Development Activity & School Impact Fee Update - 2016-9-20

10
Development Activity & School Impact Fee Update Orange County BCC September 20, 2016

Transcript of Development Activity & School Impact Fee Update - 2016-9-20

Development Activity & School Impact Fee Update

Orange County BCC

September 20, 2016

Presentation Outline

Background Outreach Current Status Next Steps

Background

School Impact Fee Ordinance 2016-08 Adopted May 10, 2016 Fee assessed at permit issuance 50% Increase on October 1, 2016 50% Increase on January 1, 2017

Background

School Impact Fee Rates

Current Rate Oct 1 Rate Single Family $6,525 $7,655 Townhouse $3,921 $5,426 Multi-Family $3,921 $4,920

Increase $999 - $1505

Outreach

Information pamphlet (since May) Permitting Services lobby signs (since May) Emailed >900 contractors (June) Posted on website and Fast Track

(since May/June)

Outreach

Association outreach (since May) Review comments (since June) Handout to each customer (since August)

Current Status

Single Family Residential

165 181

222 211 233 247 239

176

236

315

183

261

298

236

278

202

335 348 345

440

0

50

100

150

200

250

300

350

400

450

500

20152016

Current Status

Single Family Residential Plans Review –194 permits under review on September 19, 2016 –Processing time currently 28 days –Corrections received in Building Safety by

September 23, 2016

Current Status

Multi-family Plans Review –2 new Multi-Family (190 units) applications and

16 townhouse applications on September 19 –Processing time currently 42 days –Corrections received by

September 12, 2016

Next Steps

Prepare for January 1, 2017 update Continue to notify development community Ensure reviews are completed timely