Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

59
Councillor briefing Developer contributions: Community Infrastructure Levy, S106 obligations, viability Date: October 2014 www.pas.gov.uk

description

With less than a year until local authorities will be unable to pool (five or more) s106 obligations for a single project or scheme there is an immediacy for many to get a CIL in place. This presentation will help you to understand the relevance of viability and it will help you to understand the role for the Community Infrastructure Levy and other developer payments.

Transcript of Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Page 1: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Councillor briefingDeveloper contributions:Community Infrastructure Levy, S106 obligations, viability

Date: October 2014 www.pas.gov.uk

Page 2: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What is PAS ?• PAS is a DCLG grant-funded programme but

part of the Local Government Association

• Governed by a ‘sector led’ board

• 10 staff – commissioners, generalists, support

“PAS exists to provide support to local planning authorities to provide efficient and effective planning services, to drive improvement in those services and to respond to and deliver changes in the planning system”

Page 3: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Programme

Presentation:– Viability as a consideration– Types of developer contributions – Community Infrastructure Levy– Your choices

• Questions & discussion

Page 4: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Growth and Infrastructure

Page 5: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Developer payments after April 2015

Chief planner: councils 'must face consequences' of lack of CIL progress

Page 6: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

When you need to consider viability:

• Local Plans /core strategy

• Other policies affecting the cost of development proposals

• Community Infrastructure Levy

• Planning applications

• S106 obligations

Page 7: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

It is all about delivery

• Growth• Viability – including developer/landowner motivation

• Mitigation - Infrastructure

• Community expectations• Policy requirements – e.g. affordable housing

Page 8: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Basic elements of viability assessments

Page 9: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Policy costs

Including:

• materials

• sustainability codes

• BREEAM

• Affordable housing

• On-site 106 contributions

Page 10: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Developers costs

• Contaminated land• Poor ground conditions• Green field costs – connecting to infrastructure and

services.• Materials• Fees• Marketing• Profit (risk)• Finance

Page 11: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Money money money

There is only so much - how much?

• What will bring development forward?

• You need to have information on viability

• You have choices

Page 12: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Developer and other contributions

• S106 obligations

• Community Infrastructure Levy (CIL)

• Highway contributions ( s38 and s278 Highways Act)

• New Homes Bonus

• Retention of business rates

Page 13: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

s106 obligations can:

• restrict the development or use of the land in any specified way

• require specified operations or activities to be carried out in, on, under or over the land

• require the land to be used in any specified way; or

• require a sum or sums to be paid to the authority (or, to the Greater London Authority) on a specified date or dates or periodically.

Page 14: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

S106 Obligations

• S106 is not replaced by CIL

• Old reality – pre 2008

• New reality-post 2008: Times have changed – viabilityTimes have changed - legislation

Page 15: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

S106 - tests

• If the development is capable of being charged CIL, the S106 obligation must meet these legal tests:

• NECESSARY to make the development acceptable in planning terms

• DIRECTLY RELATED to the development • FAIRLY AND REASONABLY related in kind and scale to

the development

• These are also now the policy tests in the NPPF

Page 16: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Do your s 106 obligations currently meet these tests? • Most basic tariffs are already contrary to the

regulations (they do not meet the legal tests)

• If they don’t meet the regulations you are in danger of legal challenge to your decision making.

• Time is running out…. To get a CIL in place

Page 17: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

S106 obligations

• Site specific mitigation measures• For pooled contributions up to April 2015/CIL

adoption, then for up to 5 developments where infrastructure not funded by CIL

• NPPF- planning obligations should take into account changes in market conditions over time and, where appropriate, be flexible to prevent stalling(para. 205)

Page 18: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Renegotiation of s 106

• Amended Regulation (Feb 2013) to set out a procedure for amending any planning obligations entered into between 28 March 2008 and before 6 April 2010.

• Changes in the Growth and Infrastructure Act that require a council to renegotiate previously agreed affordable housing levels in a S106, or enable PINs to assess the viability arguments and change the requirement

Page 19: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Chief planner: councils 'must face consequences' of lack of CIL progress• Local planning authorities that fail to get a

Community Infrastructure Levy (CIL) charging schedule in place by next spring must 'face the consequences', the government's chief planner has said.

