*None known at this time

UNRESOLVED LANDLORD ISSUES OR DELAYS:

IS THERE ANYTHING THAT COULD POTENTIALLY DELAY THE COMPLETION?

We did have a problem with the delivery of building insulation . The Insulation company lost the order and missed delivery date.

This has to be cut to fit the building so there will be a delay getting it. I should be able to work on areas of building to keep moving the wall insulation will be here Wend and the roof Friday. We will have to put roof on last instead of next

POSSIBLE INCOMPLETE ITEMS AT SUBSTANTIAL COMPLETION:

*N/A

Page 5: DG Inyorkern Weekly Project Summary 1/17/14

DG Inyokern 1/17/14: WEEKLY PROJECT SUMMARY

POSSIBLE INCOMPLETE ITEMS AT CLIENT TURNOVER:

*None known at this time

PENDING UNRESOLVED ISSUES WITH CLIENT:

*None known at this time

AWAITING THE APPROVAL ON THE FOLLOWING CHANGE ORDERS:

POTENTIAL CHANGE ORDERS:

*None known at this time

THIS WEEKS MILESTONES ACHIEVED:

Start constuction of steel building

Start underground utilities

NEXT WEEKS PLANNED MILESTONES TO ACHIEVE:

80% completion of steel building

Finish 75% underground utilities

Start cub and gutter