• June 2014 -DCLG chief planner Steve Quartermain

Page 20: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What does this mean for you?

• From April 2015 you will only be able to pool S106 on a very

limited basis

• If a CIL is not in place your council is at risk of significantly

reducing income from developer contributions

Page 21: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Regulation 122 Regulation 123

Timing From April 2010 From adoption of charging schedule or 6th April 2015 whichever is earlier

Impact Introduction of three legal tests(a)Necessary to make the development acceptable in planning terms; (b)Directly related to the development ;and(c)Fairly and reasonably related in scale and kind to the development.

Granting planning permission cannot be dependent on a S106 or S278 for infrastructure on reg 123 list

Cannot pool from more than five separate S106 planning obligations

Limitations on pooling for infrastructure begins from 6th April 2010

No limitation on pooling for S278 agreements

Summary – key regulations

Page 22: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What are you doing?

Page 23: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Questions?

Page 24: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What is a CIL?

• A mechanism for developer contributions

• To contribute towards infrastructure needed to support the development of the area

• A charge per square metre of floorspace

• Not mandatory

Page 25: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What is CIL for?

• To help pay for infrastructure needed to support new development

• But not to remedy existing deficiencies unless the new scheme will make it worse

• Councils must spend the income on infrastructure – but you can decide what (and that can change over time)

Page 26: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Charging CIL – some basics

• £ per square metre on net additional (internal) floorspace

• Rates can vary by geographic area or use ( or both)

• Due when the development starts• It is index linked• The landowner is responsible for paying it • The local planning authority is the charging

authority (& sets the CIL)

Page 27: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

When does it apply?• To all development that involves ‘buildings that people

normally go into’• Development over 100sqm gross internal floorspace• A single dwelling ( even under 100sqm) (but not

subdivisions of dwellings)• Includes permitted development (it doesn’t have to

follow a planning permission)• Once set, you can’t pick and choose which

developments to charge • Exceptions including– self build: annexes and extension

Page 28: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Why set a CIL?

• Money for infrastructure through charging nearly all new development -a little from almost everyone (so fairer)

• There is a lack of government or other money

• It is set out in a schedule based on evidence (so more transparent)

• Developers have certainty

• Changes to s106 – legal tests and pooling

Page 29: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

CIL- positive economic effect

• “By providing additional infrastructure to support development of an area, the levy is expected to have a positive economic effect on development across an area”

para. 8 - CIL Guidance – April. 2013

Page 30: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Setting a CIL

• Identify the aggregate infrastructure funding gap- Is a CIL necessary?

• What rate is viable to charge?

• Check out the consequence of the rate on key uses

• Make sure that the rate is backed by evidence

• Consultation required

• Independent examination

Page 31: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What you need to set a CIL?

• Up to date development plan

• Evidence on infrastructure funding gap – aggregate gap

• Evidence on viability

• All evidence is ‘appropriate available evidence’

• Rates should be consistent with viability evidence across the area

Page 32: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Strike the Appropriate balance

Between– the desirability of funding the infrastructure gap to

support the development of the area from CIL

and– the potential effects (taken as a whole) of the

imposition of CIL upon the economic viability of development across the area.

Page 33: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Viability - rate setting:

• Strategic approach• Look at the effect on the whole area• The rate may put some development at risk• No requirement to use any particular models• Can set differential rates – but rate changes

can only be differentiated on viability grounds.

Note: If there is a CIL, a rate must be set for every use.

Page 34: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Differential rates

• Different between uses (not just use classes)

• Different across the geographic area

• Different by scale

• All or none

• All differential rates must be based on viability evidence (not policy objectives)

Page 35: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Different rates for different authorities

• £70 per sq Metre – flat rate – based on residential growth.

• residential charges rural - £80m2 and urban -£40m2 . All office/industrial uses £0m2 charge.

• Incl. 4 residential rates, 3 employment rates,– high level of differentiation by area and use.

Page 36: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Members role

• Make sure you know what is necessary to aid delivery of growth in your area. Make sure your priorities are clear.

• Get involved in deciding how ‘risky’ your rates are going to be - strike the appropriate balance for your area.

Page 37: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Exemptions etc

• Social housing relief

• Buildings used for charitable purposes- exempt

• Discretionary relief for charitable investments

• Self build

• Instalments policy

• Exceptional circumstances (where scheme can’t afford to pay it) but conditions apply

Page 38: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Exceptional Circumstances

• It is very difficult to get

• It is not a negotiated amount

• Should not be considered when setting rates

Page 39: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

How is the levy paid?

• Usually cash contribution but can be payment in kind- infrastructure and/or land

• Falls due on commencement of the development but you can agree to payment by instalments

Page 40: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What has PAS learnt from the early CIL authorities?

Those that succeed have:

• Councillor and management team support

• Effective project management

• Project team

• Project plan

Page 41: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What has PAS learnt from the early CiL authorities?

• There is no one way to DO a CIL

• Remember the basics

• Infrastructure – Local Authorities should use what they have

• Viability and balancing risk are key to the rate

• Keep it simple

Page 42: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Who has a CIL?

• There are  56 CIL’s adopted,

• A further 10 are through examination, and 28 submitted for examination, (October 2014)

• Many more are being worked on – 100 by April 2015 (?)

Page 43: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Questions?

Page 44: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Spending CIL – For Charging Authorities• It must be on infrastructure needed to support the

development of the area• It can be spent on infrastructure outside the CA’s

area, and spent by another body• Doesn’t have to spent on the infrastructure referred

to in your charge setting evidence but.. the links should be clear

• It is advisable to publish a list of the infrastructure you intend to use CIL for (Reg 123 list)

• You cannot spend CIL on affordable housing.

Page 45: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Purpose of the Reg 123 list

• “double dipping” is a concern for Developers• Reg123 is the requirement for a published list of

infrastructure projects or types of infrastructure that the Charging Authority intends will be, or may be, wholly or partly funded by CIL, those infrastructure projects or types of infrastructure.

• …put another way you cannot collect s106 to spend on items within your Reg 123 list

• Golden thread

Page 46: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

GOLDEN THREAD

From plan to delivery

Devising CIL spending list:

A draft Reg 123 is now part

of the examination

Page 47: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

123 LIST- Post Examination

:• Reg 123 list - should be based on the draft list

examined with the charging schedule• Need to explain the reason for any change• Appropriate local consultation• Where a change to the regulation 123 list would have

a significant impact on viability evidence requires a review of the charging schedule

Page 48: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

The greater demand on and for Council resources to deliver

Implications on Council Resources

Education

Education Transport

Education Transport

Community Facilities

Green spaceHealth

The more comprehensive the Reg 123 List

Page 49: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Neighbourhoods

Localism Act:

•localism principles – the money should benefit those who take the development. (incentivisation)

Page 50: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

CIL and Neighbourhood Planning

Page 51: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Member involvement in delivery

• Get involved early in Infrastructure prioritisation

• Decide how best you can use all income from development to aid growth

• Understand the implications of s106 vs CIL

• Work with neighbourhoods and local communities

Page 52: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Is CIL right for you?

Page 53: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Decisions

• What will you seek from CIL ?

• What will you seek from s106 ?

• How will you spend your new homes bonus and business rate retention on?

• Who do you need to be working with? County Health authority Neighbouring authority Parish

Page 54: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Tough decisions

• CIL might give you enough money for that long awaited – politically popular- skating rink

BUTIs that the best way to make your new developmentsustainable and acceptable to the community? OR should you give the CIL money to your

neighbouring authority for a new transport link in their area that improves access for the new growth in your area?

Page 55: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

Governance

• Review your infrastructure priorities

• Set up your council procedures and delegation agreements for CIL

• Create the necessary CIL management structure.

• How will you work with other organisations.

• Enter into memoranda of co- operation with other bodies e.g. neighbouring authority

Page 56: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What should be happening

• Working on your Local plan/ Core strategy• Infrastructure planning• Viability • Are you and your officers talking to your:

– county and parish – developers– communities– neighbours– infrastructure providers

Page 57: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)

What will success look like?

Page 59: Developer Payments- Community Infrastructure Levy, S106 agreements and Viability, (October 2014)